: 1 . f "
to t'„~ JL' f!. I w ' L- J
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
CENTER FOR ENVIRONMENTAL LAW
AND POLICY, AMERICAN No. 74841-6-1
WHITEWATER, and NORTH CASCADES
CONSERVATION COUNCIL, DIVISION ONE
Appellants, UNPUBLISHED OPINION
WASHINGTON DEPARTMENT OF
ECOLOGY; PUBLIC UTILITY DISTRICT
NO. 1 OF OKANOGAN COUNTY,
WASHINGTON; WASHINGTON STATE
POLLUTION CONTROL HEARINGS
BOARD,
Respondents. FILED: July 11, 2016
Appelwick, J. — The Pollution Control Hearings Board (PCHB) affirmed
the Department of Ecology's (Ecology) issuance of a Report of Examination
(ROE), ordering the approval of a water right for the Public Utility District No. 1 of
Okanogan County's (PUD) hydroelectric project. The project would divert water
from a portion of the Similkameen River through a powerhouse. To satisfy the
public interest requirement of RCW 90.03.290, the ROE included a condition that
the PUD would be required to ensure that the minimum flows in the bypass reach
portion of the river would be the same as those found to be adequate to protect
No. 74841-6-1/2
aesthetic values as determined by a future study. Appellants assert that the
PCHB erred in affirming Ecology's issuance of the ROE when the aesthetic study
has not yet been completed and when Ecology did not condition the ROE on the
minimum instream flow rule in WAC 173-549-020. We affirm.
CLEAN WATER ACT CERTIFICATION
The Enloe Dam is located on the Similkameen River near Oroville,
Washington in Okanogan County. Approximately 350 feet downstream from the
dam, there is a natural waterfall known as Similkameen Falls. The dam operated
to produce hydroelectric power from 1922 to 1958. The PUD has owned the
dam since 1945. The PUD seeks to resume hydropower operations at the dam.
Consequently, it launched the Enloe Dam Project (the Project).
The Project includes constructing a new powerhouse for hydropower
generation that will be situated on the bank of the river, raising the height of the
existing dam by five feet and increasing the size of the reservoir behind the dam.
The Project will withdraw water from the reservoir behind the dam, diverting the
water around the dam and through the new powerhouse. The diverted water will
be returned to the river 370 feet downstream from the dam, directly below the
waterfalls. The 370-foot stretch of river impacted by the diversion is referred to
as the "bypass reach."
The PUD has received various federal and state permits or approvals for
the Project. The PUD received a license from the Federal Energy Regulatory
Commission (FERC) for construction of the Project. That license required
Ecology approval of a Section 401 Water Quality Certification (401 Certification)
No. 74841-6-1/3
under the authority of the Federal Clean Water Act (CWA).1 The CWA provides
that a certification made by a certifying agency—here, Ecology2—shall include a
statement that there is a "reasonable assurance that the activity will be
conducted in a manner which will not violate applicable water quality standards."
40 C.F.R. § 121.2(a)(3).
Ecology issued the 401 Certification in July 2012. Ecology had
investigated the proposal for conformance with both state and federal law.
Ecology found reasonable assurance that the operation of the Project would
comply with state and federal water quality standards and other appropriate
requirements of state law. But, it made that finding subject to several conditions.
Among them, Ecology imposed conditions specifically related to the aesthetics of
the Project. One such condition was that the PUD would be required to ensure
that the Project divert water from the reservoir, pipe it around the dam, and
release it near the base of the dam. This would be done at a rate of 30 cubic feet
per second (cfs) from September 16 to July 15 and 10 cfs ("10/30 flows") from
July 16 to September 15, for aesthetic purposes as well as for fish and other
aquatic life purposes. This condition was ostensibly to prevent water from
warming as it flowed over the dam and through the bypass reach—something
that would be harmful for fish. The condition did not require a minimum flow over
the dam. Ecology also required a monitoring program for the period of the
license, with a five year adaptive management approach that required increasing
1 33U.S.C. §§ 1313, 1341
2 RCW 90.48.260 states that the Department of Ecology is designated as
the state water pollution control agency for purposes of the CWA.
No. 74841-6-1/4
and resetting the minimum flows for a season in which water quality standards
were violated.
Several organizations—including the appellants—appealed Ecology's 401
Certification to the PCHB. One issue in the appeal was whether the 10/30 flows
would impair the aesthetics of water flowing over the dam and the falls.
