FILED
SEPT 1, 2016
In the Office of the Clerk of Court
WA State Court of Appeals, Division Ill
IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
DIVISION THREE
GENERAL CONSTRUCTION COMPANY, )
a Delaware corporation, ) No. 32305-6-111
)
Respondent, )
)
v. )
) OPINION PUBLISHED
PUBLIC UTILITY DISTRICT NO. 2 OF ) IN PART
GRANT COUNTY, a Washington municipal )
corporation, )
)
Petitioner. )
)
PUBLIC UTILITY DISTRICT NO. 2 OF )
GRANT COUNTY, a Washington municipal )
corporation, )
)
Third-Party Plaintiff, )
)
v. )
)
GENERAL CONSTRUCTION COMPANY, )
a Delaware corporation, TRAVELERS )
CASUALTY & SURETY COMPANY; and )
TRAVELERS CASUAL TY & SURETY )
COMPANY BOND NUMBER )
41S103871237BCM, )
)
Third-Party Defendants. )
)
)
No. 32305-6-111
Gen. Constr. Co. v. PUD No. 2
GENERAL CONSTRUCTION COMPANY, )
a Delaware corporation, )
)
Fourth-Party Plaintiff, )
)
V. )
)
GLOBAL DIVING & SALVAGE, INC., a )
Washington corporation. )
)
Fourth-Party Defendant. )
KORSMO, J. - We granted discretionary review of this unduly convoluted and
overly-lawyered 1 action at the request of the Grant County Superior Court in order to
determine if the doctrine of quantum meruit recognized in Bignold v. King County, 65
Wn.2d 817, 399 P .2d 611 ( 1965), still has application after the decision in Mike M
Johnson Construction v. County of Spokane, 150 Wn.2d 375, 78 P.3d 161 (2003) upheld
contractual notice and waiver provisions in government construction contracts. In the
published portion of this case, we conclude that Bignold remains viable after Johnson for
matters not included within the contract and affirm the trial court's rulings on that point.
1
Despite the fact that this case comes to us from rulings on motions seeking
partial summary judgment, the Clerk's Papers tally 20,605 pages. Much of the record is
duplicative and unnecessary. Our commissioner's office also has been subjected to
repeated motions before discretionary review was sought as well as after review was
granted. While it is debatable whether Public Utility District (PUD) is a substantially
prevailing party, it is undebatable that both sides have contributed to the excessive
litigation. Accordingly, we exercise our discretion under RAP 14.2 and deny costs and
fees on appeal.
2
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
In the unpublished portion we affirm the majority of the trial court's remaining summary
judgment rulings, reverse some, and remand this interlocutory appeal for trial.
FACTS 2
This case arises from a contract to build a fish ladder into the Wanapum Dam on
the Columbia River immediately south of Vantage, Washington. The dam was built
between 1959 and 1963, and required the abandonment of the former Vantage town site
and its relocation above the new high water levels. The dam was constructed for Public
Utility District no. 2 of Grant County (PUD).
The dam was built with 16 intake units designed to house large, power-generating
turbines. Six of those units were left open for future expansion of the dam's power-
generating capacity. The dam was designed as a "gravity dam" that is built to withstand
upstream water pressure by its own weight. Thirteen anchor tendons help support each of
the expansion units of the dam since those units do not have sufficient weight to
withstand the water pressure. The anchor tendons consist of steel cables anchored into
the upstream bedrock.
In the early 2000s, PUD decided to construct a fish bypass in Unit 11, an
expansion unit containing three separate slots. It then contracted with an independent
2
Most of the facts necessary to the resolution of the remaining issues will be
detailed in the unpublished portion of this opinion in conjunction with the discussion of
those issues.
3
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
firm, Jacobs Engineering, to do some preliminary analysis in anticipation of soliciting
bids for the project. Jacobs Engineering produced a series of reports analyzing general,
presumptive methods of construction. Based on those reports, PUD produced and
disseminated bid specifications. General Construction Company (GCC) and other
potential bidders met with Jacobs Engineering to go over that material in preparation for
bidding.
Ultimately, PUD awarded the contract to GCC to perform "all work necessary for
the Construction of Wanapum Future Unit Fish Bypass." Clerk's Papers (CP) at 19583.
The nearly-430 page contract contains many provisions relevant to this litigation.
Among the most pertinent to this opinion are provisions that ( 1) made the overall project
engineer the primary contact person between GCC and PUD, (2) allowed the engineer to
approve or direct minor changes to the construction process, (3) required PUD
management approval for changes costing more than $10,000, (4) required all change
requests from GCC be in writing if payment was expected for the change, (5) and stated
that GCC's failure to submit a written request for damages within ten days waived the
right to payment for those damages.
Regulations promulgated by the Federal Energy Regulatory Commission (FERC)
require periodic inspection of dams by independent consultants to analyze potential and
actual deficiencies. 18 CFR § 12.32. Pursuant to this requirement, PUD periodically
contracted with independent engineering firms to conduct potential failure modes
4
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
analysis of the dam (PFMA). As a result of the periodic analyses, PUD and FERC
constantly monitored the dam for any signs of failure. The most recent analysis prior to
the fish bypass project was conducted in late 2004 by Acres International.
Since at least the mid-1980s, PUD and FERC have been aware that the anchor
tendon construction method may result in the anchors becoming weakened by the
corrosive effects of water. Consequently, the PFMAs have all assessed this possibility
and its repercussions. Because of the severity of the consequences, FERC classified this
potential failure mode as a "Category I: Highlighted Potential Failure Modes." However,
they have been unable to ascertain the likelihood that any corrosion has in fact occurred. 3
Following completion of the project, GCC obtained these reports from FERC through a
Freedom of Information Act request. 5 U.S.C. § 552
Just as no plan of battle survives first contact with the enemy4, it appears no plan
of construction survives first contact with the elements. Accordingly, original plans must
be revised to address the changed conditions. That was certainly the situation with the
Wanapum Dam fish ladder project. Change was constant; the building process saw
3
Wanapum Dam has been in the news in the last few years because of cracks that
occurred after completion of the fish bypass construction project. There is no indication
in our record that the cracking problem is related to either the construction project or to
the anchoring method.
