STATE OF MICHIGAN
COURT OF APPEALS
LINDA S. MANLEY, MARY MATTERN, UNPUBLISHED
TIMOTHY MATTERN, JANET B. MATTERN, December 6, 2016
EMORY MULHOLLAND, PAM
MULHOLLAND, RICHARD SEBRING, and
MICHAEL SMILEY,
Plaintiffs-Appellees,
v No. 327510
Lenawee Circuit Court
SUE PIKULSKI, also known as SUE HAWKINS, LC No. 89-004109-CH
and JOSEPH A. PIKULSKI, JR.,
Defendants-Appellants.
Before: JANSEN, P.J., and MURPHY and RIORDAN, JJ.
PER CURIAM.
Defendants Sue Pikulski and Joseph Pikulski appeal as of right the trial court’s June 25,
2014 order denying the parties’ motions for summary disposition, the trial court’s November 21,
2014 opinion and order entered after the bench trial in this case, and the trial court’s May 14,
2015 final judgment denying defendants’ posttrial motions and closing the case. We affirm the
trial court’s opinions and orders, but remand is necessary for the trial court to determine a
maximum width for the constructed pathway provided for in its November 21, 2014 order.
I. FACTUAL BACKGROUND
In August and December 1959, Farland R. Myers and Anna H. Myers, the previous
owners of defendants’ property, entered into several easement agreements that had substantively
identical terms. In relevant part, the agreements provided:
This indenture, made this 3rd day of December, 1959 by and between
Farland R. Myers and Anna H. Myers, of Toledo, Ohio, grantors, and [the
grantees],
Witnesseth:
That, for and in consideration of the sum of One Dollar and other valuable
considerations in hand paid by the grantee, the receipt whereof is hereby
-1-
acknowledged do hereby grant unto the grantees, [the owners of specific lots in
the Oak Shade Park Subdivision in] Cambridge Twp., Lenawee County,
Michigan, and to subsequent owners of [the specific lots] or occupiers of [the
specific lots] as tenants in possession, only, access for pedestrian traffic only,
along Outlet No. A. Supervisors Plat No. 2, a part of Lot No. 2, Government
Survey N E 1/4 Fractional Section 2, T. 5 South, Range 2 East, Cambridge Twp.,
Lenawee Co., Michigan according to the Plat thereof recorded in Liber 6 page 47
of Plats, to Wampler’s Lake and the right to maintain only one boat but no
motorized rafts at the lake dock on the frontage of said Outlet A provided
grantees, subsequent owners or occupying tenants of said premises pay their
proportionate share of the expense of maintaining the dock and of keeping it in
good condition.
It is further understood and agreed by both parties hereto that it is a
condition of this easement and binding upon grantee, subsequent owners, and
occupying tenants that the way of access must be kept clear at all times and that
the grantors, their heirs and assigns may designate the path of access as they see
fit.
In February 1989, Linda S. Manley, Donald J. Mattern, Mary C. Mattern, Mary E.
Mattern, William P. Mulholland, Vivian M. Mulholland, Ronald Saraniecki, Richard Sebring,
and Shirley Sebring filed a complaint against Sue Hawkins,1 Joseph A. Pikulski, Jr., and Kenneth
Richardson, alleging that the defendants had wrongfully and substantially interfered with the
plaintiffs’ use of the easement, and attempted to force the plaintiffs to abandon the easement,
through a variety of actions. Accordingly, the plaintiffs requested, inter alia, a declaration of
their rights and a permanent injunction enjoining the defendants from interfering with the
plaintiffs’ rights, which would be binding on the parties’ successors in interest.
In March 1989, the defendants filed an answer to the plaintiffs’ complaint, in which they
denied the plaintiffs’ allegations of interference. They also filed a counter-complaint in which
they contended that the plaintiffs, as well as their guests and invitees, had violated the easement
by using Outlot A and other property in a variety of ways. Accordingly, the defendants
requested, among other things, temporary and permanent injunctive relief requiring the plaintiffs
to strictly comply with the terms of the easement agreements, requiring the plaintiffs to stay
within the way of access designated by the defendants and only use it as a walkway, and
requiring a series of restrictions concerning the placement of the plaintiffs’ dock.
More than a year of litigation followed. On May 9, 1990, the date set for trial, the parties
placed a settlement on the record. On March 18, 1991, an order was entered consistent with the
parties’ settlement.
1
Sue Hawkins is now married to Joseph Pikulski and is a defendant in the instant appeal.
-2-
In September 2013, the plaintiffs at issue in the instant appeal2 filed a petition for a
permanent and interim injunction, as well as other relief, against defendants Sue Pikulski and
Joseph A. Pikulski, Jr. In October 2013, defendants filed a response to plaintiffs’ petition,
denying plaintiffs’ claims of wrongful conduct and requesting that the trial court deny plaintiffs’
request for relief. After subsequent filings and proceedings, the trial court denied both parties’
motions for summary disposition and other requests for pretrial relief. The trial court then held a
four-day bench trial.
In October 2014, both parties submitted proposed findings of fact and conclusions of law.
On November 21, 2014, the trial court entered its opinion and order. Most relevant to this
appeal, it found, “The 1991 Order which represents the Stipulated Agreement of the parties
altered the terms of the 1959 easement as to the walkway and to the maintenance of boats on
Wampler’s Lake.” It made the following findings of fact:
The 1991 Order is clear that the easement holders may place their boats
due east or dead east to be in compliance with said Order. Therefore . . . the
current practice employed by Plaintiffs is in compliance and the 1991 Order
pertaining to mooring of boats, facing easterly along the west side of the dock
shall not be disturbed.
Testimony was provided by Plaintiffs and Defendant regarding the
installation of the concrete break wall installed by Defendant Pikulski. The
concrete wall interrupts the natural flow of the water and Plaintiffs’ use and
enjoyment of a beach feature formerly available to them as easement holders.
Defendant may not unilaterally change the nature of the land or interfere with
Plaintiffs’ use.
The garden fence placed by Defendant along the walkway used by
Plaintiffs is of no consequence. It is too small, too light, and too easily moved
and manipulated. The walkway as is prevents foot traffic and clear parameters for
guidance. The fence was placed in the ground by Defendant solely to preclude or
inhibit Plaintiffs’ use. The fence was an attempt to make foot traffic impassible
or at best, impracticable.
Neither the 1959, nor the 1991 Order pertaining to the walkway is
ambiguous. The easement holders have a right to occupy the property at issue to
the extent necessary to fully enjoy the rights conferred by the easement document.
