DISTRICT OF COLUMBIA v. DISTRICT OF COLUMBIA CONTRACT APPEALS BOARD, and PRINCE CONSTRUCTION CO., INC., and W.M. SCHLOSSER CONSTRUCTION CO., INC

                            District of Columbia
                             Court of Appeals
No. 14-AA-396
                                                                 AUG 18 2016
DISTRICT OF COLUMBIA,
                                   Petitioner,

       v.                                               CAB-D-1369, D-1419, & D-1420

DISTRICT OF COLUMBIA CONTRACT APPEALS BOARD,
                        Respondent,

       and

PRINCE CONSTRUCTION CO., INC., and W.M. SCHLOSSER CONSTRUCTION
     CO., INC.,
                       Intervenors.

                           On Petition for Review of an Order
                   of the District of Columbia Contract Appeals Board

        BEFORE: BLACKBURNE-RIGSBY and EASTERLY, Associate Judges; and REID,
Senior Judge.

                                    JUDGMENT

              This case came to be heard on the administrative record, a certified copy of
the agency hearing transcript and the briefs filed, and was argued by counsel. On
consideration whereof, and as set forth in the opinion filed this date, it is now hereby

              ORDERED and ADJUDGED that the order of the Contract Appeals Board
(“CAB”) is reversed with respect to the intervenors’ delay claims related to the storm
drainage pipe relocation, the fire pump installation, and the truck scales wiring. The case
is remanded to the CAB to adjust the award accordingly. The CAB’s decision is
otherwise affirmed regarding the claims related to the roof deck modification, subsurface
concrete obstruction, fire-suppression system permit, and concrete mix.

                                    For the Court:




Dated: August 18, 2016.

Opinion by Associate Judge Anna Blackburne-Rigsby.
Notice: This opinion is subject to formal revision before publication in the
Atlantic and Maryland Reporters. Users are requested to notify the Clerk of the
Court of any formal errors so that corrections may be made before the bound
volumes go to press.


             DISTRICT OF COLUMBIA COURT OF APPEALS
                                                                       8/18/16
                                No. 14-AA-396

                      DISTRICT OF COLUMBIA, PETITIONER,

                                       v.

                          DISTRICT OF COLUMBIA
                   CONTRACT APPEALS BOARD, RESPONDENT,

                                      and

PRINCE CONSTRUCTION CO., INC. AND W.M. SCHLOSSER CONSTRUCTION CO., INC.,
                              INTERVENORS.

                    Petition for Review of a Decision of the
                  District of Columbia Contract Appeals Board
                    (CAB Nos. D-1369, D-1419 & D-1420)

(Argued October 6, 2015                               Decided August 18, 2016)

       James C. McKay, Jr., Senior Assistant Attorney General for the District of
Columbia, with whom Eugene A. Adams, Interim Attorney General at the time the
brief was filed, Todd S. Kim, Solicitor General, and Loren L. AliKhan, Deputy
Solicitor General, were on the brief, for petitioner.

     Richard K. Rothschild, General Counsel for District of Columbia Contract
Appeals Board, was on the statement in lieu of brief for respondent.

       Douglas L. Patin, with whom Michael J. Cohen was on the brief, for
intervenors.
                                           2

      Before BLACKBURNE-RIGSBY and EASTERLY, Associate Judges, and REID,
Senior Judge.

      BLACKBURNE-RIGSBY, Associate Judge: In this case, a contractor seeks

compensation for construction work that it completed on the Fort Totten Solid

Waste Transfer Facility in Northeast Washington, D.C. for the District of

Columbia, which went beyond the initial parameters of the construction contract.

The primary question presented in this appeal is whether the contractor’s claims

for reimbursement are barred because the contractor failed to adhere to certain

procedural requirements of the contract.



      The District of Columbia (“Petitioner” or “District”) hired joint venturers

Prince Construction Co., Inc. and W.M. Schlosser Construction Co., Inc.,

(“Intervenors” or “Prince/Schlosser”), to complete alterations and repairs to the

Fort Totten Solid Waste Transfer Facility. Unexpected and unbudgeted changes

during the course of the project caused the project to be delayed by nearly one

year, and increased the cost of completing the project by over one-half million

dollars. Prince/Schlosser filed claims with the District to be compensated for the

indirect costs (such as paying employees and subcontractors to work extended

hours, increased overhead, lost profits, and additional bond costs) resulting from

the delays (“delay claims”).     Prince/Schlosser also filed separate claims for
                                           3

additional uncompensated work it completed during the project. Principally, the

District argues that Prince/Schlosser’s delay claims are procedurally barred under

the terms of the parties’ contract because: 1) Prince/Schlosser did not “within

[thirty] days after receipt of a written Change Order”1 give the government written

notice that it “intend[ed] to assert a claim,” and 2) Prince/Schlosser did not submit

“cost or pricing data and [a] certification that the cost or pricing data submitted

was accurate . . . .”2 On the merits, the District alternatively argues that it is not

responsible for the direct or indirect costs associated with the claims.



      The District of Columbia Contract Appeals Board (“CAB”) rejected the

District’s arguments, found in favor of Prince/Schlosser, and awarded the

contractor a total of $585,498.98, plus the interest accrued from the date of the

filed claims, pursuant to D.C. Code § 2-359.09 (2012 Repl.). On review of the


      1
          The District’s contracting officer is permitted to issue “change orders,”
which the parties sometime refer to as “basic change directives,” that “make any
change in the work within the general scope of the Contract” at any time pursuant
to Article 3 of the District’s 1973 Standard Contract Provisions for Use with
Specifications for District of Columbia Construction Projects (“Standard Contract
Provisions”). Change orders could also be prompted when the contractor provides
the contracting officer with what the parties call a “proposed change order” stating
the date, circumstances, and sources of the order.
      2
         See Section 3.C of the Standard Contract Provisions (stating the thirty-day
notice requirement); Subsection H.33.E of the Contract (stating the “cost or pricing
data” requirement).
                                         4

record and the District’s legal arguments, we affirm in part.        We hold that

Prince/Schlosser’s delay claims are not procedurally barred by the contract because

the District was on notice of the circumstances giving rise to the claims, and

therefore was not prejudiced by the late claims.          We also conclude that

Prince/Schlosser’s submission of data reflecting actual expenses already incurred

instead of “cost and pricing data” does not bar its claims for reimbursement.



