This is an action for damages alleged to have been sustained by the plaintiff, in consequence of the removal by the railroad company of a quantity of earth from the land of the plaintiff which was subject to an easement of right-of-way conveyed to a predecessor of the railroad company by a predecessor in the title of the plaintiff. The excavation and removal of the earth were made upon and from the land included within the railroad company's right-of-way. *Page 395
The statement in the opinion of Mr. Justice Stabler, which I reproduce below, is not quite as full as it should be. It is declared: "It appears from the record that in the year 1925, pursuant to a general program of improvement, the defendant began the process of raising the grade of its road at several points along its line between the cities of Spartanburg and Laurens." (Italics added).
I think that the record shows that the "general program of improvement" included a great deal more than simply "raising the grade"; that it included also straightening the line in many places, reducing the curves, widening cuts, extending fills, and removing obstructions to the view of both travelers upon the highway at railroad crossings and operators of the trains, a very extensive "program of improvement," at a cost of several hundred thousand dollars; the purpose being to lower the cost of operation and to insure greater safety in operation.
At a particular point on the line, near Arkwright Mills, it appeared expedient and necessary to raise the grade, as a factor in the general plan of improvement, and to lessen the danger from two crossings near there; and in order to do this earth had to be obtained from the nearest and most available land which was the plaintiff's. The line through his land passed in a narrow cut and on a curve approaching a highway crossing.
The gist of the plaintiff's contention is that in the exercise of its rights under the easement conveyed, the railroad company did not have the right to remove any part of the earth upon the right-of-way except for the purposes of the company immediately connected with the line upon his land; that it did not have the right to remove the earth and carry it to some other point upon the line even if there used for railroad purposes. This I understood to be the conclusion announced in the opinion of Mr. Justice Stabler.
I think that so far as the issues presented in the present appeal are concerned, there are two insurmountable objections to the correctness and application of this principle. *Page 396
In the first place, as I read them, the overwhelming weight of authority, text-writers and decided cases, supports the defendant's contention that so long as earth, excavated upon the right-of-way, is used by the railroad company, for railroad purposes, upon any part of its line, the company is within its rights in removing it.
In the second place, the evidence is susceptible of no other conclusion than that, in addition to the legitimate use of the earth at another point for railroad purposes, the immediatelocus was made by the excavation, safer for highway travelers and the operation of trains, to both employees, passengers, and freight being transported.
In 1 Nicholls, Em. Dom. (2d Ed.), § 195, it is said: "The railroad company is entitled, as an exercise of its easement, to remove earth, gravel, stone and timber from any part of its location for the purpose of grading, constructing or repairing its roadbed, and it may cut the trees so as to give its engineers an unobstructed view or to diminish the danger of fire, or when they interfere with the construction or operation of any of the appurtenances of the railroad, such as a telegraph line used in connection with the railroad. Itmay carry the material from one part of the roadbed foruse on another; but it has no absolute ownership thereof; the company can use it only for railroad purposes and cannot lawfully sell it to others. So also the company is entitled to use water from springs within its location for generating stream in its engines."
In 2 Elliott, R.R. (3d Ed.), § 1222, it is said: "* * * and, even where only an easement is taken, the company ordinarily acquires a right to take so much of the earth and materials within the right-of-way as may be reasonably necessary to remove in constructing and repairing its roadbed and to use it at other points on the road."
In note 72, citing Cleveland, C., C. St. L.R. Co. v.Hadley, 179 Ind., 429, 101 N.E., 473, 45 L.R.A. (N.S.), *Page 397 796, the author adds: "There is some slight conflict among the cases upon the subject, but, as shown in the note above referred to, this is the prevailing and better rule."
In 2 Lewis, Em. Dom. (3d Ed.), § 849, it is said: "It has been held that the company has a right to use the timber and materials so far as necessary for the construction and repair of its roadway, but that it cannot sell or otherwise dispose of them merely for profit. The company may remove timber or materials in so far as may be necessary to construct or to safely and conveniently operate the road. But the company may not sell or otherwise appropriate to its own use such materials except for the construction and repair of its road."
In 10 R.C.L., 120, it is said: "It may use as much of the earth, gravel and stone within the location as it may need for the construction and maintenance of the road,and it may carry the same from one point to another onthe road as these uses may require; but it has no right to sell such material to third persons."
In 20 C.J., 590, it is said: "So a railroad company having acquired a right-of-way is entitled to use so much of the timber, earth, gravel, stone and other materials thereon as may be necessary for the proper construction or repair of its roadway, either in adjacent localities or elsewhere. * * *"
In Cleveland, etc., R. Co. v. Hadley, 190 Ind., 429,101 N.E., 473, 477, 45 L.R.A. (N.S.), 796, the Court said: "In the absence of any limitations by statute or the condemnation proceedings a railroad company, although it takes only an easement, acquired by the appropriation, the absolute right to take so much of the earth and materials within the width and length of the right-of-way as it may be necessary or convenient to remove in constructing and repairing its road bed and use it at other points.
In Kelly v. Donahoe, 2 Metc. (Ky.), 482, is was held that a turnpike company, having the right under their *Page 398 charter to make such excavations, fills, and embankments as the proper construction of their road, according to its prescribed grade and width, renders necessary, may, as incidental to this right, lawfully quarry and remove stone and earth from one point to another within the lines of the road, and from the lands of one person to the lands of another; but they have no such right to the quarries and soil under and within the space occupied by the road, for the purposes of repairing it, although the road upon which the turnpike was built may have been used by the public for more than 20 years as a public highway.
