First National Bank v. United States Fidelity & Guaranty Co.

[EDITORS' NOTE: THIS PAGE CONTAINS HEADNOTES. HEADNOTES ARE NOT AN OFFICIAL PRODUCT OF THE COURT, THEREFORE THEY ARE NOT DISPLAYED.] *Page 149 This is an appeal from a decree dismissing plaintiff's complaint in a suit brought to impress a trust on a fund in the hands of the defendant United States Fidelity Guaranty Company. It is the contention of plaintiff that respondent cannot equitably retain the sum of $6,533.84 paid it by the government, for the account of Payne and Padrick, in view of the following facts.

On the 5th of January, 1924, the United States awarded a contract to the defendants Payne and Padrick for the construction of a section of the Detroit-Niagara Forest Road on the Santiam River. Respondent United States Fidelity Guaranty Company executed a bond in the sum of $65,000 to guarantee the performance by the defendants, Payne and Padrick, of their contract. The bond was a commercial bond executed for a premium of *Page 150 $2,089.80. The defendants, Payne and Padrick, entered upon the performance of their contract and applied to plaintiff for moneys with which to finance the performance of their work. The bank was unwilling to make advances for this purpose without some assurance that the estimates would be paid to it for the satisfaction of the notes given for advances so made to the contractors. In order that assurance on this subject might be given, it was necessary that the surety should join with the contractors in the commitment which plaintiff required. Under these circumstances respondent executed and delivered to plaintiff the following letter:

"United States Fidelity and Guaranty Company,

"Portland Office, "C.O. Price, Manager. "1208 Porter Bldg., "Portland, Oregon.

"February 20, 1924.

"First National Bank of North Bend, "North Bend, Oregon.

"Gentlemen:

"Referring to the contract which Messrs. Payne and Padrick have heretofore entered into with the Bureau of Public Roads for the construction of a section of the Detroit-Niagara Forest Road on the Santiam River, we are informed that Messrs. Payne and Padrick have designated that the monies due or to become due under this contract, are to be paid to your bank in accordance with the terms and provisions of a Power of Attorney given by them to you under date of February 16, 1924. Therefore, this letter is to advise you that this company, as the surety on the bond furnished to guarantee the performance of the above mentioned contract, hereby consents to the payment of the monies due or to become due under the contract in question, *Page 151 not exceeding the sum of $25,000 in accordance with the arrangement referred to above. (Italics ours.)

"Yours very truly, "(Sgd.) O. PRICE, Manager."

On receipt of this letter and on the 21st of February, 1924, plaintiff advanced the contractors $2,000. On the 13th of March an additional $5,000 was advanced.

A question occurred whether this letter permitted aggregate advances to exceed $25,000 to clarify which the respondent, by the manager of its Portland office, wrote to the plaintiff on April 2d, 1924, in effect as follows:

"In this connection will say that we have no objection to your advancing Mr. Payne such amounts as you deem advisable, providing your outstanding loans to him at any one time do not exceed $25,000."

This letter was not regarded as satisfactory and after a conference between one of the directors and a representative of respondent, the company wrote to plaintiff the following letter dated April 9, 1924.

"In Re: Payne Padrick. "In accordance with my conversation today with Mr. Hollister, this letter is to advise you that the United States Fidelity Guaranty Company as surety on the bond furnished for Messrs. Payne Padrick to guarantee contract made with the Bureau of Public Roads, consents to the assignment to your bank of theestimates under said contract in consideration of advances made by your bank to these contractors to carry on the work." (We underscore.)

On the 5th of April plaintiff advanced the contractors $5,000 and on April 11th, $6,000, as plaintiff asserts, on the faith of the assurance given by *Page 152 respondent to plaintiff. On April 14th plaintiff wrote respondent a letter in substance as follows:

"We have your letter of the 9th instant referring to advances made on estimate on the road contract of Messrs. Payne Padrick. This to advise you that we are acting on said advice and are making advances until such consent by yourselves as surety under this contract is cancelled."