      Regarding the merits, however, we hold that the CAB erred in awarding

Prince/Schlosser damages for three of its claims: 1) the delay claim for relocating

a storm drainage pipe, 2) the delay claim for installing a fire pump, and 3) the

“constructive change” claim seeking compensation for installing wiring to five

truck scales.   Finally, we affirm the CAB’s award to Prince/Schlosser on its

remaining four claims relating to: 1) a roof deck modification, 2) subsurface

concrete obstruction, 3) obtaining a fire-suppression system permit, and 4)

purchasing a sulfate-resistant concrete mix. Thus, we reverse the CAB’s decision

on three claims, affirm the remaining four claims, and remand to the CAB to adjust

the award accordingly.
                                        5

                             I.    Factual Background



       On September 13, 2006, the District and Prince/Schlosser entered into a

government construction contract, entitled “Contract No. POKT-2005-B-0085-CM

for Alterations and Repairs of the Fort Totten Waste Transfer Facility”

(“Contract”). “The project included the construction of a new, three-level building

addition, including foundations, a ‘tipping’ floor [a floor where trash from

incoming trucks is tipped into tractor trailers on the ramp below], walls, louvers,

roofing, truck ramps, five truck scales, compaction cranes, and a truck wash

facility.”   The initial Contract price was $13,266,000, and the project was

scheduled to be completed within 275 calendar days, with a set completion date of

July 17, 2007.



       During the course of construction, however, the District directed

Prince/Schlosser to complete additional, previously unbudgeted work due to

unanticipated problems and authorized price adjustments to compensate

Prince/Schlosser for the additional work, which were reflected in five change

orders. Collectively, the five change orders authorized an increase to the Contract

price of approximately $1,028,178, but only authorized a time extension to the
                                         6

project by one day. The project did not meet the scheduled deadline and concluded

on April 4, 2008, 261 days after the planned completion date.



      The five change orders only compensated Prince/Schlosser for the costs

directly associated with the unexpected problems, and they did not reimburse

Prince/Schlosser for the indirect costs incurred during the additional 261 days of

work that were not budgeted for under the contract. These indirect costs included

paying employees and subcontractors to work extended hours, increased overhead,

lost profits, and additional bond costs. In May 2008, one month after closing the

project, Prince/Schlosser submitted written notice to the District that it would be

seeking reimbursement for those additional costs. The parties negotiated in May

and November of 2008, but failed to reach an agreement.



      Prince/Schlosser then submitted delay claims to the District’s contracting

officer on April 23, 2009, in an effort to obtain compensation.3 Prince/Schlosser

sought delay claims for indirect costs in the amount of $1,099,325.

Prince/Schlosser also submitted two additional claims for direct costs on June 24,

      3
          Prince/Schlosser submitted the claims pursuant to 27 DCMR § 3803
(2004), which permits a contractor to file claims arising from the contract with the
District’s contracting officer if the parties are “unable to resolve a dispute . . .
through informal discussions.”
                                         7

2009: 1) $32,280.67 for the additional cost of wiring five truck scales; and 2)

$8,908.63 for the additional cost of making a concrete solution sulfate-resistant.4

The District’s contracting officer did not approve any of the claims, and

Prince/Schlosser appealed to the CAB.



      During a hearing before the CAB, the District argued primarily that

Prince/Schlosser’s delay claims were barred under the contract and that, in any

event, all of the claims lacked merit. Specifically, the District asserted that the

delay claims were barred because Prince/Schlosser: 1) failed to submit written

notice of its intended claims within “[thirty] days after receipt of a written Change

Order,”5 and 2) failed to submit certified “cost or pricing data,”6 which prevented

the District from properly assessing the merits of Prince/Schlosser’s claims.


      4
          The parties attempted to resolve these issues for several months before
these claims were submitted but failed to reach an agreement.
      5
         Section 3.C of the Standard Contract Provisions states that “[i]f the
Contractor intends to assert a claim for an equitable adjustment under this Article,
he must, within [thirty] days after receipt of a written Change Order . . . submit to
the Contracting Officer a written statement setting forth the general nature and
monetary extent of such claim . . .”
      6
          Section H.33.E states that “the Contractor shall, before negotiating any
price adjustments pursuant to a change order or modification, submit cost or
pricing data and certification that, to the best of the Contractor’s knowledge and
belief, the cost or pricing submitted was accurate, complete, and current as of the
date of negotiation of the change order or modification.”
                                          8

      The CAB disagreed with the District, and held that Prince/Schlosser’s failure

to comply with the thirty-day notice requirement was not a violation of the

Contract because “[b]oards and courts have generally not strictly enforced such

notice requirements absent a finding that the government is prejudiced” by the

untimely notice. The CAB concluded that there was no prejudice to the District

here because “the District was well aware of the operative facts underlying each of

the” delay claims given that Prince/Schlosser “promptly notified the District” of

each event leading to the delays. The CAB also held that Prince/Schlosser was not

required to submit certified “cost or pricing data” with its delay claims because it

filed the claims after it accrued the actual costs associated with the delay, and once

Prince/Schlosser incurred “the impact costs by performing changed work, cost or

pricing data [was] no longer the basis of negotiation of the adjustment.” The CAB

determined that Prince/Schlosser complied with the Contract when it provided the

actual breakdown of its indirect costs.



