Filed 7/14/16 City of Selma v. City of Kingsburg CA5
NOT TO BE PUBLISHED IN THE OFFICIAL REPORTS
California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for
publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication
or ordered published for purposes of rule 8.1115.
IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA
FIFTH APPELLATE DISTRICT
CITY OF SELMA,
F071156
Plaintiff and Appellant,
(Super. Ct. No. 12CECG03223)
v.
CITY OF KINGSBURG, OPINION
Defendant and Respondent.
APPEAL from a judgment of the Superior Court of Fresno County. Jeffrey Y.
Hamilton, Jr., Judge.
Costanzo & Associates and Neal E. Costanzo for Plaintiff and Appellant.
Kahn, Soares & Conway, Rissa A. Stuart and Michael J. Noland for Defendant
and Respondent.
-ooOoo-
INTRODUCTION
The City of Kingsburg (Kingsburg) recently expanded its boundaries by annexing
approximately 430 acres of land. Before approving the annexation, Kingsburg concluded
the project would not cause any unmitigated significant environmental impacts.
Accordingly, Kingsburg prepared a mitigated negative declaration.
Shortly after approving the annexation, Kingsburg repealed certain design
standards applicable to the annexation area. Kingsburg determined the repeal was
exempt from the California Environmental Quality Act (CEQA) (Pub. Resources Code,1
§ 21000 et seq.) because it was “certain” there was “no potential” for the repeal to cause
environmental impacts. (See Cal. Code Regs., tit. 14, § 15061, subd. (b)(3)
[commonsense exemption].)2
With respect to the annexation project, we conclude the City of Selma (Selma) has
failed to carry its burden in challenging Kingsburg’s CEQA compliance. However, with
respect to the repeal of the design standards, we conclude Kingsburg failed to carry its
burden of demonstrating the commonsense exemption to CEQA applies.
Consequently, we affirm the judgment denying Selma’s petition for a writ of
mandate concerning the annexation project, and we reverse the judgment denying
Selma’s petition for a writ of mandate concerning the repeal of the design standards.
FACTUAL AND PROCEDURAL HISTORY
I. The Annexation Project
A. Background
A city may pass a resolution seeking to annex territory into its boundaries. (See
Gov. Code, § 56375, subd. (a)(4).) In 2012, Kingsburg studied a proposed project to
annex approximately 430 acres of land in Fresno County (the Annexation Territory). The
Annexation Territory is “roughly triangular in shape” and “generally bounded by
Mountain View Avenue on the north, Bethel Avenue on the east, and State Route 99
along the south and west.” Three hundred and fifty acres of the Annexation Territory
was already developed “with industrial/commercial uses.” Another 52 acres were
1Undesignated statutory references are to the Public Resources Code.
2The Guidelines for the Implementation of the California Environmental Quality Act
(Cal. Code Regs., tit. 14, § 15000 et seq.) will hereinafter be referred to as the CEQA Guidelines.
2.
undeveloped, and the remainder of the Annexation Territory consists of street rights-of-
way. The Annexation Territory is home to facilities run by Sun-Maid Growers of
California, Vie-Del Company, and Guardian Industries Corp.
The proposal provided that a portion of the Annexation Territory would be
annexed to the Selma-Kingsburg-Fowler County Sanitation District. The project also
involved detaching the Annexation Territory from the Fresno County Fire Protection
District, the Consolidated Irrigation District, and the Kings River Conservation District.
Finally, the project included prezoning a portion of the Annexation Territory.
B. Initial Environmental Analyses
1. Initial Study and Mitigated Negative Declaration
Kingsburg studied the annexation project, ostensibly to determine whether it may
have a significant effect on the environment under CEQA. Kingsburg prepared a
combined written initial study and mitigated negative declaration (MND) dated April 25,
2012. (See CEQA Guidelines, §§ 15365, 15369.5.) The study identified the
environmental factors potentially affected by the project as: biological resources,
greenhouse gas emissions, public services, agricultural resources, cultural resources,
utilities/services systems, air quality, hydrology/water quality, noise, and
transportation/traffic. The study found that with respect to each of the environmental
factors, the project would either have no impact, a less than significant impact, or a less
than significant impact with mitigation. As a result, Kingsburg concluded it could
proceed with an MND rather than an environmental impact report (EIR). The MND’s
analysis is discussed in further detail below in connection with the issues raised on
appeal.
3.
2. Service Plan for the Annexation Territory
Kingsburg prepared a document dated July 2012 entitled “City of Kingsburg
Service Plan [for the] Guardian/Sun-Maid Reorganization” (Service Plan).3 It begins
with a description of the Annexation Territory and the observation that “[a] plan for
providing services and improvements to land being annexed to cities is required by the
Local Agency Formation Commission (LAFCo) ….” It discusses several categories of
local services, including water, sanitation, storm water drainage, solid waste collection,
police and fire protection, ambulance and paramedic service, street lighting, parks and
recreation, transit services, schools, public rights-of-way, and “[o]ther services.”
With respect to water supply, the Service Plan indicated:
“Currently, the three industries that occupy all of the parcels within the
subject territory have their own water systems. The Guardian Industries
glass plant, Vie-Del grape processing facility and Sun-Maid Growers raisin
plant each have two on-site water wells. Through an extra-territorial
agreement with George and Lousie [sic] Alves, dba G & L Enterprises,
13281 Golden State Boulevard, to extend a water main from Kamm
Avenue to Amber Lane [sic]. Once the annexation has been approved
ownership of the water main will transfer to [Kingsburg] and be made
available for connection to all adjoining properties.”
Though the Service Plan is dated July 2012, there is evidence indicating it was
prepared at a later date. In an e-mail correspondence on November 2, 2012, staff at
LAFCo informed Kingsburg staff that a service plan was required. Kingsburg staff
responded by asking what a service plan was, and they were provided an exemplar by
LAFCo on November 8, 2012. This information suggests the Service Plan was not
prepared in July 2012, but rather sometime on or after November 8, 2012.
3This document appears in the record of proceedings of a separate CEQA lawsuit against
the Fresno County Local Agency Formation Commission concerning the annexation project.
This separate suit is discussed below.
4.
3. August 15, 2012, Staff Report
Kingsburg’s consulting Planning and Development Director, Darlene Mata,
authored a staff report dated August 15, 2012. The report notes Kingsburg had entered
into a “Transition Agreement” with the Fresno County Fire Protection District “wherein
[Kingsburg] agree[d] to transfer certain tax revenues to the District for each annexation
covered by the Transition Agreement.” The report observes the term of the Transition
Agreement would end on December 31, 2012, and Kingsburg was “currently in
negotiations with the Fresno County Fire Protection District in hopes of agreeing upon
the terms of a new Transition Agreement.”
Mata’s August 15, 2012, report also indicated Kingsburg had received a draft EIR
for a project called “Selma Crossings.” The Selma Crossings project was a proposal to
develop approximately 307 acres adjacent to the Annexation Territory. The Selma
Crossings project planned to include retail stores, offices, residences, an auto mall, two
hotels, and a water park. Mata’s report indicated the Selma Crossings project “will have
significant and unavoidable environmental impacts.” However, Mata’s report concluded
the planned annexation and prezoning actions do “not incrementally contribute to the
[sic] any environmental impacts resulting from the Selma Crossings project ….” (See
CEQA Guidelines, § 15064, subd. (h).)
C. City Council Actions in September 2012
On September 5, 2012, the Kingsburg City Council certified the MND and
requested LAFCo initiate proceedings to effect the annexation. On September 19, 2012,
the Kingsburg City Council prezoned approximately 183 acres of the Annexed Territory
as “Highway Commercial” and “Light Industrial.”
5.
Addendum to the MND
At some point, an undated addendum to the MND was prepared (the Addendum).4
The Addendum indicated the Transition Agreement between Kingsburg and the Fresno
County Fire Protection District had expired. The Addendum stated the expiration of the
Transition Agreement “will not result in new or increased impacts to fire protection
services upon approval of the annexation as the agreement only addressed financial
considerations.” It then noted that the “City of Kingsburg Fire Department has sufficient
capacity to service the proposed annexation area with both fire and emergency services.”
D. Filing of the Annexation Project Lawsuit
On October 5, 2012, Selma filed a petition for writ of mandate in superior court
alleging, among other things, that Kingsburg failed to adequately consider the
environmental impacts of the 430-acre annexation and prezoning project (the Annexation
action).
E. LAFCo Approval
LAFCo approved Kingsburg’s annexation on July 17, 2013. On August 23, 2013,
Selma filed suit in superior court challenging LAFCo’s approval of the Kingsburg
annexation on several grounds, including alleged CEQA violations (the LAFCo action).
Because the LAFCo action was brought, in part, under CEQA, a record of proceedings
was prepared.5 (See § 21167.6.)
4Since the Transition Agreement was set to expire on December 31, 2012, and the
Addendum refers to that expiration in the past tense, the Addendum was presumably prepared
sometime after December 31, 2012. A version of the Addendum appearing in the LAFCo
action’s record of proceedings has a notation at the top that reads “Draft 040113,” suggesting the
document was completed sometime after April 1, 2013.
5The LAFCo action is not part of the present appeal. However, we granted Selma’s
motion to augment the appellate record in this case with the LAFCo action’s record of
proceedings. We expressly reserved ruling on whether, and to what extent, the LAFCo action’s
record of proceedings is relevant to the issues presented in this appeal.
6.
II. The North Kingsburg Specific Plan
A. Background
“‘The Legislature has required every county and city to adopt “a comprehensive,
long-term general plan for the physical development of the county or city.…” (Gov.
