On Rehearing. In our original opinion, we concluded that, since the plans and specifications prepared by the city engineer were insufficient and defective in that no provision was made for stabilizing the sewer pipe *Page 910 laid by the contractor when unstable conditions in the soil would be encountered preventing the laying of the pipe to grade, the city was liable, and the contractor was entitled to recover, since he performed his obligation strictly in accordance with such plans and specifications, and that under these circumstances the case was controlled by the doctrine announced in United States v. Spearin, 1918, 248 U.S. 132, 39 S.Ct. 59,63 L.Ed. 166. Furthermore, with reference to the Wise Street job, we again applied the doctrine of the Spearin case, and in addition concluded that the refusal of the acting city engineer to issue a written order for the extra work was purely arbitrary and unreasonable, and that under these circumstances the contractor could recover for this work notwithstanding the fact that no written order was issued as required by the contract.
As pointed out in the original opinion, Brasher, the contractor, bound himself to furnish "all material and labor and construction complete of an extension of the municipal sanitary sewer system of the City of Alexandria" under certain terms and conditions as quoted and set forth in the original opinion. The specifications under the title "Final Acceptance" provided that the contractor before tendering the work for final acceptance should go over and clean up the entire line of work, restore all streets, etc., and that "He shall flush and clean all sewer lines, correct any *Page 911 deficiencies existing in the sewers, manholes or otherappurtenances, and put the entire system in working condition. This having been done, and upon notification from the Contractor that it is ready for final inspection, the Engineer will examine and test the work, and if he shall find it to be properly constructed, and in accordance with the plans, specifications, and contract, he will so report to the Mayor and Council, and the work may then be finally accepted." (All italics ours.)
In the instant case, there have never been a completion and a final acceptance of the work as contemplated by the contract. The contractor did not correct the deficiencies in the sewer or put the entire system in working order. It is true that the acting city engineer in a letter to the contractor passed the work, but, before final acceptance by the city as contemplated by the contract, the defective condition of the sewer line was discovered, and thereafter the city, so that a settlement might be made with the Federal Works Agency, which was furnishing a portion of the funds for the work, adopted a resolution of conditional acceptance, authorizing the mayor to sign a notice of conditional acceptance of the work. This notice contained the following language: "The above acceptance is without prejudice to any of the rights of the City of Alexandria to recover damages against the said Contractor for failure to comply with the terms of his contract or to maintain any claim against him for defective materials *Page 912 or workmanship or for any other items for which he is responsible under the terms of the contract, the City hereby reserving all rights against him and his bondsmen for violation of or failure to comply with the terms of said contract in any respect or any amendments, alterations or additions legally made thereto."
As pointed out, prior to this conditional acceptance, the deficiencies in the sewer system had been discovered, but had not been corrected as required by the contract.
During the course of construction the contractor, Brasher, concluded that it was impossible to proceed with the work due to a soil condition which he had encountered which made it impossible to lay the pipe to grade as required in the specifications, as follows: "Special care must be taken to lay the pipe to the exact line and grade." Upon encountering this condition, the contractor requested of the city proper instructions as to how to stabilize the trench so that the pipe might be laid to grade. The city took the position that this was his responsibility and refused to issue a written order specifying the type of cradling necessary to lay the pipe to grade, because such authorization would have bound it for the expense of the cradling as extra work. He then proceeded, without written authorization from the city, to lay the sewer pipe, using boards to stabilize or bring the pipe to grade because it was impossible to lay the pipe to grade without some kind of stabilization. *Page 913 There is evidence that the contractor's foreman was informed by a city inspector that it was not proper to bring the pipe to grade by the use of boards, but the foreman informed the inspector that the bringing of the pipe to grade was their worry, and that "We will put what we want to under there". Brasher denies this, contending that no objection was made by the city to the use of boards. However, we do not think the record supports his contention.