On the 7th of May plaintiff advanced an additional $5,000; on the 12th of May $3,500, and on the 13th of May $1,500, and on the 9th of June $5,000; on the 16th of June $2,500, and on July 3d $4,000. At that time Mr. R.B. Mason, a representative of respondent, telephoned to Mr. John H. Graves, cashier of plaintiff, asking plaintiff to make no further advances and plaintiff informed Mr. Padrick that it could advance no more money because of the attitude taken by the guaranty company. After Mr. Padrick took the matter up with the guaranty company, respondent wrote the following letter to plaintiff:

"We are enclosing Mr. Padrick's note for the balance of the June estimate. We asked you to suspend this temporarily in order that we might have a conference with Mr. Padrick and be assured that the plans for the work this month and expenditure of the funds were satisfactory. Mr. Padrick came in yesterday and we find the work going on in order. Therefore we withdraw our `stop' request and ask that this advance go through according to previous arrangement."

It appears that the contractors entered into an agreement of indemnity with the guaranty company on November 15, 1923, by the terms of which, among other things, it was provided: *Page 153

"That the said Company, as surety on said bond, as of this date, shall be subrogated to all our rights, privileges and properties as principal and otherwise in said contract, and said principal does hereby assign transfer and convey to said company all the deferred payments and retained percentages, and any and all moneys and properties that may be due and payable to said principal at the time of such breach or default, or that may thereafter become due and payable to said principal on account of said contract, or on account of extra work or materials supplied in connection therewith, hereby agreeing that all such moneys and the proceeds of such payments and properties shall be the sole property of the said company, and to be by it credited upon any loss, damage, charge and expense sustained or incurred by it as above set forth under its bond of suretyship."

REVERSED. The answer of the respondent asserts that it was understood between the bank, the respondent and the contractors, at the time the letters were given, that the bank would be protected only on such moneys as it collected on estimates for work actually done each month, and that the letters were not intended to give the bank, which was so understood by it, the right to collect the retained percentages or retained estimates. It was further contended *Page 154 in the answer, by way of defense to the bank's claim, as follows:

First: That no retained percentages ever became due the contractors, for the reason that they defaulted and abandoned their contract:

Second: That the order and power of attorney, under which the bank claimed, were invalid as an assignment, both in law and equity, as between all of the parties concerned.

Third: That the letters, on which the bank relied, neither attempted to nor constituted a waiver of the respondent's subrogation agreement with the contractors.

Fourth: That the bank had no claim in equity to the reserved percentages, for the reason that it misapplied monthly estimates received by it to pay off a previous loan made to the contractors.

Fifth: That the respondent was compelled to complete the road contracted for, at a loss of $63,000.

Sixth: That the right of the bank to the fund in question was previously adjudicated in the District Court of the United States for the District of Oregon, which suit as to the present claim isres adjudicata.

The power of attorney from Payne Padrick to the bank executed February 16, 1924, and which was duly acknowledged, authorized the bank as attorney of the contractors, "to indorse my name on and collect money due on checks drawn in my favor by any disbursing officer of the United States for whatever account (Detroit-Niagara Section of Forest Roads)"; such authority to remain in full force until revoked. This power of attorney was filed in the office of the Road Bureau on February 21, 1924. *Page 155

The contract provided that the government should retain 10 per cent of the monthly estimates until the completion of the work. On February 14, 1925, the contractors executed, and deposited with the Road Bureau, an order to the Road Bureau to pay to the plaintiff bank the moneys so retained, $6,533.84, pursuant to the authorization of February 20, 1924, when the time should come for such payment.

On July 18, 1924, the contractors abandoned the work and so notified the district engineer of the United States Bureau of Public Roads, by letter.

A copy of the notice which was on the letter-head of respondent was served upon the guaranty company. The company for its own protection took over the work and completed the contract at an expense of about $60,000 more than it received from the government. The company received the estimates rendered the contractor for the month of July, 1924.

The percentage, as retained by the United States prior to the abandonment of the contract by the contractors, as shown by final settlement, aggregated $6,533.84; with this was included $687.02 for equipment returned to the government by the surety. A draft for $7,220.86, including these two amounts, was issued by the comptroller-general and received by the surety company and paid on October 14, 1925.

The plaintiff contends that respondent was in the position of trustee for the bank to the extent of the money so received and that the letters of the respondent assured the bank that it would have precedence over the surety company in payment of all of the money due the contractor on the monthly estimates, including the reserved percentages up to the time of the abandonment of the contract. *Page 156

As the 90 per cent of the money came in from the monthly estimates, the bank applied the same to the indebtedness of the contractors, and then new loans were made to enable them to continue the work. In a number of cases the moneys received on account of the contractors were in excess of the indebtedness owing by them to the bank, and the balance, after paying the notes, was credited in the bank to the contractors.