Code, § 65300.) A general plan provides a “‘charter for future development’” and sets
forth a city or county’s fundamental policy decisions about such development.’
[Citation.]” (San Francisco Tomorrow v. City and County of San Francisco (2014) 229
Cal.App.4th 498, 508.) A city is also empowered to prepare “specific plans” to
systematically implement the general plan “for all or part of the area covered by the
general plan.” (Gov. Code, § 65450.)
On July 6, 2005, Kingsburg adopted the “North Kingsburg Specific Plan” (NKSP).
The NKSP was divided into seven parts. Part VI set forth community design standards
for the industrial corridor. The community standards addressed various aspects of design,
including building setbacks, architectural guidelines, off-street parking, landscape
guidelines, walkways, bike lines, and signs.
B. Guardian Industries Corp. Voices Concerns Relating to the NKSP
One of the largest commercial developments in the Annexation Territory is a glass
manufacturing plant run by Guardian Industries Corp. (Guardian). In an April 4, 2013,
letter, Guardian conveyed to Kingsburg its concerns about how “potentially inconsistent”
provisions of the Kingsburg Municipal Code and the NKSP could affect potential future
changes in the use of Guardian’s property. The letter listed several concerns, such as
Guardian’s fear that the NKSP’s requirement that electrical and telecommunication lines
be “undergrounded” would “render any future expansion or modification to the
[Guardian] facility infeasible.”
7.
C. Recommendations to Repeal Part VI of the NKSP
On May 15, 2013,6 Mata advised the city council in a written report that “there are
sections of the NKSP that would seem to impose very stringent requirements on the
Guardian site if Guardian were to expand or modify the plant.” The report also noted
Guardian had submitted a letter to LAFCo opposing the annexation.
Mata recommended the city council repeal part VI of the NKSP, which would
“eliminate the standards that are of concern to Guardian and allow staff the opportunity to
draft more reasonable and consistent standards for the business uses in the Heavy
Industrial zone district.” The new standards would be considered by the planning
commission and the city council at a future date.
D. June 5, 2013, Report and Public Hearing
A report from Mata, dated June 5, 2013, recommended the city council find that
repealing part VI of the NKSP is exempt from CEQA because it would “not result in a
physical change to the environment.” Mata observed that repealing part VI of the NKSP
“would not result in a lack of standards for the NKSP Planning Area” because it “would
be subject to the standards and policies found in the Zoning provisions of the Kingsburg
Municipal Code for Light and Heavy Industrial zones.”
Also on June 5, 2013, the Kingsburg City Council held a public hearing to
consider repealing part VI of the NKSP. At the hearing, Mike Slater offered comments
on behalf of the City of Selma. He submitted that repealing part VI of the NKSP was not
categorically exempt from CEQA. Mata and the Kingsburg City Attorney responded that
the repeal would not cause any physical changes to the environment.
6Mata’s report is dated May 15, 2012. However, the year “2012” appears to be a
typographical error as the report references Guardian’s April 4, 2013, letter.
8.
The mayor then closed the public hearing, after which the city council (1) found
the repeal of part VI was exempt from CEQA, (2) adopted a categorical exemption to that
effect, and (3) approved the general plan amendment.7
E. Notice of Exemption
On June 6, 2013, Kingsburg filed a notice of exemption indicating its repeal of
part VI of the NKSP was statutorily exempt from CEQA. (See § 21152, subds. (b)-(c);
CEQA Guidelines, § 15374.)
F. Filing of the NKSP Action
On July 5, 2013, Selma filed a petition for writ of mandate in superior court
alleging, among other things, that Kingsburg failed to consider the environmental impacts
of its decision to repeal part VI of the NKSP (the NKSP action).
III. Trial Court Proceedings
A. Consolidation
On October 7, 2014, the trial court consolidated the Annexation action (case
No. 12CECG03223) and the NKSP action (case No. 13CECG02139) for purposes of oral
argument and trial only.
B. Motion to Augment
Before trial, Selma moved to augment the Annexation action’s record of
proceedings with documents from (1) the LAFCo action’s record of proceedings; (2) the
NKSP action’s record of proceedings and (3) the draft EIR for the Selma Crossings
project. The trial court denied Selma’s motion to augment and a subsequent motion to
reconsider. The motion and its ruling are discussed further below.
7Though called a general plan amendment, its effect was to repeal part VI of the North
Kingsburg Specific Plan.
9.
C. Trial and Ruling
The “trial” was held on November 7, 2014, and consisted solely of oral argument
with citations to the administrative record.
After trial, the court denied Selma’s petitions for a writ of mandate in both the
Annexation and NKSP actions. The court held Selma failed to cite substantial evidence
in support of its claims regarding agricultural, water quality, fire protection, traffic and air
quality impacts. The court determined Selma had raised “only speculation and
unsubstantiated opinion.”
The court further concluded that Selma’s submission of the draft EIR for the
Selma Crossings project “without explanation of any alleged cumulative impacts … does
not constitute a specific comment requiring a response.” Finally, the court rejected
Selma’s contentions based on Water Code sections 10910-10915 because it did not raise
the issue before the planning commission or city council.
The court did not offer a written explanation of its denial of Selma’s writ petition
in the NKSP action.
STANDARD OF REVIEW
“In reviewing an agency’s decision to adopt an MND, a court
(whether at the trial or the appellate level) must determine whether there is
substantial evidence in the record to support a ‘fair argument’ that a
proposed project may have a significant effect on the environment.
[Citation.] The fair argument standard creates a ‘low threshold’ for
requiring an EIR, reflecting a legislative preference for resolving doubts in
favor of environmental review. [Citation.]
“Whether the evidence establishes a fair argument that a project may
result in significant environmental impacts is a question of law. [Citation.]
Evidence supporting a fair argument may consist of facts, reasonable
assumptions based on fact, or expert opinions supported by fact but not
‘argument, speculation, unsubstantiated opinion or narrative, evidence that
is clearly inaccurate or erroneous, or evidence of social or economic
impacts that do not contribute to, or are not caused by, physical impacts on
the environment.’ [Citations.]
10.
“If substantial evidence exists to support a fair argument that a
significant environmental effect may result from the project, the agency is
required to prepare an EIR, irrespective of whether there is other substantial
evidence in the record to the contrary. [Citations.]” (Preserve Poway v.
City of Poway (2016) 245 Cal.App.4th 560, 575-576.)
DISCUSSION
I. Motion to Augment
A. Procedural Background
Before trial, Selma filed a motion to augment the record in the Annexation action.
Selma’s notice of motion indicated it was seeking to have the following documents added
to the administrative record: “a copy of the Draft Environmental Impact Report on the
‘Selma Crossings’ Project … and … all documents included in the record of the
proceedings, on file in [the NKSP action] and the record of proceedings on file in [the
LAFCo action].” In the notice of motion, Selma indicated the augmentation was being
sought on “the ground that each and all of the documents referred to are required to be a
part of the administrative record in this proceeding pursuant to the provisions of …
§ 21167.6 in that these are written materials that are relevant to the public agency’s
compliance with CEQA in connection with the project that is the subject of the petition
for mandate. (See … §21167.6(e)(10).” Selma also requested “[i]n addition, or in the
alternative” that the court take judicial notice of the documents under Evidence Code
section 452, subdivision (d).
The trial court denied Selma’s motion, concluding Selma had “made no showing
in its motion as to why the [draft EIR] of an unrelated project should be part of the
administrative record concerning this project.” The court also observed:
“Nor can the Court judicially notice evidence not contained in the
administrative record. For whatever reason, Selma has chosen to file
multiple CEQA actions concerning the same project, but this does not
necessarily transform what would be the administrative record in one case
to something judicially-noticeable in another case. (Code Civ. Proc.,
§ 1094.5.)”
11.
Selma filed a motion urging the trial court to reconsider its ruling. Selma argued
the records of the proceedings in the NKSP and LAFCo actions were required to be
included in the Annexation action’s record of proceedings because they were written
materials relevant to CEQA compliance issues or the merits of the project. (See
§ 21167.6, subd. (e)(10).) Selma acknowledged it was not possible to evaluate whether
the documents met that standard “considering the full factual and legal basis for the
assertion of relevance, which, in turn, requires an evaluation of the claims being made on
the merits.” As a result, Selma acknowledged it had mistakenly failed to ensure the trial
court hear the motion to augment concurrently with the merits of the Annexation action.
Selma asked the trial court to reconsider its prior ruling and requested relief under Code
of Civil Procedure section 473, subdivision (b).
The trial court denied Selma’s motion for reconsideration. The court observed
Selma’s original motion to augment “did not state what documents … Selma sought to
have added to the record except, at best, the draft environmental impact report from a
project called Selma Crossings, LLC.” That is, “the original motion to augment did not
state within its four corners what … Selma sought to add to the record and why.” 8 The
court also denied Selma’s request for relief under Code of Civil Procedure section 473.
B. Law
After a CEQA action is filed, a record of proceedings must be certified and lodged
with the court. (§ 21167.6, subds. (a)-(b).) Under section 21167.6, the record of
proceedings must include certain specific items like project applications and staff reports,
as well as other, broader categories of items. (E.g., § 21167.6, subd. (e)(1)-(2), (7), (10).)
8The court did not cite this ground in its written ruling on the initial motion to augment.
Kingsburg repeats this assertion in its brief. We find it inaccurate. Selma’s notice of motion
clearly identified the documents it sought to add to the record: “a copy of the Draft
Environmental Impact Report on the ‘Selma Crossings’ Project … and … all documents
included in the record of the proceedings, on file in [the NKSP action] and the record of
proceedings on file in [the LAFCo action].”
12.