The record discloses that the contractor, Mr. Brasher, had been doing sewer and similar construction work for a period of 46 years, and that he assisted in the construction of the first sewer in Alexandria, and, at the time he undertook the present contract, was engaged in the construction of a sewer system for an army comp near Alexandria. There is no doubt whatsoever that he is an expert in such construction work. He himself testified that, in his opinion as such an expert, the proper method to use in bringing the pipe to grade where unstable soil conditions existed was to cradle it in concrete, preferably, or, as a second choice, in clam shells, or, as a third alternative, in wash gravel, and that good engineering practice would not sanction the use of boards for this purpose. Notwithstanding this opinion, he used boards to stabilize the trenches.
On February 15, 1944, during the course of construction, the contractor wrote a letter to the City of Alexandria in which *Page 914 he had this to say with reference to soil conditions:
"The specifications covering this construction state that `The excavation at the bottom is to be made in shape, or as nearly as practicable, to fit the lower half of the pipe to be laid, with holes cut out at the joints for the sockets to rest in so that the pipe shall have a uniform bearing on the ground from end to end.' Soil conditions in the trench bottom have been encountered which will not permit compliance with this section of the specifications and unless a pipe bed of some type is placed, the full strength of the pipe will not be developed. The pipe willnot hold its grade and alignment after backfilling and inaddition, failure may occur from improper bedding.
"Request is hereby made that necessary change order be issued for placing a cradle under the pipe until trench bottom conditions improve to a point where the cradle is unnecessary. The decision concerning the type of cradle to be used rests with your engineering department, and the additional cost for placing it cannot be agreed upon until its specifications are known.
"Unless you instruct me to place the cradle, or otherwise improve the bedding, at an additional cost, I, hereby, disclaim responsibility for the alignment, grade, or failure of the sewer when constructed under the existing trench bottom conditions." *Page 915
There is no doubt that the contractor realized that it was his obligation under the contract to lay the pipe to grade, and, further, there is no dispute that the proper or best method to do this under the existing soil conditions was to use a concrete cradle, or, to say the least, a cradle of clam shells or of sand and gravel, and that good engineering practice would not sanction the use of boards. The contractor himself recognized that, by improper bedding, the very thing might happen that did happen, that is, a failure in the sewer line itself. His refusal to place a proper cradle under the pipe was caused solely by the fact that he did not want to bear the extra expense thereof.
Under these circumstances, was he relieved of his obligation under the contract to correct the deficiencies and put the sewer in working order, when the sewer line failed or became defective prior to final acceptance by the city? We think not.
In our original opinion we recognized the general rule of law to be that, where one agrees to do for a fixed sum a thing possible to be performed, he will not be excused or become entitled to additional compensation because unforeseen difficulties are encountered. O'Leary v. Board of Port Com'rs for Port of New Orleans, 150 La. 649, 91 So. 139; Picard Const. Co. v. Board of Com'rs of Caddo Levee Dist., 161 La. 1002,109 So. 816; Jung et al. v. Gwin. 174 La. 111, 139 So. 774. See also *Page 916 6 Williston on Contracts, Rev.Ed., sec. 1964, p. 5512. The contractor is also liable if the building or work is destroyed before completion. This liability is expressed in our Code as follows: "When the undertaker furnishes the materials for the work, if the work be destroyed, in whatever manner it may happen, previous to its being delivered to the owner, the loss shall be sustained by the undertaker, unless the proprietor be in default for not receiving it, though duly notified to do so." C.C. Art. 2758.
The contractor, Brasher, recognizes these general principles of law, but contends that they do not apply when a contractor performs in accordance with plans and specifications furnished by the owner. He takes the position that he constructed the sewer line strictly according to the plans and specifications furnished by the owner, the city, and that due to the inadequacy and insufficiency of these plans and specifications the sewer failed, and that he is not responsible for such failure in the sewer system and is therefore entitled to recover the full contract price, together with an additional amount to cover extra work in connection with the Wise Street job.
