Barhorst, Inc. v. Hanson Pipe & Products Ohio, Inc.

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 780 {¶ 1} Plaintiffs-appellants, Barhorst, Inc. and DECC, Inc., appeal the judgment of the Shelby County Common Pleas Court, granting the "motion to compel arbitration and to stay this action pending arbitration" filed by the defendant-appellee, Hanson Pipe and Products Ohio, Inc. Based on the following, we reverse the decision of the trial court and remand the cause for further proceedings consistent with this opinion.

{¶ 2} Appellants were the only members of two Ohio limited liability companies, Robert Oldham, Ltd. and Robert Oldham Enterprises, Ltd. (hereinafter referred to as "the companies"). In April 2004, appellee submitted a letter of intent to purchase the companies from appellants. Due to a delay in closing, the parties agreed on a purchase price and created a formula for calculating the companies' net equity between June 30, 2005, and July 15, 2005, to allow the *Page 781 purchase price to be adjusted to reflect an increase or decrease in net equity during that time. Both the purchase agreement and Schedule 2.5 provide a formula for calculating net equity. However, the method of calculation is stated differently in each. The parties apparently agree that in the purchase agreement, net equity is calculated by adding the amount of notes payable to the members' equity and subtracting cash on hand. However, Schedule 2.5 contains the following language:

Net Equity is the residual amount of the Members' Equity in the Companies after the deduction of (a) balances due to lenders and (b) cash on hand. The parties have agreed that the Companies shall have a Net Equity value at Closing in the amount of ________, which is the amount calculated for Net Equity as of December 31, 2004, as shown below:

Members' Equity    $
Less:
Notes Payable
Capitalized Leases
Cash in Bank         __________
Net Equity         $ __________
Schedule 2.5 also provides an arbitration clause, which is the subject of this dispute. The arbitration clause provides:

The calculation of Net Equity value at Closing shall be performed using the same information sources and methodology as used to calculate the amounts shown above. * * * Purchaser shall calculate the Net Equity as of the Closing Date from the Closing Balance Sheet and shall promptly provide to Sellers such calculation. In the event of a dispute as to the calculation of Net Equity from the Closing Balance Sheet, Sellers and Purchaser shall negotiate in good faith toward a resolution of any such dispute. In the event that the negotiation is not successful in resolving the dispute, then Purchaser and Sellers agree to submit the dispute to binding arbitration to be conducted in Columbus, Ohio using such rules and procedures on which Sellers and Purchaser may agree.

{¶ 3} On October 26, 2005, appellants filed a complaint to compel arbitration. Appellants amended their complaint on November 17, 2005, to seek relief in the form of declaratory judgment, arbitration, specific performance, and damages for breach of contract and unjust enrichment. As part of the amended complaint, appellants alleged that appellee had failed to calculate net equity as required under the purchase agreement and Schedule 2.5. Appellee timely filed an answer, denying that it had failed to calculate net equity.

{¶ 4} On December 14, 2005, appellee filed a motion to compel arbitration and stay the proceedings. On January 24, 2006, appellants filed a motion for summary judgment and a memorandum in opposition to appellee's motion. Additionally, the parties filed several responsive briefs and memorandums. *Page 782

{¶ 5} On March 11, 2006, the trial court filed a judgment entry overruling appellants' motion for summary judgment as premature. On June 5, 2006, the trial court filed a judgment entry finding that "the parties dispute the proper calculation of post-closing net equity," ordering the parties to submit to arbitration, and ordering a stay of the proceedings pending arbitration.

{¶ 6} It is from this judgment that appellants appeal, presenting the following assignment of error for our review:

The trial court erred in granting the motion to compel of Appellee Hanson Pipe and Products Ohio, Inc. in its April 26, 2006 decision order-entry.

{¶ 7} In the assignment of error, appellants allege that appellee seeks arbitration as a way to reform the contract. Specifically, appellants contend that arbitration is required under the contract if the parties have a good-faith dispute as to the "calculation," but not for reformation of the formula used in making the calculation. Appellants also contend that Schedule 2.5 clearly evidences the distinction between "calculation" and "methodology" by using both terms. Therefore, appellants essentially argue that the only error that may be submitted to arbitration is an error caused by "plugging in" the numbers of the formula.