4
Attributed to Field Marshall Helmuth von Moltke in his 1871 essay, "On
Strategy," reprinted in DANIEL A. HUGHES, MOLTKE ON THE ART OF WAR: SELECTED
WRITINGS 45-47 (1993).
5
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
numerous changes to the projected course of the construction. For instance, although the
PUD had anticipated the three slots in Unit 11 would be worked on sequentially, GCC
bid the contract to work on the first two slots simultaneously and commenced work
according to that approach. 5 However, when Unit 11 moved during construction, tilting
very slightly before stabilizing, the engineer ordered GCC to cease simultaneous work
and proceed sequentially, delaying the project and driving up GCC's expenses. Many
additional changes, some formally requested by GCC and some not, as well as changes
directed by the engineer, occurred. GCC also did not submit timely damage claims on
some of the changes. Under a partial settlement reached in 2007 during the construction,
PUD paid GCC extra for some changes and denied payment for others.
After the project was completed, GCC initiated this litigation addressing the
damage claims that were not resolved by the settlement. Ultimately, the matter was
assigned to the Honorable John Knodell. Over the course of several years, the parties
argued the motions at issue in this appeal. By well-analyzed and thoughtful rulings, the
trial court eventually granted partial summary judgment to PUD on several of GCC's
damages claims and denied summary judgment on other claims. Similarly, GCC sought
to challenge some of the factual bases for the contract and establish that PUD had waived
compliance with the contract's notice provisions; those efforts failed.
5PUD does not agree that the contract authorized the two slot approach, but we
view the facts on this issue in the light most favorable to GCC, the nonmoving party.
6
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
Nonetheless, the trial court was concerned with the question of how strictly to
apply the notice and claim provisions of the contract, with particular concern over
whether PUD had to establish prejudice in order to rely on the notice and claim
provisions. To that end, the trial court urged this court to grant review in order to resolve
that specific legal contention and certified its partial summary judgment rulings for
appeal. This court granted both PUD's motion for discretionary review and GCC's cross
motion. The matter eventually proceeded to oral argument.
ANALYSIS
The parties understandably frame their arguments under expansive readings of the
case most favorable to their position, with PUD emphasizing Johnson and GCC relying
on Bignold. We think it is quite possible to give effect to both cases.
This court reviews orders on summary judgment de novo, and will perform the
same inquiry as the trial court. Lybbert v. Grant County, 141 Wn.2d 29, 34, 1 P.3d 1124
(2000). All facts and inferences shall be considered in the light most favorable to the
nonmoving party. Jones v. Allstate Ins. Co., 146 Wn.2d 291, 300, 45 P.3d 1068 (2002).
Summary judgment is appropriate where there are no material facts at issue and a party is
entitled to judgment as a matter of law. Lybbert, 141 Wn.2d at 34.
Bignold involved a construction project to build a road in King County. The
contractor, Bignold, was required to build the road in segments, using materials cut from
one portion of the roadway as embankment for subsequent portions. 65 Wn.2d at 819.
7
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
As with this case, a government-employed engineer had responsibility for directing the
project. Id. The primary 6 problem that developed was the discovery that large sections
of the excavated material were too wet and contained too many boulders to be used for
embankment. As a result, the contractor was ordered by the engineer to remove and
dispose of the unsuitable material and find replacement material. Id. These changed
requirements slowed the project down and imposed increased expenses for both the
unexpected disposal and for having to obtain materials from a greater distance at a greater
expense.
The county paid for only a portion of the additional work it directed Bignold to
undertake. Id. Bignold sued under a theory of quantum meruit and prevailed on the
claims related to the subsurface conditions. Id. at 819-22. The Washington Supreme
Court affirmed. In the course of its opinion, the court discussed two issues of particular
import to this case. First, after noting that the contract required the contractor to give
written notice of changed subsurface conditions to the county, the court upheld a trial
court finding that the contractor had given "timely notice of the subsurface conditions on
the job site." Id. at 821,822. The county had been alerted to the changed conditions as
soon as they were discovered and ordered the contractor to perform changes. Id. at 822.
6
Other successful claims in the case involved costs imposed by a stop work order
and costs incurred when the engineer required the contractor to work under bad weather
conditions. Bignold, 65 Wn.2d at 823-26.
8
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
"Under such conditions, the county cannot defeat recovery by a contractor even if no
written notice was given." Id. Second, the court expressly rejected King County's
argument that the doctrine of quantum meruit had no place in an action on a contract. Id.
at 826. Instead, the court expressly found it available to the subsurface condition
problems, and that it was "an appropriate basis for recovery when substantial changes
occur which are not covered by the contract and were not within the contemplation of the
parties, if the effect is to require extra work and materials or to cause substantial loss to
the contractor." Id.
Johnson involved a contract between Spokane County and the Mike M. Johnson
Construction Company to construct sewers on two separate projects in the Spokane
Valley. 150 Wn.2d at 378. Although the parties expected that Johnson would work on
the projects sequentially, the county had the ability to direct which streets to work. Id.
Both contracts required Johnson "to use mandatory notice, protest, and formal claim
procedures for claims of additional compensation, time extensions, and changed
conditions." Id. at 379. Problems developed when one of the streets needed to be
redesigned and buried telephone lines unexpectedly were discovered. Id. at 378-79. As a
result, the county changed the order of streets that Johnson was to work and directed
project changes to the street being redesigned; it paid Johnson for the extra expenses of
that component of the project, but not for increased expenses to the entire project. Id.
