THIRD DIVISION
ELLINGTON, P. J.,
DILLARD and MCFADDEN, JJ.
NOTICE: Motions for reconsideration must be
physically received in our clerk’s office within ten
days of the date of decision to be deemed timely filed.
http://www.gaappeals.us/rules
March 29, 2016
In the Court of Appeals of Georgia
A15A2326. JONES v. SABAL TRAIL TRANSMISSION, LLC.
MCFADDEN, Judge.
This appeal is from a trial court’s grant of declaratory judgment and injunctive
relief authorizing a company to enter and survey certain property for a proposed
natural gas pipeline. The appellant property owner claims that she did not get
adequate notice that the hearing on the appellant’s petition would consolidate the
interlocutory injunction and declaratory judgment requests set forth in the petition;
however, the record shows that she did receive sufficient notice and that she
acquiesced in the consolidated hearing on both issues. The appellant also claims that
the trial court erred in applying state law in this matter because it is preempted by
federal law, but she waived this issue by not raising it below. Likewise, the
appellant’s argument that the appellee did not meet the definition of the term
“pipeline company” as it is used in two code sections was also waived because it was
not raised in the trial court. Finally, appellant contends that the appellee was required
to obtain a certain federal certificate before it could be authorized under a state statute
to survey her property; however, the plain language of the applicable state statute
imposes no such requirement. Because the appellant has failed to show reversible
error, we affirm.
Sabal Trail Transmission, LLC was hired to construct and operate a natural gas
pipeline that will begin in Alabama, run through Georgia, and end in Florida. Sabal
Trail has already surveyed approximately 99 percent of the proposed pipeline route,
which will traverse property owned by Sandra Jones in Colquitt County. Sabal Trail
requested permission to enter Jones’ property to perform the survey, but Jones refused
the request.
Sabal Trail filed the instant action for interlocutory injunctive relief and
declaratory judgment, seeking authorization to enter Jones’ property to perform the
survey pursuant to OCGA § 22-3-88, which provides: “The power of eminent domain
may be exercised by persons who are or may be engaged in constructing or operating
pipelines for the transportation or distribution of natural or artificial gas and by
persons who are or may be engaged in furnishing natural or artificial gas for heating,
2
lighting, or power purposes in the State of Georgia.” Jones filed an answer and
counterclaims. After an evidentiary hearing at which both parties appeared and were
represented by counsel, the trial court entered a final declaratory judgment and
injunction, declaring that Sabal Trail has the right under OCGA § 22-3-88 to enter the
property for purposes of conducting the survey and enjoining Jones from interfering
with Sabal Trail’s right to survey the property. Jones appeals from the final
declaratory judgment and injunction.
1. Consolidated hearing.
Jones contends that the trial court erred in consolidating the hearing on the
interlocutory injunction application with the declaratory judgment action because the
notice for the hearing indicated only that it was for the interlocutory injunction. The
contention is without merit.
The notice of the hearing indicated that it was issued pursuant to Sabal Trail’s
“Motion for Interlocutory Injunction,” which, despite the style of the pleading, was
also an action for declaratory judgment; the pleading plainly asserted claims for, and
sought, both injunctive relief and a declaratory judgment as to Sabal Trail’s right to
conduct the survey. See Udoinyion v. Michelin North America, 313 Ga. App. 248,
253 (2) (721 SE2d 190) (2011) (substance, rather than nomenclature, of pleadings
3
determines their nature). The notice further ordered Jones to appear at the hearing
“pursuant to OCGA §§ 9-4-1, et seq., 9-5-1, et seq. and 9-11-65.” OCGA § 9-4-1 et
seq. is the chapter of the code governing declaratory judgments, while OCGA § 9-5-1
et seq. governs injunctions. OCGA § 9-11-65 (a) (2) expressly provides that “[b]efore
or after the commencement of the hearing of an application for an interlocutory
injunction, the court may order the trial of the action on the merits to be advanced and
consolidated with the hearing of the application.”