      Regarding the merits of the claims, the CAB reviewed the Contract, heard

testimony from representatives of both parties as well as an expert witness who

evaluated the schedule delays, and found that Prince/Schlosser should be awarded

damages. Specifically, the CAB found the District responsible for the contractor’s

indirect costs resulting from the additional work, including: 1) relocating a storm
                                          9

drainage pipe, 2) installing a fire sprinkler pump, 3) removing a subsurface

concrete obstruction, 4) obtaining a fire-suppression system permit, and 5)

completing a roof deck modification.7 It also found the District responsible for the

costs incurred from the unanticipated tasks of wiring truck scales and using a

sulfate-resistant concrete mix. The CAB calculated the award by adding together

Prince/Schlosser’s incurred costs for which the CAB concluded the District was

responsible, which amounted to $585,498.98.8 This petition for review followed.



                                   II.    Discussion



A.    Standard of Review



      Contractual interpretation is a legal question, which this court reviews de

novo. Tillery v. District of Columbia Contract Appeals Bd., 912 A.2d 1169, 1176

(D.C. 2006). We nonetheless “accord great weight to the [CAB’s] construction of

a government contract, so long as that construction is not unreasonable.” Id. at


      7
         The CAB considered but denied Prince/Schlosser’s delay claim for costs
associated with the delay in obtaining a Master Building Permit because the
District was not responsible for that delay. Prince/Schlosser does not challenge
this conclusion.
      8
          The District does not dispute the CAB’s calculations.
                                         10

1175 (quoting Unfoldment, Inc. v. District of Columbia Contract Appeals Bd., 909

A.2d 204, 208–09 (D.C. 2006)) (alteration in original). In reviewing the CAB’s

decision, we “look not only to the case law on which the [CAB] relied but to other

decisions of the United States Court of Appeals for the Federal Circuit, the former

United States Court of Claims and its successors, and the various federal boards of

contract appeals.”    District of Columbia v. Org. for Envtl. Growth, Inc.

(“OFERGO I”), 700 A.2d 185, 198 (D.C. 1997); see also Abadie v. District of

Columbia Contract Appeals Bd., 916 A.2d 913, 919 (D.C. 2007).9




      9
           Preliminarily, Prince/Schlosser contends that the District waived the
following three arguments before this court because it did not bring them before
the CAB: 1) the District was prejudiced by Prince/Schlosser’s late notice of the
delay claims, 2) there is no legal basis for Prince/Schlosser’s recovery for the roof
deck modification delay claim, and 3) there was a patent ambiguity in the contract
regarding the truck scales claim. This court will generally not review issues raised
for the first time on appeal, yet the principle that an argument is waived if not
raised below is “one of discretion rather than jurisdiction.” McClintic v. McClintic,
39 A.3d 1274, 1277 n.1 (D.C. 2012) (quoting District of Columbia v. Helen
Dwight Reid Educ. Found., 766 A.2d 28, 33 n.3 (D.C. 2001)). “Moreover, even if
a claim was not ‘pressed’ below, that claim is properly reviewed on appeal if it has
been ‘passed upon.’” Id. Here, the CAB “passed upon” each of the three issues in
its decision as it mentioned or analyzed each one. We see no prejudice in
reviewing all of the District’s arguments and thus find that none of the District’s
arguments are waived.
                                         11

B.    Prince/Schlosser’s Delay Claims are not Barred



      The District relies on two contract provisions to challenge Prince/Schlosser’s

delay claims for reimbursement and urges this court to adopt a strict adherence

approach to interpreting the Contract. First, the District argues that the delay

claims are barred because Prince/Schlosser violated a thirty-day notice requirement

found in Article 3 of the “Standard Contract Provisions,” which governed the

procedures for altering the Contract terms, as modified by Subsection H.33 of the

Contract. Second, the District argues that the delay claims are barred because

Prince/Schlosser failed to include certified “cost or pricing data” when it submitted

the claims pursuant to Subsection H.33.E of the Contract.         We address each

argument in turn.



      1.     Thirty-Day Notice Requirement



      The District argues that the Contract bars Prince/Schlosser’s delay claims

because the claims are untimely and their untimeliness prejudiced the District.

Section C of Article 3 of the Standard Contract Provisions requires the contractor

to submit to the contracting officer, in writing, a statement of “the general nature

and monetary extent” of any claim it intends to file within thirty days of receiving
                                         12

a change order. The District first asserts that this thirty-day notice requirement

should be strictly construed to bar all of Prince/Schlosser’s delay claims, regardless

of prejudice, because Prince/Schlosser submitted the claims over a year and half

after receiving the respective change orders. Alternatively, the District claims that,

while it is not required to show prejudice, it was in fact prejudiced because the lack

of notice of the upcoming claims prevented the District from mitigating damages

to avoid the delays. We disagree and affirm the CAB’s ruling on this issue,

concluding that the thirty-day notice requirement should be liberally construed to

only bar Prince/Schlosser’s claims if failure to give timely notice prejudiced the

District, which was not the case here.