On March 27, 1925, before the surety company had received the reserved percentages of the money earned by the contractor, the bank brought suit against the surety company in the District Court of the United States for the District of Oregon. The bank's bill of complaint, after amendment, included only the estimate for July, 1924. This suit was settled by the payment to plaintiff by the company of $3,650, and according to the terms of settlement the bank gave the contractors credit for the full amount, $5,147.74, which was 90 per cent of the July estimate. This left a balance due from the contractors to the plaintiff of $6,583.25, not including interest. An execution on a judgment, including this amount, has been returned unsatisfied.

The work was carried on in the name of Payne and Padrick until the road was completed. All checks were drawn in their favor and were indorsed by respondent under authority of defendant Padrick executed on July 18, 1924, in the name of his firm at a time when it is claimed the partnership had been dissolved.

The reserved percentages were, among other things, for the protection of the surety. This, however, did not prevent the surety from agreeing "to the payment of the moneys due, or to become *Page 157 due, under the contract in question," to the bank. The surety company, as shown by its letters to plaintiff, so consented apparently in order to induce plaintiff to finance the contractors in performing the work so that the company would not be compelled to take over the work, or become liable on its bond.

Again, in the letter of the respondent dated April 9, 1924, the company as such surety "consents to the assignment to your bank of the estimates under said contract in consideration of advances made by your bank to these contractors to carry on the work." This consent included the reserved percentages, $6,533.84, in controversy in this suit. It was given for a valuable consideration. It is clear that the agreement is not for the payment to the bank of a portion of the estimates, 50 per cent or 90 per cent, but of the whole thereof.

The surety company, having by such arrangement induced the plaintiff to make the advances to the contractors in reliance upon the agreement of the contractors, consented and agreed to by the respondent, it would not be consistent with equity and good conscience to permit the surety company to collect and retain a portion of the moneys so assigned and hypothecated to the bank to reimburse it for money so loaned and which remained unpaid. To do this would be a plain violation of the agreement made understandingly by the respondent company.

In 2 Story's Equity Jurisprudence (12 ed.), Section 1255, we read:

"One of the most common cases in which a court of equity acts upon the ground of implied trusts in invitum, is where a party has received money which *Page 158 he cannot conscientiously withhold from another party. It has been well remarked that the receiving of money, which consistently with conscience cannot be retained, is in equity sufficient to raise a trust in favor of the party for whom, or on whose account, it was received. This is the governing principle in all such cases, and, therefore, whenever any interest arises, the true question is, not whether money has been received by a party, of which he could not have compelled the payment, but whether he can now, with a safe conscience, ex aequo et bono, retain it."

In 26 R.C.L. 1235, Section 82, it is said:

"Equity will impress a trust contrary to the intention and will of a party where a fund has been obtained by him in violation of his duty to another. In order to raise his duty as the foundation of a constructive trust there need be neither a promise for the benefit of another, nor express fiduciary relations between them. It may be raised by representations, conduct and the like that have been relied on by another under such circumstances as create an equitable estoppel on one to pursue thereafter an opposite course for his own advantage."

See, also, Anglo-Am. Assn. v. Campbell, 13 App. Cas. (D.C.) 581 (43 L.R.A. 622, 628, 629); 3 Pomeroy's Eq. (4 ed.), § 1280;Barnes v. Thuet 116 Iowa, 359 (89 N.W. 1085).

This court is committed to the doctrine announced in the above authorities, as shown by the opinion of Mr. Justice McBRIDE, inPankey v. Oregon-California East Ry. Co., 122 Or. 346 (255 P. 470, 471). The same principles have been applied under various states of fact in numerous cases: In re Berry, 147 Fed. 208, 210, 211; Bank of Williston v. Alderman, 106 S.C. 386 (91 S.E. 296, 297, 298); Stern v. Wing, 135 Mich. 331 (97 N.W. 791); Page County v. Rose, *Page 159 130 Iowa, 296 (106 N.W. 744, 8 Ann. Cas. 114, 5 L.R.A. (N.S.) 886, 890).