Following cross motions for summary judgment, the PCHB decided that the 401
Certification provided reasonable assurance the Project would comply with
applicable water quality standards regarding temperature, recreation, salmonid
spawning, rearing, and migration. But, regarding aesthetics, the PCHB denied
summary judgment as to the issues regarding aesthetics for flows over the dam
and the falls. Specifically, was there a reasonable assurance that water quality
standards will not be violated regarding (1) Ecology's finding that no minimum
flows are required over the dam, and (2) the adequacy of the 10/30 flows
Ecology established for flows over the falls? As to the first issue, the PCHB
stated that while the dam is not a natural feature, it has created an aesthetic
feature on the river for many decades. And, it stated that minimum flows over
the dam should be considered in determining whether the 401 Certification
properly provides assurance that the operation of the Project will not violate the
water quality standards regarding aesthetics. As to the second issue, the PCHB
noted that there were disputed issues of material fact, because experts stated
No. 74841-6-1/5
that 10/30 flows did not protect aesthetic values of either the dam or the natural
falls. Consequently, the PCHB held a hearing on these issues.3
On August 3, 2013, the PCHB issued a final decision in the 401
Certification appeal. The PCHB found that ifa gate limited the surface water flow
over the dam to a 10-foot width of flow, the temperature of the water as it flows
over the dam would not increase at either 10 cfs or 30 cfs. The PCHB concluded
that expert opinions were not determinative of whether the 10/30 flows, which
included no flows over the dam, was aesthetic. The PCHB concluded that the
evidence before Ecology as to the impact on aesthetics—based on an expert's
"visualization" of the flows, modeling based on aesthetic flows at 20, 40, and 80
cfs, and photo simulations of the views of the falls—was inadequate. It
concluded that there was insufficient evidence to make a finding that the 10/30
flows meet the water quality standards for aesthetic values even when
considering protecting the fisheries. The PCHB concluded that Ecology must
develop a monitoring program of the visual effect of the different flow levels,
which can be implemented as the Project commences and becomes capable of
controlling flows over the dam and the falls. It mandated that the flow plan
3The CWA states that any applicant for a federal license or permit to
conduct any activity, which may result in any discharge into navigable waters,
shall provide the licensing or permitting agency a certification from the State that
the activity will comply with all applicable state and federal water quality
standards and any other appropriate requirement of state law. 33 U.S.C. §
1341(a)(1); 33 U.S.C. § 1341(d). The PCHB noted that the protections for
aesthetics in RCW 90.54.020(a) and (3)(a)—general declaration of fundamentals
for utilization and management of waters in Washington—is recognized as an
"otherappropriate requirement of state law" under the CWA § 401.
No. 74841-6-1/6
should include an analysis of the flows over the dam within the proposed 10-foot
wide release area.
Ultimately, the PCHB affirmed the 401 Certification subject to additional
conditions:
The §401 Certification is affirmed, subject to the additional
condition that 10/30 cfs minimum instream flows over the Dam and
Falls for the aesthetic values shall be further monitored and
evaluated by Ecology during initial operation of the Project (within
three years). After Ecology obtains additional data and analysis of
alternative flows over the Dam and the Falls, the 10/30 cfs flow
shall either be confirmed or revised as a condition of project
operation and the §401 Certification. Ecology shall develop an
aesthetic flow monitoring program ....
As a result of the monitoring program, Ecology shall make a
finding of the aesthetic flows that meet the water quality standards
for aesthetic purposes and is consistent with this Order. At the
completion of the monitoring program, the Project shall operate
subject to those flows and the §401 Certification shall be
conditioned to reflect such flows, either confirming the current flow
regime or revising it based on Ecology's findings.
WATER RIGHTS LAW
Washington has a multistep procedure before new water rights can be
acquired. Lummi Indian Nation v. Dep't of Ecology, 170 Wn.2d 247, 252, 241
P.3d 1220 (2010). Once a party has applied for a water right, Ecology
determines what water, if any, is available and finds and determines to what
beneficial use or uses it can be applied. RCW 90.03.290(1). If Ecology is
satisfied that water is available and the proposed use is a beneficial use, it issues
a permit specifying the amounts of water that can be taken and the beneficial
uses to which that water may be applied. RCW 90.03.290(3). RCW 90.03.290
No. 74841-6-1/7
90.03.290 establishes a four part test that Ecology applies when considering an
application for a water right permit. Postema v. Pollution Control Hr'qs Bd., 142
Wn.2d 68, 79, 11 P.3d 726 (2000). Under the statute, Ecology must affirmatively
find (1) that water is available, (2) for a beneficial use, and that (3) an
appropriation will not impair existing rights, or (4) be detrimental to the public
welfare. RCW 90.03.290(3); Postema, 142 Wn.2d at 79. And, under RCW
90.03.290(1), if the application proposes to appropriate water for the purpose of
power development, Ecology must investigate, determine and find whether the
proposed development is likely to prove detrimental to the public interest, having
in mind the highest feasible use of the waters belonging to the public. Where the
proposed water use threatens to prove detrimental to the public interest, it shall
be the duty of Ecology to reject the application and to refuse to issue the permit
asked for. RCW 90.03.290(3).