The owner of the land burdened by the easement cannot block the easement or
otherwise take such action as may constitute an unreasonable interference with
2
In June 2014, plaintiffs filed a motion for a substitution of parties, based on the death of
original plaintiffs to the action giving rise to the 1991 order and subsequent sales of property
benefitted by the easement, so that the current title holders or occupants of the subject properties
were listed as plaintiffs in the current action. The trial court granted the substitution.
-3-
the easement holders’ use. Further, Defendant may not unilaterally block or
change the easement.
Accordingly, it ordered:
That Plaintiffs may moor their boats on the west side of their dock, facing
due east, dead east, or in an easterly direction;
That Defendant shall, on or before July 1, 2015, remove the concrete
structure, the break wall, at the northern end of Outlot A, thereby reestablishing
the beach front currently enjoyed by the easement holders;
That the easement holders shall install a walkway, no less than 5 (five)
foot wide along the easternmost side of Outlot A. Said walkway may be wood,
concrete, blacktop, stone or any other material appropriately designated by
Plaintiffs. Plaintiffs shall bear the expense associated with materials and
installation of the walkway. Said walkway shall comply with any and all State
and local building regulations;
That in all other respects, the Orders and Agreements between the
Plaintiffs and Defendants remain in full force and effect.
Subsequently, defendants filed motions requesting amendment of the trial court’s opinion
and order, a new trial or other appropriate relief, and further clarification, in which they argued,
inter alia, that the trial court’s findings were against the great weight of the evidence admitted at
trial, and that the trial court erred by failing to address many of the purported violations of the
easement agreement and 1991 order that they raised in their counter-petition and litigated at trial.
Ultimately, the trial court denied defendants’ motions, except for their request that the trial court
clarify whether a final order closing the case had been entered, explaining that it believed that the
findings and conclusions in its November 21, 2014 opinion and order were sufficient, and that
further findings were unnecessary given the language of the 1991 stipulated order.
Defendants now appeal as of right.
II. STANDARD OF REVIEW
“The extent of a party’s rights under an easement is a question of fact, and a trial court’s
determination of those facts is reviewed for clear error.” Blackhawk Dev Corp v Village of
Dexter, 473 Mich 33, 40; 700 NW2d 364 (2005). Likewise, “[t]he scope and extent of an
easement” and “whether the scope of an easement has been exceeded” are generally questions of
fact that are “reviewed for clear error on appeal.” Wiggins v City of Burton, 291 Mich App 532,
550; 805 NW2d 517 (2011). See also Bang v Forman, 244 Mich 571, 573; 222 NW 96 (1928).
Stated differently, “[w]hat may be considered a proper and reasonable use by the owner of the
fee, as distinguished from an unreasonable and improper use, as well as what may be necessary
to [the easement holder’s] beneficial use and enjoyment, are questions of fact to be determined
by the trial court or jury.” Lakeside Assoc v Toski Sands, 131 Mich App 292, 300; 346 NW2d 92
(1983). A trial court’s “factual findings are clearly erroneous if there is no evidence to support
them or there is evidence to support them but this Court is left with a definite and firm conviction
-4-
that a mistake has been made.” A & M Supply Co v Microsoft Corp, 252 Mich App 580, 588;
654 NW2d 572 (2002) (quotation marks and citation omitted). “ ‘[G]reat deference’ [is]
generally afforded to trial courts, which are in a better position to examine the facts.” Hill v City
of Warren, 276 Mich App 299, 308; 740 NW2d 706 (2007) (citation omitted).
However, the proper interpretation of the language in an easement or deed is reviewed de
novo as a question of law, In re Rudell Estate, 286 Mich App 391, 402-403; 780 NW2d 884
(2009), as the principles applicable to contract interpretation similarly apply when a court
reviews the language establishing an easement, see In re Egbert R Smith Trust, 480 Mich 19, 24;
745 NW2d 754 (2008); Little v Kin, 468 Mich 699, 700; 664 NW2d 749 (2003). See also
Schadewald v Brule, 225 Mich App 26, 35; 570 NW2d 788 (1997). Likewise, “[i]nterpreting the
meaning of a court order involves questions of law that we review de novo on appeal.” Hanton v
Hantz Fin Services, Inc, 306 Mich App 654, 660; 858 NW2d 481 (2014) (quotation marks and
citation omitted).
Even though appellate courts generally review de novo a trial court’s determination that
equitable relief is proper under the circumstances, McDonald v Farm Bureau Ins Co, 480 Mich
191, 197; 747 NW2d 811 (2008), this Court reviews the grant or denial of injunctive relief for an
abuse of discretion, Pontiac Fire Fighters Union Local 376 v City of Pontiac, 482 Mich 1, 8; 753
NW2d 595 (2008); Martin v Murray, 309 Mich App 37, 45; 867 NW2d 444 (2015); Janet
Travis, Inc v Preka Holdings, LLC, 306 Mich App 266, 274; 856 NW2d 206 (2014). “An abuse
of discretion occurs when the court’s decision results in an outcome that falls outside the range
of principled outcomes.” Epps v 4 Quarters Restoration LLC, 498 Mich 518, 528; 872 NW2d
412 (2015).3
III. REMOVAL OF THE BREAKWALL
Defendants first contend that the trial court erred when it ordered them to remove the
concrete breakwall. We disagree.
“An easement is a right to use the land of another for a specific purpose.” Bowen v Buck
& Fur Hunting Club, 217 Mich App 191, 192; 550 NW2d 850 (1996). “An easement does not
displace the general possession of the land by its owner, but merely grants the holder of the
easement qualified possession only to the extent necessary for enjoyment of the rights conferred
by the easement.” Schadewald, 225 Mich App at 35, citing Morrill v Mackman, 24 Mich 279,
284 (1872). As such, “the owner of a fee subject to an easement may rightfully use the land only
for a purpose consistent with the rights of the owner of the easement[.]” Smith v Edwards, 249
Mich App 199, 209-210; 645 NW2d 304 (2002). See also Harr v Coolbaugh, 337 Mich 158,
165-166; 59 NW2d 132 (1953) (“[T]he owner of the servient estate may make any use of the
premises not inconsistent with easement.”) (emphasis omitted). Stated differently, the fee owner
may make any use of his land as long as it does not unreasonably interfere with the easement
holder’s use of the land. Lee v Fidelity Life & Income Mut Ins Co, 2 Mich App 82, 86-87; 138
3
Defendants’ summary disposition and directed verdict claims fail for the same reasons
discussed in this opinion.
