FILED
2016 IL App (4th) 160199 December 20, 2016
Carla Bender
NO. 4-16-0199 4th District Appellate
Court, IL
IN THE APPELLATE COURT
OF ILLINOIS
FOURTH DISTRICT
SARA J. FOSTER, Surviving Widow of John C. Foster, Appeal from
Deceased; and JACOB C. FOSTER, NICHOLAS C. Circuit Court of
FOSTER, CODY J. FOSTER, CHAD L. FOSTER, and McLean County
IAN A. FOSTER, by Sara J. Foster, Their Mother and No. 15MR429
Guardian,
Petitioners-Appellees,
v. Honorable
MITSUBISHI MOTORS NORTH AMERICA, INC., Paul G. Lawrence,
Respondent-Appellant. Judge Presiding
____________________________________________________________
JUSTICE POPE delivered the judgment of the court, with opinion.
Presiding Justice Knecht and Justice Holder White concurred in the judgment and
opinion.
OPINION
¶1 Defendant, Mitsubishi Motors North America, Inc. (Mitsubishi) appeals the
judgment of the trial court in favor of plaintiffs, Sara J. Foster, surviving widow of John C.
Foster, and Jacob C. Foster, Nicholas C. Foster, Cody J. Foster, Chad L. Foster, and Ian A.
Foster by Sara J. Foster, their mother and guardian (collectively hereinafter Sara), to enforce an
arbitration award of death benefits pursuant to section 19(g) of the Workers’ Compensation Act
(Compensation Act) (820 ILCS 305/19(g) (West 2012)).
¶2 On appeal, Mitsubishi argues (1) Sara’s petition to enforce the 2004 award should
have been dismissed because it was barred by the statute of limitations. In the alternative,
Mitsubishi contends (2) the judgment should be limited to the maximum allowable death benefit
recoverable in 2004, i.e., $1012.01 per week, and (3) any interest should be calculated from the
date of the trial court’s judgment and not from the date of the arbitration award. We affirm.
¶3 I. BACKGROUND
¶4 On October 23, 2003, John C. Foster died from injuries sustained during the course
of his employment with Mitsubishi. John was survived by his spouse, Sara, and five dependent
children.
¶5 On January 12, 2004, an arbitrator awarded Sara $1304.78 per week in death
benefits. Thereafter, the Workers’ Compensation Commission (Commission) approved and
adopted the arbitrator’s decision, and Mitsubishi began making payments. Pursuant to the
Compensation Act, death benefit awards are subject to a maximum rate. See 820 ILCS 305/7,
8(b) (West 2004). At the time of the arbitrator’s decision, the statutory maximum death benefit
rate was $1012.01 per week. See Illinois Workers’ Compensation Benefit Rates January 15,
2000, through January 14, 2005, http://www.iwcc.il.gov/RATES00-05.htm (last visited
December 7, 2016). While the parties agree this was the maximum rate in 2004, neither party
sought to correct or appeal the Commission’s award at the time it issued. Mitsubishi paid Sara
$2024.02 every two weeks, i.e., $1012.01 per week.
¶6 On May 26, 2015, Sara filed an application for judgment pursuant to section 19(g)
of the Compensation Act (820 ILCS 305/19(g) (West 2012)) seeking to enforce the 2004 award
of $1304.78 per week. Sara also argued under section 2-1303 of the Code of Civil Procedure
(Procedure Code) (735 ILCS 5/2-1303 (West 2012)) she was entitled to 9% interest on the
balance of the unpaid amounts dating back to the entry of the 2004 award.
¶7 On June 2, 2015, Mitsubishi filed a motion to dismiss Sara’s application, arguing
-2
her section 19(g) claim was barred by the five-year statute of limitations found in section 13-205
of the Procedure Code (735 ILCS 5/13-205 (West 2012)). In the alternative, Mitsubishi argued
any enforcement of the award should be limited to $1012.01, i.e., the maximum statutory amount
recoverable in 2004, because an award in excess of the statutory maximum is void and violates
public policy. Mitsubishi also maintained any interest Sara would be entitled to could only be
recovered pursuant to section 19(n) of the Compensation Act (820 ILCS 305/19(n) (West 2012)),
which provides a lower interest rate, because section 2-1303 interest applies only to a trial
court’s judgment and not a decision by the Commission.
¶8 On October 16, 2015, the trial court entered a preliminary order in favor of Sara in
the amount of $101,420.98. The court found the statute of limitations barred any claimed
deficiency of benefits paid to Sara prior to May 26, 2010, i.e., five years prior to the filing of her
application. However, the court found the statute of limitations did not bar Sara’s claim with
respect to benefits due on or after that date. The court also found the $1304.78 weekly arbitration
award was not void and did not violate public policy. The court reasoned Mitsubishi’s $1012.01
weekly payments created a weekly deficiency of $292.77. The court then calculated the
deficiency period beginning on May 26, 2010, and running through September 30, 2015, i.e., 279
weeks. As a result, the total arrearage was calculated to be $81,682.83. The court, citing section
2-1303, also found Sara was entitled to an additional 9% interest on the deficient payments
through September 30, 2015, for a total of $19,738.15. The court further found all future benefits
from October 1, 2015, on were to be paid at the $1304.78 per week rate. Finally, the court noted
its order was not final and appealable because it was reserving the issue of attorney fees and
costs for a later determination.