{¶ 8} Appellate jurisdiction is limited to review of lower courts' final judgments. Section 3(B)(2), Article IV of the Ohio Constitution. To be a final, appealable order, a judgment entry must meet the requirements of R.C. 2505.02 and, if applicable, Civ.R. 54(B). Chef Italiano Corp. v. KentState Univ. (1989), 44 Ohio St.3d 86, 88, 541 N.E.2d 64. While R.C. 2711.03(A) requires a trial court to hold a hearing prior to compelling arbitration, apparently, appellee's motion was brought under R.C. 2711.02(B). Therefore, the trial court did not err by not holding a hearing, and its judgment entry ordered a stay pursuant to R.C. 2711.02(B), which is a final, appealable order. R.C. 2711.02(C). Therefore, we have jurisdiction to determine this appeal. Maestle v. Best BuyCo., 100 Ohio St.3d 330, 2003-Ohio-6465, 800 N.E.2d 7, syllabus.

{¶ 9} Arbitration is encouraged as a method of settling disputes. See Williams v. Aetna Fin. Co. (1998), 83 Ohio St.3d 464, 700 N.E.2d 859. "A presumption favoring arbitration arises when the claim in dispute falls within the scope of the arbitration provision. An arbitration clause in a contract is generally viewed as an expression that the parties agree to arbitrate disagreements within the scope of the arbitration clause, and, with limited exceptions, an arbitration clause is to be upheld just as any other provision in a contract should be respected." Id. at 471, 700 N.E.2d 859. This case calls upon us to determine whether the parties' contract "`creates a duty for the parties to arbitrate the particular grievance,'" which is a question for the trial court, and not the arbitrator. LeROI Internatl., Inc. v. GardnerDenver Mack, Inc., 3d Dist. No. 17-03-20, 2004-Ohio-4163,2004 WL 1770494, at ¶ 18, citing Council of Smaller *Page 783 Ents. v. Gates, McDonald Co. (1998),80 Ohio St.3d 661, 666, 687 N.E.2d 1352. However, while the general policy is to favor arbitration, that policy should be denied effect when "it may be said with positive assurance that the arbitration clause is not susceptible of an interpretation that covers the asserted dispute." Gibbons-Grable Co. v. GilbaneBldg. Co. (1986), 34 Ohio App.3d 170, 173, 517 N.E.2d 559, quoting Siam Feather Forest Prods. Co., Inc. v.Midwest Feather Co., Inc. (S.D.Ohio 1980),503 F.Supp. 239, 241.

{¶ 10} When an appellate court reviews a trial court's decision to stay judicial proceedings pursuant to the parties' agreement to enter into arbitration, we accept the trial court's "findings of fact that are not `clearly erroneous,'" but we review questions of law de novo. (Citation omitted.) LeROI, 2004-Ohio-4163, 2004 WL 1770494, at ¶ 6, citing Lear v. Rusk Ind., Inc., 3d Dist. No. 5-02-26, 2002-Ohio-6599, 2002 WL 31716383, at ¶ 8. "In interpreting an arbitration clause, courts must apply the fundamental principles of Ohio contract law." Id. at ¶ 7, citing Benjamin v. Pipoly, 155 Ohio App.3d 171,2003-Ohio-5666, 800 N.E.2d 50, at ¶ 31-34. Construction of a written contract is a matter of law, and the words used in the contract must "be given their ordinary meaning unless manifest absurdity results, or unless some other meaning is clearly evidenced from the face or overall contents of the instrument."Alexander v. Buckeye Pipe Line Co. (1978),53 Ohio St.2d 241, 7 O.O.3d 403, 374 N.E.2d 146, paragraphs one and two of the syllabus. "If a contract is clear and unambiguous, then its interpretation is a matter of law and there is no issue of fact to be determined." Inland Refuse Transfer Co. v.Browning-Ferris Industries of Ohio, Inc. (1984),15 Ohio St.3d 321, 322, 15 OBR 448, 474 N.E.2d 271.

{¶ 11} Here, the issue that must first be resolved is on declaratory judgment. In doing so, the trial court must decide whether the language of the purchase agreement and Schedule 2.5, specifying the method of determining "Net Equity," is enforceable as appellants demand, or should be reformed as appellees demand. Unless and until that issue is resolved, any decision by an arbiter is meaningless. Because the asserted dispute revolves around the language of the contract, rather than the calculation that must occur as a result of enforcing or reforming that language, "the arbitration clause is not susceptible of an interpretation that covers the asserted dispute." Gibbons-Grable, 34 Ohio App.3d at 173,517 N.E.2d 559, quoting Siam Feather Forest,503 F.Supp. at 241.

{¶ 12} Accordingly, the assignment of error is sustained.

{¶ 13} Having found error prejudicial to the appellants herein, in the particulars assigned and argued, we reverse the judgment of the trial court and remand the matter for further proceedings consistent with this opinion.

Judgment reversed and cause remanded.

*Page 784

CUPP, J., concurs.

BRYANT, P.J., dissents.