IN THE SUPREME COURT OF MISSISSIPPI
NO. 2015-CA-00519-SCT
GARY ROLISON, MARTHA ROLISON, GM
LANDS, LLC AND ROLISON TIE AND TIMBER
COMPANY, INC.
v.
EDITH CAROLYN FRYAR, CALEB FRYAR, PINE
GROVE TRUCKING, INC., ROBERT A. FRYAR
AND OPERATORS INVESTMENT GROUP, P.A.
DATE OF JUDGMENT: 02/17/2015
TRIAL JUDGE: HON. ANDREW K. HOWORTH
TRIAL COURT ATTORNEYS: JOHN WEDDLE
ALAN LANCASTER
REID STANFORD
KIRK THARP
SHANE McLAUGHLIN
BRADLEY TRUETT GOLMAN
STACEY WOODRUFF GOLMAN
COURT FROM WHICH APPEALED: TIPPAH COUNTY CIRCUIT COURT
ATTORNEYS FOR APPELLANTS: BRADLEY TRUETT GOLMON
STACEY WOODRUFF GOLMON
ATTORNEYS FOR APPELLEES: MARVIN REID STANFORD
ALAN D. LANCASTER
NATURE OF THE CASE: CIVIL - CONTRACT
DISPOSITION: AFFIRMED - 12/01/2016
MOTION FOR REHEARING FILED:
MANDATE ISSUED:
BEFORE DICKINSON, P.J., KITCHENS AND KING, JJ.
KITCHENS, JUSTICE, FOR THE COURT:
¶1. Following court-ordered mediation, spouses Gary Rolison and Martha Rolison and
Caleb Fryar and his father, Robert Allen Fryar, entered into a mediation settlement agreement
that resolved four lawsuits pending between the Rolisons and the Fryars.1 After a bench trial,
the Circuit Court of Tippah County found that the Rolisons had breached the settlement
agreement, and the court entered a final judgment pursuant to Mississippi Rule of Civil
Procedure 54(b) and postponed hearing the issue of damages. The Rolisons appealed from
the final judgment but later dismissed the appeal voluntarily. After the trial on damages, the
trial court awarded the Fryars $399,733.02 in damages, including lost profits and attorney
fees.
¶2. The Rolisons appeal, arguing that their jury trial waiver was ineffective, the trial
court’s Rule 54(b) certification was erroneous, and the trial court erroneously denied a
motion to intervene filed by two interested parties. Because the Rolisons dismissed their
appeal from the Rule 54(b) final judgment, these issues are not before the Court. We do hold
that the trial court committed no error by finding that the Rolisons had waived their right to
a jury trial on damages and attorney fees. Further, we reject the Rolisons’ challenges to the
trial court’s awards of damages and attorney fees because those awards were supported by
substantial, credible evidence. Therefore, we affirm the judgment of the trial court.
FACTS
¶3. In 2006, the Rolisons purchased ninety-seven acres of land, known as the sawmill
property, from the Fryars. After the purchase, disputes arose between the Rolisons and the
Fryars concerning ownership of certain equipment and materials located on the property.
1
This litigation involved appellants Gary Rolison, Martha Rolison, GM Lands, LLC,
and Rolison Tie and Timber, Co., Inc. (the Rolisons), and appellees Edith Carolyn Fryar,
Caleb Fryar, Pine Grove Trucking, Inc., Robert Allen Fryar, and Operators Investment
Group, P.A (the Fryars).
2
Litigation ensued in the Circuit Court of Tippah County, which consolidated four of the cases
for trial. On February 15, 2011, after all parties orally waived the right to a jury trial, the trial
court ordered them to participate in mediation in an effort to resolve the four cases. The trial
court further ordered that “all of the disputed property remain where is, as is” until the cases
were resolved. The mediation occurred on March 2, 2011, and resulted in a settlement
agreement signed by Gary Rolison, Martha Rolison, Robert Allen Fryar, and Caleb Fryar.
¶4. The mediation settlement agreement provided that if the Fryars tendered $400,000 to
the Rolisons, the Rolisons would convey the sawmill property to Caleb Fryar and execute
a bill of sale for “all equipment and materials located on said property as is where is as of the
date of this agreement on March 2, 2011.”2 Approximately one week later, the Rolisons
notified the Fryars of their belief that the parties had not reached a valid agreement because
there had been no meeting of the minds. On May 24, 2011, Caleb Fryar tendered a cashier’s
check in the amount of $400,000 to the Rolisons along with proposed settlement documents.
The Rolisons returned the check and documents to the Fryars’ attorney. Then, the Fryars filed
a motion to enforce the settlement agreement, claiming reasonable damages incurred due to
the delay, plus attorney fees.
¶5. A bench trial on the Fryars’ motion to enforce the settlement agreement occurred on
October 21, 2011. The trial court heard testimony from Gary Rolison, Martha Rolison, Gary
2
The mediation settlement agreement also provided that, in the event the Fryars did
not tender $400,000 to the Rolisons on or before May 31, 2011, the Fryars would have the
option to purchase a tract of land along the eastern boundary of the sawmill property for
$40,000. Because the Fryars tendered $400,000 to the Rolisons before May 31, 2011, this
option is not at issue in this case.
3
Wayne Rolison, Jr., Caleb Fryar, and the mediator, Larry Latham. The Rolisons argued that
there had been either a mistake or no meeting of the minds on the specific equipment and
materials that they were to transfer to Caleb Fryar for $400,000. The Fryars countered that
there had been a meeting of the minds because the mediation settlement agreement stated that
the Rolisons agreed to transfer “all” equipment and materials located on the sawmill
property. The Rolisons also argued that some of the equipment and materials on the sawmill
property was owned by their son, Gary Wayne Rolison, Jr., and by their logging operation,
Rolison Logging/Timber Company Trust. Gary Wayne Rolison, Jr., and Rolison
Logging/Timber Company Trust moved to intervene to protect their interests, arguing that,
because they owned the property, it could not have been transferred to Caleb Fryar by the
mediation settlement agreement. They requested a declaratory judgment that certain property
rightfully belonged to Gary Wayne Rolison, Jr., or Rolison Logging/Timber Company Trust.