-5-
NW2d 545 (1965), citing 2 Thompson Real Property (1961 Rev), Easements, § 431, p 719, and
Kirby v Meyering Land Co, 260 Mich 156; 244 NW 433 (1932). See also Murphy Chair Co v
Am Radiator Co, 172 Mich 14, 28-29; 137 NW 791 (1912). Likewise, “[t]he owner of the right
of way has the right to a reasonably unobstructed passage at all times, and also such rights as are
incident or necessary to the enjoyment of such right of passage.” Murphy Chair Co, 172 Mich at
29. See also Blackhawk Dev Corp, 473 Mich at 41-42 (“It is an established principle that the
conveyance of an easement gives to the grantee all such rights as are incident or necessary to the
reasonable and proper enjoyment of the easement.”) (quotation marks and citation omitted).
“Once granted, an easement cannot be modified by either party unilaterally.”
Schadewald, 225 Mich App at 36. If the owner of the servient estate interferes with an easement
owner’s use of the easement, the easement owner may bring an action—seeking damages, an
injunction, or both types of remedies—in order to enforce the easement. See, e.g., Choals v
Plummer, 353 Mich 64, 73; 90 NW2d 851 (1958); Hasselbring v Koepke, 263 Mich 466, 476;
248 NW 869 (1933); Soergel v Preston, 141 Mich App 585, 587-588, 590-591; 367 NW2d 366
(1985); Bd of Comm’rs v Abraham, 93 Mich App 774, 781; 287 NW2d 371 (1979).
When an injury is irreparable, or the interference is of a permanent or continuous
character, or the remedy at law will not afford adequate relief, a bill for an
injunction is an appropriate remedy. 10 Michigan Law & Practice, Easements, §
34, p 128. The granting of injunctive relief is within the sound discretion of the
court, and the decision must be based on the facts of the particular case. [Soergel,
141 Mich App at 589-590.]
See also Janet Travis, Inc, 306 Mich App at 274-275; 2 Restatement Property, 3d, Servitudes, §
8.3, pp 495-496 (“Injunctive relief is normally available to redress violations of easements and
restrictive covenants without proof of irreparable injury or a showing that a judgment for
damages would be inadequate.”). Notably, the Michigan Supreme Court previously stated, “The
violation of complainants’ rights by the erection of a permanent structure obstructing an
easement and right of way created by deed will be relieved by injunction in a court of equity.”
Kirby v Meyering Land Co, 260 Mich 156, 167; 244 NW 433 (1932) (quotation marks and
citations omitted).
It is undisputed that plaintiffs were entitled, under the 1959 easement agreements, to use
the easement for pedestrian access to Wampler’s Lake, and that plaintiffs also were entitled,
under the 1991 stipulated order, “to utilize[] the beach on the lake front of ‘Outlot A’ as far south
as the current position of the north-east corner of defendants’ house for such purposes as the
supervision of young children in the water at the lake front of ‘Outlot A,’ ” as long as the
easement holders did not go further than the endpoints indicated in the order. After hearing the
evidence presented at trial, the trial court concluded:
Testimony was provided by Plaintiffs and Defendant regarding the
installation of the concrete break wall installed by Defendant Pikulski. The
concrete wall interrupts the natural flow of the water and Plaintiffs’ use and
enjoyment of a beach feature formerly available to them as easement holders.
Defendant may not unilaterally change the nature of the land or interfere with
Plaintiffs’ use.
-6-
Accordingly, the trial court ordered “[t]hat Defendant shall . . . remove the concrete structure, the
break wall, at the northern end of Outlot A, thereby reestablishing the beach front currently
enjoyed by the easement holders[.]” In so holding, the trial court implicitly found that removal
of the wall was necessary for plaintiffs’ use of the beach, and that defendants’ installation of the
easement was inconsistent with plaintiffs’ rights and unreasonably interfered with plaintiffs’
reasonable use of the easement. See Blackhawk Dev Corp, 473 Mich at 40; Harr, 337 Mich at
165-166; Smith, 249 Mich App at 209-210; Lakeside Associates, 131 Mich App at 300; Lee, 2
Mich App at 86-87. The trial court did not clearly err in so finding, especially given the “ ‘great
deference’ [that this Court] generally afford[s] to trial courts, which are in a better position to
examine the facts.” Hill, 276 Mich App at 308.
On appeal, defendants mischaracterize the testimony provided by plaintiffs’ witnesses,
stating, “In fact, the Easement Holders’ witnesses conceded that the breakwall was an
improvement over the old set-up.” Although plaintiffs’ witnesses confirmed that the breakwall
provided a flatter, sturdier foundation for plaintiffs’ dock, defendants fail to acknowledge trial
testimony demonstrating that defendants’ installation of the breakwall significantly inhibited
plaintiffs’ access to, and use of, the beach area. Additionally, even though defendants testified
that there still was a beach between the breakwall and the water, that the breakwall did not “hurt”
the beach area, and that whether the water “butts up against the concrete wall” depends on the
level of the lake, it appears that the trial court believed that the contrary was true following its
visit to Outlot A. The photographs admitted at trial similarly show that the wall significantly
reduced or fully eliminated the beach area.4 Given this evidence, the trial court did not clearly
err in concluding that removal of the breakwall was necessary for plaintiffs’ reasonable use of
the beach area under the 1991 stipulated order. See Lakeside Assoc, 131 Mich App at 300; A &
M Supply Co, 252 Mich App at 588.
Contrary to defendants’ claims, whether installation of the breakwall was a “per se
reasonable” action in their estimation in order to prevent further erosion of the property is not
relevant, as the pertinent focus is whether defendants’ interference was reasonable—not whether
the act itself would be objectively reasonable without considering the terms of the easement—
given defendants’ duty to refrain from any unreasonable interference with plaintiffs’ reasonable
use of the easement. See Murphy Chair Co, 172 Mich at 28-29; Smith, 249 Mich App at 209-
210; Lee, 2 Mich App at 86-87. Likewise, whether defendants’ installation of the breakwall was
expressly prohibited under the 1959 easement agreements or the 1991 stipulated order is not
dispositive, as the appropriate inquiry is whether defendants’ actions were inconsistent with
plaintiffs’ rights under the agreement, or whether defendants’ act unreasonably interfered with
plaintiffs’ rights. See Smith, 249 Mich App at 209-210; Harr, 337 Mich at 165-166.
Furthermore, contrary to defendants’ claims on appeal, there is no basis in the record for
4
Notably, at the hearing on defendants’ motions requesting amendment of the trial court’s
opinion and order, a new trial or other appropriate relief, and further clarification, the trial court
emphasized its conclusion that there is no beachfront as a result of the breakwall, and that the
easement holders are now required to access the water over a wall, which is impossible for
someone with a walker.