The "estimate" to which the respondent consented to the assignment to the bank is defined in the testimony of Mr. Eddy, civil engineer, who was a witness for respondent in this suit, as meaning, in contracting parlance, the amount that the contractor is entitled to under his contract at a time stated. That is the meaning attached to the word when found in a contract, "as monthly estimate for the contractor."

The testimony defining the word of technical significance is entitled to consideration by the court: Yreka Co. v.Lystul-Stuveland Lumber Co., 99 Or. 291 (195 P. 378);Stanfield v. Arnwine, 102 Or. 289, 298 (202 P. 559). The bank was entitled, under the arrangement made with the contractors and the surety company, to the amounts that were due or to become due, on the estimates, up to the time the contractors abandoned the contract.

If this were a case involving the rights of the surety company as against the contractors, it would be very simple. The surety company would have had the undoubted right when the contractors abandoned the work to step into their shoes and receive the benefit of all that was coming to the contractors thereafter on account of the work. However, the surety company, having agreed to the assignment of the amount of the estimates before that time, neither the contractors nor their surety had a right to the reserved percentages which had been earned prior to the default, as the same had been assigned by the contractors to the bank theretofore with the assent of the surety company. *Page 160

The respondent contends that, under the indemnity agreement between the contractors and this respondent, the latter was subrogated to all of the rights and demands of the contractors against the government and that the surety thereby obtained an interest in the estimates and retained percentages prior to any claim of the bank or other general grantor.

As authority for this proposition the defendant cites, among other authorities, Brandt on Suretyship, Volume 1 (3 ed.), page 611, Section 324, which reads in part, as follows:

"By subrogation, in this connection, is meant the equitable principle upon which one who pays the debt, or satisfies the obligation of another under such circumstances that the other ought, as a man of honor and conscience, to repay his benefactor, is, for the purpose of giving him a chance to make himself whole, put in the place of the creditor or obligee to whom he has made payment, and given all securities and all rights and remedies against any person whatever that the creditor or obligee has to secure performance of the obligation, — so far as that can be done without violating the rights of innocent third parties."

We have already noted that at the time of the default, or thereafter, when the surety company had completed the work, the contractors had no right to the fund in question. Furthermore, the rule of subrogation is applied as far as it "can be done without violating the rights of innocent third parties." The bank, under the circumstances of this case, stands in the position of an innocent third party and the rule contended for by the defendant cannot be applied without violating its rights. The case of the County of Wasco v. New England Eq. Ins. Co., *Page 161

88 Or. 465 (172 P. 126, Ann. Cas. 1918E, 656, L.R.A. 1918D, 732), also cited by respondent as authority for the above proposition, is a case which well illustrates the rights of surety companies. In that case money due on a contract, but retained by a county until completion and acceptance of work, was by written order assigned by the contractor to a bank in consideration of money loaned the contractor and used by him to pay for labor and material for which he was bound by his contract to pay. The contractors' bond, as required by law, obliged the surety to pay for labor and material and also to complete the work.

The contract also provided for retention of money assigned until completion and acceptance of the work. It was held that on the contractor's default, until claims for labor and material were paid, the county's right to the fund assigned was superior to that of the assignee bank, and when the contractor's surety paid for labor and material as required, it was entitled to be subrogated as against the bank to the rights of the county, as of date of its contract, and hence the surety's right to the fund was superior to the assignment to the bank, which was bound to know when it voluntarily loaned its money of the surety's equity in the funds reserved.

In that case the surety had nothing to do with and did not consent to the assignment to the bank. In the present case the surety company assented in the plainest manner possible to an assignment to the plaintiff bank, which widely differentiates the two cases. The cases of Derby v. United States Fidelity G.Co., 87 Or. 34 (169 P. 500), cited by respondent, is on the same footing as the Wasco County case. See, also, Ashley Rumelin v. City of Portland, *Page 162 90 Or. 40 (175 P. 447); Ausplund v. Aetna Ind. Co., 47 Or. 10,20 (81 P. 577, 82 P. 12).

The letters referred to were given by respondent in favor of plaintiff and they are therefore to be construed favorably to plaintiff: Salem Kings Prod. Co. v. Ramp, 100 Or. 329, 355 (196 P. 401). The letters were in the nature of letters of credit and should be fairly construed to effectuate the intention of the parties: Marshall-Wells v. Tenney, 118 Or. 373, 383 (244 P. 84, 45 A.L.R. 1382).

