Appellee brought suit against appellant in the chancery court of Mississippi county, Chickasawba District, to recover $15,000 for anticipated profits and for money earned under the contract for clearing the right-of-way of a drainage district, alleged to have been wrongfully annulled by appellant. The jurisdiction of the court was not questioned, presumably for the reason that the issue between the parties involved an intricate accounting. Appellant filed an answer to the bill, denying the material allegations therein, and a cross-bill seeking to recover $4,511.08 alleged to have been advanced by appellant to appellee in excess of the contract price upon work performed by said appellee.
Appellee filed answer to the cross-bill, denying the material allegations therein, and the cause was submitted by consent to the court in vacation upon the pleadings and testimony. The court found it necessary, under his view of the law applicable to the facts in the case, to refer the matter to a special master for a statement *Page 751 of account between the parties, in accordance with declarations of law announced by the court. Hon. Archer Wheatley, an ex-chancellor of broad experience, was appointed special master, with directions to consider the testimony already taken and such additional proof as might be offered by the parties. In conformity with the declarations of law, the special master carefully reviewed the evidence, which is too voluminous to set out even in substance in this opinion, and filed an itemized report showing a net balance due from appellant to appellee for work actually performed under the contract of $1,987.66.
Three specific exceptions were filed to the report of the master as follows:
"First: The master's report shows the amount cleared May 13, 1921, as shown by the defendant's exhibit No. 30, to have been 153.98 acres. This should have been 152.93 acres.
"Second: The special master credits the plaintiff with the difference between the work 40 percent complete, as shown by exhibit 30, and 50 per cent., as shown by testimony of witness Cohen to have been paid for by the district. This finding is erroneous for the reason that the witness Cohen's testimony relates to payments made by Sternberg Dredging Company for the construction of the muck ditch on the area of improvement No. 28, and there is no testimony upon which the special master could base this finding as to this item.
"Third: The special master credits plaintiff with the sum of four hundred thirteen dollars and sixty cents ($413.66), which he says is the amount paid by plaintiff on what is known as the Laxon camp. Testimony with respect to this showed that, if any payments were made, same were made a considerable time after the breach of contract herein, and defendants would not be properly chargeable therewith.
"Wherefore defendants pray that said sums be stricken out and said report be restated, and for all proper and equitable relief." *Page 752
On February 3, 1925, the cause was finally heard by the court on the report of the special master and exceptions thereto, which resulted in an approval of the report and the rendition of a decree against appellant for $2,405.50, including interest, from which is this appeal.
Appellant contends for a reversal of the decree upon the three following grounds:
First, that appellee was overpaid by appellant in the sum of $3,579.59.
Second, that the special master erroneously included the credits set forth in subdivisions B and C of paragraph 2 of his report.
And third, that the decree of the chancery court rendered in accordance with the terms of the report of the special master was erroneous.
(1) We have determined that the court correctly declared the law relative to the work actually, done under the contract, and agree with the master and, the chancellor that appellant had not overpaid appellee. Over payments for work actually done were not embraced in the exceptions to the master's report, and, after a very careful examination of the evidence, we are not able to discover where the advances exceeded the estimates.
(2): The objection to appellee's allowance of 5.75 acres additional between stations 202 to 226, 233 to 265, and 280 to 350, at $70 per acre, is that the master allowed and the chancellor approved it upon the misconception that witness Cohen testified that the clearing between the stations referred to had been cleared 50 per cent. instead of 40 per cent. Appellant is correct in his assertion that witness Cohen did not testify relative to the percentage of clearing between the stations, but incorrect in its contention that the master based his finding on Cohen's testimony. On the contrary, the master based his finding upon the fact that appellant exhibit 30 shows that the clearing of the right-of-way between, said stations had been completed between forty and fifty per cent. The finding of the master as to this item was therefore supported by the evidence. *Page 753
The objection to appellee's allowance of $413.60 for clearing at Laxon camp is that the work was done after the contract was terminated in August, 1921. In the first place, considerable work was done and accepted after appellant notified appellee that the contract had been breached by failure to give bond, and, in the next place, for aught that the record discloses, the work may have been done before the notice was given and paid for by appellee in November and December, 1921. Appellee did not testify when the work was done, but said that expenditures in that amount were made by him in November and December, 1921, for work performed at said camp. It was impossible to determine the exact acreage or percentage of clearing done at the Laxon camp, so the master only allowed appellee for the amount he was actually out. This allowance was more favorable to appellant than it was entitled to, since labor was cheaper when the work was done than when the contract was entered into. There is testimony therefore in the record to support the finding of the master.
(3). Our construction of the testimony convinces us that the decree is supported by the weight of the evidence.
This brings us to a consideration of whether appellee is entitled on his cross-bill to profits which he would have made had he been permitted to fulfill his contract. The contract provided for clearing 345 acres of right-of-way at $70 an acre. Appellee cleared 159.73 acres, when he was compelled to quit because he did not execute a bond with security. The contract contained the following provision for a bond:
"Second party (appellee) hereby agrees to furnish reliable personal or surety bond equal to the sum of thirty (30) per cent. of the total amount of this contract, to guarantee the faithful performance of his work."
This bond was never given, and not tendered until seven days before appellee instituted his suit, which was several months after appellant notified appellee not to proceed further under the contract on account of his *Page 754 failure to give the bond. We think the provision for a bond was mandatory, and that appellee was bound to give it unless waived by appellant. Appellee contends that appellant waived its right to the bond because it permitted him to work, furnished him estimates, and made payments under the contract for more than a year without requiring him to execute it. The record reflects that, although permitted to work under the contract for the time mentioned, appellant continually insisted by word and letter upon appellee executing the bond. Under these circumstances, it cannot be said appellant waived its right to the bond.
No error appearing, the decree is affirmed.