NOTICE: All slip opinions and orders are subject to formal
revision and are superseded by the advance sheets and bound
volumes of the Official Reports. If you find a typographical
error or other formal error, please notify the Reporter of
Decisions, Supreme Judicial Court, John Adams Courthouse, 1
Pemberton Square, Suite 2500, Boston, MA, 02108-1750; (617) 557-
1030; SJCReporter@sjc.state.ma.us
15-P-634 Appeals Court
DANIEL DUFF & another1 vs. JOHN McKAY & others.2
No. 15-P-634.
Plymouth. January 19, 2016. - June 14, 2016.
Present: Grainger, Rubin, & Milkey, JJ.
Contract, Settlement agreement, What constitutes, Performance
and breach. Judgment, Implementing settlement agreement.
Civil action commenced in the Superior Court Department on
April 9, 2013.
A motion to enforce settlement and to dismiss the complaint
was heard by Beverly J. Cannone, J., and entry of separate and
final judgment was ordered by her.
Stephen W. Rider for the plaintiffs.
Colin Black for the defendants.
MILKEY, J. In 2010, plaintiffs Daniel and Lisa Duff hired
the defendants to perform a renovation project at their home in
1
Lisa Duff.
2
McKay Construction Company, LLC, and Artisan Kitchen
Design, Inc. Two additional defendants were dismissed before
the appeal was filed.
2
Hingham. A dispute ensued regarding the defendants' workmanship
and their alleged failure to obtain a building permit in a
timely manner. In May of 2012, the Duffs sought redress by
initiating arbitration through the State program created in
accordance with G. L. c. 142A.3 The following year, on the eve
of the assigned arbitrator's scheduled view of the property, the
parties reached an apparent settlement of their dispute.
Nonetheless, a formal settlement document was never executed
because of a disagreement regarding payment terms. When the
parties reached an impasse in resolving that issue, the Duffs
withdrew their request for arbitration and filed a multicount
action in the Superior Court asserting their underlying claims.
The defendants moved to dismiss the action and to enforce the
settlement. A Superior Court judge allowed that motion and
entered judgment requiring the defendants to pay the agreed-to
amount within ten days. On the Duffs' appeal, we affirm.
Background. The parties' key communications were
memorialized in electronic mail messages (e-mails), copies of
which were submitted to the motion judge.4 As a result, the
3
Pursuant to G. L. c. 142A, § 4, the director of the Office
of Consumer Affairs and Business Regulation created an
arbitration program through which homeowners can resolve
disputes with home improvement contractors they hired. See 201
Code Mass. Regs. §§ 14.00 et seq. (2003).
4
The e-mails were attached to the parties' affidavits, and
their authenticity has not been questioned.
3
essential facts pertaining to the parties' negotiations are
uncontested.
At the heart of this case is a March 21, 2013, e-mail
exchange between counsel that followed extended and vigorous
settlement discussions. Counsel for the Duffs wrote to "confirm
what I believe our respective clients have agreed to." He then
listed six terms. Key among those terms were the requirements
that the defendants pay the Duffs $27,500, and that the parties
"exchange mutual general releases, subject only to the
obligations in the settlement agreement."5 The list of terms did
not specify when payment of the $27,500 was due.
The Duffs' counsel concluded his e-mail by asking his
counterpart to "confirm that I got this right by return e-mail."
Six minutes later, the defendants' counsel responded,
"Confirmed." Six minutes after that, the Duffs' counsel sent an
e-mail to the assigned arbitrator canceling the scheduled site
visit because "I am pleased to report that the parties have
reached a settlement agreement." The following morning, the
coordinator for the arbitration program sent an e-mail to
express her happiness "that the parties have settled," and she
requested clarification whether she should "consider this your
5
The remaining terms addressed the return of a wood
countertop to the defendants, confidentiality and mutual
nondisparagement provisions, the retraction of certain comments
that the Duffs had made to the Better Business Bureau, and the
dismissal with prejudice of any arbitration claims.
4
formal notice of settlement or will you mail written notice of
the settlement." Counsel for the Duffs responded by stating:
"I believe the parties are planning on preparing and
signing a formal settlement agreement and then will file a
stipulation of dismissal, with prejudice, of the claims in
the arbitration. This may take a week or so."