A water right permit represents only an inchoate right, which does not
become choate until the water right is perfected. Lummi, 170 Wn.2d at 253.
Before the right is perfected, the applicant has only an incomplete appropriate
right in good standing. kL It remains in good standing so long as the
requirements of law are being fulfilled, and it matures into an appropriative water
right on completion of the last step provided by law. \± RCW 90.03.330 governs
water right certificates. Upon a showing satisfactory to Ecology that any
appropriation has been perfected in accordance with the provisions of chapter
90.03 RCW, Ecology will issue to the applicant a certificate and it will be
recorded with Ecology. RCW 90.03.330(1).
No. 74841-6-1/8
WATER RIGHT PROCEEDINGS
Shortly after the PCHB issued its final decision in the 401 Certification
appeal, on August 6, 2013, Ecology issued a ROE and ordered the approval of
Water Right Permit No. S4-35342.4 The water right will authorize the PUD to
withdraw an additional 600 cfs of water from the river behind the dam. The ROE
noted that the only affected portion of the river would be the bypass reach with
flows in the river otherwise remaining unchanged. Consequently, Ecology
considered the use of the water to be non-consumptive,5 except with regard to
the bypass reach. The 10/30 minimum flows required by the 401 Certification
were incorporated into the ROE:
The water right holder must comply with Ecology's 401 Water
Quality Certification No. 9007, related to licensing of the Enloe
Hydroelectric Project (FERC No. 12569) on the Similkameen River,
Okanogan County, Washington issued on July 13, 2012, and any
subsequent updates.
The ROE also stated that if the 401 Certification is modified in the future, the
water right would be subject to the conditions of the revised 401 Certification.
After Ecology issued the ROE, the Center for Environmental Law and
Policy, American Whitewater, North Cascades Conservation Council (collectively
"CELP"), and Columbia River Bioregional Education Project, appealed to the
PCHB seeking that it find the ROE invalid. The PUD filed a motion for summary
judgment on all issues raised. Ecology filed a joinder in support of the PUD's
4 That ROE is the subject of this appeal.
5Water used consumptively diminishes the source and is not available for
other uses. By contrast, non-consumptive water use does not diminish the
source or impair future water use.
8
No. 74841-6-1/9
motion. On March 31, 2014, CELP filed a cross motion for summary judgment.
CELP made three arguments. First, it argued that Ecology has not and cannot
meet its statutory duty to make a final public interest determination under RCW
90.03.290 until it completes the aesthetic flow study mandated in the 401
Certification. Secondly, it argued that because Ecology lacked adequate
information to make a public interest determination, it could only deny the water
right or issue a preliminary permit. Finally, it asserted that the ROE does not
condition the PUD's water right on the Similkameen's instream flows as required
by WAC 173-549-020. Both parties agreed that there were no genuine issues of
material fact and that the matter could be resolved on summary judgment.
On June 24, 2014, the PCHB issued an order granting summary judgment
in favor of the PUD and Ecology:
Ecology's approval of the application based on the terms and
conditions of the ROE is AFFIRMED on all substantive grounds,
with the exception that Ecology shall issue the permit with a
condition that sets forth the protocol for the aesthetic flow study in
the same language as the Board had ordered for the §401
Certification, and upon completion of the study the permit shall be
amended specifying the aesthetic minimum instream flows that
shall be protected if it is other than the 10/30 flows.
It concluded that a water right certificate shall not issue prior to the completion of
the study and the permit amendment.
On July 24, 2014, CELP filed a petition for review6 of the PCHB's decision
in Thurston County Superior Court. It asserted that the PCHB's decision and the
underlying ROE decision were arbitrary and capricious, because of their
6 Columbia River Bioregional Education Project did not join the petition for
review.