¶6. The trial court denied the motion to intervene, finding that the motion was untimely
because the litigation had been ongoing for three years with no attempt to intervene. Further,
the trial court found that “the relationship between the Rolison[]s and the trust is so
hopelessly intertwined that it does not function as a separate entity” and that the Rolisons had
either express or implied authority to speak for the trust at all relevant times. The trial court
also found that, based on the testimony of the witnesses and especially the mediator, the
mediation settlement agreement had been the product of a meeting of the minds, and its terms
were clear and unambiguous. The trial court also rejected the Rolisons’ claim of a unilateral
or mutual mistake. The issues of damages and attorney fees were postponed. Upon a finding
4
of no just reason for delay, the trial court directed the entry of a final judgment on its grant
of the Fryars’ motion to enforce the settlement agreement. See M.R.C.P. 54(b). At the
conclusion of the bench trial, the trial court ordered a continuing injunction against the
removal of anything from the property by anyone.
¶7. After the Rolisons’ motion for a new trial was denied on May 3, 2012, they filed a
timely notice of appeal. On August 15, 2012, the parties entered into a second settlement
agreement providing for the transfer of the sawmill property, but preserving the Fryars’ claim
for damages. Pursuant to this agreement, the Rolisons agreed to dismiss their pending appeal.
On September 14, 2012, this Court granted the Rolisons’ motion to dismiss their appeal, and
the mandate issued on October 8, 2012.
¶8. The issues of damages and attorney fees were tried on January 12, 2015. The Fryars
presented evidence that damage had occurred to the sawmill property after the Rolisons had
breached the mediation settlement agreement. They showed that an office located on the
property had sustained water damage, a retaining wall had collapsed due to a water leak, the
Rolisons had removed lumber and scrap metal from the property in violation of the court’s
order, motors had been removed and wires cut on the sawmill, and the scales had been
damaged. The Fryars also showed that, because of a regulatory change during the breaching
period, they had to modify the scales in a manner that would not have been required due to
“grandfathering” if they had obtained the property when promised. The trial court found that
the relevant dates for the breaching period were July 1, 2011, which was the undisputed date
the Fryars would have begun sawmill operations, until September 14, 2012, the date the
5
Fryars would have been able to begin operations after they finally took possession, if the
sawmill property had not been in a state of disrepair. The trial court awarded $231,960.32
for the costs to repair or replace missing or damaged items and $75,000 in lost profits. The
trial court found that, because the Rolisons intentionally had disregarded the unambiguous
terms of the mediation settlement agreement and had removed items from the sawmill
property in violation of court orders, their conduct was so outrageous that it supported the
Fryars’ claim for attorney fees in the amount of $92,772.70.
STANDARD OF REVIEW
¶9. “A circuit court judge sitting without a jury is accorded the same deference with
regard to his findings as a chancellor, and his findings will not be reversed on appeal where
they are supported by substantial, credible, and reasonable evidence.” Brewer Constr. Co.,
Inc. v. David Brewer, Inc., 940 So. 2d 921, 925 (Miss. 2006). This Court reviews questions
of law de novo. Upchurch Plumbing, Inc. v. Greenwood Utils. Comm’n, 964 So. 2d 1100,
1107 (Miss. 2007).
DISCUSSION3
I. WHETHER THE TRIAL COURT DENIED THE ROLISONS’
CONSTITUTIONAL RIGHT TO A JURY TRIAL UNDER ARTICLE 3,
SECTION 31, OF THE MISSISSIPPI CONSTITUTION.
¶10. The Rolisons argue that they failed to effect a waiver of their state constitutional right
to a jury trial. After the trial court consolidated the four cases, all parties orally waived their
rights to a jury trial and consented to a bench trial. Then the trial court ordered mediation,
3
For clarity, we have reordered the appellate issues.
6
which resulted in a settlement. After the Rolisons failed to perform their duties under the
mediation settlement agreement, the trial court held a bench trial on the Fryars’ motion to
enforce the settlement agreement. No party requested a jury trial and all participated in the
bench trial. At the conclusion, the trial court ruled from the bench that the Rolisons had
breached the mediation settlement agreement and denied the motion to intervene by Rolison
Logging/Timber Company Trust and Gary Wayne Rolison, Jr.
¶11. Approximately one month later, on November 18, 2011, the parties appeared in court
to try the issues of damages and attorney fees. The Rolisons, now with new counsel, argued
that they had not waived their right to a jury trial. The Rolisons contended that their oral jury
trial waiver was ineffective because they had not filed a written waiver under Mississippi
Rule of Civil Procedure 38(b). Alternatively, they argued that their oral waiver extended only
to the four consolidated cases, and that a new cause of action for breach of contract had
arisen upon their noncompliance with the mediation settlement agreement, for which they
had not waived a jury trial. They argued that the Fryars should file an amended complaint
adding a breach of contract action, and that the remaining issues of damages and attorney
fees for breach of contract should be tried before a jury.
¶12. The trial court postponed the trial and ordered the parties to brief the jury trial waiver
issue. On December 9, 2011, the trial court directed the entry of a final judgment under Rule
54(b) with respect to the matters that had been adjudicated. The Rolisons appealed from that
judgment but later dismissed their appeal pursuant to their August 2012 settlement agreement
with the Fryars. On July 15, 2013, the trial court entered an order finding that the Rolisons
7
had waived their right to a jury trial at the February 15, 2011, hearing “and by subsequent
conduct, regarding the issue of the enforceability of the settlement agreement” and “on the
present issue of any damages resulting from the breach of the settlement agreement.”
¶13. On appeal, the Rolisons argue that their oral waiver of a jury trial was ineffective due
to Rule 38(b)’s requirement of a written waiver of a jury trial. Rule 38 provides:
(a) Right Preserved. The right of trial by jury as declared by the Constitution
or any statute of the State of Mississippi shall be preserved to the parties
inviolate.
(b) Waiver of Jury Trial. Parties to an action may waive their rights to a jury
trial by filing with the court a specific, written stipulation that the right has
been waived and requesting that the action be tried by the court. The court
may, in its discretion, require that the action be tried by a jury notwithstanding
the stipulation of waiver.
M.R.C.P. 38(b). The Rolisons also argue that they never waived a jury trial on the Fryars’
new cause of action for breach of contract, and that their conduct of orally waiving a jury
trial and then fully trying the breach of contract issue cannot be construed as an effective
waiver.