Over the next two and one-half weeks, the parties sought to
complete a formal settlement document. During that time,
counsel for the Duffs expressed concern over delay, stating that
he did not "want to give the clients too much time to rethink
this." As the Duffs acknowledge, some of the delay was caused
by a medical issue related to the defendants' counsel's family.
In the end, the parties agreed on every provision of the
final settlement document save one: when precisely payment of
the $27,500 was required. The Duffs insisted that payment be
made when the agreement was executed, while the defendants
insisted that they be given some time to complete payment. Each
side asserted that its position was consistent with customary
practice. In addition, each attorney asserted that his
counterpart should have raised the payment issue before an
apparent settlement had been reached if the issue had been
important to his client. As of April 8, 2013, the state of play
was as follows: the defendants were willing to pay a majority
5
of the money ($17,500) the following day,6 with the remaining
payment to be made three weeks later (April 30, 2013), while the
Duffs continued to insist that the full amount be paid
"immediately."7
With the final issue at a seeming impasse, the Duffs on
April 8, 2013, terminated the still-pending arbitration
proceeding by withdrawing their request for arbitration.8 The
following day, they filed the current action in Superior Court.
Notably, their complaint did not allege that the parties had
reached a settlement agreement, with payment due immediately.
Instead, without mentioning the putative settlement agreement or
the abandoned arbitration proceedings, the complaint simply set
forth the Duffs' underlying claims with regard to the
defendants' work on the renovation project (alleging violations
of G. L. c. 93A, breaches of contract, negligence, and
misrepresentation).
6
In fact, the defendants had already cut a bank check for
that amount dated April 8, 2013, a copy of which was sent to the
Duffs' counsel by e-mail that day.
7
The Duffs did state that they would be willing to accept
the defendants' proposed payment schedule if the total amount
paid were increased to $30,000 and various measures were
instituted to secure payment.
8
The Code of Massachusetts Regulations provides that either
party (the homeowner or contractor) may withdraw without
prejudice from arbitration "at any time prior to the hearing."
201 Code Mass. Regs. § 14.12 (2003).
6
In response, the defendants filed what was styled as a
motion to enforce the settlement agreement and to dismiss the
complaint. The motion was supported by an affidavit from
counsel setting forth the history of the negotiations as
memorialized in the trail of e-mails. In opposing the motion,
the Duffs submitted an affidavit from their own counsel that
covered the same uncontested e-mail history. However, counsel
also set forth his view, based on his experience, that
"attorneys presume that payment of settlement proceeds will be
made at the time the settlement agreements are finalized and
releases exchanged" unless the paying party requests additional
time before the settlement is reached. Daniel Duff himself also
executed an affidavit in which he stated that in authorizing
settlement, he had "understood" that payment would be due when
formal settlement papers were signed and that he otherwise would
not have agreed to settle the case for $27,500.
A Superior Court judge eventually allowed the defendants'
motion and entered judgment requiring the defendants to pay the
settlement amount within ten days.9 Dissatisfied with that
result, the Duffs appealed.
9
The docket reflects that one Superior Court judge had
ruled that an evidentiary hearing on the motion should be held
and such a hearing was scheduled on numerous occasions, but then
postponed. The motion eventually was heard and resolved by a
different judge after a nonevidentiary hearing held on December
7
Discussion. 1. Procedural posture and standard of review.
We begin by reviewing the procedural posture in which this case
has come before us. "A settlement agreement is a contract and
its enforceability is determined by applying general contract
law." Sparrow v. Demonico, 461 Mass. 322, 327 (2012). In
entering judgment enforcing the parties' apparent settlement
agreement, the judge in effect resolved a contract claim put
forward by the defendants even though that claim was presented
by motion, not as a counterclaim. The case law suggests that
such informality is acceptable where settlements have been
reached while litigation is pending. See Fecteau Benefits
Group, Inc. v. Knox, 72 Mass. App. Ct. 204, 211-212 (2008)
(affirming allowance of "motion to enforce settlement
agreement"). See also Fidelity & Guar. Ins. Co. v. Star Equip.
Corp., 541 F.3d 1, 5 (1st Cir. 2008) ("[B]efore the original
suit is dismissed, the party seeking to enforce the [settlement]
agreement may file a motion with the trial court"). Whether
this practice is appropriate where, as here, the settlement was
negotiated prior to the commencement of litigation is arguably a
23, 2013. The Duffs did not provide a transcript of that
hearing with their appeal.