No. 74841-6-1/10
deliberate and unreasoned disregard of the facts and circumstances, including
legal mandates set forth in RCW 90.03.290 and WAC 173-549-020. The
superior court affirmed the PCHB's decision, reasoning that CELP failed to carry
its burden of showing that the PCHB erred when it determined that it would be in
the public interest to issue the ROE subject to the same criteria that additional
facts be gathered as it did for the 401 Certification.
CELP filed a notice of appeal to this court, challenging the superior court's
judgment upholding the PCHB's decision granting PUD and Ecology summary
judgment.7
DISCUSSION
CELP makes three main arguments in this appeal. First, it argues that the
PCHB erred in finding that PUD's water permit complied with RCW 90.03.290's
public welfare requirement. It contends this is so, because Ecology improperly
made this determination in the face of incomplete information: the aesthetic study
required by the 401 Certification is not yet complete. Secondly, it claims that
when faced with this incomplete information Ecology had the discretion only to
deny the permit or issue a preliminary permit—not issue the ROE. Finally, it
argues that the PCHB erred in finding that the ROE did not violate the minimum
instream requirements in WAC 173-549-020.
7Northwest Hydroelectric Association (NHA) filed an amicus curiae brief in
this case opposing CELP's appeal. CELP argues that this court should disregard
NHA's brief. And, in a motion to strike, CELP asserts that the panel should strike
PUD's response to NHA's brief. Because we did not rely on the information in
the amicus curiae brief—or in PUD's response—in reaching our decision, we
need not rule on CELP's motion to strike.
10
No. 74841-6-1/11
We review PCHB orders under the Washington Administrative Procedures
Act (WAPA).8 Port of Seattle v. Pollution Control Hr'qs Bd.. 151 Wn.2d 568, 587,
90 P.3d 659 (2004). This court reviews the PCHB's action from the same
position as the superior court and applies WAPA standards directly to the
PCHB's record. Skagit Hill Recycling, Inc. v. Skagit County, 162 Wn. App. 308,
317-18, 253 P.3d 1135 (2011). Under WAPA, the party challenging an
administrative order or agency action—here, CELP—bears the burden of
demonstrating its invalidity. Port of Seattle, 151 Wn.2d at 587; RCW
34.05.570(1)(a). WAPA authorizes relief in only certain circumstances, including
if the agency's order is outside the statutory authority or jurisdiction of the
agency, if the agency erroneously interprets or applies the law, or if the order is
arbitrary and capricious. RCW 34.05.570(3). Administrative action is arbitrary
and capricious if it is willful, unreasoned, and taken without regard to the facts
and circumstances. Dep't of Ecology v. Theodoratus, 135 Wn.2d 582, 598, 957
P.2d 1241 (1998).
Where, as here, the original administrative decision was on summary
judgment, the reviewing court overlays the WAPA standard of review with the
summary judgment standard. Skagit Hill. 162 Wn. App. at 318. This court
reviews the PCHB's ruling made on summary judgment de novo, making the
same inquiry as the PCHB. Cornelius v. Dep't of Ecology, 182 Wn.2d 574, 585,
344 P.3d 199 (2015). This court's review is limited to the record before the
PCHB. Puget Soundkeeper All, v. Pollution Control Hr'gs Bd., 189 Wn. App.
8 Chapter 34.05 RCW
11
No. 74841-6-1/12
127, 135, 356 P.3d 753 (2015). Accordingly, this court reviews the facts in the
record in the light most favorable to the nonmoving party. Skagit Hill, 162 Wn.
App. at 318. Summary judgment is appropriate only where the undisputed
material facts entitle the moving party to judgment as a matter of law. JcL
Ecology's decision to issue water appropriation permits under RCW
90.03.290 is discretionary and, therefore, will not be reversed absent a clear
showing of abuse. Dep't of Ecology v. U.S. Bureau of Reclamation, 118 Wn.2d
761, 767, 827 P.2d 275 (1992).9 A party seeking a reversal under this standard
must show that the discretion was exercised in a manner which was manifestly
unreasonable or exercised on untenable grounds or for untenable reasons. Id.
