In The
Court of Appeals
Ninth District of Texas at Beaumont
_________________
NO. 09-16-00290-CV
_________________
IN RE J. ADAMS, LLC
________________________________________________________________________
Original Proceeding
County Court at Law No. 1 of Jefferson County, Texas
Trial Cause No. 125,421
________________________________________________________________________
MEMORANDUM OPINION
In this mandamus proceeding, J. Adams, LLC (Adams) contends the trial
court abused its discretion by granting Jefferson County’s (the County) motion for
new trial after Adams refused to accept a remittitur in a condemnation case. In its
order granting the new trial, the trial court found that the jury’s award to Adams of
“the difference between the market value of Plaintiff’s whole property before the
taking and the market value of Plaintiff’s remaining property after the taking and
cost[] to cure damages as presented by the evidence separately and additionally
permits a double recovery which is not permitted under Texas law.” According to
1
Adams, “[b]ecause [Adams’s expert’s] estimated cost to cure mitigated damages
distinct from the decrease in market value of the remaining property that resulted
from the County’s taking, the inclusion of these damages did not constitute a
double recovery.” Adams argues that factually sufficient evidence supports the
jury’s verdict, and that a trial court cannot grant a new trial conditioned on a
party’s refusal to accept a remittitur if factually-sufficient evidence supported the
jury’s verdict. See In re Columbia Med. Ctr. of Las Colinas, 290 S.W.3d 204, 210
(Tex. 2009) (orig. proceeding) (citing Larson v. Cactus Util. Co., 730 S.W.2d 640,
641 (Tex. 1987). We deny the petition for a writ of mandamus.
Underlying Facts
In September of 2010, the County filed Plaintiff’s Statement and Petition of
Condemnation against Adams to acquire property in Jefferson County with
existing road frontage on Frint Road. As part of a project to expand or improve
LaBelle Road, the County condemned three parcels totaling 4.21 acres out of
Adams’s 69 acre tract. The only issue at trial pertained to damages. In estimating
the market value of the property, Adams’s expert, Wayne Baer, reasoned that the
land was comprised of two separate economic units: (1) approximately eight acres
of frontage along Frint Road containing the original location of a sandblasting and
painting facility and (2) approximately sixty-one acres with frontage along Chance
2
Drive where Adams decided to relocate a new sandblasting and painting facility.
The separate economic units were depicted by Adams’s real estate appraiser as
follows:
The County condemned three parcels--parcel 28A, 28B, and 28C--totaling
4.21 acres out of the 69-acre parent tract owned by Adams. Parcels 28B and 28C
are located within the 8 acres and parcel 28A crosses the 61.005 acres. Adams’s
expert depicted the parcels as follows:
3
The primary dispute between the parties at the trial pertained to the calculation and
amount of the alleged damage to the remainder of the property after the partial
taking.
Adams’s principal owner, Judd Adams, testified at trial that operating the
sandblasting and painting facility at its original location on the 69-acre tract could
result in overspray claims from individuals travelling along the proposed alignment
of the road on Parcel 28A. Concluding that the taking rendered the original paint
and sandblasting facility unusable for its original use, Adams built a new
sandblasting and painting facility elsewhere on the remainder of the 69-acre tract at
4
a cost of approximately $180,000. Judd Adams also testified that after the County
filed the condemnation suit, Adams sold the former sandblasting and painting
facility and approximately six to eight acres1 of land adjacent thereto to a pipe
fabricator for $150,000.
Adams’s real estate appraiser, Wayne Baer, testified that the sandblasting
and painting facility contributed $351,433 in value to the property before the
taking, and after the taking, the contributory value of the improvements is
$175,716. According to Baer, the fifty percent diminution in contributory value
was in addition to the cost to cure that Adams incurred by relocating the
improvements, which Baer estimated to be $199,868. Baer testified that unless his
calculation included cost to cure as a component of damages, the value of the
remaining improvements would be diminished even more. According to Baer,
without relocating the facility, in his opinion the original sandblasting site would
have no value or negative value because the improvements would have to be
removed to restore the property to a different highest and best use. In addition to
damages of $80,248 for the part taken, Baer testified that Adams was also entitled
to $175,716 for the damage to the remainder and $199,868 for the cost to cure. The
total damage amount due, according to Baer, is $455,832.