-3
¶9 On March 3, 2016, the trial court entered a second written order incorporating its
October 2015 ruling and disposing of the remaining issues, thus making it final for purposes of
appeal.
¶ 10 This appeal followed.
¶ 11 II. ANALYSIS
¶ 12 On appeal, Mitsubishi argues (1) Sara’s petition to enforce the 2004 award should
have been dismissed because it was barred by the statute of limitations. In the alternative,
Mitsubishi contends (2) the judgment should be limited to the maximum allowable death benefit
recoverable in 2004, i.e., $1012.01 per week, and (3) any interest should be calculated from the
date of the trial court’s judgment and not from the date of the arbitration award.
¶ 13 A. Statute of Limitations
¶ 14 Mitsubishi argues the trial court erred by failing to dismiss Sara’s section 19(g)
petition entirely because it was barred by the applicable five-year statute of limitations found in
section 13-205 of the Procedure Code (735 ILCS 5/13-205 (West 2012)).
¶ 15 Section 13-205 provides the following:
“[A]ctions on unwritten contracts, expressed or implied, or on awards
of arbitration, or to recover damages for an injury done to property,
real or personal, or to recover the possession of personal property or
damages for the detention or conversion thereof, and all civil actions
not otherwise provided for, shall be commenced within 5 years next
after the cause of action accrued.” 735 ILCS 5/13-205 (West 2012).
¶ 16 According to Mitsubishi, the arbitration decision, which was rendered on January
-4
12, 2004, became final 30 days later on February 11, 2004, when neither party filed for review.
See 820 ILCS 305/19(b) (West 2004). Five years from that date was February 11, 2009.
Mitsubishi contends Sara’s entire application, filed on May 26, 2015, should therefore have been
dismissed by the trial court as untimely. We disagree.
¶ 17 “Generally, statutes of limitations begin to run from, and not until, the time the
cause of action accrued.” In re Marriage of Kramer, 253 Ill. App. 3d 923, 928, 625 N.E.2d 808,
812 (1993). Here, however, Mitsubishi’s obligation to Sara was payable in installments. “Where
a money obligation is payable in installments, a separate cause of action accrues on, and the
statute of limitations begins to run against, each installment as it becomes due.” Kramer, 253 Ill.
App. 3d at 928, 625 N.E.2d at 812 (citing Light v. Light, 12 Ill. 2d 502, 506, 147 N.E.2d 34, 37
(1957) (“We have long since held, however, that in the case of a judgment for the payment of
money in periodic installments a right of action accrues on each installment as it becomes due,
and that the period of limitations runs on each installment only from the time it becomes due.”);
Thread & Gage Co. v. Kucinski, 116 Ill. App. 3d 178, 184, 451 N.E.2d 1292, 1296 (1983) (“a
separate cause of action arises on each installment and the statute of limitations begins to run
against each installment as it becomes due”)); see also C-B Realty & Trading Corp. v. Chicago
& North Western Ry. Co., 289 Ill. App. 3d 892, 897, 682 N.E.2d 1136, 1140 (1997)
(“Obligations payable in installments run separate statutes of limitation against each installment
at the time it becomes due.” (citing Luminall Paints, Inc. v. La Salle National Bank, 220 Ill. App.
3d 796, 802, 581 N.E.2d 191, 194 (1991))). “ ‘[B]ecause each breach of a continuous duty has its
own accrual date, a plaintiff may sue on any breach which occurred within the limitation’s
period, even if earlier breaches occurred outside the limitation period. [Citations.]’ ” C-B Realty,
-5
289 Ill. App. 3d at 897, 682 N.E.2d at 1140 (quoting Hi-Lite Products Co. v. American Home
Products Corp., 11 F.3d 1402, 1409 (7th Cir. 1993)).
¶ 18 In this case, the trial court applied the statute of limitations to bar Sara’s claim
regarding deficient payments occurring prior to May 26, 2010, i.e., five years prior to the date
Sara filed her application to enforce the arbitration award. Because Mitsubishi’s obligation to
Sara was payable in installments, each of its deficient payments constituted a new cause of action
with its own independent statute of limitations. As a result, the court did not err in applying the
statute of limitations to bar just those claims relating to deficient payments occurring prior to
May 26, 2010. Mitsubishi’s argument the five-year limitation period should bar all of Sara’s
claims fails.
¶ 19 B. The Arbitration Award
¶ 20 In the alternative, Mitsubishi argues any enforcement of the arbitration award
should be limited to $1012.01, i.e., the maximum statutory weekly amount recoverable in 2004.