Here, the PCHB concluded that a water right certificate shall not issue
prior to the completion of the aesthetic study. And, it affirmed Ecology's decision
to issue a ROE on all substantive grounds.10 Therefore, the ultimate issues we
must decide are (1) whether Ecology had the authority to issue a ROE, ordering
the approval of an inchoate water right subject to the condition that it be
9 CELP argues that the standard of review is de novo. It notes that this
case poses purely a legal question—whether Ecology properly interpreted and
applied RCW 90.03.290 to authorize a water right in the face of incomplete
information. But, the issue in Bureau of Reclamation—a case in which the court
noted that Ecology's decision to issue water appropriation permits is
discretionary—was whether Ecology abused its discretion in interpreting RCW
90.03.290. 118 Wn.2d at 767. To the extent that the issues in the case call for
this court to determine whether Ecology properly interpreted RCW 90.03.290
when it issued the water right, we apply the abuse of discretion standard.
10 The PCHB determined that Ecology shall issue the permit with specific
language referencing the protocol for the aesthetic flow study in the same
language as the PCHB had ordered for the 401 Certification. CELP does not
challenge the PCHB's actions, only its final decision granting summary judgment.
12
No. 74841-6-1/13
potentially later revised to adhere to the flows deemed sufficient by a future
aesthetic study and (2) whether it abused its discretion in doing so.
I. Public Interest
CELP asserts that the PCHB erroneously interpreted and applied the law
by affirming Ecology's issuance of the ROE when the 401 Certification study had
not yet been completed. It contends that it was contrary to law for the PCHB to
assume as a matter of law that there will be no detriment to the public interest
when it is undisputed that additional information is needed to make the public
interest11 determination. CELP asserts that because there is no credible
evidence yet as to how the 10/30 flows will appear aesthetically over the dam
and the falls, that Ecology could not make the public interest finding.
RCW 90.03.290 establishes a four part test that Ecology applies when
considering an application for a water right. Postema. 142 Wn.2d at 79. Under
the statute, Ecology must affirmatively find (1) that water is available, (2) for a
beneficial use, and that (3) an appropriation will not impair existing rights, or (4)
be detrimental to the public welfare.12 RCW 90.03.290(3); Postema. 142 Wn.2d
11 The parties somewhat interchangeably use "public interest" and "public
welfare." This is likely because RCW 90.30.290 refers to both. The use of the
different terms does not appear to impact the parties' arguments nor does it
impact our analysis.
12 We note that Ecology and PUD emphasize that Ecology need only
make a finding that the Project would not likely prove detrimental to the public
welfare. While RCW 90.03.290(1) states that if a proposed water appropriation is
for the purpose of power development, Ecology's investigation should focus on
finding whether the proposed development is likely to prove detrimental to the
public interest, RCW 90.03.290(3) states that Ecology must enter a finding that
the water will not be detrimental to the public welfare. Thus, this distinction is
ultimately immaterial to determining whether Ecology had the authority to
13
No. 74841-6-1/14
at 79. Aesthetics is a component of the public interest analysis. See RCW
90.54.020(1). Management and utilization of Washington waters are guided by a
general declaration of fundamentals in RCW 90.54.020. RCW 90.54.020(1)
establishes which uses of water are deemed beneficial. Use for hydroelectric
power production and preservation of environmental and aesthetic values is
considered beneficial. Id RCW 90.54.020(3)(a) states that the quality of the
natural environment shall be protected and, where possible, enhanced such that
perennial rivers and streams shall be retained with base flows necessary to
provide for preservation of wildlife, scenic, aesthetic and other environmental
values, and navigational values.
While evaluating the Project, Ecology considered the four part test
outlined in RCW 90.03.290. In so doing, Ecology did not ignore the fact that
aesthetics is a necessary component of the public interest finding. It squarely
acknowledged the necessity of protecting aesthetics. In the 401 Certification
appeal, the PCHB noted there was evidence in the record that flows could not be
manipulated under existing conditions. There was testimony that collecting good
data and taking accurate measurements in the bypass reach for the purpose of
analyzing different flow regimes over the falls would be dangerous based on the
velocity of the flows. In order to get the necessary facts to address the
aesthetics issue, the Project had to proceed subject to further study.
condition the water right on the flow monitoring study before it had the results of
the study.
14
No. 74841-6-1/15
Ecology incorporated the same study conditions that the PCHB imposed
on the 401 Certification—which were based on this same statutory aesthetics
provision—to ensure that the spirit of the law was carried out.13 As to the public
welfare requirement, Ecology found:
Given that this project will produce valuable electrical energy and
will do so in a sustainable manner, that the impacts on the bypass
reach are reduced from those under previous project scenarios,
that minimum instream flows necessary to protect the aesthetic and
instream resources in the bypass reach will be a required condition
of project operation, and that any negative impacts are further
mitigated by the downstream discharge channel, there is no basis
on which to determine that this project will be detrimental to the
public welfare.