By its terms, the statute “contemplates that the administrative record will include pretty
much everything that ever came near a proposed development or to the agency’s
compliance with CEQA in responding to that development.” (County of Orange v.
Superior Court (2003) 113 Cal.App.4th 1, 8.)
Perhaps the broadest category of required items is subdivision (e)(10) of section
21167.6 requiring inclusion of the following:
“(10) Any other written materials relevant to the respondent public
agency’s compliance with this division or to its decision on the merits of
the project, including the initial study, any drafts of any environmental
document, or portions thereof, that have been released for public review,
and copies of studies or other documents relied upon in any environmental
document prepared for the project and either made available to the public
during the public review period or included in the respondent public
agency’s files on the project, and all internal agency communications,
including staff notes and memoranda related to the project or to compliance
with this division.”
Subdivision (e)(10) of section 21167.6 was the basis for Selma’s motion to
augment the record of proceedings with the Selma Crossings draft EIR and the records of
proceedings from the LAFCo and NKSP actions.9
C. Analysis
1. Kingsburg’s Procedural Contentions Confuse the
Administrative and Appellate Records
Kingsburg argues Selma’s motion to augment the administrative record in the trial
court did not comply with California Rules of Court, rule 8.155.10 That rule provides a
party may move to augment the appellate record, provided the party “attach to [the]
motion a copy, if available, of any document or transcript that it wants added to the
9In the alternative, Selma requested the court take judicial notice of the documents.
Selma posited that the two records of proceedings were noticeable under Evidence Code section
452, subdivision (d) and the draft EIR was noticeable under Evidence Code section 452,
subdivision (h). The trial court denied Selma’s request for judicial notice.
10Further rule references are to the California Rules of Court.
13.
record.” (Rule 8.155(a)(2).) Kingsburg contends that because Selma’s motion did not
attach the documents for which augmentation was being sought, they “are not part of the
record of proceedings in either the Annexation Action or the NKSP Action.”
Kingsburg also asserts the documents were not “specifically proffered as evidence,
admitted, refused or lodged in the Annexation Action and, thus, are not part of the trial
Court’s record as required by Rule 8.124.” Kingsburg cites Vons Companies, Inc. v.
Seabest Foods, Inc. (1996) 14 Cal.4th 434, 444 in positing “augmentation procedures
cannot be used to include or add documents from outside the Superior Court records of
the Annexation Action, especially those not offered, lodged or otherwise before the trial
court.”
Kingsburg’s contentions confuse the administrative and appellate records. “Care
must be taken to distinguish the administrative record (i.e., the ‘record of proceedings’)
from the record on appeal (see … rule 8.120 et seq.).” (Madera Oversight Coalition, Inc.
v. County of Madera (2011) 199 Cal.App.4th 48, 61, fn. 4, disapproved on another point
by Neighbors for Smart Rail v. Exposition Metro Line Construction Authority (2013) 57
Cal.4th 439, 457.) Rules 8.124, 8.155, and the Vons Companies, Inc., citation concern
augmentation of the appellate record. But the documents in question are already part of
the appellate record. (See fn. 5, ante.) The question is whether they were properly
excluded from the administrative record (i.e., the record of proceedings). These
authorities cited by Kingsburg have no bearing on that issue.
2. That Two Records of Proceedings Concern the Same Project Is
Not Dispositive as to Whether Documents from One Should Be
Included in, or Excluded from, the Other Action’s Record of
Proceedings
The trial court reasoned “Selma has chosen to file multiple CEQA actions
concerning the same project, but this does not necessarily transform what would be the
administrative record in one case to something judicially-noticeable in another case.” We
agree the record of proceedings in one case should not necessarily be included in the
14.
record of proceedings in another case merely because they involve the same project. But
neither should it be excluded for that reason. The trial court’s premise, though accurate,
does not resolve the question of whether the LAFCo and NKSP documents should have
been included in the Annexation action’s record of proceedings under section 21167.6,
subdivision (e)(10).
3. Written Materials Relevant to the Agency’s Compliance with
CEQA Must Be Included in the Record of Proceedings Even if
Prepared after Project Approval
Kingsburg argues the documents were properly excluded because they “were not
before the decision making body at the time of the approval of the Annexation.” We
conclude that fact is not dispositive. Section 21167.6 does not contain a blanket
exclusion of all documents that were not presented to the decision-making body before
project approval. Of course, the vast majority of categories set forth in section 21167.6,
subdivision (e) necessarily include only such documents. (E.g., § 21167.6, subd. (e)(1) &
(4).)
But not every category of items under subdivision (e) of section 21167.6
necessarily includes only documents prepared before project approval. With some of its
broader categories, the administrative record statute “seeks to include materials not only
relating to the ‘project,’ but also relating to ‘compliance’ with CEQA. … Compliance
necessarily envisions a review process that transcends the finished ‘project.’” (County of
Orange v. Superior Court, supra, 113 Cal.App.4th at p. 10.) Subdivision (e)(10) is one
such category, because it encompasses “[a]ny other written materials relevant to the
respondent public agency’s compliance with [CEQA] ….” (§ 21167.6, subd. (e)(10).)
And, in certain limited circumstances, documents prepared after project approval can be
relevant to the issue of whether the agency complied with CEQA prior to, and at the time
of, project approval. For example, imagine a situation where an agency prepared a
negative declaration for an annexation project based on its asserted conclusion the
15.
annexation would not lead to development. Then, after project approval, the agency
created a document clearly indicating, in fact, the annexation was the first step in a
specific development project planned before the annexation project was approved. Even
though the document was created after project approval, it would be relevant to the scope
of the true project and, therefore, “relevant to the … public agency’s compliance with
[CEQA]” (§ 21167.6, subd. (e)(10)) at the time of project approval.
We emphasize that even with our conclusion outlined above, documents created
after project approval will rarely be included in a record of proceedings. As we observed
before, most of the categories in subdivision (e) of section 21167.6 necessarily include
only documents prepared before project approval. And even the clause in subdivision
(e)(10) of section 21167.6 contains a specific relevance limitation (i.e., the written
materials must be “relevant to the respondent public agency’s compliance” with CEQA).
This limitation will often have the effect of excluding documents prepared after project
approval. Consider a hypothetical where an agency approves a project, and no future
discretionary approvals are required. Thereafter, an expert conducts a study illuminating
a novel, previously unknown environmental impact the project will likely have. In that
circumstance, because the project has already been approved, the agency is not required
to reopen the approval. (CEQA Guidelines, § 15162, subd. (c).) Consequently, the
expert’s postapproval study would not be “relevant to the … public agency’s compliance
with [CEQA] ….” (§ 21167.6, subd. (e)(10.)
D. Conclusion
Below we analyze Selma’s substantive CEQA challenges. As that analysis will
demonstrate, some of the documents from the LAFCo action’s record of proceedings are
“relevant to the … public agency’s compliance with [CEQA]” (§ 21167.6, subd. (e)(10))
with respect to issues raised in the Annexation action. Consequently, those documents
16.
should have been included in the Annexation action’s record of proceedings upon
Selma’s request, and we will consider them in analyzing the issues in this appeal.
II. Water Supply Analysis
A. Background
1. The MND
In a section concerning water facilities, the MND contains the following analysis:
“Water supplies within the area between the State Route 99 freeway
and Golden State Boulevard will be provided by … Kingsburg. A 12-inch
water main has already been extended in the western shoulder of Golden
State Boulevard from the existing city limits to Amber Avenue capable of
serving the entire area between the State Route 99 freeway and the railroad.
Each property owner will be responsible for the cost of new service
connections, including infrastructure improvements and the completion of a
loop (tie-in) with a minimum eight-inch (8”) connection between the water
main and a development project.
“The industries east of the Union Pacific Railroad already provide
for their own water supplies. The Vie-Del grape processing plant, Sun-
Maid raisin plant and Guardian Industries glass plant each has two on-site
water wells producing adequate supplies of high-quality water. The small
triangular parcel fronting on Mountain View Avenue just east of the
railroad tracks is also served by an on-site well. Eventually [Kingsburg]
may provide water service to these properties at the request of the owners.”
2. Information from LAFCo Action’s Record of Proceedings
However, Kingsburg’s Service Plan for the Annexation Territory submitted to
LAFCo indicated:
“Currently, the three industries that occupy all of the parcels within the
subject territory have their own water systems. The Guardian Industries
glass plant, Vie-Del grape processing facility and Sun-Maid Growers raisin
plant each have two on-site water wells. Through an extra-territorial
agreement with George and Lousie [sic] Alves, dba G & L Enterprises,
13281 Golden State Boulevard, to extend a water main from Kamm
Avenue to Amber Lane [sic]. Once the annexation has been approved
ownership of the water main will transfer to [Kingsburg] and be made
available for connection to all adjoining properties.” (Italics added.)
17.
A LAFCo report dated April 10, 2013, repeats information similar to the Service
Plan:
“Currently, the three industries have their own water systems. A water
main will be extended from Kamm Avenue to Amber Lane. Once the
annexation has been approved, ownership of the water main will transfer to
[Kingsburg] and be made available for connection to all adjoining
properties.” (Italics added.)
In an e-mail dated July 8, 2013, Kingsburg’s contracted city engineer provided
city staff with information concerning the water main. He explained the plans for the
water line were prepared by Kingsburg in 2008 and the water line had been in operation
without water supply issues since 2009. He also indicated the water line was supplied by
three of Kingsburg’s municipal wells. Finally, he indicated the impacts of pumping
groundwater from municipal wells were being addressed pursuant to an agreement
between Kingsburg and the Consolidated Irrigation District, which provided for a
recharge program.