Pursuant to the notice, Jones appeared at the hearing with counsel. At the start
of the hearing, the trial judge stated that the litigation involved “the petition for
declaratory judgment to conduct survey.” Thereafter, the judge stated to the attorneys,
“Gentlemen, on the petition for declaratory judgment to conduct the survey, the
petition was filed by the Plaintiff. Is the Plaintiff ready to proceed?” Counsel for
Sabal Trail responded affirmatively and then, during his opening statement, asserted
that both declaratory judgment and injunctive relief were appropriate to enforce Sabal
Trail’s right to conduct the survey and expressly asked the court to conduct a final
hearing “and grant declaratory relief on the right of entry.” Jones raised no objection
to this request.
4
Thereafter, during his opening statement, counsel for Jones said that he
believed the hearing should be “about following those elements as to whether [Sabal
Trail is] entitled to this injunction,” but he did not object to consolidating that
interlocutory injunction issue with the petition’s declaratory judgment request and he
did not claim insufficient notice. Thereafter, both sides presented evidence in the
form of testimony and exhibits. During closing argument, counsel for Sabal Trail
again expressly requested both an injunction and declaratory judgment, citing OCGA
§ 9-11-65 as support for “this being a final hearing and a declaratory judgment being
granted at this time with an associated injunction.” During his closing, counsel for
Jones argued legal issues, but did not address the consolidation of the injunction and
declaratory judgment issues or make any argument concerning the notice of the
hearing.
The trial court did not issue a decision at the conclusion of the hearing; rather,
it took the matter under advisement and instructed the parties to submit proposed
orders. There is nothing in the record showing that Jones subsequently raised any
objection to the consolidation of the injunction and declaratory judgment requests at
the hearing or asserted a claim of insufficient notice. Almost two weeks after the
hearing, the trial court entered its final declaratory judgment and injunction.
5
Under these circumstances, we find that Jones not only had sufficient notice
that the hearing would encompass both the interlocutory injunction and declaratory
judgment claims set forth in Sabal Trail’s initial pleading, but that she also acquiesced
in the consolidation of those issues, which were clearly identified by the judge and
opposing counsel, at the hearing. “Parties can not take their chances for a favorable
[judgment], and then, the result being unsatisfactory, ask that a new trial be granted
because of [alleged] irregularities which they have passed over in silence during the
progress of the [hearing].” Fulcher v. Canal Ins. Co., 132 Ga. App. 325, 328 (3) (208
SE2d 116) (1974) (citations and punctuation omitted) (rejecting claim that trial court
erred in granting declaratory relief because notice indicated hearing was only for
injunctive relief, where appellants did not object to the proceeding). Accordingly, this
enumeration of error provides no grounds for reversal.
2. Preemption.
Jones claims that the trial court erred in finding that Sabal Trail has authority
under OCGA § 22-3-88 to enter her property to survey because the Natural Gas Act,
15 U. S. C. § 717 et seq., does not authorize the entry and federal law preempts state
law in this area. However, Jones did not raise this issue below and therefore it is
waived.
6
We note that in a recent unreported opinion involving the same pipeline at
issue in this case, this same claim of error was found to have been waived because it
was neither raised below nor ruled upon by the trial court. While that unreported
opinion, in which all three judges fully concurred, is neither physical nor binding
precedent, see Court of Appeals Rule 33 (b), its analysis on this issue is persuasive.
See Bell v. Sabal Trail Transmission, ___ Ga. App. ___ (Case No A15A2390,
decided March 9, 2016). Accordingly, we adopt the analysis from that case, set it
forth in full below, and apply it to this case. As explained in our unreported opinion:
Whether the defense of preemption is jurisdictional or waivable
is a question of law we review de novo. The Supreme Court has
recognized that the defense of preemption can be jurisdictional, and
therefore nonwaivable, if success on the preemption defense would
dictate the choice of forum and thereby deprive the reviewing court of
subject matter jurisdiction. In contrast, the defense of preemption is
waivable where it merely dictates a different choice of law. Fryer v.