9
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
More changes followed and Johnson noted its unhappiness with the delay and
constant change orders, and also indicated that it was incurring additional costs. Id. at
380-81. However, it did not follow the contract provisions for protest and for claiming
additional compensation, despite the county's written indication that Johnson needed to
comply with the contract's provisions. Id. at 381-82. After extensive negotiations failed,
Johnson eventually filed suit seeking damages; the county defended on the basis that
Johnson had failed to comply with the contract. Id. at 384. The trial court ultimately
granted summary judgment in favor of the county and Johnson appealed. Id. at 384-85.
This court reversed, deciding that material questions of fact existed concerning whether
the county's "actual notice" excused Johnson from complying with the contract. Id. at
385. The Washington Supreme Court granted review and reversed in a 5 to 4 decision.
The majority concluded that there was no "actual notice" exception and that,
instead, contract requirements would "be enforced absent either a waiver by the benefiting
party or an agreement between the parties to modify the contract." Id. at 386-87 (citing
cases rejecting claims where contractor had not complied with contractual notice
provisions). The court expressly rejected Johnson's argument that Bignold had created an
actual notice exception. Id. at 387 (citing Bignold, 65 Wn.2d at 822). It read Bignold as
reaffirming "the long-established rule requiring contractors to follow contractual notice
provisions unless those procedures are waived by the owner." Id. at 388. It then
discussed the cases relied on by Johnson as examples of waiver. Id. The majority found
10
No. 32305-6-111
Gen. Constr. Co. v. PUD No. 2
that Johnson did not comply with the notice and claim provisions of the contract and that
the county did not waive its reliance on those provisions. Id. at 390-92.
By contrast, the dissent authored by Justice Chambers argued that it was unfair to
require Johnson to comply with the claims procedure when the county had been fully
informed about the problems and observed the work performed. Id. at 393. The dissent
agreed that more than actual notice was required to waive compliance with a contract
provision. Id. at 400. The dissent read Bignold as creating a rule that the failure to
comply with the "claims procedures will not defeat the contractor's right to compensation
unless that procedural error causes prejudice to the owner." Id. In support of that
statement, the dissent cites Bignold, 65 Wn.2d 817. Id. That page, however, is the title
page for the opinion and contains three of the nine headnotes for the case. See 65 Wn.2d
at 817. Thus, the dissent appears to simply be citing Bignold in passing. However,
headnote three from that page might also bear on the issue: It states:
[3] Same-Construction-Formal Notice Requirement-Actual Notice.
The fact that a contractor did not give written notice of changed conditions,
as required by the contract, did not prevent his recovery for the cost of extra
work required by conditions which had not been anticipated by the
contracting parties, where the person for whom the work was being done had
become immediately aware of the changed conditions as soon as they
developed and had ordered the contractor to perform the extra work involved.
Id. at 817-18.
11
No. 32305-6-111
Gen. Constr. Co. v. PUD No. 2
Our issue arises against this backdrop due to the trial court's concern whether the
position of Justice Chambers might have any traction. For several reasons, we think it
has none in this case.
First, this case is factually closer to Johnson than to Bignold because the contract
at issue in Johnson expressly imposed duties on the contractor to give written notice and
follow a specific written claim procedure, as does the contract here. The notice
requirements, if any, in the Bignold contract are discussed very little, and whether the
contractor complied with them is discussed even less. The only notice provision
mentioned in the opinion involved the requirement that the contractor notify the county
about changed subsurface conditions. 65 Wn.2d at 821. The trial court's finding that the
contractor had given that notice was upheld. Id. at 822. If there were any other notice
provisions at issue, they simply were not discussed. 7 Bignold does not provide implicit
factual authority for the proposition that contractual notice provisions were at issue there,
let alone any authority that they can be ignored.
Second, the Bignold passage on page 822 cited for the proposition that lack of
compliance with notice requirements is not a bar to recovery 8 is not a statement of the
7In the event the headnote states a fact that is not included in the opinion, we
simply note that headnotes are not prepared by the court and do not constitute authority.
United States v. Detroit Timber & Lumber Co., 200 U.S. 321, 337, 26 S. Ct. 282, 50 L.
Ed. 499 (1906).
8
And which subsequently became headnote 3.
12
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
facts of that case. Rather, the passage expressly cites to two 1941 federal cases that did
state that rule of law. This passage simply should be read as a general statement of law
rather than as the governing rule of the case. It would be no more than dicta if viewed as
a ruling on the issue of compliance with contractual notice provisions in Bignold and
likely would be in conflict with Johnson if treated as such.
Finally, it should go without saying that a dissenting opinion is not law. 9 While
GCC can properly urge that Justice Chambers' opinion be adopted, this court is not the
place to make that argument. We are bound by the majority opinion in Johnson. E.g.,
State v. Gore, 101 Wn.2d 481,487,681 P.2d 227 (1984). The Johnson majority speaks
squarely to the validity of contractual notice and claim provisions-they are valid unless
the party in whose favor the provisions act waives the protection. Johnson, 150 Wn.2d at
391-92. There must be unequivocal evidence of an intent to waive. Id. at 391. Bignold 's
oblique reference to the topic has no bearing on the issue in light of Johnson.
Bignold, however, is still good law for its actual holding that quantum meruit has a
place in litigation arising from a construction contract. 65 Wn.2d at 826. It applies to
"substantial changes" beyond the contemplation of the parties and not covered by the
contract that result in extra work or substantial costs to the contractor. Id. Thus, in
9
But, for those who do need a citation for that proposition, please see Cole v.
Harvey/and, LLC, 163 Wn. App. 199,207,258 P.3d 70 (2011) ("[T]he meaning of a
majority opinion is not found in a dissenting opinion.").
13
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
Bignold, the doctrine applied to the costs incurred when the subsurface conditions, duly
reported by the contractor upon discovery, varied significantly from that expected by the
parties and led to increased costs for finding new fill and the removal and transportation
of the saturated materials. Id.
