Laughman v. Sun Pipe Line Co.

This suit was instituted by G. C. Laughman to recover of the Sun Pipe Line Company damages for the breach of a contract of sale of certain iron pipe, alleged by plaintiff to have been sold by defendant to him, which defendant refused to deliver. It was alleged that the sale was of five miles of such pipe, which defendant contemplated taking up out of its pipe line, and also of whatever additional pipe defendant might take up over and above the five miles, which it is alleged amounted to an additional five miles. The pipe was to be tested at 150 pounds pressure, and was to be delivered at Spindle Top, for which appellant was to pay 20 cents per foot. It is further alleged that only 3775 feet of tested pipe was delivered and in addition 2001 feet which was not tested. Plaintiff sues for the difference between the contract price and the market value of such pipe, alleged to be 20 cents per foot.

Defendant answered by general demurrer, general denial, and specially pleaded that on March 25, 1906, it sold to plaintiff 1826 feet of pipe at 20 cents per foot, which was delivered on April 5, 1906; that on April 20, it sold to him two lots containing 430 feet and 150 feet, and on April 25, 430 feet, all of which was delivered, but, it is alleged, in each instance there was a separate contract of sale. Defendant denies specifically making any other contract of sale of pipe.

The answer further sets up that, the contract being asserted by plaintiff Laughman and denied by defendant, the matter was settled by defendant agreeing to let plaintiff have 3430 feet of pipe at the said price of 20 cents per foot, upon plaintiff's claim that he had contracted to sell and deliver that much in reliance upon what he claimed to be the contract between defendant and himself; that defendant did deliver said 3430 feet of pipe which was taken as a full settlement and compromise of the conflicting claims with regard to the contract, and a full accord and satisfaction.

By supplemental petition plaintiff denied the compromise and settlement. *Page 487

Plaintiff having died pending the suit, his widow and heirs substituted themselves as parties plaintiff.

The evidence was conflicting both as to the making of the contract and the matters pleaded as an accord and satisfaction.

Upon trial with a jury there was a verdict and judgment for defendant, and plaintiffs appeal.

The first assignment of error, when taken in connection with the single proposition under it, presents the question of the refusal of the court to give a charge requested by appellants upon the issue of a contract for the additional pipe over and above the five miles, specifically mentioned. The charge of the court submitted only the issue as to a contract for the sale of five miles of pipe. Appellants requested a charge as to the contract for the additional pipe, instructing the jury to find for plaintiffs if they found that such contract was made. This charge could not have been given as asked without ignoring the defense of accord and satisfaction, which was a complete defense to the contract, that for the five miles and for the excess also, if established by the evidence, and upon which the evidence was amply sufficient to authorize a finding in favor of appellee's plea. The court did not err in refusing to give the charge as requested. Although the court entirely omitted to charge upon the issue of the contract for the excess, limiting the charge to the five miles, we might, upon the authority of Harry v. El Paso El. Co. 37 Texas Civ. App. 90[37 Tex. Civ. App. 90]; and Metcalfe v. Lowenstein, 35 Texas Civ. App. 619[35 Tex. Civ. App. 619], decided by the Court of Civil Appeals of the Fourth District, and several times approved and followed by this court, overrule the assignment as presenting the sole question of the refusal to give the defective charge. If, however, the assignment is treated as presenting the question of the failure of the court to charge upon an issue presented by the pleadings and evidence when its attention is called to the omission by a requested charge, which, although incorrect, is sufficient to call the court's attention to the omission, we are constrained to hold that upon the whole case as presented, while such omission was error, the error was harmless and does not require a reversal of the judgment. Our reasons for such conclusion are as follows:

Appellant declared on a contract made on or about March 25, 1906, for the sale by appellee to him of five miles of the pipe and also a contract made on or about that time for the sale of all of the pipe taken up, in excess of five miles. The allegations of the petition as to this latter contract are rather indefinite both as to the offer and the acceptance, but we think they were sufficient to present the issue. The evidence introduced and relied upon by appellants, to wit, the testimony of G. C. Laughman himself and one Babcock, was clear and positive that one single contract was made which embraced all the pipe taken up, that is, the five miles and the excess. Laughman testified that he said to Pew, appellee's representative, "I will take the five miles of pipe, or will take all the pipe; 6-inch pipe; that you will deliver to me at your plant at Spindle Top tested at 150 pounds pressure at 20 cents per foot," to which Pew replied, "I accept that proposition." Laughman asked him when he could deliver it. Pew said, "I can begin delivering at once; I think I can deliver you two or three carloads this week." Babcock corroborated this conversation substantially. This was the contract *Page 488 and the only contract, as shown by appellant's testimony; in substance a single contract for the purchase and sale of all the pipe taken up by appellee, only speaking of it as five miles and in addition all in excess of that amount, nevertheless a single contract for the whole, asserted by appellants and denied by appellee, whose witness, Pew, testified that there was no contract at all of any character except specific and independent contracts for the sale of the different lots that were actually delivered. In like manner, the only testimony in regard to the facts pleaded as an accord and satisfaction showed either a complete accord and satisfaction of the entire contract as claimed by Laughman, or no accord and satisfaction of any part of it.