The PCHB addressed whether this finding could be made and should be
sustained:
This case is unique because the §401 Certification has already
been approved with a condition for a study to determine the
aesthetic flows. Ecology will be developing these aesthetic flows in
compliance with the Water Resources Act of 1971, ch. 90.54 RCW,
which requires the protection of designated beneficial uses such as
aesthetics, and using the authority of the water code for issuing
water rights and the CWA for issuing a §401 Certification. In their
appeal of the ROE, the Appellants specify that they "do not seek
additional aesthetic analysis outside of the 401 Certification
Process or challenge the sufficiency of the aesthetic flow-
monitoring program required in the PCHB's 401 Certification
decision." Under these circumstances, Ecology properly exercised
its discretion to authorize the permit and address the public interest
requirements of preserving aesthetic values with similar
requirements in the §401 Certification.
13 CELP argues that because water rights and 401 Certifications are
distinct permits with different purposes that are issued pursuant to different
statutory authority and standards, it was error for the PCHB to base its public
interest finding on the outcome of the 401 Certification aesthetic flow test. But,
the PCHB did not base its public interest finding on the outcome of that test. It
made the finding subject to the condition that the ROE eventually adhere to the
flows deemed acceptable in the aesthetic flow test.
15
No. 74841-6-1/16
Further, unlike in Black Rock[14] or Squaxin Island1151, this is not a
case in which available information shows that the applicant cannot
meet some aspect of the four-part test for a water right. Rather, the
Board concluded that some additional assessment is needed to
finalize the appropriate level of aesthetically protective flows on the
Similkameen River in the area of the project.
(Internal citations omitted.) We agree with this analysis. And, the PCHB
specifically added language mandating that a final water right certificate cannot
issue prior to the completion of the aesthetic study and the permit amendment, if
necessary.16 On this record, Ecology's finding that the public welfare
requirement was satisfied was not arbitrary and capricious. Ecology did not
abuse its discretion approving the ROE with the conditions imposed.
Next, CELP maintains that because the PCHB found that additional
monitoring and analysis of actual minimum flows is necessary to assess the
14 Black Star Ranch Neigh. Ass'n v. Dep't of Ecology, No. 87-19 (Wash.
Pollution Control Hr'gs Bd. Feb. 19, 1988) (It is clear from the record that the
PCHB's reference to "Black Rock" was in fact a reference to "Black Star.").
1* Sguaxin Island Tribe v. Dep't of Ecology, No. 05-137 (Wash. Pollution
Control Hr'gs Bd. Nov. 20, 2006).
16 CELP asserts that the study required by the 401 Certification may show
that there is no flow level that protects both aesthetic values and the fishery
resource—a higher minimum flow may result in too high of temperatures in the
bypass reach. And, it asserts that it is possible that the aesthetic flow study
could result in a required flow that is so high that it renders the Project
uneconomical and unacceptable to PUD. We accept that this is a possibility. In
fact, we acknowledge at least three possibilities: (1) The study may indicate that
either the 10/30 flows or a different flow level is protective of aesthetics, the
fishery resource, and would be sufficient to support the Project; (2) The study
may indicate that there is no flow level that is protective of both the fishery
resource and aesthetics, and Ecology may withdraw the water right permit; (3)
The study may indicate that there is no flow level that is protective of both the
fishery resource and aesthetics, and Ecology may still decide to issue the final
water certificate. Importantly, Ecology's decision to amend or not amend the
conditions after the study will be subject to challenge.
16
No. 74841-6-1/17
proper protection of aesthetic values, Ecology's discretion was limited by statute
to either deny the permit or issue a preliminary permit.
RCW 90.03.290(2)(a) states that if a water appropriation application does
not contain and the applicant does not promptly furnish sufficient information on
which to base findings that the proposed development is not likely to prove
detrimental to the public interest, Ecology may issue a preliminary permit. The
permit may be valid for up to three years while requiring the applicant to
complete investigations or studies. RCW 90.03.290(2)(a). CELP recognizes that
the language of this statute is clearly discretionary.
CELP also agrees Ecology has the inherent authority in its discretion to
impose conditions on any permit it issues. See Theodoratus, 135 Wn.2d at 597
(stating that generally, an agency which has authority to issue or deny permits
has authority to condition them); State v. Crown Zellerbach Corp., 92 Wn.2d 894,
899-900, 602 P.2d 1172 (1979) ("[T]he power to disapprove [a permit]
necessarily implies the power to condition an approval."). However, it asserts
that when the information to make one of the four required findings under the
statute is lacking, a preliminary permit is the only mechanism for the permit
application to move forward.