      Recent case law in our jurisdiction interpreting notice requirements within

government construction contracts is scarce. However, contract appeal boards and

federal courts have adopted a flexible stance on notice requirements for delay

claims: that they should be liberally construed and only strictly enforced where the

government is unaware of the circumstances surrounding the delay claims, thereby

prejudicing the government.10 See e.g., K-Con Bldg. Sys., Inc. v. United States,


      10
          We look to other boards of contract appeals and certain federal courts,
“which have particular expertise in this area,” that have interpreted analogous
notice requirements. OFERGO I, supra, 700 A.2d at 198 (quoting Dano Resource
Recovery, Inc. v. District of Columbia, 620 A.2d 1346, 1351 (D.C. 1993)); see also
                                                                   (continued . . .)
                                         13

115 Fed. Cl. 558, 573 (2014) (“The notice requirement contained in the contract’s

changes and suspension of work clauses . . . is flexible; and [the government] has

not demonstrated that it was prejudiced by the timing of [the contractor’s] notice.”

(citing Hoel-Steffen Constr. Co. v. United States, 456 F.2d 760, 768 (Ct. Cl.

1972))); Nova Group/Tutor-Saliba v. United States, 125 Fed. Cl. 469, 474 (2016)

(“This case falls squarely within the exception to strict enforcement of the [twenty-

day] notice requirement where the Contracting Officer is on notice of the

circumstances giving rise to the claim”); Monster Gov’t Solutions, Inc. v. United

States Dept. of Homeland Security, DOTCAB No. 4532, 06-2 BCA ¶ 33,312 (June

7, 2006) (“When a contracting officer has actual knowledge of the facts, lack of

written notice does not bar a claim absent evidence of prejudice to the

[g]overnment.”).




(. . . continued)
Abadie, supra, 916 A.2d at 919. Historical support for the liberal approach to
notice requirements adopted by other boards of contract appeals and federal courts
can be found in United States v. Cunningham, 125 F.2d 28, 30 (D.C. Cir. 1941),
which involved a government construction contract provision that required the
contractor to give the government written notice of any delays to the project
“within ten days from the beginning of any such delay.” Id. at 29. The underlying
purpose of the requirement was “to inform the government of the cause of delay
and afford an opportunity to remove [the cause of delay].” Id. at 30. Cunningham
held that a contractor’s claim is barred “unless the contractor had at the time
notified the government in writing of the facts and circumstances” surrounding the
delay. Id. (internal quotations omitted).
                                         14

      In this case, the CAB recognized that Prince/Schlosser submitted monthly

schedule adjustments throughout the project and “[m]onth-by-month, the schedules

show the expected completion date slipping further into the future as delaying

events occurred.”     The CAB also noted that “[t]hroughout the period of

performance, the District did not reject any of the monthly schedule updates.” In

fact, after reviewing “the Contract plans and specifications, meeting minutes, daily

reports, [requests for information], payment applications, email and other

correspondence,” the expert witness at the CAB hearing testified that

Prince/Schlosser’s “periodic schedule updates were consistent with the contract

requirements and conformed to industry practice,” and that the project would have

been completed on time “but for the delays caused by the District.” Contrary to

the District’s arguments, Prince/Schlosser provided timely written notice to the

District “of the circumstances giving rise to the claim[s].” Nova Group/Tutor-

Saliba, supra, 125 Fed. Cl. at 474. The District’s assertion that it would have hired

another contractor to complete the work had it known of the upcoming delay

claims, thereby taking the “opportunity to remove [the cause of the delay],” does

not negate the fact that the District was aware of the facts underlying the delay

claims, and continued to press forward with the contract. See Cunningham, supra

note 10, 125 F.2d at 30 (explaining that notice requirements allow the government

to eliminate the cause of the delay). There is no prejudice to the District for
                                         15

Prince/Schlosser’s failure to meet the technical requirement to submit its claims

within the thirty-day window.



      The District contends that we took the opposite approach in OFEGRO I,

supra, 700 A.2d at 204, where we strictly interpreted the Material Management

Manual, which contains a similar thirty-day notice requirement. We disagree. In

OFEGRO I, we questioned whether the violation of a thirty-day notice requirement

would bar a claim, but we did not explicitly hold so. Id. at 205. Instead, we

remanded the case to the CAB to decide that issue, id., and, on remand, the CAB,

citing several CAB decisions and federal court opinions, stated that the thirty-day

requirement should be liberally construed and held that a contractor’s claim should

only be barred where the government is prejudiced.11 In re Org. for Envtl. Growth,

Inc., DCCAB No. D-850, 2001 WL 433422 (Apr. 13, 2001). We now expressly

adopt the rule well-established by federal courts and contract appeal boards that the

thirty-day notice requirement should be liberally construed. By adopting this rule,

we adhere to the sound policy underlying its purpose — that “[i]f the contracting


      11
          That decision was appealed for a second time, where we stated that the
CAB’s conclusion appeared to conflict with another ruling in its order, and we
remanded the case again for the CAB to address a separate issue. Abadie v. Org.
for Envtl. Growth, Inc. (OFEGRO II), 806 A.2d 1225, 1230 (D.C. 2002). In
OFEGRO II, we gave no further opinion or conclusion on how the thirty-day
notice requirement should be interpreted or applied.
                                          16

officials have knowledge of the facts or problems that form the basis of a claim and

are able to perform necessary fact-finding and decision[-]making,” the government

is not prejudiced by a late claim and should not be permitted to avoid

compensating a contractor for services provided simply due to the contractor filing

a late claim. Calfon Const. Inc. v. United States, 18 Cl. Ct. 426, 438–39 (1989).



      2.     Certified Cost or Pricing Data



      The District also argues that the delay claims are barred because

Prince/Schlosser failed to submit certified “cost or pricing data” with its request for

compensation, which prevented the District from properly assessing the merits of

the contractor’s claims. The District relies on Subsection H.33.E of the Contract

which provides that:


             the Contractor shall, before negotiating any price
             adjustments pursuant to a change order or modification,
             submit cost or pricing data and [a] certification that, to
             the best of the Contractor’s knowledge and belief, the
             cost or pricing data submitted was accurate, complete,
             and current as of the date of negotiation of the change
             order or modification.