The fund earned by the contractors is subject to a lien in favor of plaintiff to the extent of the indebtedness incurred by the contractors for advances made to them by plaintiff.

In 21 C.J., page 1204, Section 205, we find the following:

"Where a person has acted or refrained from acting in a particular manner upon the request or advice of another, the latter is estopped to take any position inconsistent with his own request or advice, to the prejudice of the person so induced to act."

See C.A. Babcock v. Katz, 121 Or. 64 (253 P. 373);Snell v. Baker Bank, 29 Or. 250, 253 (45 P. 783); Sharkey v. Candiani, 48 Or. 112, 126 (85 P. 219, 7 L.R.A. (N.S.) 791); Ashley v. Pick, 53 Or. 410, 417 (100 P. 1103); GrandPrize Hyd. Mines v. Boswell, 83 Or. 1, 12, 14 (151 P. 368, 162 P. 1063).

For the purpose of effecting justice under facts similar to those in the present case, courts have frequently imposed an equitable lien upon funds or property: 10 R.C.L. 351; 17 R.C.L. 604, 605.

Walker v. Brown, 165 U.S. 654, 663, 664 (41 L. Ed. 865, 870,871, 17 Sup. Ct. Rep. 453), was a suit in equity brought by Walker Company for the purpose *Page 163 of charging an equitable lien on bonds held by Mrs. Brown as a gift from Brown, who had loaned $15,000 of bonds to J.C. Lloyd for the use of Lloyd Company. In a letter to Walker Company, Brown advised them that the loan "is with the understanding that any indebtedness that they may be owing to you at any time shall be paid before the return to me of these bonds, or the value thereof, and these bonds, or the value thereof, are at the risk of the business of Lloyd Company, so far as any claim you may have against said Lloyd Company is concerned." In reliance upon this letter Walker Company extended payment on a small debt of Lloyd Company and made further advances in goods so that the unpaid indebtedness of Lloyd Company to Walker Company amounted to $13,916.39, when Lloyd Company became insolvent. The bonds were afterward returned to Brown and given to Mrs. Brown. It was held that the agreement embodied in the letter created an equitable lien in favor of Walker Company upon the bonds; that the bonds which had been returned by Lloyd Company to Brown were subject to an equitable charge for the payment of Walker Company's debt. See Hawes Co. v. Trigg Co.,110 Va. 165 (65 S.E. 538, 542), where the court quotes from the opinion in the case of Tatum v. Ballard, 94 Va. 370 (26 S.E. 871), as follows:

"`Words which show an intention of transferring or appropriating a chose in action to or for the use of another, if based upon a valuable consideration, will, in contemplation of a court of equity operate as an assignment.'"

In that case it appears that a power of attorney had been executed by the Trigg Company authorizing *Page 164 the bank to collect all payments under its contract with the government for the construction of revenue cutters, on the faith of which the bank made loans to the Trigg Company. It was held that transaction constituted an assignment to the bank which was not defeated or invalidated by reason of the provision of Section 3477 of the Revised Statutes of the United States. See, also,York v. Conde, 147 N.Y. 486 (42 N.E. 193).

Respondent contends that the United States statute forbids the assignment of the funds due a contractor on public work, and that, therefore, it was not competent for these contractors or their surety to assign this fund to plaintiff. The equitable assignment on which plaintiff relies is, therefore, alleged to be unlawful and void.

The arrangement made with the plaintiff to advance the money was a tri-party agreement and respondent was a party thereto; moreover, respondent secured the fund which is the subject matter of this litigation on an order executed by the defendant Padrick. It relies on the same order as its authority for indorsing the check which included the fund of $6,533.83, which plaintiff contends is its property. Respondent is in no position to question the title of appellant to this fund, claimed by plaintiff under a similar instrument. The United States statute has been construed by the courts. The statute was passed for the protection of the government and it will not be permitted to defeat the rights of a private litigant whose controversy is not with the government, but with another claimant of the fund:Jennings v. Whitney, 224 Mass. 138 (112 N.E. 655); Lay v.Lay, 118 Miss. 549 (79 So. 291, 293); Goodman v.Niblack, 102 U.S. 556 (26 L. Ed. 229); York v. *Page 165 Conde, 168 U.S. 642 (42 L. Ed. 611, 18 Sup. Ct. Rep. 234).