Giving effect to both Bignold and Johnson, we discern the following rules. First,
for work within the scope of the contract, which here was "all work necessary for the
Construction of Wanapum Future Unit Fish Bypass," the terms of the contract must be
complied with unless there is evidence that PUD waived compliance with the notice and
claim requirements. For work outside 10 of the contract, and changed work within the
scope of the contract where GCC satisfied the contractual notice and claim provisions,
quantum meruit applies and entitles GCC to compensation. In essence, Bignold provides
a supplemental means of recovery when the contract is not applicable. 11
The trial judge typically took this approach to the various claims presented. An
example involved a contractual requirement that an inspector certified by the National
Association of Corrosion Engineers (NACE) oversee the painting of the flow fairing
1
°For instance, if PUD had required GCC to repair or replace an anchor tendon,
the work would have been outside of the scope of the contract to build the fish passages.
11
GCC sees Bignold as providing an alternative theory of recovery rather than
merely a supplemental one. We reject that approach.
14
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
modules that were to be inserted in the fish bypass. 12 GCC asked that it be allowed to use
an internal quality assurance manager employed by one of its subcontractors. That
individual, however, was not NACE certified and PUD declined to waive the certification
requirement. GCC then hired an outside inspector who had NACE certification at a cost
of $67,000.
It later sought reimbursement from PUD for this expense in this litigation. The
trial court dismissed the claim on the grounds that GCC had failed to notify PUD of the
claim when it arose. Although GCC contends that PUD modified the contract by
requiring a third-party inspector, the record does not support the claim. 13 The contract
always required a certified inspector without mandating that the person be an independent
employee.
The trial court correctly concluded that the Selway claim was barred by the failure
to provide timely notice to the PUD. We affirm the dismissal of that claim.
A majority of the panel having determined that only the foregoing portion of this
opinion will be printed in the Washington Appellate Reports and that the remainder
12
The production of the modules was subcontracted to Selway Corporation. The
parties identify this issue as "Claim 12" or as "the Selway claim."
13
GCC also argues here, as it does in all instances where the court determined that
a claim was not timely raised under the contract, that PUD had waived the notice and
claim requirements. We address, and reject, that argument in the unpublished portion of
this opinion.
15
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
having no precedential value shall be filed for public record pursuant to RCW 2.06.040, it
is so ordered.
The remaining claims are reorganized and addressed differently than the parties
have asserted them. We first address the cross appeal claims that the contract should be
invalidated or modified due to mistake or superior knowledge, before turning to the "Slot
Claim" and GCC's contention that PUD waived compliance with the notice and claim
provisions. We next address, sometimes summarily, the "Coffer Cell" claim, the
"District Instruction" claims, and the remaining "Flow Fairings" claims.
Cross Appeal
GCC contends that the FERC documents demonstrate that it is entitled to damages
due to either mistake or an alleged intentional withholding of information concerning the
stability of the dam. The trial court properly rejected this argument.
GCC primarily relies on "the doctrine of superior knowledge" in support of its
argument, although it also argues that either mutual or unilateral mistake entitles it to
relief. The trial court found that the facts presented did not support either theory because
the information contained in the FERC documents was not material. We agree.
In essence, the doctrine of superior knowledge is a variety of fraud where, prior to
entering a contract, one party fails to disclose information peculiarly in its possession or
unavailable to the other that materially impacts the other's costs or ability to perform on
16
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
the contract. 14 See Jordan v. Corbin Coals, 162 Wash. 503,298 P. 712 (1931); Lincoln v.
Keene, 51 Wn.2d 171, 316 P .2d 899 ( 1957); Nelson Const. Co. of Ferndale, Inc. v. Port
of Bremerton, 20 Wn. App. 321, 582 P.2d 511 (1978); see also Walla Walla Port Dist. v.
Palmberg, 280 F .2d 23 7 (9th Cir. 1960). The law of mistake allows one party to reform
the contract where there has either been a mutual mistake by the parties as to the content
of the contract, or one party is mistaken about material facts that the other concealed.
Wash. Mut. Savs. Bank v. Hedreen, 125 Wn.2d 521, 525-26, 886 P.2d 1121 (1994).
Both of these theories hinge on establishing that GCC was unaware of information
existing prior to entering the contract that would have indicated Unit 11 could not
withstand the two slot construction method. 15 The sole evidence that GCC relies on to
establish this particular fact is the FERC classification of a potential failure of the anchor
tendons as a "Category I Potential Failure Mode." However, nothing about that
information adversely implicates the stability of the dam. Rather, the FERC reports
14
Some of the authority GCC cites involves claims of breach of implied warranty
such as an owner representing to the bidding contractor that certain methods of
construction would work despite knowing that they would not. See, e.g., Md. Cas. Co. v.
City ofSeattle, 9 Wn.2d 666, 116 P.2d 280 (1941).
15
GCC's mutual mistake contentions before the trial court were premised on two
alternative theories: (1) that the parties mistakenly believed they were agreeing to the two
slot method and (2) that the parties were mistaken about the stability of the dam. The
bulk of its argument here addresses facts concerning that first theory, one that the trial
court agreed had sufficient factual support to deny summary judgment on that claim. CP
at 7802, 17050-52. Only the second theory was dismissed, and, consequently, is the only
theory of mistake addressed in this section. Id.
17
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
address the possible consequences of dam failure; it does not provide any evidence that
anyone knew whether the dam could withstand the two slot construction method. Rather,
the evidence in the record seems to indicate that it is impossible to actually assess the
probability that the anchor tendons might fail. The trial court correctly concluded that the
FERC documents were not material evidence. 16
Summary judgment was properly granted on the superior knowledge and mistake
claims related to the FERC documents.
Slot Claim
The remaining slot claim argument is that the parties agreed to build under the two
slot method and had to alter that agreement due to the instability of Unit 11. PUD argues
that this claim is barred by failure to follow the notice and claims procedure. GCC
argues that the contractual notice provisions are irrelevant to its quantum meruit claim,
that PUD waived the provisions through the conduct of its engineer, Dana Jeske, and that
it gave notice, including notice written on a chalkboard. The trial court concluded that
whether the parties understood that there would be two slot construction, regardless of
16
Materiality aside, it appears that the claims also lack a factual basis since the
record is replete with evidence that GCC had access to information indicating that
possibility. For instance, Jacobs Engineering had conducted a stability analysis
specifically in anticipation of the fish bypass project and the bid documents reference
specifications resulting from dam stability studies. There is no dispute that GCC's
engineer met with and went over substantial material prepared by Jacobs Engineering.