1
The testimony in the record appears to reference six, eight, and ten acres
being sold by Adams along with the old sandblasting and painting facility.
5
The County’s real estate appraiser, Stephen Duplantis, testified at trial that
he estimated the total compensation at $88,500. According to the record, prior to
trial the County hired another real estate appraiser, Jimmy Bishop, to perform a
real estate appraisal and provide a report. Bishop prepared two reports and an
addendum, but Bishop was not available to testify at trial. The County engaged
Duplantis to review the other appraisals and to testify at trial. Both Baer and
Duplantis referenced Bishop’s report and addendum in their testimony to the jury.
Bishop’s addendum provides his estimate of the just compensation due to
Adams as $125,000 for Parcel 28-A, $72,000 for Parcel 28-B, and $3,885 for
Parcel 28-C, for a total compensation of $201,000. Duplantis agreed with part of
Bishop’s appraisal and disagreed with other parts of Bishop’s appraisal. Duplantis
testified that the just compensation for the three parcels should be $88,500.
The jury was asked one question:
Jury Question No. 1
By a preponderance of the evidence, what do you find to be the
difference between the market value of Plaintiff’s whole property
before the County’s taking on December 20, 2010, and the market
value of Plaintiff’s remaining property after the taking, giving
consideration to the uses to which the condemned parts are to be
subjected?
The jury was instructed that it could “consider necessary modifications to the
remaining property resulting from the condemnation, if any, in determining the
6
market value of the remaining property after the taking.” The jury returned a
verdict in the amount of $455,832.
After the verdict, the County filed a motion to disregard the jury’s finding,
arguing that Adams could not recover cost to cure as a separate item of damage
and that the jury’s award to Adams of both the diminution in market value and the
cost to cure constituted a double recovery. The County requested a remittitur in the
amount of $199,868 and entry of judgment in the amount of $255,964. On May 19,
2016, the trial court entered judgment on the jury’s verdict. However, the trial
court simultaneously entered a Suggestion of Remittitur or Alternatively New
Trial, concluding that allowing Adams to recover the difference in the market
value of its property before and after the taking, including cost-to-cure damages,
“permits a double recovery which is not permitted.” Under the trial court’s
suggestion of remittitur, Adams was required to accept the remittitur or be
subjected to a new trial. Adams did not accept the suggestion of remittitur. The
County then filed a motion for new trial on several grounds. On June 8, 2016, the
trial court set aside its May 19, 2016 judgment on the verdict and ordered a new
trial based on the grounds suggested in the County’s motion for new trial. Adams
then filed a Petition for Writ of Mandamus with this Court.
7
In ordering a new trial, the trial court found that “under the circumstances of
the case,” the “cost[] to cure damages” amounted to an improper recovery,
resulting in “an erroneous measure of damage in excess of [the expert’s]
determination of the loss of value to the remainder resulting from the taking.” The
trial court also concluded that “[b]oth the double recovery and the errors in
allowing consideration by the jury of an improper element of damages[]” could be
cured by a remittitur but the “Plaintiff has elected not to file the suggested
remittitur necessitating the granting of a new trial.”