8
different matter. We need not resolve that question, as the
Duffs do not press this issue on appeal.10
That said, the parties do debate the applicable standard of
review. As the defendants point out, there is case law to
suggest that in enforcing settlement agreements, judges enjoy
substantial leeway to resolve open issues and to dispose of the
matter summarily. See Fidelity & Guar. Ins. Co., supra. See
also Mathewson Corp. v. Allied Marine Indus., Inc., 827 F.2d
850, 852 (1st Cir. 1987) (noting "inherent power" of courts to
oversee and enforce settlement agreements). The Duffs counter
that even to the extent that might be true with regard to
settlements of pending litigation, ordinary procedural rules
apply to the enforcement of any out-of-court agreements reached
prior to the commencement of litigation. See In re Mal de Mer
Fisheries, Inc., 884 F. Supp. 635, 637 (D. Mass. 1995) ("The
court's inherent power of enforcement, however, is limited to
cases pending before it"). Because the judge here enforced a
prelitigation settlement agreement without an evidentiary
hearing, the Duffs argue that the judge in effect treated the
10
Thus, for example, the Duffs do not challenge the form of
the disposition (a judgment in their favor for the settlement
amount). They seek only to repudiate the settlement agreement
in its entirety.
9
defendants' motion as one for summary judgment and that his
ruling must be reviewed as such.11
Under the circumstances of this case, we agree with the
Duffs that the defendants' motion should be treated as akin to
one for summary judgment. Thus, we review the allowance of the
defendants' motion de novo, to determine "whether, viewing the
evidence in the light most favorable to the nonmoving party, all
material facts have been established and the moving party is
entitled to a judgment as a matter of law." Bank of N.Y. v.
Bailey, 460 Mass. 327, 331 (2011), quoting from Augat, Inc. v.
Liberty Mut. Ins. Co., 410 Mass. 117, 120 (1991).12
2. Merits. The Duffs rest their appeal on two alternative
theories that lie in tension with each other. One is that
because the parties never agreed on a specific date when payment
was due, any agreement they had reached was too indefinite to
constitute an enforceable contract. Without an enforceable
contract in place, they argue, they were free to sue on their
11
The judge did not require the parties to comply with
Superior Court Rule 9A. Although the Duffs touched on that
issue below, they have not pressed it on appeal.
12
"That some facts are in dispute will not necessarily
defeat a motion for summary judgment. The point is that the
disputed issue of fact must be material." Hudson v.
Commissioner of Correction, 431 Mass. 1, 5 (2000), quoting from
Beatty v. NP Corp., 31 Mass. App. Ct. 606, 607 (1991). "A fact
is 'material' only if it might provide a basis for a fact finder
to find in favor of the [nonmoving] party." Liss v. Studeny,
450 Mass. 473, 482 (2008).
10
underlying claims. The Duffs' other theory is that the two
sides reached a fully enforceable agreement on March 21, 2013,
with payment due immediately upon execution of a formal document
memorializing that agreement. According to the Duffs, the
defendants breached the agreement by refusing to make timely
payment, and this breach justified the Duffs in repudiating the
agreement. We address these arguments in order.
a. Whether there was an enforceable settlement agreement.
The legal standard for whether an enforceable agreement has been
reached is well established. "An enforceable agreement requires
(1) terms sufficiently complete and definite, and (2) a present
intent of the parties at the time of formation to be bound by
those terms." Targus Group Intl., Inc. v. Sherman, 76 Mass.
App. Ct. 421, 428 (2010).
There is no suggestion in the record that the parties ever
discussed when payment of the agreed-to settlement amount would
be due.13 To the contrary, each side faults the other for not
raising the issue sooner. However, "the presence of undefined
or unspecified terms will not necessarily preclude the formation
of a binding contract." Situation Mgmt. Sys., Inc. v. Malouf,
Inc., 430 Mass. 875, 878 (2000). The determinative question is
whether the absence of an agreed-upon specific payment date
13
Nor do the Duffs make any claim that they had informed
the defendants that time was of the essence in completing
payment.