A LAFCo report dated July 17, 2013, corrected the April 10, 2013, report’s
description of the water supply as follows:
“Currently, the three industries have their own water systems. A water
main has been extended from Kamm Avenue to Amber Lane. The
waterline is currently owned and operated by … Kingsburg and is available
for connection to all adjoining properties. Water is supplied through …
Kingsburg municipal wells. Industry wells do not and will not connect to
the waterline. The pumping of groundwater from [Kingsburg] wells and
the associated impact to groundwater has been addressed through the
existing agreement between … Kingsburg and [the] Consolidated Irrigation
District. This agreement provides a groundwater recharge program to
offset groundwater pumping by … Kingsburg wells.” (Italics added.)
B. Analysis
Selma challenges the accuracy and sufficiency of Kingsburg’s water supply
analysis. First, Selma argues Kingsburg misrepresented the scope of the project by
failing to disclose a plan to extend or install water infrastructure to serve the existing
18.
industries after the annexation was approved. Kingsburg counters that a water main was
already in place and there was “no plan for development of a new watermain.”
Kingsburg points to the portion of the MND quoted above stating: “A 12-inch water
main has already been extended in the western shoulder of Golden State Boulevard from
the existing city limits to Amber Avenue ….” In response, Selma argues the 12-inch
water main referenced in this excerpt “is not the same water line that needs to be
extended to serve … the ‘existing industries’ ….”
C. Selma Has Failed to Carry Its Burden in Showing Kingsburg
Concealed a Plan to Install Undisclosed Water Supply Infrastructure
1. The MND Water Facilities Analysis Is Not Conclusive
The cited language from the MND does not support Selma’s contention the MND
“shows on its face that the 12 inch line has been extended to serve an area that does not
include the location of the ‘existing industries.’” While the MND does clearly indicate
the 12-inch main was extended and is capable of serving properties west of the railroad, it
does not say the same 12-inch main cannot also be used to serve the existing industries
east of the railroad once appropriate connections are made. In other words, nothing in the
MND suggests the 12-inch line was not extended to serve both the properties west of the
railroad and, eventually, the existing industries east of the railroad. To the contrary, the
MND clearly indicates the properties east of the railroad may connect to city water at
their initiation. More importantly, the MND does not expressly contemplate the
construction of any additional water mains apart from the 12-inch line (and connections
to it).
Of course, neither does the MND language expressly establish Kingsburg’s
position that “[t]here is no plan for development of a new watermain for the Annexation
Territory.” That is, the MND does not explicitly state there are no plans to construct a
new water main. However, since Selma is the party contending Kingsburg harbored an
undisclosed plan to extend or install a separate water main, it bears the burden of pointing
19.
to evidence supporting that claim. The MND’s water facilities analysis does not suffice
to support Selma’s claim because it does not indicate, on its face, that there is an
undisclosed plan to extend or install a separate water main for the existing industries.
We now consider Selma’s contentions such evidence exists elsewhere.
2. Selma’s Citation to the Service Plan Does Not Show Kingsburg
Planned Expansion or Installation of a Separate Water Main to
Serve the Existing Industries
Selma points to the Service Plan in the LAFCo action’s record of proceedings to
support its claim the 12-inch water main referenced in the MND must be different from
the one planned to service the existing industries. Selma contends the Service Plan
indicates the water main for the existing industries will extend “from Kamm and Amber
Lane” whereas the 12-inch main referenced in the MND goes to Amber Lane. However,
the Service Plan actually says the water main for the existing industries would extend
from Kamm to Amber Lane, not “from Kamm and Amber Lane” as Selma indicates.
Correctly stated, the Service Plan’s description does not materially differ from the
MND’s description of the 12-inch water main as having been extended “in the western
shoulder of Golden State Boulevard from the existing city limits to Amber Avenue.”
(Italics added.) There is no irreconcilable inconsistency between these two descriptions
and therefore no indication they pertain to two different water mains.
D. Adequacy of Water Supply Analysis
Selma next argues that even if Kingsburg did not misrepresent the scope of the
project with respect to the provision of water to the existing industries, it was nonetheless
“required to carefully evaluate the impact to City water supplies of serving the existing
industries” and did not do so. Specifically, Selma contends Kingsburg “failed, to identify
any public water supply available to supply water to the annexed territory.”
In arguing Kingsburg was required to analyze water supply issues in more detail,
Selma cites cases such as Vineyard Area Citizens for Responsible Growth, Inc. v. City of
20.
Rancho Cordova (2007) 40 Cal.4th 412, 432-434, Preserve Wild Santee v. City of Santee
(2012) 210 Cal.App.4th 260, 283-284, and Santiago County Water Dist. v. County of
Orange (1981) 118 Cal.App.3d 818, 829-831. However, all of those cases concerned the
level of water supply analysis required in an EIR, not an initial study. “An initial study is
only a ‘preliminary analysis’ [citation] and the regulatory requirements regarding its
contents are not as demanding as those imposed upon an EIR. [Citations.] ‘[A]n initial
study is neither intended nor required to include the level of detail included in an EIR.’
[Citation.]” (Lighthouse Field Beach Rescue v. City of Santa Cruz (2005) 131
Cal.App.4th 1170, 1192.)
Selma fails to appreciate that “‘the ultimate issue is not the validity of the initial
study, but rather the validity of the lead agency’s adoption of a negative declaration.
Even if the initial study fails to cite evidentiary support for its findings, “it remains the
appellant’s burden to demonstrate by citation to the record the existence of substantial
evidence supporting a fair argument of significant environmental impact.” [Citation.]
“An absence of evidence in the record on a particular issue does not automatically
invalidate a negative declaration. ‘The lack of study is hardly evidence that there will be
a significant impact.’”’” (Rominger v. County of Colusa (2014) 229 Cal.App.4th 690,
725.)
Accordingly, we reject Selma’s claim concerning water supply analysis in the
initial study. It is not enough to “complain[] about supposed deficiencies in the water
supply assessment” without showing the record contains substantial evidence supporting
a fair argument the project may have a significant impact notwithstanding the agency’s
conclusion to the contrary. (Rominger v. County of Colusa, supra, 229 Cal.App.4th at p.
729.) In other words, claiming there are holes in the environmental analysis is not the
same as affirmatively showing there is evidence supporting a fair argument a project may
cause significant environmental effects.
21.
Moreover, we note the record does contain evidence concerning how water would
be supplied to the existing industries should they decide to connect. The Service Plan
described a water line extended by G & L Enterprises and observed the line will be made
available for connection after annexation. In a correspondence appearing in the LAFCo
action’s record of proceedings, Kingsburg’s contracted city engineer notes the water line
itself is supplied by three municipal wells. And the MND states that groundwater supply
in the area is “ample” and a “future municipal well is planned near the northwestern end
of the annexation ….” The MND also notes that, pursuant to an agreement with the
irrigation district, Kingsburg “is mitigating groundwater overdraft in the City … by
instituting a process as identified in the … agreement, for the payment of contributions
into a groundwater management and replenishment fund for the purpose of implementing
groundwater replenishment methodologies ….”
In sum, these documents indicate that should the existing industries decide to
connect to the line constructed by G & L Enterprises, they will be supplied by municipal
wells, and measures are being taken to mitigate overdraft of Kingsburg’s wells. It is not
enough to simply assert this analysis was insufficient; Selma needed to point to
substantial evidence supporting a fair argument that significant environmental impacts
may result if the existing industries decide to connect to Kingsburg’s water. It did not do
so.
E. Selma Failed to Raise Alleged Violations of the Water Code in
Accordance with Section 21177
Selma also contends Kingsburg violated several Water Code provisions
concerning water supply analysis for CEQA projects. (See Wat. Code, §§ 10910-10915.)
Kingsburg argues Selma failed to exhaust its administrative remedies on this issue by
failing to raise it before or during the close of the public hearing. (See § 21177.)
Section 21177, subdivision (a) provides “[a]n action or proceeding shall not be
brought … unless the alleged grounds for noncompliance with [CEQA] were presented to
22.
the public agency orally or in writing by any person during the public comment period
provided by [CEQA] or prior to the close of the public hearing on the project before the
issuance of the notice of determination.”
The exhaustion statute does not apply “if the public agency failed to give the
notice required by law.” (§ 21177, subd. (e).)
Selma responds section 21177, subdivision (a) does not apply because the project
description was so misleading in its failure to properly describe the planned water
infrastructure that it amounted to a complete lack of notice. Since we concluded the
project description was not misleading in this respect (see DISCUSSION, pt. II.A, ante), we
reject Selma’s argument concerning inadequate notice and find this issue was forfeited by
a failure to exhaust administrative remedies.
III. Fire Protection
A. Background
The MND indicated the Annexation Territory would be served by Kingsburg’s
Fire Department (KFD). The MND further indicated it had been determined the KFD
“has sufficient service capability to meet the fire and emergency response needs of the
area.”
According to Kingsburg’s July 2012 Service Plan, the Annexation Territory was
then being served by the Fresno County Fire Protection District (FCFPD) from Station
83, with supplemental protection from several agencies including KFD. FCFPD’s
Station 83 is directly across from the Guardian glass plant on Mountain View Avenue.
A staff report authored by Mata and dated August 15, 2012, notes Kingsburg had
previously entered into a Transition Agreement with FCFPD “wherein the City agree[d]
to transfer certain taxes revenues to the District for each annexation covered by the
Transition Agreement.” The report observed the term of the Transition Agreement would
23.
end on December 31, 2012, and that Kingsburg was engaged in “negotiations with the
[FCFPD] in hopes of agreeing upon the terms of a new Transition Agreement.”