-7-
concluding that the breakwall “saved” the beach area. Rather, as previously discussed, the
testimony and photographic evidence confirms that the breakwall wholly altered the portion of
the easement adjacent to the lake and effectively eliminated the beach area.5
Thus, the trial court did not abuse its discretion when it issued an injunction requiring
defendants to remove the breakwall, as defendants’ unilateral change of the property—which
affected plaintiffs’ access to the water as well as the character of the beach—obstructed and
interfered with plaintiffs’ rights to use the beach area in accordance with the 1991 order.
IV. CONSTRUCTION OF WALKWAY
Next, defendants contend, for a variety of reasons, that the trial court erred when it
ordered plaintiffs to construct a walkway along Outlot A. We disagree, except to the extent that
we find that remand is required so that the trial court may establish a maximum width for the
walkway.
First, the trial court did not clearly err in concluding that “[t]he walkway as is prevents
foot traffic and clear parameters for guidance.” The evidence presented at trial supported this
conclusion and demonstrated that a constructed walkway was necessary and reasonable for
plaintiffs’ use of the easement. See Blackhawk, 473 Mich at 41-42. Photographs and witness
testimony indicated that the garden fence was flimsy and easily moved or damaged, confirming
the trial court’s conclusion that it did not clearly demarcate the pathway established by
defendants. Additionally, witnesses testified at trial that the unevenness of the pathway makes it
difficult for some people to maintain their footing, and that the narrow width of the pathway
defined by defendants makes it impossible to walk down the pathway while holding a child’s
hand or while walking side-by-side with another adult, impossible to carry a paddle boat or
canoe down the path, difficult to carry an inner tube down the path, and impossible for easement
holders in wheelchairs to access the lake. Additionally, when plaintiff Pamela Mulholland, an
easement holder, was assisting plaintiff Mary Mattern, an elderly easement holder, down the
easement, she had to walk single file in front of Mary, while Mary held on to Pamela’s
shoulders, due to the narrow width. Individuals using the easement also have to wait to access
the walkway if others are already traversing in the opposite direction due to the narrow width.
Although defendant Joseph testified that he has seen the easement holders walk side-by-side and
carry inner tubes down the path, this Court must defer to “the trial court’s superior ability to
judge the credibility of the witnesses who appeared before it,” Ambs v Kalamazoo Co Rd
Comm’n, 255 Mich App 637, 652; 662 NW2d 424 (2003), especially in the face of conflicting
evidence, Dawe v Bar-Levav & Assoc (On Remand), 289 Mich App 380, 401; 808 NW2d 240
(2010) (“[I]f there is conflicting evidence, the question of credibility ordinarily should be left for
the fact-finder.”). See also MCR 2.613(C).
5
At oral argument, defendants’ counsel admitted that defendants erected the concrete breakwall
without obtaining approval from the relevant regulatory agencies and without obtaining an
opinion from an engineering expert regarding the necessity or efficacy of a breakwall for their
intended purpose of preventing erosion of their lake frontage.
-8-
Likewise, the trial court did not clearly err in concluding that defendants installed the
garden fence “solely to preclude or inhibit Plaintiffs’ use,” and that “[t]he fence was an attempt
to make foot traffic impassible or at best, impracticable.” Defendant Joseph repeatedly testified
that he believed that the 41-inch pathway was an appropriate and sufficient width, commenting
that he thought that he was “real liberal on what [he] did with that boundary.”6 He explained that
he has seen the easement holders walk side-by-side and walk inner tubes down the path, and that
he believes that the “easternmost side” of the easement under the 1991 order is 42 inches wide.
However, as previously discussed, multiple witnesses provided testimony directly contrary to
defendant Joseph’s, and the trial court was in the best position “to judge the credibility of the
witnesses who appeared before it.” MCR 2.613(C). See also Dawe, 289 Mich App at 401;
Ambs, 255 Mich App at 652. Additionally, defendant Joseph’s trial testimony plainly revealed
defendants’ uninhibited frustration with plaintiffs’ use of Outlot A to access their dock and the
beach area, which prompted defendants to limit plaintiffs’ use as much as possible by taking
numerous actions, including, inter alia, taking countless photographs of plaintiffs using the
easement, installing four surveillance cameras, calling the police and posting no trespassing
signs, and circulating a notice to the easement holders that stated, among other things, that
defendants “will be enforcing our contract to the fullest extent,” that “[d]ue to a few, everyone
must suffer the consequences of their actions,” and that they were “installing 24 hour
surveillance cameras to make sure that you all abide by the contract.” Notably, defendant Joseph
also testified that he installed the garden fence the night before plaintiffs installed their dock in
2013, knowing that they would be installing the dock the following day. This deliberate action
further reveals an intent to limit plaintiffs’ use of the easement. From this testimony, and the
trial court’s opportunity to observe defendant Joseph’s demeanor as he testified, the trial court
did not clearly err in concluding that defendants intended to limit the pathway to such an extent
that it was impracticable, impassable, or, at the very least, inconvenient for some or all of the
easement holders. See MCR 2.613(C); Dawe, 289 Mich App at 401; Ambs, 255 Mich App at
652.
“The courts of this state have repeatedly held that ‘equity may shape her relief according
to the situation as it may present itself when the time for the decree arrives[.’] ” Greenspan v
Rehberg, 56 Mich App 310, 325; 224 NW2d 67 (1974), quoting Thompson v Enz, 385 Mich 103,
110; 188 NW2d 579 (1971). As mentioned supra, when the owner of a servient estate interferes
with an easement, the owner of the easement may proceed by bringing an action for damages,
injunctive relief, or both. See, e.g., Choals, 353 Mich at 73; Hasselbring, 263 Mich at 476;
Soergel, 141 Mich App at 587-588, 590-591; Bd of Comm’rs, 93 Mich App at 781. Notably,
“[i]f a grantee is not content with a way designated by his grantor, and an agreement cannot be
reached, a court of equity has power to designate a convenient way . . . .” Douglas v Jordan, 232
Mich 283, 288; 205 NW 52 (1925).
Here, similar to Greenspan, given the intense and ceaseless conflict between the parties
in this case, “[t]he trial court was faced with the situation in which the only feasible method of
6
Defendant Joseph did not have any expertise in this regard. Therefore, we conclude that his
opinion on the issue has no merit.