The contention of the contractor would be well founded if his defective performance was caused by inadequate or insufficient plans and specifications, the sufficiency of which had been expressly or impliedly warranted by the owner which furnished them. *Page 917
The general rule is that, if destruction of a work during the course of construction is caused by defective, inadequate, or insufficient plans and specifications furnished by the owner, the contractor is nevertheless liable. Dermott v. Jones, 2 Wal. 1, 17 L.Ed. 762; Stees et al. v. Leonard et al., 20 Minn. 494; Magnan Co. v. Fuller et al., 222 Mass. 530, 111 N.E. 399; Lonergan et al. v. San Antonio Loan Trust Co., 101 Tex. 63,104 S.W. 1061, 106 S.W. 876, 22 L.R.A., N.S., 364, 130 Am.St.Rep. 803; Board of Education of City of Millville v. Empire State Surety Co. of New York et al., 83 N.J.L. 293,85 A. 223. An exception to this rule is recognized where the owner expressly or impliedly warrants the sufficiency of the plans furnished by him. United States v. Spearin, supra; Passaic Valley Sewerage Com'rs v. Tierney, 3 Cir., 1 F.2d 304; Kinnear, Inc., v. City of Lincoln Park et al., 260 Mich. 250,244 N.W. 463.
In Lonergan v. San Antonio Loan Trust Co., supra, the problem of liability for defects in plans and specifications furnished by the owner was explored fully. In that case the contractor contended that the destruction of the building was caused by defects in the specifications furnished by the owner, and that the owner expressly guaranteed the sufficiency of the specifications, and that, if the guaranty was not express, the terms of the contract were such that the law should imply a guaranty in favor of the contractor. What the court *Page 918 said in regard to those contentions is pertinent here [101 Tex. 63,104 S.W. 1066]:
"* * * We have not been able to find, from a careful examination of the contract and specifications, any terms used therein from which we think there could by any fair construction arise by implication a guaranty of the sufficiency of the specifications, and no such clause has been pointed out.The plaintiffs in error [the contractor and the surety]claim that this can be derived from the fact that the architectis to have supervision and control of all the work and othercircumstances of that character; but these are provisions simplyfor the protection of the owner, who was represented in theexecution of the work by the architect, while the builderrepresented himself. We are of the opinion that Thos. Lonergan Co., having failed to comply with their agreement to constructand complete the building in accordance with the contract andthe specifications, must be held responsible for the loss,notwithstanding the fact that the house fell by reason of itsweakness arising out of the defects in the specifications andwithout any fault on the part of the builder. Dermott v. Jones, 2 Wall. 1, 8, 69 U.S. 1, 17 L.Ed. 762; School Dist. No. 1 v. Dauchy, 25 Conn. [530], 535, 68 Am.Dec. 371; Superintendent etc. of Public Schools of City of Trenton v. Bennett, 27 N.J.L. 513, 72 Am.Dec. 373; Clark v. Pope, 70 Ill. [128], 133. *Page 919
"Counsel for plaintiffs in error have cited many cases in which the courts have said that the builder or contractor does not guarantee the sufficiency of the specifications. It is acorrect proposition, because the specifications are, as a matterof law, not guaranteed by either party to the other. In the cases cited, we believe that without exception the contractor had performed his work according to the terms of his agreement and had fulfilled his contract by finishing the structure, terminating his relation as contractor, after which the house was destroyed by some accident or calamity, or had fallen from some defect or weakness in the structure or fault of the soil, and in such cases the courts have held that the contractor does not guarantee the sufficiency of the specifications, but only the skill with which he performs his work and the soundness of the material used therein. He is therefore not liable for the destruction of the building after he has performed his agreement by completing the structure. Clerk v. Pope, 70 Ill. [128], 132. It has been just as uniformly held, however, that whenever the building or structure has been destroyed by reason of any defect in the work done, or by any accident or any means whatever before the contract has been completed, then the contractor must bear the loss, no matter what might be the occasion thereof, unless it be some wrong done by the owner subsequent to the making of the contract which caused the fall. Liability of the builder *Page 920 does not rest upon a guaranty of the specifications, but upon his failure to perform his contract to complete and deliver the structure."