The PCHB responded to this argument by noting:
The Board finds [RCW 90.03.290(2)(a)] to be unambiguous. See
State v. Keller, 143 Wn.2d 267, 276, 19 P.3d 1030 (2001) ("The
courts do not engage in statutory interpretation of a statute that is
not ambiguous[.]"). Rather than limiting Ecology's authority to issue
a permanent new water right, the plain language of the statute
provides Ecology with authority to issue a different kind of permit (a
"preliminary permit") that ensures the application can remain in
17
No. 74841-6-1/18
good standing while the applicant undertakes "such surveys,
investigations, studies, and progress reports, as in the opinion of
the department may be necessary." RCW 90.03.290(2)(a). The
decision whether to issue a preliminary permit in lieu of a
permanent new water right, when information is incomplete on an
aspect of the four-part test, is still a choice that remains within
Ecology's discretion.
We agree. The statute is not ambiguous and does not require construction.
Nothing in RCW 90.03.290(2) limits Ecology's authority to impose conditions on
permits that are not issued pursuant to that section. Therefore, we reject CELP's
argument that Ecology had the authority to issue only a preliminary permit or to
deny the permit.
We conclude that Ecology had authority to issue a ROE, and water permit,
which was subject to a condition to ascertain information that was not available
prior to proceeding with the Project. Ecology did not abuse its discretion in
determining that the PUD's water permit should issue subject to the stated
conditions. We hold that the PCHB properly granted respondents' motion for
summary judgment on these issues.
II. Minimum Instream Flow Rule
Next CELP argues that the PCHB erred when it found that the ROE did
not violate the minimum flow requirements in WAC 173-549-020. WAC 173-549-
020(2) establishes a minimum instream flow for the Similkameen River—
between 400 cfs and 3,400 cfs depending upon the month. WAC 173-549-
020(5), however, states that projects that would reduce the flow in a portion of
the stream's length (such as a hydroelectric project that bypasses a portion of the
stream) will be subject to instream flows as specified by Ecology. The flows may
18
No. 74841-6-1/19
be those established in WAC 173-549-020 or, when appropriate, may be flows
specifically tailored to that particular project and stream reach. WAC 173-549-
020(5).
The PCHB found that WAC 173-549-020(5) explicitly excludes those
projects that reduce the flow in only a portion of a stream's length from
compliance with the minimum instream flows established by WAC 173-549-
020(2). As a result, it found that the minimum instream flows for the
Similkameen River in WAC 173-549-020(2) do not apply to the Project unless
Ecology decides to apply those flows in its discretion.
This court shows deference to an agency's interpretation of its own
regulations. Puget Soundkeeper, 189 Wn. App. at 136. Nonetheless, the
agency's interpretation is not binding and deference to an agency is
inappropriate where the agency's interpretation conflicts with a statutory
mandate, ig\ To interpret agency regulations, this court applies the same
principles used to interpret statutes. ]d_.
CELP argues that the ROE improperly invoked the exception in WAC 173-
549-020(5) and does not condition PUD's water right on the minimum instream
flows as required by law. CELP notes that the general rule for instream flows is
outlined in RCW 90.03.247 ("Whenever an application for a permit to make
beneficial use of public waters is approved relating to a stream or other water
body for which minimum flows or levels have been adopted and are in effect at
the time of approval, the permit shall be conditioned to protect the levels or
flows."). CELP notes that there is only one statutory exception to the general
19
No. 74841-6-1/20
rule—RCW 90.54.020(3)(a). RCW 90.54.020(3)(a) states that withdrawals of
water which conflict with base flows necessary to provide for preservation of
wildlife, fish, scenic, aesthetic and other environmental values shall be authorized
in only those situations where it is clear that overriding considerations of the
public interest (OCPI) shall be served.
CELP maintains that even if the regulatory exception outlined in WAC
173-549-020(5) applies, all water right applications must first satisfy the OCPI
exception in RCW 90.54.020(3)(a). CELP asserts there was no such finding
here. CELP cites to Swinomish Indian Tribal Community, v. Department of
Ecology, 178 Wn.2d 571, 311 P.3d 6 (2013), to support its assertion. In
Swinomish, Ecology issued an amended instream rule. Id at 577-78. That rule
authorized appropriations of water that would impair the minimum instream flows
based on Ecology's finding that the uses of the water were for "overriding
considerations of the public interest" pursuant to RCW 90.54.020(3). 178 Wn.2d
at 576. The Swinomish court held that the OCPI exception does not permit
Ecology to reallocate water that is needed to maintain the instream flows through
reservations of water for future beneficial uses. Id. at 602.