The Contract explains that cost and pricing data:

             includes all facts as of the time of price agreement that
             prudent buyers and sellers would reasonably expect to
                                          17

             affect price negotiations significantly. Cost or pricing
             data are factual, not judgmental, and are therefore
             verifiable. While they do not indicate the accuracy of the
             prospective Contractor’s judgment about estimated future
             costs or projections, cost or pricing data do include the
             data forming the basis for that judgment.12 (emphasis
             added)


      The District’s reliance on Subsection H.33.E.1 of the Contract is misplaced.

Prince/Schlosser did not bring these claims when costs were prospective but

instead brought them post-performance when the actual costs incurred were readily

available. Rather, Subsection H.33.C.2 of the Contract is the applicable provision.

It states that “if agreement on costs cannot be reached prior to execution of

changed work, payment will be made for the actual costs[,] provided records of

such costs are made available and that such costs are reasonable.” (emphasis

added). Prince/Schlosser submitted a record of the actual costs it incurred, which

permitted the District to assess the merits of the claims.13 See Civil Constr., LLC,


      12
         Separate from change orders and modifications, Article 7 of the Standard
Contract Provisions explains that the contractor can bring “any dispute concerning
a question of fact arising under the Contract which is not disposed of by the
agreement,” to be decided by the contracting officer in a written decision. The
contractor can then appeal the contracting officer’s written decision on the claim to
the CAB. Notably, Article 7 does not require that certified “cost or pricing data”
be submitted to the contracting officer with the filed contract claims.
      13
          The District’s reliance on the District of Columbia Procurement Rules, 27
DCMR § 1624 (1988), which the District claims requires the submission of
certified “cost or pricing data” with contract claims, is also misplaced. Instead, the
                                                                       (continued . . .)
                                         18

CAB Nos. D-1294, D-1413 & D-1417, 2013 WL 3573982, at *16 (Mar. 14, 2013)

(stating that actual costs incurred should be submitted when available).         We

conclude that Prince/Schlosser’s delay claims are not procedurally barred, and now

turn to the merits of all of Prince/Schlosser’s claims for compensation.



C.    The District Is Not Responsible for the Costs Underlying Three of
      Prince/Schlosser’s Claims


      The District asserts that the language found in the Contract and other

documents (including contract modifications signed by the parties, drawings of the

proposed work, and specifications of the work in the Contract) indicate that the

District is not responsible for the costs underlying all of Prince/Schlosser’s

claims.14 We conclude that the District is partially correct; it must compensate



(. . . continued)
applicable section of the District of Columbia Procurement Rules is 27 DCMR
§ 3803.2 (2004), which addresses claims by a contractor and requires that a
contractor submit “any data or other information in support of the claim,” and does
not require that the data be certified “cost or pricing data.” (emphasis added).
Prince/Schlosser met this requirement by submitting its actual cost breakdown, and
thus the claims are not barred.
      14
           In addition to challenging the merits of the delay claims, the District
argues that the CAB incorrectly placed the burden of proof on the District to prove
that there were concurrent causes of the delays, which is inconsistent with federal
contract law that requires the contractor to prove that the delays caused by the
District were “not concurrent with a delay caused by the contractor or some other
                                                                    (continued . . .)
                                         19

Prince/Schlosser for the costs associated with its claims except for the three claims

(. . . continued)
reason.” P.J. Dick Inc. v. Principi, 324 F.3d 1364, 1370 (Fed. Cir. 2003). In the
District of Columbia, however, the CAB has established that the “District bears the
burden of proving concurrency” as an “affirmative defense to liability for delay
damages.” MCI Constructors, Inc., DCCAB No. D-924, 1996 WL 331212 (June
4, 1996). The CAB acknowledged in footnote 53 of the order that this affirmative
defense is different from the burden generally placed on the contractor in federal
contract law. The CAB supported this distinction by citing Williams Enterprises v.
Strait Mfg. & Welding Inc., 728 F. Supp. 12, 16, 23 (D.D.C. 1990), aff’d sub nom.
Williams Enters., Inc. v. Sherman R. Smoot Co., 938 F.2d 230 (D.C. Cir. 1991),
where the United States District Court for the District of Columbia stated that
defendants, such as the District in this case, “have the burden of proof of claim in
the District [of Columbia]” for affirmative defenses “tending to exculpate
defendants from liability.” We will not disturb the legal standard for the burden of
proof of concurrent delays adopted by the CAB in this jurisdiction. See OFEGRO
I, supra, 700 A.2d at 198 (“On questions of law, although the Board’s decision is
not final or conclusive, ‘we give careful consideration to [its] interpretation
because legal interpretations by tribunals having expertise are helpful even if not
compelling.’”).

       The District also points to the language in Section H.33.C of the Contract
governing changes in the time period of performance, which states that
Prince/Schlosser is required to “describe in detail” how a change in the time period
of performance “affects the . . . concurrency with other delays,” and points to
Section H.33.D, which states that the project would only be extended by the
number of days “which is not concurrent with another delay for which a time
extension” has been requested. The District argues that this language places the
burden on Prince/Schlosser to disprove concurrency and requests that we remand
for the CAB to apply that burden on Prince/Schlosser. However, remand on this
issue is not necessary because the record reflects that Prince/Schlosser did indeed
proffer an expert witness who testified that “there was no concurrent delay of
[Prince/Schlosser’s] making,” and the CAB accepted this conclusion.
                                         20

discussed in this section: 1) the delay claim for the storm drainage pipe relocation,

2) the delay claim for the fire pump installation, and 3) the constructive change

claim for wiring truck scales. We reverse the CAB’s holdings for these claims

because the CAB misinterpreted the Contract and incorrectly applied the law.