At the September 5, 2012, public hearing, KFD Chief Tim Ray addressed the city
council. Chief Ray indicated Kingsburg currently had an automatic aid agreement with
Fresno County. Under the terms of that agreement, both KFD and FCFPD are
simultaneously dispatched to certain calls and “it’s basically a race to whoever gets there
first.” Due to its proximity to the plant, FCFPD’s Station 83 would often respond more
quickly to the Guardian plant than KFD could. KFD, however, is closer to Sun-Maid
Growers of California raisin plant.
Chief Ray acknowledged there was uncertainty as to whether Fresno County
would renew its automatic aid agreement with Kingsburg. However, Chief Ray indicated
that in addition to the automatic aid agreements with Fresno and Tulare Counties, there
are also “mutual aid agreements” in effect. Chief Ray opined that whether the automatic
aid agreement would be renewed is “immaterial” because the “mutual aid agreement”
would remain in effect. He also stated there is a “State of California Blanket Mutual
Aid,”11 which “basically in layman terms says that if I ask you to come and you are
available, you will come. So, that includes everybody in this entire area.”
Chief Ray concluded that “regardless of whose area [i.e., the Annexation
Territory] that actually is, I don’t believe that our response to that area is going to be any
different whether its Fresno County’s or if it’s the City of Kingsburg. We both have an
engine that’s staffed.” Chief Ray acknowledged that large fires could require additional
resources, but that would also be true if FCFPD were responding. Chief Ray opined, “In
my opinion, I don’t see this annexation changing the fire response in any way.”
11Unfortunately, the parties’ briefing fails to discuss Chief Ray’s reference to the “State
of California Blanket Mutual Aid.” Chief Ray may have been referring to the California Disaster
and Civil Defense Master Mutual Aid Agreement created to facilitate the implementation of the
California Emergency Services Act (Gov. Code, § 8550 et seq.). (See Gov. Code, § 8561.)
24.
The MND Addendum, apparently created sometime in 2013, indicated the
Transition Agreement between Kingsburg and FCFPD had expired. The Addendum
states the expiration of the transition agreement “will not result in new or increased
impacts to fire protection services upon approval of the annexation as the agreement only
addressed financial considerations.” It then notes the “Kingsburg Fire Department has
sufficient capacity to service the proposed annexation area with both fire and emergency
services.”
During the subsequent LAFCo approval process, FCFPD opposed Kingsburg’s
annexation of the Annexation Territory. In a March 28, 2013, letter to LAFCo, the
FCFPD explained it receives funding primarily through taxes levied on all property
within its boundaries. The FCFPD claimed that over the last 10 years, city annexations
had resulted in a funding loss of $5.5 million in property tax revenue. With respect to
this project, detaching the Annexation Territory from the FCFPD would cause the
FCFPD to lose $101,302 in annual funding. This would “equate[] to” a loss of two full
time paid firefighter positions at Station 83. This placed the station “at risk of being
closed,” which would “result in reduced emergency services to the Guardian Glass, Sun
Maid Raisin, and Vydell [sic] Winery facilities, an overall reduction in services
throughout the Fire District, as well as less support to the Cities ….”
The March 28, 2013, letter indicated LAFCo’s existing policies required cities
seeking annexation to have a transition agreement in place before an annexation would be
approved. The letter encouraged LAFCo not to change that policy. The letter also
indicated FCFPD had offered “several transition agreement options” to Kingsburg, but
they were all refused. The letter closed by claiming Kingsburg did not have the ability to
provide “the appropriate level of emergency services to protect the people that work
within the Guardian Glass and SunMaid facilities.”
25.
B. Analysis
Selma contends Kingsburg did not adequately study its “ability to provide fire
service from, or without, Station 83 which depended on whether a Transition Agreement
was in place.”
1. Selma’s Contentions Contain Several Inaccurate Factual
Assertions
In its arguments on the fire protection issue, Selma misconstrues the record in
several respects. First, Selma states the Addendum “states expiration of the
transition/mutual aid agreements did not impact Kingsburg’s ability to respond to
emergency calls, contrary to the Fire Chief’s testimony and [FCFPD]’s submissions to
LAFCO.” (Italics added.) However, the Addendum only refers to expiration of the
Transition Agreement, not any mutual aid agreements.
Selma also claims Chief Ray testified Kingsburg could not provide services
without station 83. It offers no citation to the record in support of this assertion. To the
contrary, Chief Ray said it would not matter whether KFD or FCFPD responded to the
annexation territory because both agencies “have an engine that’s staffed.”
2. The Record Does Not Support Selma’s Contention that Chief
Ray Was Merely Speculating When He Testified He Believed
FCFPD Would Continue to Respond to Fires in the Annexation
Territory
Selma contends Chief Ray was “essentially speculating” that the expiration of the
transition agreement would not cause FCFPD “to cease to provide fire services from
Station 83.” We disagree.
Chief Ray articulated specific reasons for his belief FCFPD would continue to
provide services. Chief Ray observed that whether the automatic aid agreement with
FCFPD would be renewed was “immaterial” because the “mutual aid agreement” would
remain in effect. He also stated there is a policy called “State of California Blanket
26.
Mutual Aid,” which “basically in layman terms says that if I ask you to come and you are
available, you will come.” This policy applied to “everybody in this entire area.”
More fundamentally, however, Selma’s focus on Station 83 seems misplaced.
Even if we accepted Selma’s assertion the expiration of the Transition Agreement meant
FCFPD would no longer respond to fires in the Annexation Territory, we fail to see how
this undermines the MND. The MND said the Annexation Territory would be served by
KFD, which was determined to have “sufficient service capability to meet the fire and
emergency response needs of the area.” Another way of phrasing the MND’s analysis is
that even without FCFPD’s help, KFD could provide a sufficient level of fire protection
services such that no significant impact to the environment would occur. This conclusion
is supported by Chief Ray’s testimony the fire response to the Annexation Territory
would be the same whether KFD or FCFPD was responding because both agencies had
“an engine that’s staffed.” To contradict the MND on this point, Selma needed to do
more than raise a fair argument KFD would no longer have FCFPD’s help going forward.
Selma needed to raise a fair argument that without FCFPD’s responding to fires in the
Annexation Territory, the project may cause significant impacts to the environment. In
other words, Selma needed to point to evidence the purported decrease in fire protection
was substantial enough to potentially cause significant environmental impacts. Selma has
not done so.
IV. Various Procedural Claims
A. Combined Initial Study and MND
Selma contends the failure to prepare an initial study before the MND is a failure
to comply with CEQA. It cites Lighthouse Field Beach Rescue v. City of Santa Cruz,
supra, 131 Cal.App.4th at pages 1192-1193 in support of this contention, but that
authority simply does not discuss the issue. Selma has not carried its burden.
27.
B. Purported Failure to Consult with LAFCo
Selma argues Kingsburg failed to informally consult with LAFCo prior to the
adoption of the MND. Selma does not support this factual claim with any citation to the
record and we consider it forfeited. (See North Coast Rivers Alliance v. Kawamura
(2015) 243 Cal.App.4th 647, 677-678.)
C. Subsequent EIR/Negative Declaration
Selma argues the repeal of the design standards in the NKSP “eliminates
mitigation measures from the MND and, therefore, makes a significant change to the
MND.” But even if we accept Selma’s interpretation that repealing the design standards
effectively removed a mitigation measure from the annexation project’s MND, Selma has
failed to show how that change met the substantiality requirements of CEQA Guidelines
section 15162. Not all new information or changes to a project (or its circumstances)
trigger the need for new CEQA analysis. (See CEQA Guidelines, § 15162, subd. (a).)
The change or new information must somehow involve a new significant environmental
effect, substantially increase the severity of previously identified effects, or show a
mitigation measure would substantially reduce one or more significant effects. (CEQA
Guidelines, § 15162, subd. (a)(1)-(3).) Selma has not explained how changes to the
NKSP meet this substantiality requirement.
D. Propriety of the Addendum
Selma argues Kingsburg violated CEQA’s procedural requirements when it issued
a purported Addendum to the MND.
1. The Addendum Is in the Administrative Record
Preliminarily, Kingsburg claims the Addendum is outside the administrative
record. This assertion is incorrect; the Addendum can be found in the Annexation
action’s record of proceedings at pages K0026-K0027.
28.
2. An Addendum Was an Appropriate Means for Addressing the
Expiration of the Transition Agreement
Selma argues the Addendum was inappropriate because it involved more than a
minor or technical change.
An agency may prepare an addendum to a negative declaration “if only minor
technical changes or additions are necessary or none of the conditions described in
[Guidelines] Section 15162 calling for the preparation of a subsequent … negative
declaration have occurred.” (CEQA Guidelines, § 15164, subd. (b).)
CEQA Guidelines section 15162 lists three conditions necessitating a subsequent
EIR or negative declaration, only two of which are conceivably relevant here.12 (CEQA
Guidelines, § 15162, subds. (a)(1)-(3).)
First, a subsequent negative declaration must be prepared when there is a
substantial change in “circumstances under which the project is undertaken which will
require major revisions of the previous … negative declaration due to the involvement of
new significant, environmental effects or a substantial increase in the severity of
previously identified significant effects.” (CEQA Guidelines, § 15162, subd. (a)(2).)
Here, the “change” in circumstance was the expiration of the Transition
Agreement concerning fire protection. However, the original MND indicated Kingsburg,
not the FCFPD, would be providing fire protection to the Annexation Territory. The
Addendum did not change this fact and indicated the expiration of the Transition
Agreement would not “result in new … impacts to fire protection services” because the
Transition Agreement concerned only financial considerations. Thus, the expiration of
the Transition Agreement did not effect a “substantial change[]” to the circumstances
under which the Annexation project was being undertaken, nor did it involve “new
12Subdivision (a)(1) of CEQA Guidelines section 15162 applies when certain changes to
the project are proposed. Here, there was a change in circumstance (i.e., the expiration of the
Transition Agreement concerning emergency services), not a change in the project itself.