The verdict of the jury, under the evidence and the charge of the court, could only have been predicated upon a finding either that no contract for the five miles had ever been made, as testified by Pew, or that, if there had been, the whole matter had been compromised and settled as testified by him. Upon the evidence the jury could not, except in the sense that they had the physical power to write and return such a verdict, have found that there was no contract for the five miles of pipe, but there was a contract for the excess over five miles. Such a verdict is inconceivable from reasonable men, in view of the evidence which showed either one single contract for the whole or no contract for any. For the same reason it is inconceivable that the jury would have found, upon the issue of accord and satisfaction, that this was a settlement of the dispute as to the five miles of pipe, but not a settlement as to the excess. No such result could have been gotten by any process of reasoning out of the evidence. So that if the court had submitted the issue as to the excess of pipe over five miles, it is inconceivable that the jury would have found for appellants upon either the issue of contract, or of accord and satisfaction, as to the excess over five miles, and for appellee as they did do, as to the five miles. (Smith v. Trader's Nat. Bank, 74 Tex. 465; Jones v. Ford, 60 Tex. 131 [60 Tex. 131].)

We do not claim that the authorities above cited are directly in point, but we think they tend to support the general principle that a failure to charge upon an issue presented by the pleadings and evidence would be harmless where a verdict of the jury against appellants upon the issues submitted necessarily includes a finding against them upon the omitted issues, as the question is here presented. The first assignment of error is therefore overruled.

It is contended by the second assignment that the failure of the court to submit the issue as to the excess of pipe over five miles so discredited appellants' evidence as to the contract as to induce the jury to find against them as to the issues submitted, and so was upon the weight of the evidence. There is no merit in the assignment, but it lends force to what has been said, that the jury could not have found for the appellants upon the omitted issue in view of their findings upon the submitted issues. Appellants' contention is that the failure to submit the issue as to the excess was a reflection of the court's view that there was not sufficient evidence to support this issue, and carried with it an intimation that the evidence would not authorize a finding in favor of appellants as to the five miles of pipe, the only possible reason for such conclusion being that there was in fact only one contract. *Page 489

The third assignment of error can not be sustained. The evidence showed a dispute between Pew, appellee's manager, and Laughman as to the existence of any contract at all, Pew stoutly asserting that he had never heard of any such contract until the day the compromise was made. The court properly submitted to the jury the issue as to whether this denial was made by Pew in good faith. There can be no doubt, from the evidence, that it was. In this state of the minds of the respective parties, according to Pew's testimony, it was agreed that as a settlement of the dispute Pew would deliver such pipe as Laughman had contracted to sell, at the price contended for by Laughman, and that this should be a full and final settlement of Laughman's claim, which was agreed to by Laughman, and upon this agreement Pew delivered the agreed amount of pipe, which he was in no way obligated to do, if his contention as to the contract was true. This afforded a sufficient consideration for the contract, and it does not matter if, in fact, Pew's contention was unfounded. It needs only that he acted in good faith in denying all liability. (Hunter v. Lanius, 82 Tex. 685; Little v. Allen, 56 Tex. 138 [56 Tex. 138]; Berdell v. Bissell, 6 Colo. 162; note to Fuller v. Kemp, 20 L. R. A., 795.) The court did not err in refusing the charge set out in the third assignment of error.

There is no merit in the fourth assignment. The testimony as to the settlement tended to show that the price for the pipe then agreed to be delivered by appellee was fixed at 20 cents per foot. Pew testified that he agreed to deliver the pipe at Round Lake at 20 cents per foot, and the memorandum made at the time by Pew and, according to his testimony, assented to by Laughman, so distinctly specifies.

We find no error in the record requiring a reversal. The judgment is affirmed.

Affirmed.