11
meant that "significant, material terms were still to be
negotiated." Ibid. If so, then no contract was formed. See,
e.g., Rosenfield v. United States Trust Co., 290 Mass. 210, 216-
217 (1935) (no contract where parties had not agreed on all
material terms). If, instead, the date for payment was a
"subsidiary matter[]" that did not alter the essential nature of
the bargain, then there was a contract that could be enforced
(so long as the parties also intended to be bound at the time an
agreement was reached). McCarthy v. Tobin, 429 Mass. 84, 86
(1999). Where, as here, the negotiations were memorialized in a
trail of uncontested e-mails, whether the parties agreed on all
material terms is treated as a question of law that we review de
novo. Basis Technology Corp. v. Amazon.com, Inc., 71 Mass. App.
Ct. 29, 36 (2008).14 Accord Fecteau Benefits Group, Inc. v.
Knox, 72 Mass. App. Ct. at 212 ("[E]-mail exchanges between the
parties formed a clear and complete agreement . . . [under which
t]he material terms were set and agreed upon").
14
The Duffs cannot create a dispute of material fact by
setting forth their own understanding of when payment would be
due under the settlement agreement. As we recently reiterated
and "Justice Holmes said more than one century ago, a party's
'private understanding or intent' regarding the meaning of a
contract is 'immaterial.'" Chambers v. Gold Medal Bakery, Inc.,
83 Mass. App. Ct. 234, 245 (2013), quoting from Equitable Marine
Ins. Co. v. Adams, 173 Mass. 436, 438 (1899). See Beatty v. NP
Corp., 31 Mass. App. Ct. at 612 ("[C]ontracts rest on
objectively expressed manifestations of intent").
12
The case law recognizes a number of principles that help
inform the analysis of whether an absent term renders an
agreement fatally indeterminate. First, that question is to be
addressed based on the status of things at the time the parties
signaled that an agreement had been reached. See Shea v. Bay
State Gas Co., 383 Mass. 218, 223 (1981), quoting from Bryne v.
Gloucester, 297 Mass. 156, 158 (1937) (contracts should be
interpreted "with reference to the situation of the parties when
they made it"). See also McCarthy v. Tobin, supra at 87-88
(offer to purchase real estate was binding despite subsequent
dispute over entering into purchase and sale agreement). The
fact that the negotiations eventually were scuttled over an
issue does not mean that it necessarily was an essential term of
the settlement.
Second, seeming indeterminacy can be resolved by reference
to professional norms in the practice area in which the
remaining disputes lie (to the extent such norms exist). See,
e.g., McCarthy v. Tobin, supra at 87, quoting from Goren v.
Royal Invs., Inc., 25 Mass. App. Ct. 137, 141 (1987) (fact that
terms of purchase and sale agreement had yet to be negotiated
did not preclude binding agreement based on acceptance of offer
because "norms exist for their customary resolution").
Third, where a written agreement fails to specify a
deadline by which a contractual obligation or right must be
13
exercised, courts may infer that the parties intended a
"reasonable" date if this can be done without changing the
essence of the contract. See Plymouth Port, Inc. v. Smith, 26
Mass. App. Ct. 572, 575 (1988); Middleborough v. Middleborough
Gas & Elec. Dept., 47 Mass. App. Ct. 655, 658 (1999).15 In turn,
"[w]hat is a reasonable period of time depends on the nature of
the contract, the probable intention of the parties, and the
attendant circumstances." Plymouth Port, Inc. v. Smith, supra.
With these principles in mind, we conclude as a matter of
law that the agreement the parties reached in their March 21,
2013, e-mail exchange was not fatally indefinite. See Basis
Technology Corp. v. Amazon.com, Inc., 71 Mass. App. Ct. at 38-39
(concluding that settlement agreement was sufficiently definite
even though it left open specific ratio for converting one type
of stock to another). Indeed, the Duffs themselves maintain,
supported by their counsel's affidavit, that background
professional norms exist through which the specific payment date
could have been determined. Even if resort to professional
norms alone would not have resolved the extraordinarily limited
15
This principle has long been recognized. See, e.g.,
Atwood v. Cobb, 16 Pick. 227, 231 (1835) ("As to the uncertainty
of the time, at which the agreement is to be executed, the case
is clear, that where on an executory contract, a party
stipulates to do some act, and no time is limited, it is to be
done within a reasonable time, and, therefore, the want of any
stipulation to that effect does not render the instrument
void").
14
remaining dispute, this could have been resolved -- without
altering the essential terms of the parties' settlement -- based
on what was "reasonable."16 Therefore, we conclude that the
March 21, 2013, e-mail exchange included "terms sufficiently
complete and definite." Targus Group Intl., Inc. v. Sherman, 76
Mass. App. Ct. at 428.17
To enforce the terms of the March 21 agreement, the
defendants also must demonstrate "a present intent of the
parties at the time of formation to be bound by those terms."