In Davidson v. R. Co. (Tex.Civ.App.), 194 S.W. 211,214, the Court said: "The appellant, however, seems to be of the opinion that the railway company could not use any part of the sand or dirt on this right-of-way at any point on its railroad, or for any purpose connected with its business as a railroad company, save and except to the extent of using the same in connection with its track over that portion of the right-of-way within the limits of the easement. We do not think this is the proper construction to be placed upon appellee's rights under the law of this state, and therefore overrule this contention, and hold that the Court was correct in instructing a verdict in favor of appellee as against appellant on his cross-action."
In Wilson v. R. Co., 17 Pa. Dist., 151, the Court held: "The general principle seems to be that when it is necessary to remove material, such as earth, in constructing the road on its established grade or changing the grade over a right-of-way, such material may be used by the company even onother parts of the road."
In Nashville, C. St. L. Ry v. Karthaus, 150 Ala., 633,43 So. 791, 793, the Court said: "But, * * * while it entitles the company to use the earth, gravel and stone within their location for all railway purposes, it does not entitle them to sell any such material." *Page 399
In New Orleans, B.R., V. M.R. Co. v. Brown,64 Miss., 479, 1 So. 637, the syllabus is: "A railroad company, having acquired a right-of-way by condemnation proceedings, has a right to make excavations thereon for the purpose of obtaining dirt for surfacing its road-bed; and the company is not liable in damages to an adjacent property owner by reason of the unsightliness of his plantation, or its supposed unhealthliness from standing water, or the inconvenience of crossing over caused by the pits made in such excavations."
In Aldrich v. Drury, 8 R.I. 554, 5 Am. Rep., 624, the syllabus is: "A railroad company, or any contractor employed by them to build a railroad, may use any material removed by them in grading the road, either in the adjacent or, it seems, in other localities, but they have no right to sell such material to third parties."
In Lewis, Em. Dom. (3d Ed.), § 849, it is said: "Most of the earlier authorities and some of the later ones apply the same rules to railroads as to highways, in determining the respective rights of the owner of the easement and the owner of the fee."
In New Haven v. Sargent, 38 Conn., 50, 9 Am. Rep., 360, it was held that where a city laid out a new street across defendant's land, which it condemned for that purpose, the city was entitled to the filling extracted from that part of the street abutting plaintiff's property, with which to fill a hollow in another street, without rendering further compensation to the owner than that adjudged in the condemnation proceedings.
In Bissell v. Collins, 28 Mich., 277, 15 Am. Rep., 217, it was held that a city is entitled to take material found within the limits of a street, and distribute it to improve its streets within the city limits, without rendering compensation to the abutting property owners for its removal
In Robert v. Sadler, 104 N.Y., 229, 10 N.E., 428, 58 Am. Rep., 498, it was held that where land is taken for a *Page 400 highway, soil may be removed from one point therein, to be used in filling at another point, only so far as the removal of it is necessary for the process of construction and repair; and the digging of gravel from the bed of a road below grade for use on the surface, with the intention of filling with less valuable earth, is a violation of the abutter's rights.
The cases cited by Mr. Justice Stabler as sustaining his conclusion, are: Hendrix v. R. Co., 162 N.C. 9,77 S.E., 1001; Chapin v. R. Co., 39 N.H. 564, 75 Am. Dec., 237;Cleveland, C., C. St. L.R. Co. v. Hadley, 179 Ind., 429,101 N.E., 473, 45 L.R.A. (N.S.), 796.
The Chapin case may be quickly disposed of. There the Court said: "It may not, however, be improper to state our decided impression, that, in such case, the railroad might and would have been entitled to employ the whole or any portion of the earth, stone and gravel excavated on one portion of the line in the proper construction of any other portion thereof."
The Hadley case sustains the contention of the defendant, as appears from a quotation from the opinion of the Court in that case set out above.
In addition to these three cases, two of which sustain the contention of the defendant, Mr. Justice Stabler refers to a note to the Hadley case in 45 L.R.A. (N.S.), at page 797, which discusses the case of Hendler v. R. Co.,209 Pa., 256, 58 A., 486, 103 Am. St. Rep., 1005. The Hendlercase, I concede, sustains the contention of the contention of the plaintiff, but it and the Hendrix case are the only two cases I have encountered which do so.
The Hendrix case, in the bald conclusion of the Court, sustains the plaintiff's contention. The opinion was upon a demurrer and the declaration is without comment, reasoning or citation of a single authority.
I think that for the second reason above stated the circuit Judge was in right in directing a verdict for the defendant. *Page 401
Assuming that my conclusion above is erroneous. I think that the evidence is susceptible of but one inference, that the excavation was justifiable by reason of the peculiar situation presented where the line passed through the land of the plaintiff, and if there was nothing in the case which would otherwise justify the excavation and removal in the extended program at heavy cost, this was enough. The line passed through a deep and narrow cut; just beyond it was a highway crossing, as every one knows presenting a dangerous situation for both travelers and train operators. Can it be conceived that in case of a collision this situation would not have been presented to the jury, not only as evidence of maintaining a dangerous condition, but in exoneration of the contributory negligence of the traveler? Then what is the railroad company to do? Leave it in that condition and take the chances of a verdict against them, or remove the obstructing banks or sides of the cut? If that be their duty, what will be done with the excavated earth? They cannot put it back on the land owner; they cannot remove it to some other part of their railroad line, else they will have to defend just such a lawsuit as this.
There were but two witnesses for the defendant. I have read and re-read the cross-examination of both of them and have failed to find anything to sustain the conclusion that it raised an issue as to the reasonable necessity of widening the cut.
I think therefore that the judgment entered upon the directed verdict should be affirmed.