-9-
insuring that the originally expressed intent of the parties was fulfilled[] was by ordering the
construction of” a walkway. Greenspan, 56 Mich App at 325. During the hearing on
defendants’ posttrial motions, the trial court specifically recognized defendants’ right to
designate a pathway for plaintiffs, but it found that “[i]t’s just not able to be done by them [so
that] the easement [is] practical or even possible the way it’s been handled at this point, which is
why the Court had to intervene and had to adjust what would otherwise have been a process they
could’ve carried out, but they wouldn’t, and the Court so determined.” As the trial court
concluded, it was clear from the evidence presented at trial that allowing the parties to determine
the width of the walkway on their own in accordance with the 1959 easement agreements and
1991 stipulated order would not resolve the ongoing dispute between the parties regarding the
path or walkway that plaintiffs may use in accordance with the easement. See id. As such,
simply ordering plaintiffs to comply with the existing terms of the 1959 easement agreements
and 1991 order “would be only a temporary and wholly unsatisfactory solution to the problem.”
See id. On this record, the trial court did not abuse its discretion in concluding that ordering
plaintiffs to construct the walkway was proper in the interest of equity. See id.
However, we find that the trial court’s order fails to resolve the incessant dispute between
the parties with regard to the pathway, which has continued while this case has been on appeal.
Given the seemingly never-ending conflict and animosity between the parties, the trial court’s
decision to prescribe only a minimum width for the constructed pathway leaves the issue subject
to an expansive range of interpretations and thus is outside the range of principled outcomes.
See Epps, 498 Mich at 528. Remand is necessary only for the trial court to determine an
appropriate maximum width for the pathway under the circumstances of this case so that this
issue can be put to rest, rather than subject to further litigation. See MCR 7.216(A)(7).
V. GUESTS
Defendants also argue that the trial court “erred by ruling that guests of the easement
holders have the right to utilize the easement.” We disagree. Contrary to defendants’ statement
in their questions presented, the trial court did not explicitly rule on the guest issue, but, instead,
found that this issue was addressed by the 1991 order and that further findings would be
redundant. Nevertheless, we conclude that the trial court did not err in concluding that the 1991
order was dispositive on the issue of guests and implicitly rejecting defendants’ claim that
plaintiffs had violated the 1959 easement agreements and 1991 order by allowing guests to
utilize the easement.
“The scope of an easement [should] encompass[] only those burdens on the servient
estate that were contemplated by the parties at the time the easement was created.” Wiggins, 291
Mich App at 551-552 (quotation marks and citations omitted). When easement rights are
conveyed by grant, an easement can be altered if the parties mutually agree to the modification.
See Blackhawk Dev Corp, 473 Mich at 46 (“Where the rights to an easement are conveyed by
grant, neither party can alter the easement without the other party’s consent.”); Douglas v
Jordan, 232 Mich 283, 287; 205 NW 52 (1925).
We agree with the parties and the trial court that the language of the 1959 easement
agreements and the language of the 1991 stipulated order are unambiguous. See Coates v
Bastian Bros, Inc, 276 Mich App 498, 503-504; 741 NW2d 539 (2007) (“A contract is
-10-
ambiguous when two provisions irreconcilably conflict with each other, or when [a term] is
equally susceptible to more than a single meaning.”); Port Huron Ed Ass'n, MEA/NEA v Port
Huron Area Sch Dist, 452 Mich 309, 323; 550 NW2d 228 (1996) (indicating that contract
language is ambiguous when it is “unclear or susceptible to multiple meanings”). Thus, the plain
language of the documents must be enforced as written. Wiggins, 291 Mich App at 551-552.
The 1959 easement agreements did not expressly discuss the issue of guests. Rather, as
defendants repeatedly emphasize, the only language that could be construed as suggesting
whether guests are permitted to use the easement pursuant to that document is the statement that
the easement was “grant[ed] unto the grantees, . . . and to subsequent owners of [the specific
lots] or occupiers of [the specific lots] as tenants in possession, only. . . . .”
As the trial court recognized, it is clear from the language of the 1991 order
memorializing the stipulated agreement between the parties that the parties clarified—and, in the
process, altered—their respective rights under the easement by adding specific terms and
conditions that were not included in the original easement agreements. Most relevant to this
issue, the order clarifies that “in 1959 easements were granted across . . . Outlot A . . . for the
benefit of lots 1, 3, 5, 9, 11, 12 . . . .” As such, based on the plain language of the stipulated
agreement and order, the easements were granted for the benefit of particular lots, not particular
individuals who fulfilled particular classifications of ownership or rights of possession.
Additionally, the order also states, “IT IS FURTHER ORDERED that each individual
easement holder shall provide all children utilizing the easement through them with such care
and supervision as is appropriate for their age and maturity.” (Emphasis added.) The
emphasized language in this provision clearly assumes that individuals other than the easement
holders themselves may use the easement “through” the easement holders, meaning they may use
the easement “by means of,” “by the agency of,” or “because of” an easement holder, not in their
own right. See Merriam-Webster’s Collegiate Dictionary (11th edition) (defining “through”).
There are no other provisions in the 1991 order that indicate the contrary, or that apply to this
issue.
To counter this understanding of the 1991 order, defendants argue that “children can be
owners or occupiers of benefited parcels.” However, this mere possibility does not make less
significant the specific language indicating that children may “utiliz[e] the property through” an
individual easement holder. (Emphasis added.)
Accordingly, to the extent that defendants claim that the 1959 easement agreements
specifically prohibited non-easement holders (i.e., anyone who was not a grantee, subsequent
owner, or occupier who specifically constituted a tenant in possession) from using the easements,
it is clear that this limitation or understanding was altered by the language of the 1991
agreement. The 1991 order specifically states that only the provisions of the 1959 easement
agreements that are “not inconsistent” with the 1991 order “shall remain in full force and effect.”
Defendants’ position, based on the 1959 easement agreements, is irreconcilable with the
language in the 1991 order, and the trial court correctly determined that the guest issue was
addressed, albeit minimally, by the 1991 order.
In sum, even if we assume, arguendo, that the quoted language from the 1959 easement
agreements underscored by defendants precludes guests from utilizing the easement, the plain
-11-
language of the 1991 stipulated order clearly contemplates that individuals other than the
grantees, subsequent owners, or “occupiers . . . as tenants in possession” of the lots benefitted by
the easement may use the property “through” the easement holders. Accordingly, even though
neither the 1959 easement agreements nor the 1991 order expressly allow guests to use the
easements, it is clear that the parties, in conjunction with the 1991 order, specifically envisioned
use of the easement by individuals not named as easement holders. To the extent that the 1959
easement agreements contemplated otherwise, the 1991 stipulated order properly altered
easement agreements, as the parties negotiated the settlement agreement and stipulated to the
trial court’s entry of the order memorializing the agreed-upon terms. See Blackhawk Dev Corp,
473 Mich at 46; Douglas, 232 Mich at 287.
Thus, the trial court did not clearly err in concluding that the 1991 order indicated
whether guests are allowed to use the easement and implicitly finding that defendants are not
entitled to relief based on their claim that plaintiffs violated the easement agreements and 1991
order by allowing guests to use the easement.