¶14. The Rolisons’ argument that they were entitled to a jury trial on the issue of whether
they breached the mediation settlement agreement is not properly before the Court. This is
because, after the bench trial on that issue, the trial court entered a final judgment under
Mississippi Rule of Civil Procedure 54(b). Rule 54(b) provides that “the court may direct the
entry of a final judgment as to one or more but fewer than all of the claims or parties only
upon an expressed determination that there is no just reason for delay and upon an expressed
direction for the entry of the judgment.” M.R.C.P. 54(b). A party has thirty days after the date
8
a final judgment is entered to perfect an appeal. M.R.A.P. 4(a). If the Rolisons had wished
to appeal the denial of a jury trial on the issue of whether the mediation settlement agreement
was breached, they should have filed an appeal within thirty days after the entry of the Rule
54(b) final judgment. In fact, the Rolisons did perfect an appeal from the Rule 54(b) final
judgment but later dismissed that appeal. Therefore, the issue of whether they were entitled
to a jury trial on the matters resolved by the Rule 54(b) final judgment is not before this
Court.4
¶15. After the entry of the Rule 54(b) final judgment, the issues of damages and attorney
fees remained before the trial court. Because the issue of whether the Rolisons were entitled
to a jury trial solely on damages and attorney fees was not encompassed by the final
judgment, it is properly before this Court. However, the issue is without merit. The Rolisons
cite Burnette v. Hartford Underwriters Ins. Co., 770 So. 2d 948, 951-52 (Miss. 2000), for
the proposition that the right to a jury trial cannot be waived under Mississippi Rule of Civil
Procedure 38(b) through implied conduct. In Burnette, this Court found that the filing of an
action in chancery court, where a jury is not available, did not function as a waiver of the
right to a jury trial when the case was transferred to circuit court, where a jury is available.
Id. at 952. The Court held that, because the Burnettes had not filed “a specific written
4
The Fryars claim that the Rolisons’ argument is barred by Mississippi Code Section
11-3-15 (Rev. 2014), which provides that “[a]fter the dismissal of an appeal or supersedeas
by the Supreme Court, another appeal or supersedeas shall not be granted in the same cause,
so as to bring it again before the Court.” The Fryars claim that the Rolisons raised the jury
trial issue in their dismissed appeal and they cannot raise it again. We do not address this
statutory argument because the jury trial issue may be resolved fully under the Mississippi
Rules of Civil Procedure and the Mississippi Rules of Appellate Procedure.
9
stipulation waiving their right to a jury, they have not waived that right. Id. Thus, Burnette
held that a party may waive the right to a jury trial under Rule 38(b) only by filing a written
waiver.
¶16. In this case, it is undisputed that the Rolisons never filed a written jury trial waiver.
Therefore, the trial court erred by finding that they had waived the right to a jury trial.
However, this Court will affirm if the trial court reached the correct result, but for the wrong
reason. Love v. Barnett, 611 So. 2d 205, 207 (Miss. 1992). Although the trial court
incorrectly determined that the Rolisons had waived their right to a jury trial, we find the
issue to be one of forfeiture. “[W]aiver is different from forfeiture. Whereas forfeiture is the
failure to make the timely assertion of a right, waiver is ‘the intentional relinquishment or
abandonment of a known right.’” U.S. v. Olano, 507 U.S. 725, 733, 113 S. Ct. 1770, 1777,
123 L. Ed. 2d 508 (1993) (quoting Johnson v. Zerbst, 304 U.S. 458, 464, 58 S. Ct. 1019,
1023, 82 L. Ed. 1461 (1938)). When a party fails to demand a jury trial and proceeds to try
the case to the bench, the party, having failed to exercise the jury trial right in a timely
manner, forfeits the right to complain. That is what occurred in this case. The Rolisons tried
the breach of contract issue to the bench and failed to demand a jury trial until the damages
phase. Because the Rolisons forfeited the right to a jury trial by failing to exercise the right
in a timely manner, we affirm the trial court’s finding that the Rolisons were not entitled to
a jury trial on the issues of damages and attorney fees.
II. WHETHER THE TRIAL COURT ERRED BY DIRECTING THE ENTRY
OF THE RULE 54(B) FINAL JUDGMENT.
¶17. Under Rule 54(b), the trial court may “direct the entry of a final judgment as to one
10
or more but fewer than all of the parties only upon an expressed determination that there is
no just reason for delay and upon an expressed direction for the entry of the judgment.”
M.R.C.P. 54(b). This Court has held that a decision that leaves a portion of a claim pending
as to all defendants may not be certified as a final, appealable judgment under Rule 54(b).
Brown v. Collections, Inc., 188 So. 3d 1171, 1175 (Miss. 2016). The Rolisons argue that this
prohibition is implicated in this case because the Fryars brought a single claim, for breach
of the mediation settlement agreement, against all defendants. The Rolisons argue that the
trial court erred by directing the entry of the Rule 54(b) final judgment after ruling on the
breach of the mediation settlement agreement. They contend that, because the Fryars’
remaining requests for damages and attorney fees were simply damages for their breach of
contract claim, they were not separate “claims” for the purposes of Rule 54(b).The Rolisons
argue that, because the entry of a Rule 54(b) final judgment was erroneous, this Court can
now address all claims adjudicated by the Rule 54(b) final judgment.
¶18. This Court lacks jurisdiction to address any claims embraced by the Rule 54(b) final
judgment. This is because the Rolisons’ time for appealing that judgment has expired. A
notice of appeal must be filed within thirty days after the date of the entry of the judgment
from which appeal is taken. M.R.A.P. 4(a). The Rolisons appealed the Rule 54(b) final
judgment; but, when they voluntarily dismissed their appeal after the expiration of the thirty
day period, they lost the opportunity to challenge any issues embraced by the Rule 54(b) final
judgment.
¶19. The Rolisons argue that, because the trial court’s Rule 54(b) certification was
11
erroneous, the judgment was not final, but interlocutory, and ineffective to commence the
running of the thirty day time for appeal. This argument is without merit. “A judgment
merely voidable because based upon an erroneous view of the law is not open to collateral
attack, but can be corrected only by a direct review . . . .” Federated Dep’t Stores, Inc. v.
Moitie, 452 U.S. 394, 398, 101 S. Ct. 2424, 69 L. Ed. 2d 103 (1981) (citations omitted). This
precept applies to an erroneous Rule 54(b) certification. “A Rule 54(b) certification, right or
wrong, starts the time for appeal running.” In re Lindsey, 59 F.3d 942, 951 (9th Cir. 1995).