Ibid. This issue requires little discussion. Although the
parties appear to have contemplated that they would memorialize
their agreement in a formal settlement document,18 neither side
16
We note that when the settlement fell apart, the matter
was still in arbitration. The parties presumably could have
sought a speedy resolution of the single remaining issue from
the assigned arbitrator.
17
Because the Duffs have sought to avoid the settlement
agreement, not to enforce it, we need not "fill in the blank" of
when precisely payment had to be completed. Thus, we need not
decide which party had the more compelling claim regarding that
payment date. Moreover, we need not address the Duffs'
contention that resolving exactly when payment was due might
involve factual disputes that fall to a jury to resolve.
Compare Targus Group Intl., Inc. v. Sherman, 76 Mass. App. Ct.
at 431-432 (resolving as matter of law when settlement payment
was due where agreement was ambiguous on that point). See
generally Powers, Inc. v. Wayside, Inc. of Falmouth, 343 Mass.
686, 691 (1962) (determining what is "reasonable" period to
exercise contractual right is generally question of fact, but it
becomes one of law where facts are undisputed).
18
The statement by the Duffs' counsel to the arbitration
coordinator that "I believe the parties are planning on
15
suggested that it would not be bound until that document was
executed. See McCarthy v. Tobin, 429 Mass. at 87, quoting from
Goren v. Royal Invs., Inc., 25 Mass. App. Ct. at 140 ("If . . .
the parties have agreed upon all material terms, it may be
inferred that the purpose of a final document which the parties
agree to execute is to serve as a polished memorandum of an
already binding contract"). Contrast Blomendale v. Imbrescia,
25 Mass. App. Ct. 144, 146-147 (1987) (no enforceable contract
to purchase property where check for buyer's deposit could be
cashed only upon execution of purchase and sale agreement, and
where "sketchy preliminary document . . . . [left] many points
uncovered"). Instead, the Duffs' counsel informed the
arbitrator, without qualification, "that the parties have
reached a settlement agreement." Like a report of a settlement
to a trial court, a report of a settlement to an arbitrator
"presumably comes from careful reflection and contemporaneous
acceptance of an agreement." Basis Technology Corp. v.
Amazon.com, Inc., 71 Mass. App. Ct. at 43. "This court's
decisions have consistently emphasized the qualities of
seriousness and commitment characterizing a settlement agreement
reported to a trial court." Id. at 42. Both parties exhibited
preparing and signing a formal settlement agreement" may cast
some doubt on whether a formal agreement initially was
contemplated. However, if anything, this cuts against the
Duffs' argument that they had not agreed to be bound by a
sufficiently definite settlement agreement.
16
their intent to be bound by the March 21 settlement agreement,
and each party could have enforced that agreement.
b. The Duffs' alternative theory. As noted, the Duffs
alternatively argue that background professional norms establish
that the parties agreed that final payment would be made when
the formal settlement agreement was executed. Based on that
premise, the Duffs contend that the defendants breached that
agreement, and that this breach justified the Duffs in
repudiating the agreement. For purposes of assessing this
alternative theory, we accept arguendo the Duffs' premise that
the defendants were at fault for insisting that they be given
three weeks to complete payment.19 However, this does not in the
end assist the Duffs, because they are seeking to repudiate the
settlement agreement, not to enforce it.
A party to a contract generally is relieved of his
obligations under that contract only when the other party has
committed a material breach, that is, "a breach of 'an essential
and inducing feature of the contract[].'" Lease-It, Inc. v.
Massachusetts Port Authy., 33 Mass. App. Ct. 391, 396 (1992),
quoting from Bucholz v. Green Bros., 272 Mass. 49, 52 (1930).
19
The Duffs highlight that when the agreement fell apart,
eighteen days had already elapsed since the March 21 e-mail
exchange. However, even under the Duffs' own view of the case,
they would not be receiving payment until a formal agreement was
finalized and executed. There was no agreed-upon deadline for
that to occur (only a voiced expectation that finalizing the
agreement likely would take "a week or so").
17
"When a party to an agreement commits an immaterial breach of
that agreement, the injured party is entitled to bring an
immediate action for damages; it may not stop performing its
obligations under the agreement." Lease-It, Inc. v.