VI. DIRECTION OF BOAT PARKING
Defendants next contend that the trial court erroneously concluded that plaintiffs could
park their boats due east in order to comply with the 1991 order, and that it erroneously declined
to modify the 1991 order. We disagree.
In relevant part, the 1991 order provides:
IT IS FURTHER ORDERED that easement holders shall moor their boats on
the western side of their dock facing in an easterly direction with the first boat
being moored at the northern most end of the western side of the dock with the
remainder of the easement holders boats being placed in the same manner along
the western side of the dock immediately to the south of the first boat.
As the trial court concluded, the 1991 order is unambiguous. “Easterly” is defined as
“situated toward or belonging to the east.” Merriam-Webster’s Collegiate Dictionary (11 ed).
As such, it is apparent that “easterly” necessarily encompasses “due east.”7 There is absolutely
no indication in the definition of “easterly” that an object facing directly east would be excluded
from the common meaning of “easterly.” Defendants’ claim attempts to draw a distinction
where none exists and, therefore, has no merit.
Nonetheless, defendants highlight defendant Joseph’s trial testimony indicating that he
did not realize, when he entered into the agreement giving rise to the 1991 order, that plaintiffs
would be authorized to park their boats due east so that their “boats would be sticking out across
his lakeview.” Rather, defendants contend that defendant Joseph believed that the boats would
7
The caselaw cited in defendants’ brief on appeal does not hold otherwise. See Ortynski v
Grand Trunk W R Co, 307 Mich 61, 63; 11 NW2d 326 (1943); Fors v La Freniere, 284 Mich 5,
8; 278 NW 743 (1938).
-12-
be parked parallel to the dock, which defendants characterize as “in an easterly direction,” like
other boats on the lake. Defendants also note defendant Joseph’s trial testimony that plaintiffs’
mooring of the boats due east makes it difficult or impossible for defendants to utilize their own
boat and dock. This Court should not consider this extrinsic evidence in interpreting the 1991
order memorializing the parties’ stipulated agreement, which clarified the 1959 easement
agreements. “Only where the language in the granting instrument is ambiguous may this Court
examine evidence extrinsic to the document to determine the meaning within it,” Blackhawk Dev
Corp, 473 Mich at 42; see also Little, 468 Mich at 700, and, again, the parties as well as the trial
court agree that the language is unambiguous. See also Dyball v Lennox, 260 Mich App 698,
703-704; 680 NW2d 522 (2004) (explaining that it is inappropriate for a trial court to consider
“the circumstances existing at the time [an] easement was granted” if the language of the
easement is unambiguous).
In the alternative, defendants argue that the trial court “should still have modified the
parking arrangement, either to better conform to the term ‘easterly’ in the 1991 Order, and/or in
order to keep the peace.” For the reasons already discussed, the current parking arrangement is
consistent with the word “easterly.” As such, it would be nonsensical for the trial court to alter
the parking arrangement in order to make the parking situation “better conform” to the 1991
order. Moreover, defendants have cited no authority that trial courts are required to modify
easements “in order to keep the peace,” and Michigan caselaw undermines defendants’ claim.
See Little, 468 Mich at 700 (“Where the language of a legal instrument is plain and
unambiguous, it is to be enforced as written and no further inquiry is permitted.”). The 1991
order is unambiguous, and the trial court was constrained to enforce it as written.
VII. ADDITIONAL CLAIMS RAISED IN THE TRIAL COURT
Defendants argue that reversal or remand is required based on the trial court’s failure to
enter an injunction—or, at a minimum, make factual findings—regarding several of plaintiffs’
alleged violations of the 1959 easement agreements and 1991 stipulated order that defendants
raised in the trial court. We disagree.
A. STANDARD OF REVIEW
In addition to the standard of review described supra, “[f]ollowing a bench trial, we
review for clear error the trial court’s factual findings and review de novo its conclusions of
law.” Ligon v City of Detroit, 276 Mich App 120, 124; 739 NW2d 900 (2007). See also MCR
2.613(C). Because the purpose of the requirement that a trial court must articulate its factual
findings is to facilitate appellate review, People v Johnson, 208 Mich App 137, 141-142; 526
NW2d 617 (1994), this Court reviews the adequacy of the trial court’s findings of fact and
conclusions of law to determine whether the court was aware of the issues in the case, whether it
correctly applied the law, and whether appellate review would be facilitated by requiring further
explanation. Triple E Produce Corp v Mastronardi Produce Ltd, 209 Mich App 165, 176; 530
NW2d 772 (1995).
B. ANALYSIS
-13-
“A trial court sitting without a jury must make specific findings of fact, state its
conclusions of law separately, and direct entry of the appropriate judgment. MCR 2.517(A)(1).”
Triple E Produce Corp, 209 Mich App at 176. “Findings of fact regarding matters contested at a
bench trial are sufficient if they are “[b]rief, definite, and pertinent,” and it appears that the trial
court was aware of the issues in the case and correctly applied the law, and where appellate
review would not be facilitated by requiring further explanation. Id. at 176-177, citing MCR
2.517(A)(2), and People v Porter, 169 Mich App 190, 194; 425 NW2d 514 (1988).
Given the context of this case and the findings and ruling delineated in the trial court’s
November 21, 2014 opinion and order, the trial court’s factual findings were sufficient in this
case, and remand is unnecessary. See People v Rushlow, 179 Mich App 172, 177; 445 NW2d
222 (1989) (“The sufficiency of factual findings cannot be judged on their face alone; the
findings must be reviewed in the context of the specific legal and factual issues raised by the
parties and the evidence.”), aff’d 437 Mich 149 (1991). The trial court specifically recognized
that “[b]oth sides seek injunctive relief based upon their facts, the law[] (Defendant raised the
Funneling Ordinance), the original easement of 1959, and the 1991 Order.” It then omitted any
factual findings supporting injunctive relief in favor of defendants. Accordingly, given its
express recognition of defendants’ request for relief, it is clear that the trial court implicitly
rejected defendants’ claims by concluding that it was unnecessary to specifically enjoin any of
plaintiffs’ conduct.