29.
significant, environmental effects or a substantial increase in the severity of previously
identified significant effects.” (CEQA Guidelines, § 15162, subd. (a)(2).)
Second, a subsequent negative declaration must be prepared when certain “[n]ew
information of substantial importance, which was not known and could not have been
known with the exercise of reasonable diligence at the time the previous … negative
declaration was adopted” is discovered.13 (CEQA Guidelines, § 15162, subd. (a)(3),
italics added.) There is no indication that when it adopted the original negative
declaration, Kingsburg did not know the Transition Agreement would expire on
December 31, 2012. Indeed, the Transition Agreement itself clearly specified it would
“automatically terminate no later than December 31, 2012, unless it has been terminated
prior to that time ….”
Since “none of the conditions described in [Guidelines] Section 15162 calling for
the preparation of a subsequent … negative declaration … occurred” (CEQA Guidelines,
§ 15164, subd. (b)), Kingsburg was permitted to prepare an addendum to its negative
declaration.
3. Kingsburg Failed to Consider the Addendum Prior to Project
Approval in Violation of CEQA Regulations
The CEQA Guidelines require that “[t]he decision-making body shall consider the
addendum with the final … adopted negative declaration prior to making a decision on
13The new information must show either: “(A) The project will have one or more
significant effects not discussed in the previous EIR or negative declaration; [¶] (B) Significant
effects previously examined will be substantially more severe than shown in the previous EIR;
[¶] (C) Mitigation measures or alternatives previously found not to be feasible would in fact be
feasible and would substantially reduce one or more significant effects of the project, but the
project proponents decline to adopt the mitigation measure or alternative; or [¶] (D) Mitigation
measures or alternatives which are considerably different from those analyzed in the previous
EIR would substantially reduce one or more significant effects on the environment, but the
project proponents decline to adopt the mitigation measure or alternative.” (CEQA Guidelines,
§ 15162, subd. (a)(3)(A)-(D).)
30.
the project.” (CEQA Guidelines, § 15164, subd. (d).) Selma cited this guideline in its
opening briefs in the trial court and on appeal. Kingsburg offers no response.
The Addendum indicates that after the MND was adopted, the Transition
Agreement between Kingsburg and the FCFPD expired. The Transition Agreement
indicated it would end on December 31, 2012. Thus, while the Addendum itself was
undated, it was clearly completed sometime after Kingsburg approved the annexation
project in 2012. This chronology violates the CEQA Guidelines. (See CEQA
Guidelines, § 15164, subd. (d).)
Selma insists the Addendum is a “nullity.” We agree only insofar as the
Addendum cannot be a basis for determining Kingsburg satisfied CEQA. But that
conclusion does not get Selma very far. Even without the Addendum, the original MND
indicated KFD will be providing fire services to the Annexation Territory, and the
Addendum did not change that. It would be a different case if Kingsburg were relying on
the Addendum as an essential aspect of its CEQA compliance. But that is not the
situation here. Even if we were to completely ignore the Addendum, it remains Selma’s
burden to point to substantial evidence to support a fair argument the changes to fire
protection may cause a significant environmental impact. As explained above (see
DISCUSSION, pt. III, ante), it has not met that burden.
4. The Addendum Did Not Violate CEQA Guidelines Section
15164, Subdivision (e)
Selma contends the Addendum also violated CEQA Guidelines by failing to
include “[a] brief explanation of the decision not to prepare a subsequent EIR pursuant to
[Guidelines] Section 15162.” (CEQA Guidelines, § 15164, subd. (e).) We disagree.
First, we note CEQA Guidelines section 15164, subdivision (e) indicates only that
an addendum “should” contain such an explanation. Second, the Addendum did provide
a brief explanation of the decision not to prepare a subsequent EIR:
31.
“In preparing this Addendum, all of the potential impacts identified on the
CEQA ‘Environmental Checklist’ were considered. For all impact areas,
staff’s review indicated that the expiration of the fire transition agreement
would not result in physical changes on the property or changes to the
project that would change the environmental analysis. Public Services and
other environmental conditions have not changed significantly since the
Guardian/Sun-Maid Reorganization Mitigated Negative Declaration was
adopted on August 15, 2012. Therefore, the project would have no new
impact(s) not already identified in the Guardian/Sun-Maid Reorganization
Mitigated Negative Declaration, nor would it result in a substantial increase
in the severity of previously identified impacts. In summary, the analysis
concludes that none of the conditions described in Section 15162 of the
CEQA Guidelines calling for preparation of a subsequent EIR or Negative
Declaration have occurred, and thus an Addendum to the Guardian/Sun-
Maid reorganization Mitigated Negative Declaration is appropriate to
satisfy CEQA requirements for the proposed project.”
Consequently, we conclude Kingsburg did not run afoul of the Guidelines’
requirement an addendum contain a “brief explanation of the decision not to prepare a
subsequent EIR pursuant to [Guidelines] Section 15162 ….” (CEQA Guidelines,
§ 15164, subd. (e).)
V. Selma Fails to Carry Its Burden of Raising a Fair Argument that Potential
Modification or Expansion of Guardian’s Plant Would Be a Direct or
Indirect Effect of the Project
Selma asserts the MND does not properly study the possibility of facility
modifications at the Guardian property and potential resultant impacts on agricultural
land, etc.14
An initial study is required to analyze direct and indirect effects of the project. “A
direct physical change in the environment is a physical change in the environment which
is caused by and immediately related to the project.” (CEQA Guidelines, § 15064, subd.
(d)(1).) “An indirect physical change in the environment is a physical change in the
environment which is not immediately related to the project, but which is caused
14The MND observed Guardian owns a 15-acre vineyard in the Annexation Territory.
The MND states it is “anticipated it will be used for future expansion.”
32.
indirectly by the project.” (CEQA Guidelines, § 15064, subd. (d)(2).) Thus, in order to
be a direct or indirect effect of a project, the future physical change in the environment
must have a causal link to the project.
Selma does not point to substantial evidence supporting a fair argument a future
modification of the Guardian plant would be an “effect” of the project at all. To the
contrary, the evidence strongly indicates that if Guardian ultimately expanded its plant, it
would not be doing so as a result of the annexation project.
First, Guardian initially opposed the annexation because it might hinder its ability
to modify its facilities. This obviously undermines the suggestion that modification of
the Guardian facilities would be an “effect of” the annexation.15
Second, Guardian’s April 10, 2013, letter to LAFCo expressly discusses why it
would possibly modify its facility in the future:
“While Guardian has not proposed any specific project on the Guardian
Property, to remain competitive in the glass manufacturing business,
Guardian from time to time is required to perform modifications to its
facility, which usually requires discretionary permits from the applicable
local agency.”
Thus, the evidence shows future changes to the Guardian property would be driven by
business considerations.
15At oral argument, Selma’s counsel indicated the anticipated modifications would
require rezoning of a 15-acre parcel owned by Guardian, and the annexation project
accomplished such a rezoning. Counsel claimed that “if you look at the letters from Guardian
that say ‘we’re going to expand’ you can tell it’s a big expansion and it’s going to take up a lot of
that previously agriculturally zoned land.”
We reject this contention. Guardian’s letters do not identify any specific planned use for
the 15-acre parcel. Moreover, while Guardian’s letters identify several impediments to potential
future modifications—such as the NKSP design standards, etc.—they do not claim that rezoning
of the 15-acre parcel is required to accommodate future plant modifications.
33.
The MND’s acknowledgment Guardian may modify or expand its facilities after
annexation does not constitute substantial evidence supporting a fair argument such a
modification or expansion would be the result of the annexation project.
VI. Mitigation Measures 3.1 and 16.1 Do Not Improperly Defer Analysis of
Potential Future Development Projects
A. Background
The MND indicated certain traffic and air quality impacts would be less than
significant with mitigation. With respect to traffic, the MND acknowledged: “Additional
traffic loads will be generated by commercial and industrial development as individual
development projects are proposed. Transportation related impacts will be addressed on
a project by project basis, with resulting impacts mitigated through design or construction
of new facilities and improvements.” The MND adopted mitigation measure 16.1, which
required that future development projects within the Annexation Territory would need to
“analyze their project specific traffic impacts … and will be responsible for mitigating
the project specific impacts.” Mitigation measure 16.1 also provided that any proposed
project “generat[ing] 100 or more trips per day shall be required to perform a traffic
impact study to determine current levels of service and anticipated impacts of the project
on adjacent roadways.”
With respect to air quality impacts, the MND indicated the project itself would
“not significantly increase the production of any criteria pollutant ….” However, the
MND acknowledged that future development “may contribute to criteria pollutants.”
Accordingly, the MND adopted mitigation measure 3.1, requiring “[a]ny future
development will comply with appropriate policies or regulations of the San Joaquin
Valley Unified Air Pollution Control District …, including, but not limited to Regulation
VIII (Fugitive Dust Control) and Rule 9510 (Indirect Source Review).”
Selma contends these purported mitigation measures constitute improper deferral
under City of Antioch v. City Council (1986) 187 Cal.App.3d 1325 (City of Antioch).
34.