Thus, once a trial court has directed the entry of a final judgment under Rule 54(b), any party
seeking relief from that judgment, even on the ground that the judgment is, in fact,
interlocutory, must perfect an appeal within thirty days after the entry of judgment. Id. When
a party perfects an appeal from a Rule 54(b) final judgment, this Court’s routine
jurisdictional inquiry includes determining whether the judgment was, in fact, a proper
exercise of the trial court’s authority under Rule 54(b). See Brown, 188 So. 3d at 1173. If the
judgment was interlocutory because the requirements of Rule 54(b) were not met, this Court
has not hesitated to reverse for lack of jurisdiction. Id.; Cox v. Howard, Weil, Labouisse,
Friedrichs, Inc., 512 So. 2d 897, 899 (Miss. 1987).
¶20. Because the Rolisons dismissed their appeal, they lost their opportunity to challenge
the issues embraced by the Rule 54(b) final judgment, including whether the entry of the
judgment complied with Rule 54(b). The Rolisons’ argument that the Rule 54(b) final
judgment was interlocutory is untimely. Therefore, this Court lacks jurisdiction to adjudicate
the argument. M.R.A.P. 4(a).
12
III. WHETHER THE TRIAL COURT ERRED BY DENYING THE
MOTION TO INTERVENE BY GARY WAYNE ROLISON, JR., AND THE
ROLISON LOGGING/TIMBER COMPANY TRUST.
¶21. The Rolisons complain that the trial court erroneously disallowed the intervention of
Gary Wayne Rolison, Jr., and the Rolison Logging/Timber Company Trust. They argue that,
because these parties owned equipment and material on the sawmill property, their
participation in the litigation was necessary. They also contend that the trial court’s finding
that Gary Rolison and Martha Rolison had express or apparent authority to bind their son or
the trust was baseless.
¶22. Again, this issue is not properly before the Court. The trial court resolved this issue
in its bench ruling after the trial on the motion to enforce the mediation settlement agreement.
Subsequently, it entered a Rule 54(b) final judgment, from which the Rolisons perfected, and
later dismissed, an appeal. Because the Rolisons dismissed their appeal and the time for
taking an appeal from the Rule 54(b) final judgment has long passed, the Rolisons lost the
opportunity to challenge the trial court’s denial of the motion to intervene.
IV. WHETHER, BECAUSE THE PLAINTIFFS FAILED TO MITIGATE
THEIR DAMAGES, THE TRIAL COURT ERRED BY FINDING THAT
THE BREACHING PERIOD WAS FIFTEEN MONTHS.
¶23. The trial court found that the breaching period was fifteen months, with a beginning
date of July 1, 2011, when the Fryars would have begun sawmill operations had they
purchased the sawmill property as promised, and an ending date of September 14, 2012,
when the Fryars would have been able to begin sawmill operations after taking possession
pursuant to the second settlement agreement if the sawmill property had not been in disrepair.
13
The Rolisons and the Fryars consummated the second settlement agreement in August 2012.
This settlement agreement provided that the Rolisons would convey the sawmill property to
the Fryars by quitclaim deed. It also provided that the Rolisons would convey certain sawmill
equipment to the Fryars, including the blue mill. The agreement stated that the Rolisons had
fourteen days to remove certain equipment and materials from the property, including eighty
percent of the cypress lumber and eighty percent of the pine lumber and timber. The
agreement provided that the Rolisons would leave twenty percent of the cypress lumber and
twenty percent of the pine lumber and timber on the property. In exchange for all of this, the
Fryars would pay the Rolisons $400,000.
¶24. At trial, the Rolisons showed that the Fryars had refused a similar settlement
arrangement that they were offered on November 23, 2011. On that date, the Rolisons offered
to execute a quitclaim deed for the land and a bill of sale for the same equipment, including
the blue mill. But they did not offer to sell the Rolisons any of the lumber on the property.
Significantly, both the August 2012 settlement agreement and the November 2011 offer
provided that the Rolisons would get less than “all equipment and materials located on said
property as is where is as of the date of this agreement . . . .” as they had been promised in
the mediation settlement agreement.
¶25. The Rolisons argue that, if the Fryars had accepted the November 23, 2011, settlement
offer, they would have had the sawmill operational in the next six weeks, prevented nine
months of deterioration to the sawmill property, and likely prevented the theft and vandalism
that further damaged the property. They contend that the Fryars’ refusal of the November 23,
14
2011, offer was unreasonable and failed to mitigate damages and, therefore, the trial court
should have limited the breaching period to six months. The Fryars counter that this
argument is “absurd” because they had no duty to mitigate damages by accepting less than
they had been promised in the mediation settlement agreement.
¶26. An injured party has a duty to take reasonable steps to mitigate damages. Nat’l Dairy
Prods. Corp. v. Jumper, 241 Miss. 339, 334, 130 So. 2d 922, 923 (1961). Under the doctrine
of avoidable consequences, an injured party is not entitled to recover damages which he or
she could have avoided through reasonable efforts. Manhattan Nursing & Rehab. Ctr., LLC
v. Pace, 134 So. 3d 810, 818 (Miss. Ct. App. 2014) (citing Munn v. Algee, 924 F.2d 568,
573 n.9 (5th Cir. 1991) (collecting Mississippi cases)). “This legal principle ‘deals not with
the conduct of a plaintiff contributing to his injury, but with his failure to avoid the
consequences of his injury after it has been inflicted, to avoid or diminish the damages
resulting from his injury.’” Manhattan Nursing, 134 So. 3d at 818 (quoting Yazoo & M.V.R.
Co. v. Fields, 188 Miss. 725, 732, 195 So. 489, 490 (1940)).
¶27. This Court rejects the Rolisons’ argument that the trial court should have limited the
breaching period to six months due to their November 2011 settlement offer. The Rolisons’
November 2011 offer was for less than the Fryars were entitled to receive under the court
order for performance of the mediation settlement agreement. The Fryars did not act
unreasonably by refusing to enter into a new contract for less than they had bargained for in
the mediation settlement agreement. Although the Fryars’ negotiation of the August 2012
agreement gained them little more than the Rolisons had offered in November 2011, the
15
Fryars had no duty to mitigate damages by entering into a new contract for less than they
were entitled to receive under the mediation settlement agreement. See United States v.
Sabin Metal Corp., 151 F. Supp. 683, 690 (S.D.N.Y. 1957) (stating that “[t]he defendant’s
offer to the plaintiff of something other than that to which it is entitled as compensation is
not admissible in mitigation”).
V. WHETHER THE TRIAL COURT ERRED BY AWARDING THE
FRYARS DAMAGES FOR DETERIORATION OF THE SAWMILL
PROPERTY.