It is contended by respondent that the present suit is barred by the decree passed May 5, 1926, in the federal court in a former action brought by appellant against respondent, and shows the settlement of the action, "as amended by interlineation."

At the time of the action in the federal court the reserve percentages had not been paid to respondent and the present claims of plaintiff were not barred thereby. The amendment made to the bill in the federal court confined the controversy in the former suit to the money received by respondent on the July, 1924, estimate: La Follett v. Mitchell, 42 Or. 465, 471, 472 (69 P. 916, 95 Am. St. Rep. 780); Stillwell v. Hill, 87 Or. 112,116, 117 (169 P. 1174). The decree in the former case therefore, is conclusive only as to the $5,147.74 received by the surety company on the July estimate.

Respondent submits that by reason of the default of the contractors they never became entitled to the percentages retained by the government. Respondent's brief states "the letters consent to the payment to the bank of all moneys due orto become due the contractors," and as the contractor defaulted and as respondent completed the contract at a loss, the bank is not entitled to the reserved percentages.

The work for which the 10 per cent was finally to be paid had been performed when the default was made. The contractors would not be entitled to the payment withheld for the reason that they had assigned such right to the bank.

We must, in order to arrive at the equities of the case, consider the matter as it stood when the so-called tri-party arrangement was made to which the *Page 166 surety consented. If the work had been completed at a cost of one half of the amount of the contract price unpaid at the time of the default, the bank would have had no stronger claim than it has as matters now stand. In other words, at the time the surety company induced the bank to loan the money to the contractors and made the agreement which was for its interest the surety company took upon itself the risk of taking over the contract at a later date, which was no doubt delayed by virtue of the arrangement made with the bank, and at a time when it had by its own voluntary act released its right to the reserved percentages. The right of the government is not involved herein.

It is contended on behalf of respondent that it did not release its right to the fund in question for the reason it did not use the word "waive" in its letter. We fail to see how the language employed in the agreement can make a material difference if the understanding and arrangement is plainly expressed by the words used, and the rights and equities of the parties are clearly delineated in the carefully considered and integrated memoranda.

We recognize that it was unfortunate that the undertaking of the company turned out unprofitably in the end. Under the arrangement made for financing the contractors, when the bank paid the money to the contractors to enable them to carry on the work, it performed its part of the plan. It was not incumbent on the bank to see that the money was expended on the road. This would have been practically impossible. However, plaintiff offered to show that all of the money advanced was actually used in the road work. This was rejected on objection of respondent, and we think properly. The *Page 167 monthly estimates were ordered paid to the bank with the surety's assent, as security for the loans made at different dates to Payne Padrick. When a monthly estimate was made and the amount then due thereon was paid, and the notes of Payne Padrick taken by the bank then in existence were satisfied, it was proper for the bank to credit the balance, if any, to the account of the contractors. There appears to have been no dissent to this from the surety at any time. The surety cannot now successfully claim that such procedure was a misapplication of monthly payments. The limit of $25,000 at any one time, mentioned in the letter, as well as the terms of the construction contract, indicate that the contractors were entitled to 90 per cent of the monthly estimates, and it appears to have been the plan that the bank and the contractors would square up, if possible, when the monthly estimates were made. In other words, the bank had no right to retain a portion of the 90 per cent of any monthly estimate as security for future advances not then made. The surety company, under any circumstances, was entitled to have held back only 10 per cent of the estimates. The contractors were entitled to all except this reserved percentage, and if the bank paid it to them, or for their account, it was all according to the original contract.

The equities are with the plaintiff. The decree of the trial court will be reversed and one entered in favor of plaintiff, that the United States Fidelity Guaranty Company be declared to be the trustee for plaintiff, as to $6,533.84 of the draft, for and containing the reserved percentages mentioned by the United States government in favor of Payne Padrick, and that respondent be required to pay said *Page 168 amount to plaintiff, together with interest thereon at the rate of 6 per cent per annum from the 14th of October, 1925, the date of the receipt of said draft by respondent as prayed for in plaintiff's complaint.

REVERSED.

RAND, C.J., and BROWN and BELT, JJ., concur.