In Magnan Co. v. Fuller et al., supra, where the contractor was bound to build according to plans and specifications furnished by the owner, the court found no circumstances in the record which would constitute an implied guaranty of the plans by the owner. The court said there:
"* * * When one enters into a contract with a builder to erect a structure in accordance with plans and specifications, which are open to inspection, without express provision touching the subject, there is no implied warranty or agreement on the part of the owner in the absence of circumstances which by necessary intendment are the equivalent of a warranty or agreement, that the work can be done according to the plans and specifications, or that, if so done, it will be safe. It is the duty of one, who proposes to enter into a building contract to examine the contract, plans and specifications, and to determine whether it is possible to do the work before entering into the engagement, or to insist upon some stipulation covering that matter. If, without a special agreement upon that point, he makes a general contract without fraud or mutual mistake, he has bound himself to do the work. If it turns out that he has agreed to do something which is impossible or impracticable, he cannot for that *Page 921 reason alone refuse to go forward. Having made his contract, he must fulfill it or bear the consequences of a breach. * * *
"The contract in the case at bar is simple, direct and unequivocal. It contains no stipulation on the part of the committee that the grand stand could be completed or that it would be safe when completed. There are no circumstances revealed in the record which constitute an implied guaranty to this effect. The undertaking of the contractor is unqualified that he will complete the grand stand `in accordance with the plans and specifications.' The evidence offered and excluded constituted no excuse for failure to perform the contract."
Williston, a well recognized authority on contracts, states and discusses this rule and its exception as follows:
"Even though the plans upon which a contractor undertakes to construct a building are so defective as to cause the building to fall while in course of erection, he is not generally relieved from liability.
"The propriety of these decisions depends upon the questionwhether the owner can be regarded as warranting the sufficiencyof the plans. If the owner through his architect or engineer can be regarded as having superior expert knowledge, and on the basis of such knowledge to represent to the builder the feasibility of carrying out the plans, the owner must be held responsible for the consequences of any defects in them. In ordinary cases, perhaps, *Page 922 the builder may be supposed to have sufficient knowledge of what is feasible to make unfounded the assumption of justifiable reliance by him on the superior knowledge of another; but where the work in question involves technical engineering skill, and the plans are made by expert professional men engaged by the owner, there seems good reason for implying a warranty.
"Though the builder may be liable if he fails, by reason of defective plans furnished him, to complete work which he has undertaken, yet if he can and does complete it according to the plans he is not liable for subsequent inferiority, injury, or destruction of the work, due to the defective character of the plans." 6 Williston on Contracts, Rev.Ed., sec. 1966, pp. 5515-5518. See also Berick, Warranties in Building Contracts, 6 U.Cin.L.Rev. 121; Note 21, Minn.L.Rev. 70.
In the instant case, it is true that the city did have the benefit of expert engineering advice both in the preparation of the plans and specifications and in the supervision of the work, but at the same time Brasher, the contractor, was an expert himself in the construction of sewer lines, and was assisted therein by superintendents and foremen who were expert and professional men with many years' experience. It therefore cannot be said that the city had superior expert knowledge at its disposal. The plans themselves did not purport to be extensive and minutely detailed as to the method of laying the pipe to grade, and *Page 923 thus did not purport to cover every contingency. In the plans and specifications, the city made no representation, expressly or otherwise, that soil conditions would not be encountered which would present difficulties in laying the pipe to grade, nor was there contained therein any representation that any particular type of construction would take care of difficulties encountered in the soil. It is not contended that the owner had any actual knowledge of the faulty condition of the soil which it withheld from the contractor. On the other hand, the contractor was required to examine the site and to inform himself fully of the conditions relating to the construction and labor under which the work was to be performed, and in his proposal, accepted by the city, he stated that he had examined the site.
In soliciting bids for the construction of the sewer line, the city of Alexandria in Section 7 of its "Information for Bidders", styled "Examination of Site", stipulated that all bidders were required to inform themselves fully of the conditions relating to the construction and labor under which the work would be or was then being performed, and in the proposed schedule signed by plaintiff, the contractor, and submitted to the city, which was accepted, the contractor stipulated: "The undersigned hereby declares that he has visited the site and has carefully examined the Contract Documents relating to the work covered by the above bid or bids." Notwithstanding that all bidders for this job were required *Page 924 to examine the site, and that Brasher, as the successful bidder, declared that he had visited the site, Mr. Harold Miles, acting engineer for the city, testified without contradiction that he asked Mr. Bowdon, manager for plaintiff, whether he was going to make borings along the sewer line to determine what kinds of soil would be encountered so that proper preparations could be made, and that Mr. Bowdon stated that no such borings had been made, and that the soil conditions would be ascertained as the trench was dug.