B. Law
In City of Antioch, supra, 187 Cal.App.3d 1325, a developer sought a permit to
construct a roadway and sewer system. The sole purpose for the project was to spur
further development. (Id. at p. 1337.) Nonetheless, the city argued a negative declaration
was appropriate because “the project involves no building construction or introduction of
new land uses and that at present it is not known what type of development will occur on
the surrounding undeveloped land,” and “proposals for future development will be
subject to further environmental review at the time of development of the surrounding
land.” (Id. at p. 1333.)
The court held an EIR was required. The court refused to “look at the proposed
project in a vacuum” and rejected assurances that “other phases of development of the
entire property will be accorded appropriate environmental review in due course.” (City
of Antioch, supra, 187 Cal.App.3d at p. 1334.) The court summarized its reasoning as
follows
“In sum, our decision in this case arises out of the realization that the sole
reason to construct the road and sewer project is to provide a catalyst for
further development in the immediate area. Because construction of the
project could not easily be undone, and because achievement of its purpose
would almost certainly have significant environmental impacts,
construction should not be permitted to commence until such impacts are
evaluated in the manner prescribed by CEQA.” (City of Antioch, supra, at
pp. 1337-1338.)
City of Antioch did not create a bright-line rule. The detail required in the analysis
of potential future development continues to depend on a variety of factors.
“[A]n agency cannot avoid the EIR process simply because a project does
not itself call for the construction of housing or other facilities that will be
needed to support the growth contemplated by the project. It does not
follow, however, that an EIR is required to make a detailed analysis of the
impacts of a project on … growth. Nothing in the Guidelines, or in the
cases, requires more than a general analysis of projected growth. The detail
required in any particular case necessarily depends on a multitude of
factors, including, but not limited to, the nature of the project, the directness
35.
or indirectness of the contemplated impact and the ability to forecast the
actual effects the project will have on the physical environment. In
addition, it is relevant, although by no means determinative, that future
effects will themselves require analysis under CEQA.” (Napa Citizens for
Honest Government v. Napa County Bd. of Supervisors (2001) 91
Cal.App.4th 342, 369.)
Here, we find several factors militate against the need for detailed environmental
analysis of potential future development.
First, future development projects in the Annexation Territory will be subject to
CEQA review. While this fact is not always determinative, it is a relevant consideration.
(E.g., Clover Valley Foundation v. City of Rocklin (2011) 197 Cal.App.4th 200, 228.)
In City of Antioch, the court essentially concluded that immediate environmental
analysis of future development resulting from the project was appropriate because the
location and design of the road and sewer would effectively commit the city to a certain
development pattern for the future. This consideration, which was central to City of
Antioch,16 is not nearly as strong here. The present annexation project is a change in
political boundaries. (See Gov. Code, § 56017.) This fact does not render any resultant
development irrelevant (see Bozung v. Local Agency Formation Com. (1975) 13 Cal.3d
263, 279-281), but it does distinguish this case from City of Antioch. An annexation does
not irreversibly impact the range of future development options in the way that a roadway
and sewer constructed in a specific location does. In other words, we are not yet at the
proverbial fork in the road when it comes to future development. Consequently,
permitting detailed environmental analysis to occur in connection with the specific
development projects that may be proposed in the future—rather than requiring it now—
is the preferable course.
16Indeed, City of Antioch itself distinguished Brentwood Assn. for No Drilling, Inc. v.
City of Los Angeles (1982) 134 Cal.App.3d 491 because “[t]he size, location and configuration
of the roadway and utilities will influence not only the fact but the nature of later development to
a much greater degree than the [project] at issue in Brentwood.” (City of Antioch, supra, 187
Cal.App.3d at p. 1335.)
36.
Second, little is known of how future development will proceed in the Annexation
Territory. This fact reduces both the utility and the feasibility of currently studying the
potential environmental impacts of unspecified future development in detail.
Environmental analysis need not “engage in sheer speculation as to future environmental
consequences.” (Towards Responsibility in Planning v. City Council (1988) 200
Cal.App.3d 671, 681.) It would be unreasonable to expect environmental analysis to
include detailed information about the environmental impacts of future development
“whose scope is uncertain and which will in any case be subject to its own environmental
review.” (Ibid.) Requiring detailed environmental analysis of “unspecified and uncertain
development that might be approved in the future … would be speculative, wasteful, and
of little value …. Far too little is known about the scope, the location, or the types of
projects that might be proposed in the future to assist decision makers in evaluating any
potential environmental tradeoffs. Thus, the amorphous nature of possible development
… stands in stark contrast to the related projects ignored in … City of Antioch.”
(Environmental Council of Sacramento v. City of Sacramento (2006) 142 Cal.App.4th
1018, 1032.)
For the same reasons, we reject Selma’s contention there is insufficient analysis of
cumulative impacts resulting from the annexation project and the Selma Crossings
project. The only potential cumulative significant impacts would be between the Selma
Crossings project and any future development projects that may occur in the Annexation
Territory. And that dynamic cannot be meaningfully studied at this juncture because it is
unknown what type of development may occur in the Annexation Territory. Of course,
when and if specific development projects in the Annexation Territory go through the
CEQA process, it may be necessary, at that time, to analyze their potential cumulative
effects in light of the Selma Crossings project.
Selma also cites CEQA Guidelines sections 15162-15163 and claims it was
improper for the MND to rely on the NKSP EIR for evaluation of air quality impacts
37.
without finding there is no change in circumstances. But those Guidelines require a
subsequent EIR when changes to a project or its circumstances occur or new information
becomes available after the adoption of the negative declaration. (See CEQA Guidelines,
§ 15162, subd. (b).) Otherwise, the lead agency may determine whether to prepare a
subsequent negative declaration, an addendum, or no further documentation at all. (Ibid.)
Selma does not explain how the failure to analyze changes between the adoption of the
NKSP EIR and the adoption of the annexation project’s MND is relevant under CEQA
Guidelines sections 15162-15163, which concern changes after the adoption of the
project’s MND.
Selma argues that since the MND states net increases in pollutants are less than
significant only with mitigation, and the MND failed to properly incorporate mitigation
measures from a separate document, there is “necessarily” a fair argument of potential
significant impacts. But this contention ignores that the MND indicated the only
potential air quality impacts would come from future development projects, and those
impacts would be mitigated by measures specific to the future development projects. In
other words, the MND was not relying on the NKSP EIR’s mitigation measures, but
instead on mitigation measures that would be developed in conjunction with any future
development projects. Requiring anything more would be to ask Kingsburg to “engage in
sheer speculation as to future environmental consequences.” (Towards Responsibility in
Planning v. City Council, supra, 200 Cal.App.3d at p. 681.)
VII. Purported “Mitigation Measure 16.2” Is Not a True Mitigation Measure
The MND also identifies mitigation measure 16.2 as follows:
“The City of Kingsburg intends to initiate the preparation of a traffic impact
fee study for the purpose of analyzing the impacts of contemplated future
development on City-wide traffic facilities along with an analysis of the
need for new traffic facilities required by new development in the City,
including new development in the project area. The traffic impact fee study
will also identify the relationship between new development and the needed
traffic facilities and will identify the estimated cost of the needed traffic
38.
facilities. Following the preparation of a traffic impact fee study, the City
Council will consider the adoption of an ordinance amending the City
traffic impact fees.”
Selma argues this is not truly a mitigation measure. We agree.
“Mitigation” includes (1) avoiding an impact altogether by not taking a certain
action or parts of an action; (2) minimizing impacts by limiting the magnitude of the
action; (3) rectifying the impact by restoring the impacted environment; (4) reducing or
eliminating the impact over time by preservation and maintenance operations during the
life of the action; and (5) compensating for the impact by replacing or substituting
resources or environments. (CEQA Guidelines, § 15370.)
Generally, “it is inappropriate to postpone the formulation of mitigation
measures.” (POET, LLC v. State Air Resources Bd. (2013) 218 Cal.App.4th 681, 735.)
“However, this general rule against deferring the formulation of mitigation measures is
not absolute. Courts have recognized that ‘there are circumstances in which some aspects
of mitigation may appropriately be deferred.’” (Ibid.) But in order to defer formulation
of a mitigation measure, the agency must “commit itself to specific performance criteria
for evaluating the efficacy of the measures implemented.” (Id. at p. 738.)
Moreover, “[m]itigation measures must be fully enforceable through permit
conditions, agreements, or other legally-binding instrument.” (CEQA Guidelines,
§ 15126.4, subd. (a)(2).)
Mitigation measure 16.2 is simply an announcement that Kingsburg “intends” to
initiate a study after which it will “consider” adopting an ordinance implementing
unspecific changes to the city’s traffic impact fees. As the language of the measure
makes clear, Kingsburg could, after considering the issue, decide not to change the city’s
traffic impact fees at all. Mitigation measure 16.2 offers no enforceable standards by
which to exert a mitigating effect on potential environmental impacts. (Cf. Gray v.
County of Madera (2008) 167 Cal.App.4th 1099, 1122.) Nor does mitigation measure
39.
16.2 provide specific performance criteria. (See POET, LLC v. State Air Resources Bd.,
supra, 218 Cal.App.4th at p. 738.) Accordingly, it is not truly a mitigation measure at all.
However, we disagree with Selma’s argument the MND should be invalidated as a
result. The potential impact mitigation measure 16.2 was formulated to mitigate was the
additional traffic loads that could be created by future development projects. Even
without mitigation measure 16.2, the traffic impacts of future projects will be mitigated
with project-specific measures under mitigation measure 16.1. Therefore, we reject
Selma’s contention the potential ineffectiveness of mitigation measure 16.2 warrants
invalidation of the MND.