He merely claims not to have seen or requested the stability analysis report; no evidence
suggests that the information was withheld from GCC.
18
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
whether the contract called for it to be two slots, was a factual issue to be decided at trial
and might, therefore, be outside the contract's notice provisions. Clerk's Papers (CP) at
7802.
With respect to the notice argument, we decline to address PUD's claim because
the trial court did not analyze the notice aspect of this issue and we are loathe to
scrutinize a record of this size in an interlocutory appeal in order to resolve a claim the
trial court did not resolve. The trial court is free to reconsider this issue in light of our
analysis of the relationship between Bignold and Johnson.
We do have to address two 17 of GCC's cross appeal arguments related to this
claim. The factual basis for these contentions is a claim that the PUD's engineer directed
that GCC not file claim letters. 18 When engineer Jeske directed GCC to abandon the two
slot construction due to stability issues, GCC engineer Ed Kittle allegedly provided
notice to PUD by writing it on the project blackboard.
We first consider GCC's claim that the writing on the blackboard constituted
written notice of its challenge to the change to a single slot method. The trial court
concluded that an unpreserved writing on a chalkboard did not provide written notice to
17
GCC's contention that the contract is irrelevant to its quantum meruit argument
is rejected for the reasons stated in the first portion of this opinion.
18
Our review of the record suggests that the engineer asked GCC to attempt to
settle matters informally before submitting claims, but we again view this issue in favor
ofGCC.
19
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
PUD. We agree. Even if it were semantically correct to call this "written," it defies the
clear contractual intent that notice be made in a substantial and permanent manner, which
could, if necessary, be forwarded to PUD management for approval. Writing on a
blackboard which is subsequently erased evinces no intent by GCC to provide that notice.
The trial court understandably, and quite properly, dismissed this argument.
While the waiver argument has a better grounding in law and in fact than the
chalkboard claim, it fares no better because it runs directly contrary to the contract. This
claim is based on contentions that the engineer, Jeske, could waive the notice provisions
for PUD. He could not.
The contract restricts which individuals have the authority to modify the contract
and what situations can constitute waiver of contractual provisions, as well as explicitly
defining the authority of the engineer. As the engineer, Mr. Jeske did not have authority
under the contract 19 to modify its provisions. His authority extended to direct changes
that would not result in additional costs as well as limited authority to direct changes that
19
GCC contends that Mr. Jeske's actions manifested apparent authority as an
agent of PUD. However apparent authority can only be derived by the objective
manifestations of the principal. King v. Rive/and, 125 Wn.2d 500, 507, 886 P.2d 160
(1994 ). Here, the objective manifestations of the principal are set forth in the contract
documents that vest certain, specific authority in Mr. Jeske as an agent; contract
modification is not part of the authority granted. GCC also contends that since Mr. Jeske
was an employee of PUD rather than a third-party contractor, he had actual authority.
This argument ignores the fact that an agent only has authority to the extent objectively
manifested by the principal.
20
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
would cost less than $10,000. He could also require GCC to continue with that changed
work pending a decision by PUD on GCC's objection. However, the contract explicitly
precluded him from directing work changes that would result in substantially increased
costs or from otherwise modifying the contract.
Accordingly, the trial court properly rejected GCC's claim that PUD had waived
the protection of the notice requirements. The engineer simply had no authority to
modify the contract and GCC knew that fact.
We remand the slot claim argument to the trial court.
Coffer Cell Claim
PUD next challenges the denial of its motion for summary judgment on its "Coffer
Cell" claim (also referred to by the parties as the "Tailrace Claim"). GCC sought
damages for the costs of pumping water from its coffer cell on four occasions where it
faced higher water levels than expected because PUD actions delayed work into the high
water season. We reverse the trial court and grant summary judgment to PUD.
The coffer cell dams were built to create dry work areas on the downstream side of
the dam (the tailrace). The appropriate height of the coffer cells was the subject of
significant discussion before and after the parties entered into the contract, with historic
monthly water levels provided for at least the previous decade. Those documents showed
that the water level varied between 480 and 500 feet above sea level, with an average
between 490 and 494 feet. GCC decided to build the coffer cell at 497 feet despite the
21
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
concerns of PUD engineer Jeske that the height might be insufficient. The historic data
suggested that the 497 foot level was seldom exceeded until late March. That, in fact,
was the time period when the water level first exceeded the coffer dam.
The contract expressly provided that GCC might encounter "high tailrace levels
(tailrace elevation 500.0) during the course of the work." CP at 35-36. It also provided
that "no time extensions or extra compensation will be given by the District based on
weather conditions. The Contractor shall be responsible for the cost of
protecting/sheltering of all work vulnerable to such extreme weather conditions." Id.
Despite the contract provision, the trial court denied summary judgment on the ground
that this claim arguably sounded in quantum meruit. GCC believed that its damages were
caused by the PUD delay, not by extreme water conditions, and that the extra costs of re-
dewatering should be borne by PUD.
The problem with this contention is that claims in quantum meruit are, by
definition, claims for activities or costs not contemplated in the contract. The contract
clearly assigned GCC the obligation of sheltering the work from tailrace levels up to 500
feet and stated that there would be no extra compensation based on river conditions.
GCC determined, against the recommendation of PUD's engineer, that a 497 foot coffer
cell dam would be sufficient. The gamble backfired when GCC was confronted with
water levels between 497 and 498 feet on four days in the spring and summer of 2007.
But for the delay, those damages may not have occurred, but nothing about that fact
22
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
changed GCC's contractual obligation to shelter the work from high water.
Consequently, this was not a quantum meruit claim.