The record discloses that, when unstable soil conditions were encountered, all parties realized and knew that cradling was necessary to stabilize the pipe for the completion of the sewer, and the contractor knew the best manner of stabilizing the trench bottom and the proper method of preparing the cradling for this purpose. Therefore, the difficulty encountered did not involve any work requiring technical engineering skill not possessed by the contractor.
In the instant case, although the city furnished the plans and specifications, it did not in any manner expressly warrant the sufficiency thereof, nor do we find, after a consideration of all the facts and circumstances, any implied warranty as to their sufficiency. Even the fact that the work was done under the supervision of the owner does not, of itself, imply a warranty. See Lonergan et al. v. San Antonio Loan Trust Co., supra. See also Berick, Warranties in Building Contracts, loc. cit *Page 925 supra, p. 132. In the absence of any such warranty, express or implied, the contractor was obligated under his contract to construct the sewer line complete, to correct any deficiencies therein, and to put the entire system in working order prior to final acceptance by the city. The city therefore properly deducted the item of $13,588.45, the cost of repairing the sewer, from the balance due on the contract, and properly refused to pay the item of $3060.98 for the work in repairing the Wise Street sewer extension.
Our original opinion in this case was based principally upon the doctrine announced in the cases of United States v. Spearin, supra, and Louisiana Shipbuilding Co. v. Bing Dampskibsaktieselskab, 158 La. 548, 104 So. 364. A further study of these cases has convinced us that the doctrine announced therein has no application in the instant case, and is not controlling here.
For instance, in the Spearin case the contractor agreed to build a dry dock according to plans and specifications which had been prepared by the government. The site of this dry dock was intersected by a six-foot brick sewer, and it was necessary to divert and relocate a section thereof before the work of constructing the dry dock could begin. The plans and specifications provided that the contractor should do the work, and prescribed the dimensions, material, and location of the section to be substituted. Both before and after diversion *Page 926 of the six-foot sewer, it was connected with a seven-foot sewer. All of the prescribed requirements were fully complied with by the contractor. About a year after its relocation, the six-foot sewer broke in several places as a result of internal pressure, and the excavation of the dry dock under construction was flooded. There was a dam, from five to five and one-half feet high, in the seven-foot sewer with which the relocated sewer was connected. During a heavy rainfall and high tide, the presence of this dam forced the water up the six-foot sewer as thus constructed, and caused it to break, as hereinabove set forth. The dam which obstructed the seven-foot sewer was not shown either on the city's plans of the sewer system or on the United States government's plans and blue prints which were submitted to the contractor, but, on the contrary, on the government's plans the seven-foot sewer appeared as unobstructed. Under these circumstances, the Supreme Court of the United States in holding the government liable found that there was an impliedwarranty to the effect that, if the specifications were complied with, the sewer as thus relocated would prove adequate. In that case the plans and specifications prescribed the dimensions, material, and location of the six-foot sewer, which provedinadequate. In the course of the opinion the court said:
"But the insertion of the articles prescribing the character, dimensions and location of the sewer imported a warranty *Page 927 that if the specifications were complied with, the sewer would beadequate. * * * The obligation to examine the site did not impose upon him [the contractor] the duty of making a diligent inquiry into the history of the locality with a view to determining, at his peril, whether the sewer specifically prescribed by the government would prove adequate."
In the Spearin case, there was an implied warranty, which we do not find in the instant case, that, if the sewer were constructed pursuant to the plans and specifications prepared by the government, it would prove adequate, and these plans and specifications prescribed and set forth with exactness the character, dimensions, and location of the sewer to be relocated.