¶28. The Rolisons argue that language in the August 2012 settlement agreement foreclosed
the Fryars’ recovery for deterioration of the sawmill property that occurred during the
breaching period. Specifically, the Rolisons assert that the August 2012 settlement agreement
stated that the Fryars accepted the sawmill property and equipment “as is, where is,” as of
the date of the agreement. But the August 2012 settlement agreement and the associated bills
of sale do not contain the words “as is, where is” or any other language indicating the Fryars
intended to relinquish their claim for damages attributable to the breached mediation
settlement agreement. To the contrary, the settlement agreement stated that “[t]his Settlement
Agreement in no way compromises or addresses the claim for damages that Caleb Fryar has
against the parties to the above captioned litigation, should he choose to pursue that cause
of action.” In the motion to enforce the settlement agreement, the Fryars had claimed
reasonable damages incurred due to the delay caused by the Rolisons’ breach. Thus, the
August 2012 settlement agreement preserved the Fryars’ claim for damages for breach of the
mediation settlement agreement, including deterioration of the sawmill property.
16
VI. WHETHER THE TRIAL COURT ERRED BY AWARDING DAMAGES
FOR THE STOLEN MOTORS AND STOLEN AND/OR DAMAGED
WIRING AT THE MILL.
¶29. The Fryars showed that, during the breaching period, several motors had been
removed and wiring intentionally was cut and/or removed from the blue mill, which was the
sawmill the Fryars eventually began operating. Investigator Josh Bateman with the Tippah
County Sheriff’s Department testified that three persons had been charged with theft of
motors and wiring from the sawmill property that had been reported on July 6, 2012, and July
13, 2012. The Fryars presented evidence that the missing motors had a value of $39,433.50.
They showed that the damaged or missing wire had cost $36,827.50 to replace or repair. The
trial court accepted the Fryars’ proof and awarded them the amounts claimed.
¶30. The Rolisons contend that the trial court erred by awarding the Fryars damages for the
missing motors and missing or damaged wiring. First, they argue that the Fryars’ agreement
to accept certain equipment at the sawmill property “as is, where is” on August 15, 2014,
precludes their recovery. As noted in the discussion of the previous issue, the August 15,
2014, agreement does not include the language, “as is, where is,” and it expressly preserved
the Fryars’ claim for damages for breach of the mediation settlement agreement.
¶31. Second, the Rolisons argue that the Fryars failed to prove that the value of the missing
motors was $39,433.50. However, even if the extent of damages is uncertain, recovery is
allowed if the nature of the damages is certain. Benchmark Health Care Ctr., Inc. v. Cain,
912 So. 2d 175, 179 (Miss. Ct. App. 2005). This Court has stated that:
[W]here it is reasonably certain that damage has resulted, mere uncertainty as
to the amount will not preclude the right of recovery or prevent a jury decision
17
awarding damages. This view has been sustained where, from the nature of the
case, the extent of the injury and the amount of damage are not capable of
exact and accurate proof. Under such circumstances, all that can be required
is that the evidence – with such certainty as the nature of the particular case
may permit – lay a foundation which will enable the trier of fact to make a fair
and reasonable estimate of the amount of damage. The plaintiff will not be
denied a substantial recovery if he has produced the best evidence available
and it is sufficient to afford a reasonable basis for estimating his loss.
Cain v. Mid-South Pump Co., 458 So. 2d 1048, 1050 (Miss. 1984).
¶32. The Fryars’ proof that the value of the missing motors was $39,433.50 was a quote
from supplier JESCO, Inc., to replace each type of missing motor with a new motor. The
Rolisons did not refute the reasonableness of these costs. In fact, the Rolisons admitted that
they had claimed $55,000 from their insurance company for the value of the missing motors.
We find that the Fryars provided the trial court a reasonable foundation to estimate the
damages, and the trial court’s decision to award the Fryars $39,433.50 for the missing motors
was supported by substantial, credible evidence.
¶33. Next, the Rolisons argue that they should not have been held liable for missing motors
and wire removed from the sawmill property by thieves. However, they cite no authority for
this proposition. “This Court has repeatedly held that failure to cite any authority may be
treated as a procedural bar.” City of Jackson v. Internal Engine Parts Grp., Inc., 903 So.
2d 60, 66 (Miss. 2005) (citing Williams v. State, 708 So. 2d 1358, 1361 (Miss. 1998)).
Notwithstanding the procedural bar, the theft and vandalism itself evidenced that the
Rolisons had failed to secure the property reasonably against third-party criminal activity.
VII. WHETHER THE TRIAL COURT ERRED BY COMPENSATING THE
FRYARS FOR DAMAGE TO THE SCALES.
18
¶34. A set of scales was located on the sawmill property that was used to weigh logging
trucks. Ownership of the scales was disputed between the Rolisons and the Fryars; however,
at the trial it was established that the Fryars owned the scales. But, because the scales were
located on the sawmill property which the Rolisons owned, the Rolisons exercised dominion
and control over the scales during the breaching period. In fact, at the bench trial on the
motion to enforce the settlement agreement, Gary Wayne Rolison, Jr. testified that the
Rolisons had paid to have concrete poured so the scales could be recertified to comply with
certain government regulations.
¶35. Caleb Fryar testified that, when the Fryars took possession of the property after the
August 15, 2012, settlement agreement, he discovered that the wires to the scales had been
cut, necessitating repair costs. He also incurred costs to add concrete and asphalt to level the
scales to comply with a new regulation. He testified that, if he had gained possession of the
sawmill property in 2011 pursuant to the mediation settlement agreement, the scales would
have been “grandfathered in,” and no modifications would have been required to comply
with the new regulation. The trial court awarded the Fryars the $10,873.02 they claimed for
damages related to the scales.
¶36. The Rolisons argue that, because the Fryars owned the scales, they were not entitled
to recover the costs of the cut wires or the required modifications to the scales. They further
argue that, because the Fryars owned the scales, they and not the Rolisons were responsible
for their upkeep. Further, they argue that, because the Fryars had owned the scales all along,
the scales were “grandfathered in” and the Fryars were not required to modify them and did
19
so at their own peril.
¶37. We find that the trial court’s award of the full cost claimed by the Fryars to repair and
modify the scales was supported by substantial, credible evidence. The damage to the scales’
wiring occurred when the scales were under the dominion and control of the Rolisons. And
Caleb Fryar testified that the regulation required modification of the scales when they came
into his possession. The Rolisons did not refute this testimony by showing that the regulation
required no modification of the scales if they were under continuous ownership by the same
individual or entity. Certainly, the scales were not in continuous operation, and the regulation
may have required the modification when use of the scales resumed. In any event, Caleb
Fryar’s testimony constituted substantial, credible evidence upon which the trial court was
entitled to rely.