We reverse the trial court's ruling and direct that summary judgment be entered in
favor of PUD on this claim.
District Instruction Claims
PUD next argues that the trial court erred in not granting summary judgment on 28
district instruction claims that it alleges GCC did not timely contest under the notice and
claim provisions of the contract. 20 As the trial court did not analyze this argument, we
decline to address it, leaving the matter in the capable hands of the trial court on remand.
The essence of this argument involves a series of changes ordered by engineer
Jeske under contractual provisions that allowed him to order GCC, in writing, to proceed
differently in its construction methods. The contract assumed the changes were not
expected to alter GCC's costs, so compliance with the changes was treated as agreement
that no additional costs would be incurred. In those instances where the changes would
increase costs, GCC was required to file written objections and await a determination by
PUD.
20
PUD concedes, somewhat grudgingly, that District Instruction 188 "arguably"
and "partially" complied with the notice requirements. Br. of Appellant at 22. GCC
appears to have conceded that some of its claims were not timely raised. Id. at 21.
23
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
It appears that the trial court had concerns about which claims GCC thought were
outside the scope of the contract and denied the motion, in part, pending GCC's
clarification. CP at 10001. The denial also appears to have been tied into the concern
over the application of the Bignold quantum meruit doctrine to these claims. While we
do not believe vagueness should be a defense to summary judgment, it does appear that
the trial judge did not address the merits of the summary judgment motion. Accordingly,
neither should we do so.
We decline to address the order in light of the fact that the trial judge may still
address the motion.
Upstream Stoplog Guiderail Claim
The trial court denied summary judgment on this claim because questions of fact
remain for resolution at trial. Again, we agree.
This claim concerns prefabricated components designed to be attached to the dam.
Additional costs were incurred when the dam's surface was determined to not be smooth,
as it was depicted on PUD's drawings, but instead bulged-apparently a common
condition among middle-aged men and middle-aged dams. Unlike the previous district
instruction claims, GCC clearly and properly objected in writing. GCC argues, with
appropriate supportive authority, that it was entitled to rely on the drawings. PUD
responds, with equally supportive authority, that GCC was required to determine dam
surface conditions for itself.
24
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
We agree with the trial court that the reasonableness of GCC's reliance on PUD's
plans is a question of fact for trial. Summary judgment was properly denied.
Remaining Flow Fairings Claims
These final claims are related to the initial claim addressed in the published
portion of this opinion. They involve the assembly of the flow fairing modules prior to
installation and a related claim involving the cost of "shrink wrap" that was obtained for
use while installing the modules, but was subsequently destroyed by wind prior to the
install ati on.
The flow fairings consisted of three large steel structures fixed to the upstream
side of the dam to guide and smooth water flow to the fish bypass. The modules were
manufactured in segments, assembled at the jobsite, and then lowered into place and
bolted on to the face of the dam. The trial court denied summary judgment. We, once
again, agree with the trial court.
The parties seem to be talking about different issues. PUD contends that its
approval of GCC's request to assemble the flow fairings by use of two four-segment
components put the onus on GCC to ensure the components fit properly. However, this
"fit-up" requirement is distinct from the "pre-fit" requirement argued by GCC. The
district instruction merely directed GCC to insure that the components would fit together.
GCC's claim is that a different instruction, allegedly given at the last minute during a
meeting, required it to pre-fit the two modules together prior to installation and increased
25
No. 32305-6-III
Gen. Constr. Co. v. PUD No. 2
its costs. GCC objected and promptly filed the general notice required to maintain claims
under the contract. CP at 6352.
Similarly, the shrink wrap issue did not arise from a district instruction. Instead,
this was an additional requirement, tentatively inserted into the plans, and then ultimately
omitted per the verbal instructions of PUD representatives. As notice was timely given,
the claim was preserved. Trial will determine the party responsible for this claim.
The trial court correctly denied summary judgment on these issues.
In summary, we affirm the trial court in part, reverse in part, and remand this
interlocutory appeal for further proceedings.
I CONCUR:
26
No. 32305-6-111
FEARING, C.J. (concurring)- I concur in all of the majority's rulings.
Nevertheless, I disagree with or wish to expand some of the analysis of the majority on
two subject matters.
Bignold and Mike M Johnson
I disagree with the tenor of the majority opinion that Bignold v. King County, 65
Wn.2d 817, 399 P .2d 611 ( 1965) and Mike M Johnson, Inc. v. Spokane County, 150
Wn.2d 375, 78 P.3d 161 (2003) may be reconciled. Mike M Johnson v. Spokane County
silently overrules Bignold v. King County's ruling that a contractor may recover for
additional work resulting from changed conditions, if the public owner of the project
knows of the changed conditions, despite the contractor's failure to obey contract
requirements demanding compliance with formal written claim procedures.
The majority correctly notes that the opinion in Bignold v. King County fails to
I
outline many of the relevant contract provisions in the subject public works contract. The
Bignold opinion notes that the contract contained a "changed condition" section similar to
that found in other standard construction contracts. 65 Wn.2d at 821. Nevertheless, the
I
J
decision does not cite any of the language of the section or detail what the court
I'
I
tI
l
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
considered to be a standard contract. What was standard in 1965 might not be standard in
2005. At any rate, the public works contract in Bignold had a provision admonishing the
contractor to fully examine the contract site before bidding. Another provision demanded
the contractor give notice in writing to the county of any subsurface or latent physical
conditions materially different from conditions described in the contract. Finally, a
provision required the contractor to invoke some section of the contract if it wished
payment for extra material. A provision may have exculpated the owner of the project,
King County, from any extra costs incurred by the contract by reason of unforeseen
conditions at the site.
The Washington Supreme Court, in Bignold v. King County, refused to enforce
many of the relevant contractual terms. Although the contractor gave oral notice, the
contractor failed to provide any written notice of unanticipated subsurface conditions and
withheld any written notice of an expectation of additional payments. The trial court
granted additional recovery caused by unanticipated conditions, nonetheless, and the
Supreme Court affirmed. The high court held that the contractor may recover for
additional costs.