Under the facts and circumstances of the Spearin case, the court very properly found that there was an implied warranty of the plans, but in the course of the opinion pointed out that "The risk of the existing system proving adequate might have rested upon Spearin [the contractor], if the contract for the dry dock had not contained the provision for relocation of the six-foot sewer."
In the Louisiana Shipbuilding Co. case, supra, the builder agreed to build certain ships according to plans and specifications furnished by a steamship company. The contract, immediately after the stipulation that the ships would be built to such plans and specifications, contained a provision that the vessels should be constructed according *Page 928 to the requirements of American record to class A No. 1 for ocean-going vessels. The ships were built according to the plans and specifications, but did not class A No. 1 for ocean-going vessels according to the requirements of the American Bureau of Shipping, and the question was whether the builder or the steamship company was responsible for the failure. In holding the liability to be on the steamship company, this court said in the course of its opinion in that case [158 La. 548,104 So. 365]: "Both parties to the contract believed that the ships, when completed, would be approved by the American Bureau of Shipping, to class A No. 1 for ocean-going vessels, if built according to the plans and specifications that had been approved by the bureau's chief inspector, and especially when built under the direct observation and inspection of the bureau's local inspector. The builder had no right to deviate from the plans or specifications that had been furnished by the steamship company or to deviate from the working plans or instructions that were given by the steamship company's draftsman as the work progressed. The double requirement in the contract that the ships should be built to the plans and specifications annexed to the contract, and that they should `be constructed according to the requirements of American record to class A No. 1 for ocean-going vessels', did not make the builder a warrantor thatthe ships, when completed, would be classed A No. 1 by theAmerican Bureau of Shipping. It would *Page 929 have been so perhaps if the builder had furnished the plans and specifications, representing them as for a ship to class A No. 1 for ocean-going vessels. * * *"
That case is authority solely for the proposition that the builder was not a warrantor that the ships when completed would be classed A No. 1 by the American Bureau of Shipping, since they were to be constructed according to detailed plans and specifications furnished by the steamship company, from which the builder had no right to deviate, and, further, the court specifically found that there was not any defect in the plans and specifications except that the ships which were built accordingly did not pass muster. In that case the court was not concerned with the liability as between the owner and the contractor when a work collapses before completion because of defects in the plans and specifications, but had before it the question of whether the contractor had bound himself to produce a certain result in addition to his obligation to build according to plans and specifications. The question was answered by considering whether there was a builder's warranty, and not whether there was a warranty by the owner. In that case there was no warranty by the builder, either express or implied, that the ships constructed according to the plans and specifications would be classed A No. 1 for ocean-going vessels, and the court held that it was not liable for the failure of the ships to pass as such. *Page 930
In brief on rehearing, Brasher contends that the instant suit is based upon a completed contract, and that, as the defect in the sewer system was caused by the soil condition, under the law of this state the responsibility is on the city of Alexandria. In support of this contention he cites Article 2762 of our Civil Code and the following decisions of this court: Fremont et al. v. Harris et al., 9 Rob. 23; Powell v. Markham, 18 La.Ann. 581; Police Jury of Parish of Vernon v. Johnson,111 La. 279, 35 So. 550; and A. M. Blodgett Const. Co. v. Cheney Lumber Co., Ltd., 129 La. 1057, 57 So. 369. Article 2762 reads as follows: "If a building, which an architect or other workman has undertaken to make by the job, should fall to ruin either in whole or in part, on account of the badness of the workmanship, the architect or undertaker shall bear the loss if the building falls to ruin in the course of ten years, if it be a stone or brick building, and of five years if it be built in wood or with frames filled with bricks."
The corresponding article of the Code Napoleon is Article 1792, which (as translated in Louisiana Legal Archives, Volume 3, Part 2, Compiled Edition of the Civil Codes of Louisiana, under Article 2762) reads as follows: "If a building which an architect or other workman has undertaken to make by the job, should fall to ruin either in whole or in part, on account ofthe badness of the workmanship, or even because of badness ofthe soil, the architect and undertaker *Page 931 shall bear the loss, if the building falls to ruin in the course of ten years."