VIII. WHETHER THE TRIAL COURT ERRED BY AWARDING THE
FRYARS COMPENSATION FOR MISSING SCRAP METAL.
¶38. During the breaching period, the Rolisons’ son, Gary Wayne Rolison, Jr., removed
scrap metal from the sawmill property despite the court order not to remove anything from
the property. Caleb Fryar presented photographs of Gary Wayne Rolison, Jr., removing scrap
metal, and he testified that approximately one-half of the scrap metal on the property had
been removed. The trial court found that the Rolisons had allowed items to be removed from
the sawmill property in violation of the court order. The Fryars valued the missing scrap
metal at $22,471.95, representing the amount they had received when they sold the remaining
scrap metal. The trial court found that the Fryars had presented the best estimate of the value
of the missing scrap metal, and awarded them $22,471.95.
20
¶39. The Rolisons argue that the Fryars were not entitled to compensation for the missing
scrap metal because Gary Wayne Rolison, Jr., was not a party to the litigation. With this
contention, they repeat their argument that the Rolisons cannot be held liable for damage to
the sawmill property caused by third parties. Again, the Rolisons cite no authority for this
proposition, so this argument is procedurally barred. Internal Engine Parts Grp., Inc., 903
So. 2d at 66. Notwithstanding the procedural bar, the trial court specifically found that the
Rolisons had allowed others to remove items from the property, in violation of the court
order.
¶40. The Rolisons also argue that Gary Wayne Rolison, Jr., would have been unable to
remove the 130 tons of scrap metal which the Fryars claimed was missing because removing
that amount would have required multiple eighteen wheelers. The trial court was faced with
conflicting evidence on the scrap metal issue. We find that the trial court’s resolution of the
conflicting evidence in favor of the Fryars was supported by substantial, credible evidence.
IX. WHETHER THE TRIAL COURT ERRED BY AWARDING THE
FRYARS DAMAGES FOR LOST PROFITS.
¶41. The Fryars claimed lost profits of $230,356.47 attributable to their inability to run the
blue mill during the breaching period. The trial court found that they had presented the
testimony of “experts with substantial experience” in the sawmill industry to support the lost
profits claim. With the assistance of the experts, the Fryars compiled monthly profit and loss
projections which were admitted into evidence.
¶42. The Fryars’ projections showed they expected to cut an average of 20,000 board feet
of lumber per day. The projections included the number of work days per month, the cost of
21
logs, and the prices at which the Fryars expected to sell the three types of lumber produced
by the blue mill, including crossties, one-inch lumber, and “cants,” defined as four-by-six-
inch lumber. The projections also included other expected costs of production including
payroll, workers’ compensation insurance, and other expenses. Caleb Fryar testified that, for
the breaching period, Koppers, Inc., had agreed to buy all crossties produced, Hassell &
Hughes Lumber Company had agreed to buy all one-inch lumber produced, and Tenn-Tom
Pallet had committed to buy all cants produced. Representatives from Koppers, Inc., and
Hassell & Hughes Lumber Company corroborated Caleb Fryar’s testimony about their
companies’ purchasing commitments. The general manager of another lumber company gave
expert testimony supporting the Fryars’ projections. The Fryars also showed that they had run
the blue mill for approximately six days in December 2014 and averaged more than 20,000
board feet per day.
¶43. The Rolisons presented the testimony of an accountant, Charles L. Davis, Jr., along
with documents showing that Rolison Tie and Timber Company had operated the blue mill
at a loss in 2006. Davis testified that he had compared the Fryars’ projections with the actual
operating expenses that Rolison Tie and Timber Company had incurred in 2006 and had
concluded that the Fryars would have operated at a loss during the breaching period.
However, it was established that Davis had not considered certain lumber that Rolison Tie
and Timber Company had cut, but not sold, that was left on the sawmill property. Nor did he
take into consideration that, instead of the fifteen employees that Rolison Tie and Timber
Company had used to run the blue mill, the Fryars planned to use eight. Further, Davis
22
admitted that the Fryars planned to cut different types of wood than Rolison Tie and Timber
Company had cut. He also admitted that the goal of cutting 20,000 board feet per day was
a conservative estimate of what the Fryars could produce.
¶44. The trial court found that the Fryars had sustained lost profits during the breaching
period. The trial court found from the testimony of the industry experts and the accountant
that, if the sawmill had operated during the breaching period, a supply of materials and a
market had existed for the sawmill’s finished products. The trial court found that this
testimony “removed the question of whether revenue, costs, and profit might be speculation.”
The trial court further found from the testimony of Samuel Robert Bradley, a regional
director for Koppers, Inc., that the amount of money available from Koppers for lending to
sawmills had reduced drastically from the time the Fryars had tendered their purchase money
to the Rolisons under the mediation settlement agreement and when the Fryars actually took
possession of the sawmill in August 2012. Bradley testified that, if the Fryars had received
the sawmill when promised under the mediation settlement agreement, Koppers, Inc., had
$250,000 available for the purchase of logs to get the mill running.5 Bradley testified that,
due to changes in the market and funds availability unrelated to this case, the funds available
to the Fryars had been reduced to $50,000. The trial court found that the evidence supported
a loss of profits of $75,000. Thus, the trial court awarded less than half of the lost profits
claimed by the Fryars. The trial court did not explain how it determined this number or note
which evidence it found most credible.
5
Caleb Fryar testified that Koppers had agreed to lend him money to buy logs and
to fund operating expenses with repayment in crossties.
23
¶45. The Rolisons argue that the Fryars’ projections contain several miscalculations which,
when corrected, show that the blue mill would have operated at a loss. First, they contend
that the Fryars’ claim that they would have produced an average of 238 crossties a day is
erroneous, because the evidence showed they would have averaged only 217 crossties a day.
The Fryars claimed they would have averaged 10,000 board feet of crossties per day. The
Fryars’ evidence that they would have averaged 238 crossties a day was based on the
testimony of Koppers, Inc., employee Joe Foley and sawmill manager Tony Jarrell that
10,000 board feet would yield approximately 238 seven-by-nine-inch crossties. Thus, the trial
court was presented evidence supporting the Fryars’ projected crosstie production.