Based on Bignold v. King County, this court, in Mike M Johnson, Inc. v. Spokane
County, reasonably held that Mike M. Johnson need not have necessarily followed the
notice provisions in Spokane County sewer installation contracts. Instead, a question of
2
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
fact existed as to whether the county waived the claims procedures. The Supreme Court
reversed us.
I find language in Bignold v. King County irreconcilable with language in Mike M
Johnson, Inc. v. Spokane County. In the former decision, the Supreme Court announced
the controlling principles: Courts generally allow recovery for additional costs when the
condition complained of could not reasonably have been anticipated by either party to the
contract. Bignold v. King County, 65 Wn.2d at 821-22. This rule remains true despite
admonitory or exculpatory phrases such as those requiring the contractor to carefully
examine the site. Bignold v. King County, 65 Wn.2d 822. If the contractor gives timely
oral notice of an unanticipated condition and/or the owner becomes immediately aware of
the changed conditions as soon as they develop and orders the contractor to perform the
changes and extra work, the owner cannot defeat recovery by the contractor for additional
costs even if the contractor provided no written notice of unforeseen conditions and extra
work. Bignold v. King County, 65 Wn.2d at 822. The owner cannot preclude recovery
for extra costs incurred by the contractor and caused by a shutdown of work, if the
owner's engineer gives instructions to shut down despite the engineer giving no written
instruction as required by the construction contract. Bignold v. King County, 65 Wn.2d at
822-23. Under the previous circumstances, equitable estoppel bars the owner from
relying on a contract provision that requires any instructions to be in writing. Bignold v.
3
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
King County, 65 Wn.2d at 823. Quantum meruit provides an appropriate basis for
recovery when substantial changes occur which are not covered by the contract and were
not within the contemplation of the parties, if the effect is to require extra work and
materials or to cause substantial loss to the contractor. Bignold v. King County, 65
Wn.2d at 826. The owner cannot rely on contract notice provisions for claims sounding
in quantum meruit. Bignold v. King County, 65 Wn.2d at 826. A claim in quantum
meruit is outside the coverage of the contract. Bignold v. King County, 65 Wn.2d at 826.
These controlling principles in Bignold v. King County conflict with the following
rules applied in Mike M Johnson, Inc. v. Spokane County: Washington law generally
requires contractors to follow contractual notice provisions unless those procedures are
waived. Mike M Johnson, 150 Wn.2d at 386. A contractor's claim for extra work will
be dismissed when there was no written order for the extra work as required by the
contract and no waiver of the requirement. Mike M Johnson, 150 Wn.2d at 387. When
the engineer issued no required written order for extra work, the contractor may recover
for the extra work only if it shows a waiver by the owner. Mike M Johnson, 150 Wn.2d
at 3 87. A building contract provision requiring a written order for alterations or extras
will be enforced. Mike M Johnson, 150 Wn.2d at 387. Despite an owner having actual
notice of a contractor's protest or claim, the notice, in and of itself, does not excuse the
contractor from complying with mandatory contractual protest and claim procedures.
4
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
Mike M Johnson, 150 Wn.2d at 377, 3 87. Even if the contractor gives notice of a claim
or even if the owner knows of concerns of delay, if the contractor does not give notice of
the amount of the claim or length of delay, as required by the contract, the contractor
cannot recover for costs caused by delay. Mike M Johnson, 150 Wn.2d at 389. Even if
the contractor submits a letter to the owner indicating a concern over a change order and
that it expected additional compensation for its work under the order, if the letter does not
supply the information required by the contract to support a protest or a formal claim, the
contractor will be denied recovery for extra work required by the change order. Mike M
Johnson, 150 Wn.2d at 390. A general notice to the owner that the contractor expects
additional compensation does not excuse the contractor from complying with the
contractual claim procedures. Mike M Johnson, 150 Wn.2d at 390. A contractor's
notice of protest to the owner does not excuse the contractor from complying with
mandatory claim procedures. Mike M Johnson, 150 Wn.2d at 391.
In Mike M Johnson, Inc. v. Spokane County, 150 Wn.2d 375 (2003), the
contractor of a sewer installation public works contract encountered buried telephone
lines, which halted work until the county and the utility company resolved the conflict.
The construction contract placed all risks from utilities mislocated on the plans or not
shown on the plans on the contractor. The contract also required the contractor to use
mandatory notice, protest, and formal claim procedures for claims of additional
5
No. 32305-6-III (concurring)
Gen. Constr. Co. v. PUD #2
compensation, time extensions, and changed conditions. The contract read that the
contractors' failure to follow the procedures resulted in waiver of any claims for
protested work. In a 5 to 4 decision, the Supreme Court dismissed Mike M. Johnson's
claim for additional work because of its failure to follow contract procedures, despite
other written notice to the county of the additional work caused by the unforeseen
utilities.
Two facts found in Mike M Johnson, Inc. v. Spokane County may distinguish it
from Bignold v. King County. First, Mike M. Johnson's owner admitted knowing of the
formal protest procedures, but decided to ignore the procedures because of the time
needed to comply. Second, the City of Spokane repeatedly warned Mike M. Johnson of
the need to follow the contract provisions with regard to notice of additional claims. The
Mike M Johnson court formulated no rules for use in the future based on these peculiar
facts.
!
I
!
The majority downplays notice requirements found in the public works contract in I
Bignold v. King County. The majority may emphasize that the contractor, in Bignold v.
I
King County, sued in quantum meruit. The Mike M Johnson, Inc. v. Spokane County I
opinion does not show that the contractor, Mike M. Johnson, sued in quantum meruit.
!
I
The majority in this appeal may also highlight that the contractor, in Bignold v. King
Ii,
i
County, sought recovery for work outside of the contract. I find the distinction between
I
\
6
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
quantum meruit and other forms of recovery and the distinction between suit for work
covered by the contract and for work not covered by the contract hollow. Recovery
should not be based on magic Latin words employed in the complaint. Distinguishing
between work within the contract terms and outside the contract provisions is sometimes
difficult and nonsensical. Washington courts have never provided working definitions
for "work on the contract" and "work outside the contract."