CELP also cites to Foster v. Department of Ecology, 184 Wn.2d 465, 362
P.3d 959 (2015) to support its assertion. Foster involved a challenge to a water
right permit issued by Ecology to a city. Id at 468-69. The city's application was
for a municipal water permit to meet the water needs of the city's growing
population. Id at 469. Because the appropriation would impair the minimum
flows of two waterways, the city created a mitigation plan and Ecology approved
20
No. 74841-6-1/21
the permit conditioned on the mitigation plan. Jd at 469. Citing to Swinomish,
the Foster court held that Ecology exceeded its authority by approving the city's
water permit under the narrow OCPI exception, because the exception permits
only temporary impairment of minimum flows—not the permanent impairment of
minimum flows. Id at 474-75. CELP argues that likewise, here, the water right
would permanently impair the instream flows adopted in the minimum instream
flow rule. It argues that permanent impairment of an instream flow under the
guise of an exception that is not compliant with RCW 90.54.020 is precisely what
Foster forbids.
Unlike in Swinomish and Foster. Ecology did not approve the water right
under the OCPI exception. And, this was not because Ecology erroneously
skipped over the OCPI exception step. Instead, Ecology did not need to invoke
that exception, because it invoked the regulatory exception in WAC 173-549-
020(5)—a rule promulgated under chapters 90.22 RCW and 90.54 RCW.17 RCW
90.22.010 grants Ecology express authority to establish minimum water flows.
And, RCW 90.54.040 provides that Ecology is directed, through the adoption of
rules, to insure that the waters of the state are utilized in the best interest of the
people. WAC 173-549-020(1) establishes the minimum instream flows for the
Similkameen River. And, WAC 173-549-020(5) provides a minimum instream
flow exception for hydroelectric projects such as the PUD's that are consumptive
for only a portion of the stream's length. Chapter 90.22 RCW and 90.54 RCW
17 RCW 90.03.247 also establishes that Ecology has the exclusive
authority to establish minimum flows and levels.
21
No. 74841-6-1/22
authorized the adoption of WAC 173-549-020, and it went through the
rulemaking process. Therefore, whether Ecology can decrease the minimum
instream flow via a regulatory exception has been resolved. Notably, CELP does
not challenge the validity of WAC 173-549-020. The plain language of WAC 173-
549-020(5) is clear, and it carves out a regulatory exception to WAC 173-549-
020(1) and (2)'s minimum flows notwithstanding the statutory OCPI exception in
RCW 90.54.020(3)(a).
Still, CELP contends that when Ecology invokes the exception set forth in
WAC 173-549-020(5), which authorizes a deviation from the instream flows set
by rule, it must do so in a manner that complies with the requirements of RCW
90.54.020(3)(a). CELP argues that, in this case, Ecology failed to comply with
RCW 90.54.020 by "specifically tailoring" flows for the Project as is required
under WAC 173-549-020(5). CELP maintains that "specifically tailor" implies that
there must be some basis to justify the alternative flow. And, that Ecology's
exclusive reliance on flows that have been deemed in need of further study by
the PCHB was not a "specific tailoring" to the Project and stream reach.
But, the aesthetic flow testing required by the 401 Certification and
incorporated into the ROE is plainly designed to result in instream flows that are
specifically tailored to the particular circumstances of the Project. CELP provides
no support for its implicit assertion that the flows specifically tailored to the
Project need be definitively determined before issuance of the ROE. The flow
study required by the 401 Certification may confirm that the 10/30 flows are
protective of aesthetic values, in which case the flows need not change, or it may
22
No. 74841-6-1/23
trigger amendment of the flows in the 401 Certification and the ROE. In other
words, the flows will be specifically tailored. CELP did not carry its burden of
demonstrating that the ROE violates the minimum instream flow rule.
Consequently, we hold that the PCHB did not err when it granted summary
judgment on this issue.18
We affirm.
WE CONCUR:
\A4^i
f 7
X
18 Because CELP is not the prevailing party, its request that this court
award it attorney fees and costs pursuant to RCW 4.84.350 is moot.
23