Big Rock Stone Material v. U.S. Fid. Guaranty

Appellant brought suit on October 21, 1931, against appellee in the circuit court of Pulaski County, Second Division, upon a surety bond to recover $1,188.40, with interest, for stone furnished by it to McWilliams Company, Inc., to complete certain work it had undertaken to do for Farelly Lake Levee District under written contract executed on July 21, 1926. The bond, made the basis of the action, is as follows:

"Whereas, Geo. C. Lewis and A. Lawrence Mills, receivers for the Farelly Lake Levee District of Arkansas and Jefferson counties, Arkansas, have on this date entered into a construction contract with McWilliams Company, Inc., for the performance of certain work, as shown by the supplemental contract attached hereto, and

"Whereas, said McWilliams Company, Inc., have agreed to execute a surety bond in the sum of fifty thousand dollars to guarantee the faithful performance of said supplemental contract;

"Now therefore we, the undersigned, McWilliams Company, Inc., as principal, and the United States Fidelity Guaranty Company, a corporation, as surety, hereby acknowledge ourselves indebted to the State of Arkansas for the use and benefit of Farelly Lake Levee District of Arkansas and Jefferson counties, in the sum of $50,000 that the said McWilliams Company, Inc., a corporation, shall well and truly perform all and singular the several respective agreements set out in the supplemental contract made on this the 20th day of October, 1928, by and between the said Geo. C. Lewis and A. Lawrence Mills, as receivers of Farelly Lake Levee District of Arkansas and Jefferson counties, a copy of which agreement is hereunto attached and made a part hereof.

"Now, if McWilliams Company, Inc., a corporation, well and truly perform said agreement, this bond to be *Page 907 null and void; otherwise, it is to remain in full force and effect from now and after this date.

"Witness our hands and seal of said corporation on this 20th day of October, 1928.

"McWilliams Company, Inc., a Corporation, "By R. H. McWilliams, Jr., President, Principal, "United States Fidelity Guaranty Company, a Corporation, "By Wylie B. Miller, Surety."

The supplemental contract attached to said bond is as follows:

"This agreement made and entered into on this 20th day of October, 1928, by and between Geo. C. Lewis and A. Lawrence Mills, as receivers of Farelly Lake Levee District of Arkansas and Jefferson counties, Arkansas, parties of the first part, hereinafter referred to as receivers, and McWilliams Company, Inc., second parties, hereinafter referred to as contractor, witnesseth:

"1. That contractor hereby agrees with said receivers to complete the floodgates, point up the walls, and clean off floors as provided by a certain contract now existing between said Levee District and second parties, on or before November 15, 1928.

"2. That contractor hereby agrees with said receivers to reconstruct or repair Fin Wall No. 2, which is now cracked, so as to make it meet with the requirements of the plans and specifications governing said work under the original contract, which work is to be performed and completed on or before December 1, 1928.

"3. That contractor hereby agrees with said receivers to install and complete the rip rap stone work in accordance with the requirements of the plans and specifications governing said work under the original contract on or before December 15, 1928.

"4. That contractor hereby agrees with said receivers to construct the inlet and outlet channels to the *Page 908 floodgates in accordance with the plans and specifications governing said work under the original contract, which inlet and outlet are to be completed on or before December 31, 1928.

"5. Contractor hereby agrees to execute and deliver surety bond executed by a reputable surety company in the sum of $50,000 to guarantee the faithful performance of the above conditions, which bond is to be delivered in five days.

"6. Receivers hereby agree that upon receipt of said bond they will execute and deliver necessary papers accompanying engineers' estimate covering all work performed to date, in order to obtain voucher for said estimate out of the Federal court at Little Rock, Arkansas.

"7. Receivers hereby agree that hereafter they will cause semimonthly estimates to be made on or before the 5th or 20th of each month, which estimates are to be paid in cash as the work progresses, until the cash is exhausted and then to make suitable arrangements for the payment of any balance, which arrangement is to be agreed upon mutually between the parties, the parties now contemplating the use of receivers' certificates, if permissible.

"8. This agreement and contract is intended to operate as a supplemental contract to the original contract, dated July 21, 1926, between Farelly Lake Levee District of Arkansas and Jefferson counties, Arkansas, and McWilliams Company, Inc., and is not intended to cancel, set aside or modify said contract in any manner except as herein set forth.

"Witness our hands on this the 20th day of October, 1928.

"Geo. C. Lewis, "A. Lawrence Mills, receivers, "Parties of First Part, "McWilliams Company, Inc., "Party of Second Part."