Distinguishing Bignold v. King County and Mike M Johnson, Inc. v. Spokane
County by reason ofBignold suing in quantum meruit and Mike M. Johnson not raising
such a claim is unsatisfactory. In each case, the contractor performed additional work
and incurred increased costs as a result of unforeseen underground conditions. Although
the respective owners directed each contractor to perform work in manners unexpected at
the time of contracting, neither contractor performed work beyond the scope anticipated
in the contract. The finished project remained the same.
Bignold v. King County, 65 Wn.2d 817 ( 1965) stands for the following rules.
Quantum meruit means "as much as deserved." Bignold v. King County, 65 Wn.2d at
I
826 (quoting Losli v. Foster, 37 Wn.2d 220,233, 222 P.2d 824 (1950)). Quantum meruit I
I
provides an appropriate basis for recovery when substantial changes occur which are not ·I
covered by the contract and were not within the contemplation of the parties, if the effect
Ii
is to require extra work and materials or to cause substantial loss to the contractor.
7
I
I
II
I
I
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
Bignold v. King County, 65 Wn.2d at 826. The owner cannot rely on contract notice
provisions for claims sounding in quantum meruit. Bignold v. King County, 65 Wn.2d at
826. A claim in quantum meruit is outside the coverage of the contract. Bignold v. King
County, 65 Wn.2d at 826. Mike M Johnson, Inc. v. Spokane County, 150 Wn.2d 375
(2003) did not expressly overrule these quantum meruit rules.
The remainder of this opinion is not to be published to coincide with the lack of
publication of the corresponding portion of the majority opinion.
Cross Appeal of Superior Knowledge Claim
General Construction Company (GCC) seeks recovery for additional costs
allegedly resulting from its abandonment of a two slot method of construction. GCC
argues that the Public Utility District (PUD) demanded it change to a consecutive slot
construction method after movement in the dam. GCC further contends that it lacked
knowledge of facts existing prior to entering the contract that would have informed it that
Unit 11 could not withstand the two slot construction method. In turn, GCC maintains
that the PUD had information of a possible dam failure because of corroding anchor
tendons. The PUD knew that Federal Energy Regulatory Commission (FERC) classified
a potential failure of the anchor tendons as a category 1 potential failure mode.
Based on these alleged facts, GCC argues that the PUD is liable to it for the extra
costs attended to the abandonment of the two slot construction method on the basis that
8
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
the PUD had superior knowledge that it should have disclosed to GCC. GCC also claims
a mistake should lead to reformation of the contract.
I agree with the majority in dismissing GCC's cross appeal. As noted by the
majority, the FERC report addresses the possible consequences of a dam failure. The
report does not indicate that a two slot method of construction of a fish bypass was not
safe. The report does not support the factual contention that the PUD should have known
the dam could not withstand the two slot construction method.
I write separately to note other defects in the PUD's claim of mistake and superior
knowledge. In opposition to the PUD's motion for summary judgment to dismiss GCC's
claim for additional costs resulting from the abandonment of the two slot method of
construction, GCC relies on the declarations of Dave Anderson and Scott Hanson. The
two declarations fail to raise an issue of fact on the claim.
Scott Hanson was the project sponsor for GCC with regard to the Wanapum
Future Unit Fish Bypass project. Hanson testified to the PUD's approval of the two slot
construction method. Documents attached to Hanson's declaration confirm the PUD's
knowledge and approval of the method.
Scott Hanson testified in his declaration that on January 6, 2006, "GCC was
directed to discontinue performance of the work in accordance with the July 31, 2005
schedule and was further directed to resequence and reschedule its work in a fashion
9
No. 32305-6-III (concurring)
Gen. Constr. Co. v. PUD #2
requiring slot work to be performed essentially sequentially rather than according to the
Two Slot Method GCC had proposed and the PUD had designed and approved." Clerk's
Papers (CP) at 1296. The PUD denies that it gave any direction to GCC to abandon the
two slot method. In his declaration, Hanson does not indicate who directed GCC to
resequence its work or who at GCC received the directive. The declaration does not even
expressly state that the direction came from the PUD. Scott Hanson does not declare that
he was present when the PUD gave any new instructions to GCC. He does not indicate
the basis of his knowledge of the direction. Hanson does not attach any document to his
declaration confirming any directive from the PUD.
In his declaration, Scott Hanson claims the PUD had superior knowledge with
regard to dam stability. Records show that the PUD knew of possible failure of anchor
tendons. Nevertheless, Hanson provides no testimony that, assuming he had personal
knowledge of such, any movement in the dam, on January 6, 2006, resulted from failure
of anchor tendons.
Dave Anderson is a licensed engineer apparently hired by GCC for purposes of
this litigation, to review PUD and FERC records. Anderson notes the wealth of reports
l
that show concern for failure of dam anchor tendons resulting from corrosion. Anderson
avers: "Production of the known, but undisclosed stability concerns ofFERC, PUD and I
I
its consultants to the bidders would have caused GCC and, presumably the other bidders, I
10
i
l
II
!
I
No. 32305-6-111 (concurring)
Gen. Constr. Co. v. PUD #2
to consider the accompanying unknown, increased risk of re-sequencing work in [Future I
Unit Intakes] No. 11." CP at 2700-01. I question whether the thinking process of a
construction bidder is a permissible subject of opinion testimony. Nevertheless, I
Anderson does not state that, in fact, GCC would have no longer bid on the assumption I
Il
that it would be able to engage in the two slot method if it had the same information that !
I
the PUD held. Anderson supplies no testimony that the January 6, 2006, movement
I
resulted from corroding anchor tendons.
I
I CONCUR:
Fearing, C.J.
I
Ii
I
II
I
I
11 l
I
I
I
I
I
I