      1.     Delay Claim for Relocating Storm Drainage Pipe



      While laying concrete during the performance of the Contract,

Prince/Schlosser discovered a storm drainage pipe that interfered with its work.

Prince/Schlosser was not previously aware of the pipe because the District

incorrectly indicated the pipe’s location in the project drawings that it gave to

Prince/Schlosser.    Prince/Schlosser notified the District of the problem by

submitting Proposed Change Order No. 20. In response, the District’s contracting

officer issued Basic Change Directive No. 3, directing Prince/Schlosser to relocate

the pipe, and Basic Change Directive No. 5, directing Prince/Schlosser to fill and

replace the storm drains.    This additional work of relocating the pipe caused

delays, and Prince/Schlosser incurred additional costs as a result.
                                        21

      The contracting officer also issued Change Order No. 3, which compensated

Prince/Schlosser for the direct costs of the additional work but contained language

releasing the District

             from any and all actual or potential claims and demands
             for delays and disruptions, additional work which the
             contractor or any person claiming by, through, or under
             the contractor, may now have, or may in the future, have
             against the District of Columbia government, for . . .
             any manner connected with the subject Change Order or
             the prosecution of the work hereunder. (emphasis added)


Change Order No. 3 referenced Basic Change Directive Nos. 3 and 5 and

specifically listed the task of “[d]emolishing the existing storm sewer pipe at

column lane #1 and filling it with concrete,” among other tasks. The District

claims that the language in Change Order No. 3 releases the District from liability

for any “claims and demands for delays” resulting from the storm drainage pipe

relocation because that work was referenced in the change order and is therefore

“connected with” Change Order No. 3.



      The CAB held that the release language did not apply to the storm drainage

pipe work because Change Order No. 3 did not reference any of Prince/Schlosser’s

Proposed Change Orders including Proposed Change Order No. 20, which

specifically discussed the storm drainage pipe work. Yet, Change Order No. 3

referenced the contracting officer’s Basic Change Directive No. 3, which directed
                                          22

Prince/Schlosser to relocate the pipe, and Basic Change Directive No. 5, which

directed Prince/Schlosser to fill and replace the storm drains. Change Order No. 3

also listed the task of demolishing the storm drainage pipe. Because Change Order

No. 3 expressly referenced the storm drainage pipe work, the District is released

from liability for any delay claims seeking additional compensation for relocating

the storm drainage pipe. Patterson v. District of Columbia, 795 A.2d 681, 683

(D.C. 2002) (“[T]he written language of a contract governs the parties’ rights

unless it is not susceptible of clear meaning.”).



      2.     Delay Claim for Fire Pump Installation



      Under the Contract, Prince/Schlosser had the responsibility of designing and

installing a fire-suppression system for the project, but the Contract’s drawings and

specifications did not indicate whether a fire pump would be necessary for the fire-

suppression system. Before awarding the Contract, Prince/Schlosser asked the

District for clarification regarding whether a fire pump was a necessary element of

the fire suppression system. The District responded that a fire pump was not

necessary as long as the system’s performance requirements could “be met with

available water supply.”     During the performance of the Contract, the parties

discovered that a fire pump was necessary to meet the performance requirements,
                                        23

and the contracting officer ordered Prince/Schlosser to furnish and install a fire

pump. The installation led to delays in the project, which caused Prince/Schlosser

to incur additional costs. The District issued Change Order No. 5, authorizing

additional compensation of $108,224 for this work, but it did not compensate

Prince/Schlosser for the indirect costs of the delay such as increased overhead and

lost profits.



       The CAB held that Prince/Schlosser was entitled to compensation for the

delay costs resulting from the installation of the fire pump because the fire pump

was not included in the original Contract. The failure to include the fire pump in

the original Contract, the CAB held, was a breach of the implied warranty that the

plans and specifications would produce an acceptable result. See White v. Edsall

Constr. Co., 296 F.3d 1081, 1084 (Fed. Cir. 2002) (awarding a contractor

additional costs resulting from a subtle flaw in the design drawings). We reverse

the CAB’s decision on this claim because it misapplied the law.



       Where the government provides drawings or specifications that a contractor

must adhere to, the document creates an implied warranty that the specifications

are accurate and, if followed, will yield satisfactory results. Id. at 1084–85. But,

“[t]his implied warranty attaches only to design specifications detailing the actual
                                        24

method of performance” and “does not accompany performance specifications that

merely set forth an objective without specifying the method of obtaining the

objective.” Id. at 1084. The Contract provisions discussing the fire suppression

system were “performance specifications,” which gave Prince/Schlosser discretion

to choose the method of completing the system. The Contract makes clear that the

fire-suppression system was a performance specification because it tasked

Prince/Schlosser with “designing, fabricating, and installing” the fire-suppression

system but did not elaborate on how this task should be completed.

Prince/Schlosser acknowledged that the work was a performance specification in

communications with the District by distinguishing the task from other work that

had to be “performed per plans and specs.” As a result, the fire-suppression

system work was a performance specification, and the implied warranty does not

apply.15 See White v. Edsall Contr. Co., supra, 296 F.3d at 1084; see also District

of Columbia v. Savoy Constr. Co., 515 A.2d 698, 702 (D.C. 1986) (“This rule rests

on the presumed expertise of the government where it sees fit to prescribe detailed

specifications.”).   We reverse the CAB’s holding requiring the District to


      15
          The fact that the District compensated Prince/Schlosser for the fire pump
is not dispositive because, as we stated in OFEGRO I, a contractor “may not
properly use a change order as an excuse to shift his own risks or losses to the
government.” OFEGRO I, supra, 700 A.2d at 203. Thus, there is no basis to hold
the District liable for the delays related to this performance specification.
                                          25

compensate Prince/Schlosser for the indirect costs for the delay resulting from

installing the pump for the fire suppression system.16



      3.     Constructive Change Claim for Truck Scales Wiring



      Pursuant to the contract, Prince/Schlosser was required to “[f]urnish and

install” five truck scales along with their “associated electronic controls.” During

pre-contract negotiations, Prince/Schlosser informed the District that “Project

Drawing E6” did not provide instructions for wiring three of the five truck scales

that Prince/Schlosser would be responsible for installing. The District responded

in Addendum No. 2, which was later included in the Contract, that “ductbanks will

be used by others to automize [sic] the operations of the two new scales.”