¶46. Second, the Rolisons contend that the Fryars underestimated the costs to operate the
blue mill. The Fryars’ expenses for the approximately six days of operation in December
2014 showed $158 for workers’ compensation insurance and nothing for taxes and liability
insurance. The Rolisons complain that the Fryars’ expert, Tony Jarrell, represented that it
would cost $4,000 per month for taxes and liability insurance and $2,000 a month for
worker’s compensation insurance to run the sawmill. The Rolisons claim that, correcting for
these errors, a proper calculation of operating expenses would mean the mill cost $134.56
per thousand board feet to operate, not $112.50 as claimed by the Fryars. However, the
Rolisons’ expert accountant testified that, considering Tony Jarrell’s calculations, $112.50
per thousand board feet in operating expenses for the blue mill was a conservative estimate.
And Tony Jarrell testified that the cost of workers’ compensation insurance varies, and that
his workers’ compensation estimate of $2,000 per month was based on the cost of workers’
24
compensation for his own sawmill, which had increased coverage costs due to accidents.
Thus, the trial court was within its discretion in relying, to whatever extent it did, on the
Fryars’ estimate of tax and insurance expenses. Moreover, the trial court awarded the Fryars
less than half of their claim for lost profits.
¶47. Next, the Rolisons attack the Fryars’ claim that the cost of logs was $55 per ton. They
contend that the Fryars’ expert, Tony Jarrell, admitted that the cost of oak logs was between
$60 and $62 per ton, and Gary Rolison testified that he had sold oak logs for between $60
and $68 during the breaching period. However, Caleb Fryar testified that the projections
considered that they would buy both oak and mixed hardwood logs, and Tony Jarrell testified
that mixed hardwood logs cost $55 per ton. The Rolisons fail to explain how these
differences in log costs would have destroyed the profitability of the Fryars’ milling
operation during the breaching period. Importantly, the trial court awarded the Fryars less
than half of their claimed lost profits. The trial court was permitted to accept, to the extent
that it did, the Rolisons’ estimate of the cost of logs.
¶48. The Rolisons also complain that the representative from Hassell & Hughes Lumber
Company testified that, although the company had committed to purchase all the one-inch
lumber the Fryars produced, the company never had bought one-inch lumber from the Fryars.
However, Caleb Fryar testified that he currently was selling all the one-inch lumber to
another customer. Thus, contrary to the Rolisons’ argument, the Fryars did present evidence
of a market for one-inch lumber.
¶49. The Rolisons also argue that the trial court should have placed more weight on the fact
25
that, in 2006, Rolison Tie and Timber Company had run the blue mill at a loss than on the
Fryars’ projection of future profits. They also complain that the Fryars had operated the blue
mill in October and November 2014 but submitted no data for those months. “In Mississippi,
a party may recover for loss of future profits in a breach of contract action so long as such
profits are proved to a reasonable certainty and not based on mere speculation or conjecture.”
Benchmark Health Care Ctr. v. Cain, 912 So. 2d 175, 179 (Miss. Ct. App. 2005). When
damages have occurred, mere uncertainty as to the amount does not preclude recovery. Id.
(quoting Cain v. Mid-South Pump Co., 458 So. 2d 1048, 1050 (Miss. 1984)). “[A]ll that can
be required is that the evidence – with such certainty as the nature of the particular case may
permit – lay a foundation which will enable the trier of fact to make a fair and reasonable
estimate of the amount of damage.” Cain, 458 So. 2d at 1050. The plaintiff is entitled to
recover if he has produced the best evidence available and that evidence provides a
reasonable basis for estimating the loss. Id. Purely speculative evidence of lost profits is
inadequate to support an award. Benchmark, 912 So. 2d at 180. But “[s]ome speculation
must be involved in an attempt to compute unrealized profits.” Id.
¶50. The Rolisons argue that, unlike in this case, in Benchmark, the lost future profits
evidence was based on past profits. Id. They further argue that, in Ballard Realty Co., Inc.
v. Ohazurike, 97 So. 3d 52 (Miss. 2012), this Court found that the plaintiff had not presented
adequate evidence of lost profits. In Ohazurike, this Court found that the plaintiff’s proof of
lost profits was unreliable because the plaintiff’s expert merely had adopted the plaintiff’s
“grandiose figures” and had reduced those amounts to present value. Id. at 61. And the expert
26
failed to deduct overhead, depreciation, taxes, or inflation. Id. This Court also found that
another expert’s testimony was unreliable because it was based on lofty estimates from the
plaintiff’s business plan, and the expert had admitted that historical data is a better basis for
valuation. Id. at 64.
¶51. We conclude that the trial court’s award of $75,000 for lost profits was supported by
substantial evidence. The trial court found that the Fryars had put forth the best evidence of
lost profits. Unlike Ohazurike, the Fryars’ projections were based on sound testimony of
industry experts and included estimates for the anticipated expenses of running the sawmill.
Thus, the projections were not purely speculative, and the trial court was entitled to rely on
them. Notably, the trial court awarded the Fryars less than half their projected lost profits.
The Rolisons are entitled to no relief on this issue.
X. WHETHER THE TRIAL COURT ERRED BY AWARDING THE
FRYARS THE FULL AMOUNT OF ATTORNEY FEES CLAIMED.
¶52. The trial court found that the Fryars had incurred attorney fees in the amount of
$92,772.70 in connection with the enforcement of the breached mediation settlement
agreement and that those fees were reasonable and necessary to enforce the settlement
agreement fully. The trial court awarded the full amount of attorney fees requested because
the Rolisons “intentionally disregarded the expressed and unambiguous terms of the
Mediation Agreement and the orders of the Court and removed property or allowed property
to be removed that was subject to the Mediation Agreement.” The trial court found that this
conduct was so outrageous that it supported an award of attorney fees.
¶53. Generally, a party may not recover attorney fees for breach of contract. Bluewater
27
Logistics, LLC v. Williford, 55 So. 3d 148, 164 (Miss. 2011). However, attorney fees may
be awarded if they are provided for in the contract, or for conduct that is so outrageous that
it would support an award of punitive damages. Id. The Rolisons argue that attorney fees
were not warranted because they complied with the trial court’s order enforcing the
settlement agreement by making the November 23, 2011, settlement offer to the Fryars.