Further, as defendants emphasize on appeal, all of plaintiffs’ purported violations were
expressly or implicitly addressed by the language of the 1959 easement agreements and the 1991
order, which established the scope of plaintiffs’ rights under the easement. Moreover, it is
apparent from the trial transcripts that nearly all of the violations raised in defendants’ counter-
petition and contested by defendants at trial concerned specific incidents that had ceased before
the trial began and, in many cases, occurred years before the petitions at issue in this appeal were
filed. Accordingly, when the trial court held, “[I]n all other respects, the Orders and Agreements
between the Plaintiffs and Defendants remain in full force and effect,” it implicitly—and
properly—held that plaintiffs remain bound by the terms of the documents governing the parties’
rights with regard to the easement and that plaintiffs must abide by the requirements of those
documents in the future. See Blackhawk Dev Corp, 473 Mich at 41. As the trial court
concluded, it would have been redundant to enter an injunction in addition to its holding that the
easement agreements and the 1991 order otherwise remained in effect.
Accordingly, the trial court’s factual findings and conclusions of law were sufficient in
this case, as it is apparent from the language of the trial court’s November 21, 2014 order that
“the trial court was aware of the issues in the case and correctly applied the law,” and that
“appellate review would not be facilitated by requiring further explanation.” Triple E Produce
Corp, 209 Mich App at 176-177. And, for the same reasons previously discussed, the trial court
did not abuse its discretion when it failed to separately enjoin each of alleged violations of the
1959 easement agreements and 1991 stipulated order raised by defendants below.
VIII. VIOLATION OF ZONING ORDINANCE
-14-
Lastly, defendants argue that the trial court erred when it failed to invalidate some or all
of the 1991 order based on the anti-“funneling” provision of the Cambridge Township Zoning
Ordinance. We disagree.
A. STANDARD OF REVIEW
This Court reviews de novo the interpretation and application of ordinances, City of
Riverview v Sibley Limestone, 270 Mich App 627, 630; 716 NW2d 615 (2006), the proper
interpretation of a court order, see Cardinal Mooney High School v Michigan High School
Athletic Ass’n, 437 Mich 75, 80; 467 NW2d 21 (1991); Silberstein v Pro-Golf of Am, Inc, 278
Mich App 446, 460; 750 NW2d 615 (2008), and issues of law generally, see Oakland Co Bd of C
Rd Comm’rs v Mich Prop & Cas Guaranty Ass'n, 456 Mich 590, 610; 575 NW2d 751 (1998).
B. ANALYSIS
The Cambridge Township Zoning Ordinance prohibits “funneling,” as defined in § 2.2.57
of the ordinance, unless certain restrictions are followed. Cambridge Township Zoning
Ordinance, § 5.21. It appears that the plaintiffs’ use of the easement constitutes “funneling”
under the zoning ordinance, and that Outlot A does not comply with the restrictions under § 5.21.
See Cambridge Township Zoning Ordinance, §§ 2.2.57, 5.21. However, the underlying use of
Outlot A for “funnelling” did not change in conjunction with the 1991 order. Thus, the use of
Outlot A for “funnelling” purposes constituted a valid nonconforming use after the anti-
“funnelling” section was enacted in July 1989. See Cambridge Township Zoning Ordinance, §
5.7. See also MCL 125.3208(1); Edw C Levy Co v Marine City Zoning Bd of Appeals, 293 Mich
App 333, 341-342; 810 NW2d 621 (2011).
Defendants’ claim is solely based on purported “expansions” of plaintiffs’ use of the
easement under the 1991 order that violated of the nonconforming use provisions of the zoning
ordinance, which prohibit the expansion of an existing nonconforming use. See Cambridge
Township Zoning Ordinance, § 5.7 (including multiple references to the principle that
nonconforming uses shall not be enlarged, expanded, or expanded). Thus, the crux of
defendants’ claim is that the trial court erred in failing to amend the 1991 order or enjoin any
conduct pursuant to the 1991 order which constitutes an expansion of plaintiffs’ rights under the
1959 easement agreements.
It appears that defendants would have standing to bring a claim seeking relief based on a
violation of the zoning ordinance.8 Likewise, Michigan courts have recognized that neighboring
property owners may bring an equitable cause of action in order to enforce compliance with a
zoning regulation.9 However, consistent with plaintiffs’ arguments on appeal that defendants are
8
See Bowie v Arder, 441 Mich 23, 42-43; 490 NW2d 568 (1992); Towne v Harr, 185 Mich App
230, 232; 460 NW2d 596 (1990).
9
See, e.g., Cook v Bandeen, 356 Mich 328, 330-334; 96 NW2d 743 (1959); Jones v De Vries,
326 Mich 126, 128-135, 139; 40 NW2d 317 (1949); Baura v Thomasma, 321 Mich 139, 142-
-15-
not entitled to raise this claim given their previous agreement to the 1991 order, it is well
established that this Court will not allow a party to benefit from a claim of error arising from
conduct that the aggrieved party contributed to by plan or negligence. Lewis v LeGrow, 258
Mich App 175, 210; 670 NW2d 675 (2003). It is apparent that defendants seek to benefit from
full or partial reversal of the 1991 stipulated order, in which defendants fully participated and to
which defendants unequivocally agreed. If the zoning ordinance was, in fact, violated by the
1991 stipulated order, defendants were active participants in that violation, and they should not
benefit now from their prior unlawful actions. On this basis, the trial court did not err in
declining to grant defendants’ relief and failing to reverse any portion of the 1991 stipulated
order.
Further, it also appears that defendants’ claim is barred by the equitable doctrine of
judicial estoppel, “which generally prevents a party from prevailing in one phase of a case on an
argument and then relying on a contradictory argument to prevail in another phase.” Spohn v
Van Dyke Pub Sch, 296 Mich App 470, 479; 822 NW2d 239 (2012) (quotation marks and
citations omitted). See also Opland v Kiesgan, 234 Mich App 352, 362-365; 594 NW2d 505
(1999) (explaining the equitable doctrine of judicial estoppel in detail, including the “prior
success” model adopted in Michigan).
Here, there is a danger of inconsistent rulings, given defendants’ specific advancement
of, and agreement to, the stipulated 1991 order in the previous proceeding involving the exact
same easement, and many of the same issues, contested in the instant appeal. See id. at 365
(stating that the focus of the “prior success” model is “the danger of inconsistent rulings”).