It thus appears that the drafters of our Code saw fit, under Article 2762, to limit the liability of the architect or undertaker to defective workmanship, as the provision found in the Napoleonic Code extending the liability to "badness of the soil" was omitted therefrom.
To determine the proper meaning and construction to be placed on Article 2762 of the Civil Code, it is necessary that we read and consider in connection therewith Article 2758, which provides:
"When the undertaker furnishes the materials for the work, if the work be destroyed, in whatever manner it may happen,previous to its being delivered to the owner, the loss shall be sustained by the undertaker, unless the proprietor be in default for not receiving it, though duly notified to do so."
A consideration of these two articles shows conclusively that Article 2762 applies, and can only apply, where the building or other structure has been completed and delivered to the owner, and in such case the liability of the undertaker is restricted to a loss resulting from defective workmanship and does not extend to a loss caused by soil conditions. See Comment, 7 La.L.Rev. 564, 569.
In the instant case, as we have previously stated, there had never been a completion and a formal acceptance of the work *Page 932 or delivery to the owner as contemplated by the contract. Article 2762 is therefore without application.
A reading of the cases of Fremont et al. v. Harris et al., Powell v. Markham, Police Jury of Parish of Vernon v. Johnson, and A. M. Blodgett Const. Co. v. Cheney Lumber Co., Ltd., all cited supra, discloses from the facts as stated therein or by express statements in the opinions that in each of these cases the work undertaken by the undertaker had been completed and the building or other structure had been delivered and accepted by the owner. Under this fact, these cases are not applicable to the case here under consideration.
Brasher also cites and relies on two cases decided by the Federal courts, these being Penn Bridge Co. v. City of New Orleans et al., 5 Cir., 222 F. 737, and Alonzo B. Hayden, Inc., v. Town of Covington, D.C., 27 F.2d 354.
In the Penn Bridge Co. case, supra, the bridge company contracted with the City of New Orleans to build for it a bridge strictly in accordance with plans and specifications furnished to the city by bridge architects employed by the city. When the bridge company, pursuant to the terms of the contract and under the supervision of the city engineers, had proceeded with the work to a point near completion thereof, but prior to delivery and acceptance, the bridge collapsed and fell while it was being lowered from a vertical to a horizontal position upon the request and order of the *Page 933 official of the city who was supervising the work on behalf of the city. The Circuit Court of Appeals concluded that the lower court was in error in a ruling that had the effect of denying to the bridge company the right to recover for work done under this contract, and for this reason remanded the case for a new trial. The court found that the collapse of the bridge was not due to any fault or omission on the part of the bridge company or to any defective material used therein or to any non-observance by it of the terms of the contract, but was due altogether to the fact that the plans and specifications which the contract required the builder to observe strictly were fundamentally defective and insufficient. The opinion does not disclose, nor can we ascertain from a reading thereof, in what manner these plans were defective and insufficient, nor does the opinion point out what was the immediate cause of the collapse of the bridge. In the course of its opinion the court said [222 F. 742]:
"* * * We understand it to be well settled that by the making of such a contract as the one involved in this case the owner impliedly warrants the sufficiency for the purpose in view of the plans and specifications which the contractor is required to follow, and subjects himself to liability to the contractor for loss or damage entailed upon the latter in consequence of a fatal deficiency or fault in the plans or specifications not discoverable by him by the exercise of ordinary diligence upon inspection. * * *" *Page 934
If it was the meaning of the court by the above quoted statement to hold that the city warranted the sufficiency of the plans and specifications, that case has no application here, for, as we have stated hereinabove, in the instant case we have found that there was no warranty as to the sufficiency of the plans and specifications, either express or implied. Further, the cited case does not disclose what considerations compelled the court to conclude that there was an express or an implied warranty of the sufficiency of the plans and specifications, unless it regarded the mere act of the owner in furnishing such plans and specifications as a warranty by the city as to their sufficiency. If this is the correct interpretation of that case, we do not choose to follow it, as the effect of the decision is to relieve the contractor from all liability in all cases of ascertaining for himself the feasibility of performing under the plans and specifications furnished by the owner, and, if such defective or insufficient plans prevent the accomplishment of the object and purpose of the contract prior to delivery and final acceptance, the contractor is not liable therefor. If we are in error that the basis of this opinion was that the court found a warranty by the owner as to the sufficiency of the plans and specifications, and if the correct interpretation of the ruling therein is to the effect that the contractor was free from fault, and that the bridge collapsed because of defective plans and specifications, this decision is contrary to the general rule that, if defective *Page 935 performance is caused by defective or insufficient plans and specifications furnished by the owner, the contractor is nevertheless liable. See Stees et al. v. Leonard et al., Magnam Co. v. Fuller et al., Lonergan et al. v. San Antonio Loan Trust Co., all cited supra. See also 6 Williston on Contracts, supra, sec. 1966, note 1, p. 5516.