¶54. The Rolisons’ argument misconstrues the trial court’s findings. The trial court found
that the Rolisons’ breach of the March 2, 2011, mediation settlement agreement was
intentional. This finding had nothing to do with the order enforcing the mediation settlement
agreement, which the trial court had entered as a remedy for the Rolisons’ breach of that
agreement. Copious evidence was before the trial court that the Rolisons’ breach of the
mediation settlement agreement was intentional, including the plain language of the
mediation settlement agreement and the testimony of the mediator that, to all appearances,
the Rolisons knowingly had agreed to its terms when they signed it. Further, the trial court
was confronted with evidence that the Rolisons had removed items from the sawmill
property, or had allowed items to be removed, in violation of court orders. Therefore, the trial
court’s finding that the Rolisons’ wrongful conduct was intentional was supported by
substantial, credible evidence.
¶55. The Rolisons also argue that the Fryars were not entitled to full attorney fees because
they did not mitigate damages by accepting the November 23, 2011, settlement offer. As
discussed in Issue IV, the Fryars’ duty to make reasonable efforts to mitigate their damages
did not include an obligation to accept the November 23, 2011, offer and to accept less from
28
the Rolisons than what they had bargained for in the mediation settlement agreement.
Therefore, this argument is without merit. The trial court did not err by awarding the Fryars
their full attorney fees.
CONCLUSION
¶56. Because the Rolisons dismissed their appeal from the Rule 54(b) final judgment, their
arguments that their jury trial waiver was ineffective, that the trial court’s Rule 54(b)
certification was erroneous, and that the trial court erroneously denied a motion to intervene
are not properly before the Court. The trial court’s finding that the Rolisons waived their
right to a jury trial on damages and attorney fees was not manifestly erroneous. And the trial
court’s awards of damages and attorney fees were supported by substantial, credible
evidence. Therefore, we affirm the judgment of the Circuit Court of Tippah County.
¶57. AFFIRMED.
WALLER, C.J., DICKINSON AND RANDOLPH, P.JJ., KING, COLEMAN
AND BEAM, JJ., CONCUR. MAXWELL, J., CONCURS IN PART AND IN RESULT
WITH SEPARATE WRITTEN OPINION JOINED BY LAMAR, J.
MAXWELL, JUSTICE, CONCURRING IN PART AND IN RESULT:
¶58. I agree that the trial court’s final judgment should be affirmed. The Rolisons forfeited
the right to a jury through their conduct. And the Fryars’ award for damages and attorney
fees was supported by the evidence.
¶59. But I question the Rule 54(b) certification and the majority’s reliance on the finality
of that judgment. To me, the December 2011 judgment declaring the settlement agreement
enforceable does not appear to have been a final, appealable judgment—despite its Rule
29
54(b) designation. See M.R.C.P. 54(b). As this Court recently reiterated, Rule 54(b) can be
invoked only “in a relatively select group of cases and applied to an even more limited
category of decisions.”6 Brown v. Collections, Inc., 188 So. 3d 1171, 1175 (Miss. 2015).
And “decisions that leave a portion of the claim pending as to all defendants” do not fit in
this narrow category. Id.
¶60. Here, as the majority acknowledges, the December 2011 order left a portion of the
Fryars’ settlement-enforcement claim pending—i.e., the issues of damages and attorney fees.
So according to our precedent, it was “not a true Rule 54(b) judgment.” White v. Mills, 735
So. 2d 428, 431 (Miss. 1999) (holding the grant of summary judgment was “not a true Rule
54(b) judgment” because it “left a portion of the claim pending—i.e., that portion dealing
with the relief due”); see also Colum Law Firm v. Bd. of Trustees, 16 So. 3d 692, 695
(Miss. 2009) (holding that “the trial court’s ruling as to whether the meeting could be
declared void does not properly fall within the purview of Rule 54(b)” because “portions of
the claim—the factual allegations and the remaining prayers for relief—are still pending as
to all the defendants”). And since it was not a true Rule 54(b) judgment, no appellate
jurisdiction arose over the Rolisons’ earlier appeal. See Brown, 188 So. 3d at 175-77
(dismissing the appeal sua sponte for lack of jurisdiction because Rule 54(b) certification was
invalid); White, 735 So. 2d at 432 (holding, despite no challenge to the Rule 54(b)
certification, the Court of Appeals plainly erred by entertaining the appeal).
6
“For an order or judgment to qualify for Rule 54(b) finality, the case must include:
(1) either multiple claims, multiple parties, or both; and (2) either one or more but fewer than
all claims must have been decided or all rights and liabilities of at least one party must have
been adjudicated.” Brown v. Collections, Inc., 188 So. 3d 1171, 1175 (Miss. 2015).
30
¶61. It is this lack of appellate jurisdiction that distinguishes this case from the Ninth
Circuit case the majority cites, In re Lindsey, 59 F.3d 942, 951 (9th Cir. 1995). In that case,
the district court made a Rule 54(b) certification without making the requisite on-the-record
findings. Still, the Ninth Circuit held that the Rule 54(b) certification triggered the time to
appeal because the “lack of . . . findings is not a jurisdictional defect.” Id. See also Cox v.
Howard, Weil, Labouisse, Friedrichs, Inc., 512 So. 2d 897, 901 (Miss. 1987) (suggesting,
but not requiring, the “trial court to set forth specific reasons and findings prefatory to
entering a Rule 54(b) judgment”). But here, the defect is jurisdictional. This is not a case
where the trial court should not have certified as final a judgment disposing of less than all
claims. See, e.g., Cox, 512 So. 2d at 901. Rather, this is a case where the trial court could
not certify its decision as final, because it did not dispose of any claim. See, e.g., Brown, 188
So. 3d at 175-77; White, 735 So. 2d at 432.
¶62. So the Rolisons have not “lost their opportunity to challenge the issues embraced by
the Rule 54(b) final judgment,” because no such opportunity arose in the first place. Had the
Rolisons pursued their prior appeal—as the majority finds they should have—this Court
could not have addressed the issues raised, due to the lack of appellate jurisdiction. Instead,
it was only when the settlement-enforcement claim was fully resolved in February 2015 that
all underlying issues became final and appealable.
¶63. That said, there is no merit to the Rolisons’ jury-trial argument. As the majority points
out, the Rolisons litigated the enforcement issue through a bench trial “without objection and
without demanding a jury trial.” So they forfeited their right to a jury trial. And because of
31
this forfeiture, I concur with the majority that the trial court did not err by continuing the
bench trial on the issues of damages and attorney fees.
¶64. I also concur with the majority’s holding that the trial court did not err in denying the
motion to intervene and in determining appropriate amount of damages and attorney fees.
Thus, I concur in part and in result.
LAMAR, J., JOINS THIS OPINION.
32