A.S.A.P. Fire & Safety Corp., 658 F3d 85, 90 (II) (1st Cir. 2011)
(citations omitted). “Here, the preemption defense is not jurisdictional
because a successful preemption defense under [the Natural Gas Act]
would dictate only a change in law, not a change in forum.” Id.; see also
Van Syoc v. Equitrans, L.P., 2:13-CV-01735, 2015 WL 1346872, *6
(III) (W.D. Penn. 2015) (because natural gas regulation is not a
completely preempted field, defendants’ eminent domain counterclaim
could not provide a basis for removal or otherwise support subject
matter jurisdiction upon federal court); Vaden v. Discover Bank, 556
U.S. 49, 61-62 (II) (129 SCt 1262; 173 LEd2d 206) (2009) (state-law-
based counterclaim does not qualify a case for federal court jurisdiction,
even if counterclaim relies exclusively on federal substantive law). The
7
preemption claim in this case involves a choice of federal law, rather
than a choice of forum. (Footnote omitted).
Consequently, we conclude that Jones’ failure to raise this preemption claim
below waives the issue and we will not consider it for the first time on appeal.
3. OCGA §§ 22-3-80 and 22-3-81.
Jones argues that it was error for the trial court to find that Sabal Trail has
eminent domain authority because it is not a pipeline company as that term is used in
OCGA §§ 22-3-80 and 22-3-81. Pretermitting the fact that those code sections
concern petroleum pipeline companies, not natural gas pipeline companies like Sabal
Trail, is the fact that this argument has been waived because it was not raised and
ruled on in the trial court. “An appellate court will not consider an issue raised for the
first time on appeal, because the trial court has not had the opportunity to consider it.”
(Punctuation and footnote omitted.) Sitton v. Print Direction, 312 Ga. App. 365, 370
(3) (718 SE2d 532) (2011) (citation and punctuation omitted).
4. FERC certificate.
Jones argues that the trial court erred in finding that Sabal Trail has the right
under OCGA § 22-3-88 to enter and survey her property because Sabal Trail has not
yet obtained a certificate of public convenience and necessity from the Federal
8
Energy Regulatory Commission (“FERC”). As with the federal law preemption issue
discussed above in Division 2, this same issue concerning a FERC certificate was
addressed and rejected by this court’s unreported opinion in Bell v. Sabal Trail
Transmission, supra, ___ Ga. App. ___ . As noted above, this unreported decision is
not physical or binding precedent. See Court of Appeals Rule 33 (b). Nevertheless,
we find its analysis of this issue to be persuasive and therefore set it out below in full
and follow it in this case. As explained in our unreported opinion:
By its plain terms, OCGA § 22-3-88 does not condition its grant
of eminent domain on the possession of any certificate or permit. If the
General Assembly had intended to condition the right of eminent
domain for natural gas pipelines upon a certificate of convenience and
necessity, it could have made the certificate an express condition, as it
did with petroleum pipelines. See OCGA § 22-3-81 (2) (defining
“pipeline company” as one which transports petroleum and petroleum
products); OCGA § 22-3-82 (c) (pipeline company has right of
reasonable access for surveying after obtaining certificate of
convenience and necessity); and OCGA § 22-3-83 (a) (pipeline
company’s exercise of eminent domain right conditioned upon obtaining
certificate of public convenience and necessity).
Moreover, the certificate prerequisite for the exercise of eminent
domain for petroleum pipelines was enacted at the same time as the
statute governing eminent domain for natural gas pipelines, which has
no such prerequisite. Accordingly, we conclude that a certificate is not
a condition precedent to the survey and entry rights granted by OCGA
§ 22-3-88 and Georgia case law. See, e.g., Robinson v. Transcontinental
Gas Pipe Line Corp., 421 F2d 1397, 1398 (5th Cir. 1970). See also
Walker v. Gateway Pipeline Co., 601 So2d 970, 975 (Ala. 1992)
(“Although a FERC certificate may have been a prerequisite to
9
construction of pipeline facilities, such a certificate was not a
prerequisite to precondemnation entries for the purpose of survey and
examination.”).
Accordingly, the trial court did not err in finding that Sabal Trail is not required
to have a FERC certificate in order to exercise its rights under OCGA § 22-3-88.
Judgment affirmed. Dillard, J., concurs; Ellington, P. J., concurs in the
judgment only.
10