In the Alonzo B. Hayden, Inc., case, supra, it was expressly provided in the contract that the engineers of the town would decide when a foundation was necessary in the trenches for the sewer, that they would designate the material for the foundation, and that the contractor would be paid extra therefor. The provision in this respect is quoted in the opinion as follows [27 F.2d 354]: "`Where the bottom of the trench does not, in the opinion of the engineers, make a suitable foundation for the sewer, the trench shall be deepened and a new foundation of such material as the engineers may require shall be put in as directed by them. The contractor shall receive for this extra foundation the price bid per 1,000 feet B. M. if foundation is of lumber, on the price bid per cubic yard for concrete masonry if the foundation is concrete, and for additional excavation as is made necessary by reason of such foundation; he shall also receive the price per cubic yard for such additional excavations as is estimated by the engineers.'"
In that case, the owner by contract provision expressly undertook the liability for any unstable conditions of the trench. For *Page 936 this reason that case is not in point, and the holding therein is not applicable here.
In further support of his contention that the city was liable for conditions of the soil, the contractor relies on the well recognized rule that, when there is doubt as to the meaning of the contract, the practical construction of it by the parties should be given great weight in determining the meaning. The cases cited by counsel are authority for this rule, but the facts are not pertinent to this case. Brasher argues that, since the city issued 17 change orders for extra work during the course of construction, this showed that the intention of the parties was that the city should supply any needed engineering omitted from the contract. Of course, the contract itself contained an ordinary and usual provision that the owner could order extra work, or alter, add to, or deduct from the work without invalidating the contract. Actually, neither party intended anything either way regarding liability for the soil condition encountered, because neither contemplated or anticipated such a situation at the time of the making of the contract; therefore, the primary problem in this case is not to interpret the meaning of a contract, but to determine where the law places liability when plans and specifications furnished by the owner are inadequate and insufficient. If we apply the rule urged by Brasher, however, it is doubtful from the record that the city's action showed that it considered that it was liable for the soil *Page 937 conditions encountered by the contractor which necessitated stabilization of the trenches. Certainly, a fair appraisal of the city's action in taking advantage of the provision permitting the issuance of change orders and orders for extra work would not result in the conclusion that it thus considered that it was liable for every difficulty requiring engineering work that would be encountered in the course of the construction.
The contractor's contention would be strengthened in this case if the record disclosed that the city authorized cradling in the change orders to take care of the unstable soil conditions encountered in the trenches. The acting city engineer, Mr. Miles, testified that he never issued an order for concrete cradling to take care of the soil condition. His testimony is verified by that of the contractor himself, who testified that from the beginning of this construction project, when the trouble was first called to the city's attention, it took the position that it was not liable for the condition found in the soil. The record as a whole confirms the fact that the city was consistent in this position. There is no basis, therefore, for finding that the city construed the contract to mean that the liability was on it for the condition of the soil.
For the reasons assigned, the judgment appealed from is reversed, and it is ordered that plaintiff's claim be rejected and his suit dismissed at his costs. *Page 938
The right to apply for a second rehearing is expressly reserved.
McCALEB, J., concurs with written reasons.
O'NIELL, C. J., does not take part.