Likewise, given the fact that defendants stipulated to the earlier order, they are effectively
attempting to invoke the authority of a later trial court to override a bargain that they made with
an earlier court presiding over the same case. See id. (“The prior success rule limits the
application of judicial estoppel to a situation where a party attempts to invoke the authority of a
second tribunal to override a bargain made with a prior tribunal.”). Additionally, given the trial
court’s entry of the stipulated order, it is clear that the trial court accepted the fact that defendants
actually agreed to the terms of the 1991 order as true, and defendants’ current position that the
order is invalid is wholly inconsistent with their earlier position that the 1991 stipulated order
was appropriate. See id. at 362 (stating that under the “prior success” model, “there must be
some indication that the court in the earlier proceeding accepted that party’s position as true”).
See also Szyszlo v Akowitz, 296 Mich App 40, 51; 818 NW2d 424 (2012). Accordingly, we
conclude that defendants are judicially estopped from claiming that the trial court’s entry of all
or part of the 1991 order was in error, such that the trial court did not err in declining to grant
their requested relief.
Even if defendants were entitled to seek relief on this claim, we conclude that their claim
lacks merit. Defendants argue that the 1991 order is wholly or partially unenforceable based on
the rule that agreements that violate the law are void. “Contracts founded on acts prohibited by a
statute, or contracts in violation of public policy, are void.” Michelson v Voison, 254 Mich App
691, 694; 658 NW2d 188 (2003). See also Am Trust Co v Michigan Trust Co, 263 Mich 337,
143, 146; 32 NW2d 369 (1948); Indian Village Ass'n v Shreve, 52 Mich App 35, 38; 216 NW2d
447 (1974).
-16-
340; 248 NW 829 (1933) (“The general rule of law is that a contract made in violation of a
statute is void, and that, when a plaintiff cannot establish his cause of action without relying
upon an illegal contract, he cannot recover.”) (quotation marks and citation omitted).10
Likewise, if a “statute precludes entering into an agreement providing exactly what the
[disputed] clause states . . . the clause is void and unenforceable as a matter of law.” Mino v Clio
School Dist, 255 Mich App 60, 71; 661 NW2d 586 (2003).11 Thus, the critical inquiry is
whether an illegal provision is “central to the parties’ agreement.” See Stokes v Millen Roofing
Co, 466 Mich 660, 666; 649 NW2d 371 (2002). There are exceptions to the rule that a contract
is void if it is based on illegal conduct, including if the parties were ignorant of the illegal nature,
if it is a matter of slight illegality, if it involves an unessential legal provision, or if the illegal
portion can be severed from the rest of the contract. See Kukla v Perry, 361 Mich 311, 323; 105
NW2d 176 (1960).
As previously discussed, the underlying use of Outlot A for “funneling” did not change in
conjunction with the 1991 order. As such, the underlying activity regulated by the 1991 order,
which constituted the fundamental or “central” portion of the settlement agreement and
stipulated order, was not illegal. See Kukla, 361 Mich at 323; Michelson, 254 Mich App at 694;
Mino, 255 Mich App at 71; Stokes, 466 Mich at 666. Further, although, as the trial court
recognized, the 1991 order altered the 1959 easement agreements “as to the walkway and to the
maintenance of boats on Wampler’s Lake” by establishing specific limitations or restrictions
applicable to those activities and plaintiffs’ overall use of the easement, there is no indication
that these additional specifications increased the use or materially changed the location of the
use. Therefore, contrary to defendants’ characterization of the 1991 order, there is no indication
in its plain language that the parties intended to expand the easement through the 1991 order.
See Wiggins, 291 Mich App at 551-552 (explaining that easements are interpreted like contracts,
and that the plain language of contracts and easements, if clear, must be enforced as written).
Likewise, there is no indication in the language of the 1991 stipulated order that the parties
created new rights under the order. Instead, all of the provisions in the order appear to specify
particular restrictions or limitations on activities already performed by both parties. See id. As
such, there is nothing dispositive in the 1991 stipulated order that the “funnelling” uses of the
easement were expanded after the ordinance section prohibiting “funnelling” was enacted.
Notably, defendants have failed to identify any specific language in the 1991 order that
10
Settlement agreements are contracts, constituting “a compromise of a disputed claim,” and
they are “governed by the legal rules applicable to the construction and interpretation of other
contracts.” Reicher v SET Enterprises, Inc, 283 Mich App 657, 663; 770 NW2d 902 (2009).
See also MacInnes v MacInnes, 260 Mich App 280, 289-290; 677 NW2d 889 (2004). Courts
will enforce contracts, including settlement agreements, as written unless they violate law or
public policy. See Reicher, 283 Mich App at 663; Bloomfield Estates Improvement Ass’n Inc v
City of Birmingham, 479 Mich 206, 212; 737 NW2d 670 (2007).
11
Ordinances have the same effect as statutes. Gale v Bd of Sup'rs of Oakland Co, 260 Mich
399, 404; 245 NW 363 (1932).
-17-
specifically expanded plaintiffs’ rights and, instead, mention blanket categories of rights that
were allegedly expanded without providing any citations to the order.
There is no basis for concluding that the 1991 order is invalid based on the Cambridge
Township Zoning Ordinance. The trial court did not err in declining defendants’ request for
relief based on the “funnelling” ordinance.
IX. CONCLUSION
Defendants have failed to establish that any of their claims warrant relief, except to the
extent that they have demonstrated that remand is necessary for the trial court to establish a
maximum width for the constructed pathway. Therefore, we affirm the trial court’s opinions and
orders, but remand this case for that limited purpose. The court shall have 60 days to supplement
its opinion on remand and transmit a copy of its supplemental order to this Court. See MCR
7.216(A)(7). On remand, the trial court may make its finding regarding the maximum width of
the pathway on the existing record, or it may take additional testimony if the court deems it
necessary.
Affirmed, but remanded for further proceedings consistent with this opinion. We retain
jurisdiction.
/s/ Kathleen Jansen
/s/ William B. Murphy
/s/ Michael J. Riordan
-18-
Court of Appeals, State of Michigan
ORDER
Kathleen Jansen
Linda S. Manley v Sue Pikulski Presiding Judge
Docket No. 327510 William B. Murphy
LC No. 89-004109-CH Michael J. Riordan
Judges
Pursuant to the opinion issued concurrently with this order, this case is REMANDED for
further proceedings consistent with the opinion of this Court. We retain jurisdiction.
The trial court shall have 60 days from the date of the Clerk's certification of this order to
supplement its opinion on remand and transmit a copy of its supplemental order to this Court. See MCR
7.216(A)(7). The supplemental order shall be limited to establishing a maximum width for the
constructed pathway. The trial court may make its finding on the existing record, or it may take
additional testimony if the court deems it necessary.
We retain jurisdiction.
A true copy entered and certified by Jerome W. Zimmer Jr., Chief Clerk, on
DEC 0 o 2016
Date