In defense to the action, appellee pleaded a settlement and complete release from liability under the bond *Page 909 by the receivers of the Farelly Lake Levee District and the statute of limitations as a bar to appellant's right to recover on the bond.

The cause was submitted to the court, sitting as a jury, upon the issues joined, testimony showing that the stone was furnished to McWilliams Company, Inc., and used in the construction of the work, the original and supplemental contracts, and the following stipulation and receipt:

"STIPULATION

"It is hereby stipulated and agreed by and between Chas. A. Walls, attorney for plaintiff, and O. E. Williams and W. M. Hall, attorneys for defendant, in the foregoing entitled cause of action, that:

"1. That McWilliams Company, Inc., became insolvent and went into the hands of receivers on the first day of March, 1929, and that the receivers for McWilliams Company, Inc., elected not to proceed with the performance of the contract, and abandoned the contract that McWilliams Company, Inc., had with Farelly Lake Levee District of Jefferson and Arkansas, for the construction of certain works, including the floodgates in said district.

"2. That the receivers of Farelly Lake Levee District, obligees on the bond, on or about March 10, 1929, took over the work and thereafter completed the work called for by the supplemental contract on or about December 12, 1929, at a cost exceeding the contract price by $15,398.04. There was included in said amount as part of the cost of completion additional engineering services of Ayres Miller, engineers, amounting to $2,550, and the cost of leasing rails for a tramway needed in connection with the work from St. Louis Southwestern Railway Company, amounting to $858.29; and the cost of leasing right-of-way for the tramway from C. F. Rose, amounting to $50, and the receivers, having exhausted their available cash, requested United States Fidelity Guaranty Company to pay those amounts to said parties pending final settlement with the receivers, which said guaranty company did. *Page 910

"3. That the receivers thereafter made demand upon said United States Fidelity Guaranty Company under its bond for payment of the balance of $11,939.35, and said guaranty company, on April 9, 1930, paid said amount, and said receivers thereupon executed the receipt exhibited with the guaranty company's answer herein.

"4. It is further agreed that the receipt exhibited to the answer, dated April 9, 1930, is a true and exact copy of the original executed by the receivers of said district.

"5. It is further stipulated and agreed that this stipulation may be read in evidence on behalf of either party desiring to introduce same in the record.

"(Signed) Chas. A. Walls, "Attorney for Plaintiff, "(Signed) Wm. M. Hall, "O. E. Williams, "Attorneys for Defendant."

"RECEIPT

"Received of the United States Fidelity Guaranty Company eleven thousand nine hundred and thirty-nine dollars and seventy-five cents ($11,939.75) which with two thousand five hundred and fifty dollars ($2,550) paid to Ayres Miller, engineers, covering balance due them as engineering fees, eight hundred and fifty-eight dollars and twenty-nine cents ($858.29) paid to the St. Louis Southwestern Railway Company covering amount due for lease of rails, and fifty dollars ($50) to C. F. Rose, covering amount due for lease of right-of-way is in full settlement, satisfaction and discharge of all liability of McWilliams Company and the United States Fidelity Guaranty Company, its surety, under and by reason of a certain contract and bond executed on or about October 20, 1928, designated as supplemental contract to original contract of McWilliams Company dated July 31, 1926. *Page 911

"Witness our hands this the 9th day of April, 1930.

"Geo. C. Lewis (s) and "A. Lawrence Mills, receivers (s) "Farelly Lake Levee District."

The court found against appellant and dismissed its complaint, from which finding and judgment an appeal has been duly prosecuted to this court.

Appellant contends that the trial court should have held, and this court ought to hold, that the bond sued on is a special bond which, in terms, guarantees the payment of all materials furnished and used by the contractor in completing the improvement. We are unable to discover any language in the bond itself which would warrant any such interpretation even from inference. It cannot be gleaned from the language used that the bond was intended to be a statutory bond; so we would not be justified in reading the statute, 6913 of Crawford Moses' Digest, into the bond; but, if it were possible, by a strained construction, to do so, it would and could not afford any relief to appellant because, if aided by the statute invoked, its right of action would be barred. Section 6914 of Crawford Moses' Digest bars rights of action on bonds for materials furnished if not brought within six months after the completion of the improvement. Appellant argues that it brought the suit for materials furnished within six months after the improvement was completed, but the agreed statement of facts and the receipt show otherwise. According to the agreed statement of facts and the receipt referred to, the work contemplated by the supplemental contract was completed on December 12, 1929, and this suit was not commenced until October 21, 1931.

The trial court was correct in finding that the bond afforded no protection to appellant; hence the judgment is affirmed. *Page 912