(emphasis added). A District representative testified that this answer meant that

“other individuals ‘outside the contract’ would be responsible for the wiring, rather


      16
            Prince/Schlosser also argues that, even though the work was a
performance specification, the District still had the responsibility to ensure that the
information provided was accurate and that the District’s omission of the fire pump
constituted a defect. Prince/Schlosser muddies the waters with this argument.
Given that the fire suppression system was a performance specification,
Prince/Schlosser carried the responsibility of the method of execution for this part
of the project. Moreover, Section 13921 of the Contract Specifications specifically
mentions the maintenance of fire pumps in the performance requirements.
Therefore, some information about a fire pump was included in the original
Contract.
                                          26

than Prince/Schlosser or its subcontractors.” Yet, during the performance of the

contract, District representatives required Prince/Schlosser to complete the wiring

for all five truck scales.



       The    CAB     held   that,   although   the   Contract   originally   required

Prince/Schlosser to complete the wiring, and although Prince/Schlosser’s pre-

contract inquiry only asked about “the three outbound scales, . . . the District’s

response reasonably led [Prince/Schlosser] to the conclusion that other entities . . .

would be providing the power and signal wiring for the scales.” As a result, the

CAB held, Prince/Schlosser did not anticipate wiring any of the truck scales and

did not account for the cost of that work in its bid for the Contract. Accordingly,

the CAB concluded that when the District required Prince/Schlosser to complete

the wiring, it was required to provide additional compensation for that work.



       However, the District’s answer in Addendum No. 2 states that other entities

would do the wiring for “the two new scales.” (emphasis added). Indeed, a

District representative confirmed during the hearing that the answer referred to

“the two inbound scales as opposed to the three outbound scales.” There is no

other evidence in the record supporting the CAB’s application of the language to

all five truck scales. Given that Prince/Schlosser’s inquiry referred to the three
                                         27

outbound scales, the District’s response about the “two new scales” appears non-

responsive to Prince/Schlosser’s question. The District argues on appeal that there

is no support for the CAB’s conclusion that a reasonable reading of Addendum No.

2 released Prince/Schlosser from the task of wiring all five truck scales and that the

non-responsive answer in Addendum No. 2 created a patent ambiguity about which

Prince/Schlosser had the duty to inquire. We agree.



      The doctrine of patent ambiguity “is an exception to the general rule of

contra proferentem, which courts use to construe ambiguities against the drafter.”

Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308, 1313 (Fed. Cir. 2007)

(quoting E.L. Hamm & Assocs. v. England, 379 F.3d 1334, 1342 (Fed. Cir. 2004).

The doctrine states that “where a government solicitation contains a patent

ambiguity, the government contractor has ‘a duty to seek clarification from the

government.’” Id. Should the contractor fail to inquire about the patent ambiguity

during the bidding processes, it is precluded from recovering any costs associated

with the ambiguity. See E.L. Hamm & Assocs., supra, 379 F.3d at 1342. An

ambiguity is deemed to be patent if “it is so glaring as to raise a duty to inquire”

regardless of the contractor’s interpretation. Newson v. United States, 676 F.2d

647, 650 (Ct. Cl. 1982).
                                         28

      The District’s answer in Addendum No. 2 constitutes a patent ambiguity.

The Contract initially required Prince/Schlosser to install five truck scales. The

Contract dictates that Prince/Schlosser is to “[f]urnish and install three-70 foot,

multi-platform steel deck and two-60 foot, mono platform concrete platform motor

truck scales and associated electronic controls.” Thus, a clear distinction was

made between a set of two scales and a set of three scales that needed wiring.

Prince/Schlosser inquired about the wiring for three of the scales, and in its

response, the District informed Prince/Schlosser that another entity would be

wiring two of the scales. While the record shows that the District intended to

relieve Prince/Schlosser of the task of wiring the set of two scales, this response

“glaringly raises a duty [for Prince/Schlosser] to inquire” about whether the

District’s response was addressing the three outbound scales referenced in

Prince/Schlosser’s question to the District. Prince/Schlosser failed to inquire about

this ambiguity, and therefore cannot recover the cost of wiring those three scales.

Thus, we conclude that Addendum No. 2 only relieved Prince/Schlosser of its

responsibility of wiring two of the truck scales, but the District ultimately required

Prince/Schlosser to wire those two truck scales, and the District must therefore

compensate Prince/Schlosser for the cost of wiring only those two scales. We

reverse the CAB’s award for this claim and remand for the CAB to adjust the

award accordingly.
                                         29

D.    The District Is Responsible for the Costs Underlying the Remaining
      Claims


      We affirm the CAB’s holding regarding the remaining delay claims and

summarily address the arguments raised in connection with these remaining

claims.