Massachusetts Port Authy., supra. "[O]nly a material breach of
a contract . . . justifies a party thereto in rescinding it."
Ibid., quoting from 6 Williston, Contracts § 829 (3d ed. 1962).
For the reasons set forth above, a specific deadline by
which full payment of the settlement sum would be due was not a
material term of the March 21, 2013, agreement. It follows that
even if the defendants' demand that they be given three weeks to
complete payment were considered an actual breach of the
agreement,20 this would not be a material breach, and the Duffs
still would not have been entitled to repudiate the settlement
agreement. Their remedy for such a breach would have been for
enforcement of the agreement and damages (including statutory
20
Arguably, even if the parties had agreed that the
settlement payment would be due immediately upon execution of
the formal settlement document, the defendants still had
committed only an anticipatory breach (for which the remedy
would have been, at most, enforcement of the contract). See
K.G.M. Custom Homes, Inc. v. Prosky, 468 Mass. 247, 253-254
(2014). In K.G.M. Custom Homes, Inc., supra at 249, 253, an
anticipatory breach "morphed" into an actual breach, because the
offending party's efforts to "scuttle the deal" amounted to a
breach of the implied covenant of good faith and fair dealing.
The Duffs have not raised such a claim.
18
interest from the date of the breach).21 The Duffs have not
sought such remedies, seeking instead to avoid the settlement
agreement and to bring their underlying claims. The only remedy
the Duffs have pursued is not available to them.22
Judgment affirmed.
21
The Duffs argue that the defendant materially violated
the settlement agreement by insisting that their interpretation
be accepted before the settlement were implemented. However,
the same logic would apply to the Duffs (who, after all, were
equally insistent that their interpretation be adopted).
22
Because the Duffs' appeal is not frivolous, we deny the
defendants' request for appellate attorney's fees and costs.
GRAINGER, J. (concurring). I agree with the result of the
majority opinion because I conclude that the plaintiffs'
behavior was commercially unreasonable and tantamount to a
breach of the settlement agreement. The protracted nature of
the parties' dispute before they agreed to a settlement is
irrelevant to this appeal. The plaintiffs have raised only two
issues: (1) Whether the payment schedule was a material part of
the settlement, and (2) Whether the defendants breached the
settlement agreement.
In the absence of a stipulated time for payment and without
even a standard provision that "time is of the essence," the
parties had an obligation to perform within a reasonable time.
The defendants' offer to pay $17,500 at the time of signing the
settlement agreement and to remit the balance of $10,000 within
three weeks was reasonable under any recognizable standard of
commercial dealing.
The payment schedule offered by the defendants cannot
sensibly be characterized as a material departure from the
settlement terms. The use of $10,000 for twenty-one days had an
arguable value between $7.77 and $18.95 at the time in question.1
1
The United States Treasury Department set the Federal
Reserve Prime Interest Rate at 3.25% throughout 2010. See
http://www.federalreserve.gov/releases/H15/data.htm
[https://perma.cc/AZ7B-CHH3]. Application of this rate is
generous to the plaintiffs, as many market rates, including
2
The offer to pay the second installment within three weeks thus,
at most, can be claimed to have reduced the value of the $27,500
settlement by between .0003 and .0018 (.03% and .18%).
I am unpersuaded by the assertion that requiring the
plaintiffs to execute a signed copy of the previously negotiated
agreement including the defendants' proposed payment schedule
was a repudiation of the settlement. For whatever reason, the
intended execution of a signed copy of the agreement had been
subject to delay.2 The defendants' manifest desire was to
confirm, not repudiate, the agreement. If the plaintiffs
desired to quibble over the point they were required to counter
the proposed payment schedule with a different, but also
reasonable, proposal. While such an exchange might eventually
have resulted in unraveling the agreement, the alacrity with
which the plaintiffs demanded an additional $2,500 and then
filed suit on the following day suggests strongly that the
defendants' desire to secure the plaintiffs' signature on the
existing agreement was based on a legitimate concern, accurately
perceived.
regulated benchmarks (e.g., rates applied to unpaid taxes),
reduce that rate by 200 basis points, in this case to 1.25%.
2
The plaintiffs' counsel expressed concern during the
period of delay that he did not "want to give the clients too
much time to rethink this." Subsequent events have justified
this remark.