VIII. Kingsburg Failed to Carry Its Burden in Showing the Commonsense
Exemption Applied to the Repeal of Part VI of the NKSP
Kingsburg determined its repeal of part VI of the NKSP would “certainly” not
cause any environmental impacts. Accordingly, it invoked the “commonsense
exemption” to CEQA. (See CEQA Guidelines, § 15061, subd. (b)(3).) Selma challenges
the applicability of that exemption.
A. Law
A project may be found exempt from CEQA “under what is sometimes called the
‘commonsense’ exemption, which applies ‘[w]here it can be seen with certainty that there
is no possibility that the activity in question may have a significant effect on the
environment’ [citation]. [Citation.]” (Muzzy Ranch Co. v. Solano County Airport Land
Use Com. (2007) 41 Cal.4th 372, 380.) “The exemption can be relied on only if a factual
evaluation of the agency’s proposed activity reveals that it applies.” (Id. at p. 386.) “If
legitimate questions can be raised about whether the project might have a significant
impact and there is any dispute about the possibility of such an impact, the agency cannot
find with certainty that a project is exempt.” (Davidon Homes v. City of San Jose (1997)
54 Cal.App.4th 106, 117.) “[I]f a reasonable argument is made to suggest a possibility
that a project will cause a significant environmental impact, the agency must refute that
40.
claim to a certainty before finding that the exemption applies.” (Id. at p. 118.) “[T]he
agency invoking the exemption has the burden of demonstrating it applies. [Citation].”
(Muzzy Ranch Co., supra, at p. 386.) Under this strict standard, we conclude Kingsburg
failed to carry its burden.
B. Analysis
Kingsburg defends its determination the commonsense exemption applies by
observing that even after the repeal of part VI of the NKSP, future development projects
would still have to comply with city zoning ordinances and codes, as well as statewide
plans and standards. This argument does not go quite as far as Kingsburg needs it to. In
order to invoke the exemption, Kingsburg needed “to be certain that there [was] no
possibility [that repealing the NKSP design standards] may cause significant
environmental impacts.” (Davidon v. City of San Jose, supra, 54 Cal.App.4th at p. 117.)
The mere existence of other standards does not preclude the possibility that repealing the
design standards could still cause significant environmental impacts. For example, if the
NKSP design standards offered substantially more environmental protection in one or
more areas compared to existing codes and ordinances, then one could not be certain that
repealing the design standards falls under the commonsense exemption. And it was
Kingsburg’s burden to refute that possibility “to a certainty” (id. at p. 118) before
concluding the commonsense exemption applied. Kingsburg did not do so and thereby
failed to carry its burden.
We also conclude Kingsburg’s notice of exemption for repealing part VI of the
NKSP was inadequate. An “‘agency’s exemption determination must [rely on] evidence
in the record demonstrating that the agency considered possible environmental impacts in
reaching its decision.’ [Citation].” (Muzzy Ranch Co. v. Solano County Airport Land
Use Com., supra, 41 Cal.4th at pp. 386-387.) An agency errs when it fails to “reference
the factual record in its Notice of Exemption.” (Id. at p. 389.) Here, the notice of
41.
exemption simply stated in conclusory fashion: “It can be seen with certainty that there
is no potential for environmental impacts that may result from the proposed amendment
as it is a repeal of text in an adopted Specific Plan.” Accordingly, Kingsburg “erred in
failing to reference the factual record in its Notice of Exemption.” (Muzzy Ranch Co.,
supra, at p. 389.)
Kingsburg’s decision that repealing the design standards of the NKSP was exempt
from CEQA under the commonsense exemption must be set aside. However, it is
important to note we only find Kingsburg failed to carry its burden in showing the
commonsense exemption applies. We do not conclude the commonsense exemption is
definitely inapplicable. (See DISCUSSION, pt. IX, post.) Under these circumstances,
Kingsburg may again invoke the exemption if, after proper consideration, it hereafter
finds to a certainty there is no possibility significant environmental impacts may result
from the project, and that finding is supported in the record. (Davidon v. City of San
Jose, supra, 54 Cal.App.4th at p. 119.) “If it cannot make such a finding, it must proceed
to the next tier of environmental review and conduct an initial study. (Guidelines,
§ 15063.)” (Id. at pp. 119-120.)
IX. Selma Failed to Exhaust Its Administrative Remedies With Respect to
Identifying Specific Potential Environmental Impacts of Repealing Part VI of
the NKSP
Selma tries to go a step further, suggesting the repeal of the NKSP design
standards certainly does present the possibility of significant environmental impacts.
Specifically, Selma argues the NKSP design standards “enhance aesthetics by ‘land use
and circulation proposals’ and ‘design, development and maintenance standards.’ It
mitigates noise impacts by standards for placement of industrial structures, wall
construction, ‘buffer landscaping,’ fencing and barriers.”
Of course, if we conclude there was substantial evidence of possible significant
environmental impacts, then Kingsburg would be precluded from invoking the
42.
commonsense exemption on remand. However, we reject Selma’s contentions because it
failed to raise these issues administratively.
A. Law
A CEQA action may not be brought “unless the alleged grounds for
noncompliance with [CEQA] were presented to the public agency orally or in writing by
any person during the public comment period provided by [CEQA] or prior to the close
of the public hearing on the project before the issuance of the notice of determination.”
(§ 21177, subd. (a).) “‘“The essence of the exhaustion doctrine is the public agency’s
opportunity to receive and respond to articulated factual issues and legal theories before
its actions are subjected to judicial review.”’ [Citation.]” (North Coast Rivers Alliance v.
Marin Municipal Water Dist. Bd. of Directors (2013) 216 Cal.App.4th 614, 623.) “‘The
purposes of the doctrine are not satisfied if the objections are not sufficiently specific so
as to allow the Agency the opportunity to evaluate and respond to them.’ [Citation.]”
(Ibid.)
B. Analysis
Kingsburg published notice of a public hearing on the repeal of part VI of the
NKSP. The notice indicated: “It has been determined that the action is exempt from the
California Environmental Quality Act as it will not result in a physical change to the
environment.” The notice also contained the following text: “NOTICE: If you
challenge the decision on any of the forgoing [sic] matters in court, you may be limited to
raising only those issues you or someone else raised at the public hearing described in
this notice, or in written correspondence delivered to the Kingsburg Planning Department
prior to the public hearing.” The notice was published in a newspaper of general
circulation on May 22, 2013, and the hearing was held on June 5, 2013. At the public
hearing, no one mentioned the specific potential environmental impacts Selma now
43.
identifies (e.g., enhanced aesthetics, noise mitigation, etc.). Accordingly, those issues
cannot be raised in this appeal. (See § 21177, subd. (a).)
Selma responds that since CEQA itself does not provide for a public comment
period when an agency proceeds with a notice of exemption under CEQA Guidelines
section 15061, subdivision (b)(3), the exhaustion statute may not apply. (See § 21177,
subd. (a) [CEQA action precluded “unless … alleged grounds for noncompliance … were
presented … during the public comment period provided by” CEQA].) Selma contends
Tomlinson v. County of Alameda (2012) 54 Cal.4th 281 suggests section 21177 “only
comes into play when there has been a ‘public comment period’ provided under the
provisions of CEQA.” We disagree, as this is the opposite of what Tomlinson—and the
statutory text—suggests.
Tomlinson began its exhaustion analysis—as we do now—by observing section
21177, subdivision (a) “states that a court action alleging a public agency’s failure to
comply with CEQA may be brought only if ‘the alleged grounds for noncompliance with
[CEQA] were presented to the public agency orally or in writing by any person during
the public comment period provided by this division or prior to the close of the public
hearing on the project before the issuance of the notice of determination.’” (Tomlinson v.
County of Alameda, supra, 54 Cal.4th at p. 289.) The Supreme Court observed that, by
its terms, subdivision (a) of section 21177 “requires either (1) a public comment period
provided by CEQA (the public comment provision) or (2) an opportunity for public
comment at public hearings before issuance of a notice of determination (the public
hearing provision).” (Tomlinson, at p. 289, italics added.) Thus, while the public
comment provision was inapplicable to categorical exemption cases because CEQA does
not provide for a public comment period in those circumstances, the public hearing
provision may still apply. (Tomlinson, at pp. 289-290.) Accordingly, Tomlinson held
“the exhaustion-of-administrative-remedies requirement set forth in subdivision (a) of
section 21177 applies to a public agency’s decision that a proposed project is
44.
categorically exempt from CEQA compliance as long as the public agency gives notice
of the ground for its exemption determination, and that determination is preceded by
public hearings at which members of the public had the opportunity to raise any concerns
or objections to the proposed project. [Citation.]” (Id. at p. 291.) Thus, Selma’s
contention Tomlinson suggests section 21177 only comes into play when there has been a
“public comment period” provided under the provisions of CEQA is clearly wrong.
Section 21177 also applies when there has been a properly noticed public hearing.
It was Selma’s burden to demonstrate it raised these specific issues at the
administrative level. (See Citizens for Responsible Equitable Environmental
Development v. City of San Diego (2011) 196 Cal.App.4th 515, 527.) Because Selma
failed to carry that burden, we reject its contentions concerning specific potential
environmental impacts that might result from repealing the NKSP’s design standards.
DISPOSITION
The judgment in the Annexation action (i.e., case No. 12CECG03223) is affirmed.
The judgment in the NKSP action (i.e., case No. 13CECG02139) is reversed. The
trial court is directed to issue a writ of mandate directing the City of Kingsburg to set
aside its determination that its repeal of part VI of the North Kingsburg Specific Plan is
exempt from CEQA review under the commonsense exemption.
Each party shall bear its own costs on appeal.
___________________________
PEÑA, J.
WE CONCUR:
__________________________
KANE, Acting P.J.
__________________________
DETJEN, J.
45.