      1.     Delay Claim for Roof Modification



      Prince/Schlosser was tasked with installing a roof deck addition for the

project. Prior to installing the roof deck addition, the contractor took the required

steps to verify that the existing conditions of the roof matched the dimensions in

the District’s drawings. Upon inspection, Prince/Schlosser discovered a five-inch

difference between the height of the existing structure and the height of the roof in

the drawings.     Prince/Schlosser performed additional work to correct this

discrepancy, which caused delays and additional delay costs.17 The CAB held that

the District breached its implied warranty that these drawings, or design

specifications, were sufficient and must compensate Prince/Schlosser for the


      17
           The work ultimately delayed the project by nineteen days and also
delayed the installation of the sprinkler system, which was to be connected to the
roof deck.
                                          30

additional work and cost of delay. We agree.18 Savoy Constr. Co., supra, 515

A.2d at 702 (stating that government-issued design specifications create an implied

warranty that the specifications are accurate and, if followed, will yield satisfactory

results).



       2.    Delay Claim for Subsurface Concrete Obstruction



       During the project, Prince/Schlosser encountered subsurface concrete that

obstructed its work. The contracting officer issued Change Order No. 4, directing

Prince/Schlosser to remove the concrete and compensating it for the additional

work but not extending the timeline for the project. The District relies on Section

H.33.C of the Contract and argues that, by agreeing to the upward adjustment in

the contract price but no adjustment in the period of performance in Change Order

No. 4, Prince/Schlosser accepted this price adjustment as full compensation for the

work, including any costs of delay.        This provision, however, does not bar

subsequent delay claims based on the work mentioned in the change order.

       18
           The District contends that the verification clause in the Contract requiring
Prince/Schlosser to verify the work conditions releases the District from any
liability for the discrepancy. Such verification clauses in a contract, however, do
not override the implied warranty created by design specifications. See White,
surpa, 296 F.3d at 1086 (holding that the verification clause “did not shift the risk
of design flaws to” the contractor). Thus, the implied warranty in the District’s
design specifications still applied.
                                         31

Instead, Article 7 of the Standard Contract Provisions allows the contractor to

bring “any dispute concerning a question of fact arising under the Contract, which

is not disposed of by the agreement.” See supra note 12. Thus, we affirm the

CAB’s decision that the District must compensate Prince/Schlosser for those

indirect delay costs, which resulted from the concrete obstruction.



      3.     Delay Claim for Obtaining Fire-Suppression System Permit



      Under the Contract, Prince/Schlosser had the responsibility of obtaining a

fire alarm system permit for the project.      Prince/Schlosser requested that the

District assist in obtaining the permit by providing plans and project drawings to

submit with the application.        However, the District’s engineers repeatedly

mislabeled certain rooms in the drawings, which caused delays in obtaining the

approval for the permit. Further, Prince/Schlosser asked one of the District’s

engineers to meet with the Fire Marshal to assist in the approval process; however,

the engineer did not meet with the Fire Marshal until one month before the

application was finally approved.



      “[I]n every contract there is an implied covenant that neither party shall do

anything which will have the effect of destroying or injuring the right of the other
                                         32

party to receive the fruits of the contract, which means that in every contract there

exists an implied covenant of good faith and fair dealing.”          Abdelrhman v.

Ackerman, 76 A.3d 883, 891 (D.C. 2013) (alteration in original). The CAB held

that the record reflects reluctance on the District’s part to cooperate with

Prince/Schlosser in obtaining the permit for the alarm system because the

engineers delayed in responding to Prince/Schlosser’s request for help and delayed

in meeting with the Fire Marshal, which caused the Fire Marshal to approve the

application long after the scheduled Contract completion date.         The District

provides no explanation for its behavior and instead adheres to its argument that

Prince/Schlosser had the ultimate responsibility to obtain the permit. The fact that

Prince/Schlosser was tasked with obtaining the permit does not overcome the

evidence that the District did not fully comply with its duty to cooperate. We

affirm the CAB’s conclusion that the District did not fully cooperate with

Prince/Schlosser in getting the permit, and therefore, is responsible for the costs

associated with the delay in obtaining the alarm system permit, and the District

must compensate Prince/Schlosser for those delay costs.
                                         33

      4.     Constructive Change Claim for Concrete Mix



      Just before pouring concrete for the project, Prince/Schlosser notified the

District that the project required a different kind of concrete mix. In response, the

District directed Prince/Schlosser to use a more expensive sulfate-resistant mix

“regardless of what is specified in structural plans or project specifications.” The

District, however, refused to compensate Prince/Schlosser for the additional cost of

the new more expensive concrete mix, which amounted to $8,908.63 in additional

costs. In awarding Prince/Schlosser the cost, the CAB relied on an unchallenged

finding of fact to conclude that the subcontractor “could have met the strength

specifications in the Contract . . . by supplying less expensive concrete of a non-

sulfate-resistant mix.” Instead, the District directed Prince/Schlosser to use a more

expensive mix “regardless of what is specified in structural plans or project

specifications.” Thus, the District acknowledged that it issued a directive that was

outside of the specifications of the Contract. Had Prince/Schlosser known it would

have to purchase and use more expensive concrete mix, it would have accounted

for the cost in its bid for the Contract. Thus, we affirm the CAB’s conclusion that

the District is responsible for the cost of the more expensive concrete.
                                          34

                                   III.   Conclusion



      We hold that the two contractual provisions requiring thirty-day notice and

certified “cost or pricing data” do not bar Prince/Schlosser’s delay claims. We

conclude, however, that the CAB erred in its interpretation of the contract and

application of law for the three claims related to the storm drainage pipe relocation,

the fire pump installation, and the truck scales wiring. We therefore reverse the

CAB’s order with respect to those three claims and remand to the CAB to adjust

the award accordingly. We otherwise affirm the CAB’s decision on the remaining

claims related to the roof deck modification, subsurface concrete obstruction, fire-

suppression system permit, and concrete mix.



                                                     So ordered.