Standard of Review
A trial court’s order granting a new trial may be reviewed by an appellate
court in a mandamus proceeding. See In re United Scaffolding, Inc., 377 S.W.3d
685, 688-89 (Tex. 2012) (orig. proceeding). A writ of mandamus will issue to
correct a clear abuse of discretion committed by a trial court in granting a new
trial. In re Whataburger Rests. LP, 429 S.W.3d 597, 598 (Tex. 2014) (orig.
proceeding) (per curiam) (citing In re Toyota Motor Sales, U.S.A., Inc., 407
S.W.3d 746, 756-57 (Tex. 2014) (orig. proceeding)). The Texas Supreme Court
has stated:
[A] trial court does not abuse its discretion so long as its stated reason
for granting a new trial (1) is a reason for which a new trial is legally
appropriate (such as a well-defined legal standard or a defect that
probably resulted in an improper verdict); and (2) is specific enough
8
to indicate that the trial court did not simply parrot a pro forma
template, but rather derived the articulated reasons from the particular
facts and circumstances of the case at hand.
Toyota, 407 S.W.3d at 756-57 (emphasis in original) (quoting United Scaffolding,
377 S.W.3d at 688-89). A new trial order “cannot stand[,]” however, when the
“trial court’s articulated reasons are not supported by the underlying record.” Id. at
758. The appellate court continues to apply “the abuse-of-discretion standard . . . to
merits review just as it does in all mandamus proceedings.” In re Bent, 487 S.W.3d
170, 178 (Tex. 2016).
Arguments of Parties
In this mandamus proceeding, Adams argues that the trial court abused its
discretion in conditioning a new trial upon Adams’s failure to accept a remittitur
when “factually sufficient evidence supported the jury’s verdict” that the loss to
the remainder of Adams’s property was $455,832. The County disagrees and
argues that Adams’s expert improperly calculated damages and that Adams has
been allowed a duplicate recovery.
Damages Available in a Partial Taking
The measure of compensation in a partial taking is “‘the market value of the
part taken plus damage to the remainder caused by the condemnation.’” State v.
Petropoulos, 346 S.W.3d 525, 530 (Tex. 2011) (quoting Westgate, Ltd. v. State,
9
843 S.W.2d 448, 456 (Tex. 1992)). Determination of the fair market value of the
remainder property requires measuring the difference between the value of the
property immediately before and immediately after the taking. Exxon Pipeline Co.
v. Zwahr, 88 S.W.3d 623, 627 (Tex. 2002). Evidence and testimony regarding the
cost to relocate certain facilities or improvements may be admissible, “not as a
separate element of damage, but as information that could be used by the jury to
arrive at the diminished value of the remainder tract after the taking, if any.” City
of Sugar Land v. Home & Hearth Sugarland, L.P., 215 S.W.3d 503, 514 (Tex.
App.—Eastland 2007, pet. denied). Cost to cure is a method of decreasing the
amount of damages below the diminution in market value, not increasing the
damages beyond the diminution in market value caused by the taking. Id. “This
approach allows the property owner to recover the cost to cure the portion of the
damage that can be cured, plus any diminution in value to the remainder which
cannot be cured, when the total of those two is less than the overall diminution in
value of the remainder uncured.” 4A Nichols, Eminent Domain, § 14.02[3][d].
To be admissible evidence upon which the jury may base its award of
damages, the expert’s calculation must be based upon a reliable methodology. See
E.I. du Pont de Nemours and Co., Inc. v. Robinson, 923 S.W.2d 549, 558 (Tex.
1995). To the extent that Baer calculated cost to cure as a distinct element of
10
damage separate from the diminution in the fair market value of the improvements,
the trial court reasonably could have concluded that Baer’s testimony had been
improperly admitted before the jury and was factually insufficient to support the
damage award because his methodology was unreliable. See Home & Hearth
Sugarland, 215 S.W.3d at 510. After reviewing Adams’s petition, the record, and
the response filed by the real party in interest, Jefferson County, as well as the
reply brief, we conclude that the trial court provided a reasonably specific and
valid explanation for granting the motion for new trial that is supported by the
record. See Toyota, 407 S.W.3d at 759-60. Accordingly, we deny the petition for a
writ of mandamus.
PETITION DENIED.
PER CURIAM
Submitted on September 23, 2016
Opinion Delivered November 17, 2016
Before McKeithen, C.J., Kreger and Johnson, JJ.
11