Mitsubishi contends because the $1304.78 award was in excess of the statutorily permitted
maximum weekly amount, it was void and violated public policy.
¶ 21 Section 19(g) of the Compensation Act provides a claimant with a statutory remedy
to reduce an award of benefits to an enforceable judgment in the trial court when an employer
fails to pay a final award. Estate of Burns v. Consolidation Coal Co., 2015 IL App (5th) 140503,
¶ 17, 35 N.E.3d 236. Section 19(g) confers authority on the trial court to render a judgment in
accordance with an award of the Commission when a certified copy of the decision is presented
to the court. Dallas v. Ameren CIPS, 402 Ill. App. 3d 307, 311, 929 N.E.2d 1267, 1271 (2010)
(citing Ahlers v. Sears, Roebuck Co., 73 Ill. 2d 259, 264, 383 N.E.2d 207, 209 (1978)). Section
-6
19(g) provides, in relevant part, the following:
“Except in the case of a claim against the State of Illinois, either
party may present a certified copy of the award of the Arbitrator, or a
certified copy of the decision of the Commission when the same has
become final, when no proceedings for review are pending, providing
for the payment of compensation according to this Act, to the Circuit
Court of the county in which such accident occurred or either of the
parties are residents, whereupon the court shall enter a judgment in
accordance therewith.” (Emphasis added.) 820 ILCS 305/19(g)
(West 2012).
¶ 22 Section 19(g) is “designed to permit speedy entry of judgment on an award.”
Aurora East School District v. Dover, 363 Ill. App. 3d 1048, 1055, 846 N.E.2d 623, 629 (2006).
Section 19(g) provides for a collateral proceeding designed for the entry of judgment, and a party
should not be allowed to use it to relitigate the Commission’s decision. Franz v. McHenry
County College, 222 Ill. App. 3d 1002, 1007-08, 584 N.E.2d 536, 540 (1991). As a result, the
trial court’s inquiry was limited to whether the requirements of section 19(g) have been met.
Ahlers, 73 Ill. 2d at 268, 383 N.E.2d at 211. “The court cannot question the jurisdiction of the
Commission, question the legality of the Commission’s actions, review the Commission’s
decision, or ‘otherwise construe the Act, even if the decision appears too large on its face.’ ”
Dallas, 402 Ill. App. 3d at 312, 929 N.E.2d at 1272 (quoting Aurora East School District, 363
Ill. App. 3d at 1055, 846 N.E.2d at 629); see also Ahlers, 73 Ill. 2d at 268, 383 N.E.2d at 211 (the
court can refuse to “enter judgment only, for example, when a lack of jurisdiction appears on the
-7
face of the record”). “[A]bsent fraud or lack of jurisdiction, a party may not obtain review of the
Commission’s award in the course of a section 19(g) proceeding.” Konczak v. Johnson
Outboards, 108 Ill. App. 3d 513, 517, 439 N.E.2d 16, 19 (1982).
¶ 23 Here, Mitsubishi does not argue the requirements of section 19(g) have not been
met. Indeed, Sara properly submitted a certified copy of the Commission’s decision to the trial
court satisfying section 19(g)’s statutory requirements. Instead, Mitsubishi contends the award
was too large. Such an argument is not appropriately raised in a section 19(g) proceeding as a
party may not contest the validity of the Commission’s award in that context. See Aurora East
School District, 363 Ill. App. 3d at 1055, 846 N.E.2d at 629; Konczak, 108 Ill. App. 3d at 516
17, 439 N.E.2d at 19 (trial court “may not review the Commission’s decision or otherwise
construe the statute even if the [award] appears too large on its face”); St. Louis Pressed Steel
Co. v. Schorr, 303 Ill. 476, 478, 135 N.E. 766, 767 (1922) (if a certified copy of an award or
decision is properly presented in a section 19(g) proceeding, the trial court must enter judgment
even if the award is too large). In other words, if the strictures of section 19(g) are met, the trial
court must enter judgment on the award without questioning the Commission’s decision, even if
the court disagrees with the Commission’s construction of the law. See Sunrise Assisted Living v.
Banach, 2015 IL App (2d) 140037, ¶ 28, 35 N.E.3d 189 (citing Ahlers, 73 Ill. 2d at 268, 383
N.E.2d at 211).
¶ 24 As part of its argument, Mitsubishi emphasizes it has always made full payments to
Sara. While we agree payment can be raised as a defense to a section 19(g) petition (see Dallas,
402 Ill. App. 3d at 312, 929 N.E.2d at 1272), it is undisputed Mitsubishi has not done so
according to the terms of the arbitration award. Moreover, as this case involves installment
-8
payments, Sara has not yet received full payment of the benefits. While full payment of the final
award is a complete defense to an application for judgment under section 19(g), if anything is
properly due under the final award at the time application for judgment is made, then the trial
court should enter judgment as provided in section 19(g). Voorhees v. Industrial Comm’n, 31 Ill.
2d 330, 332, 201 N.E.2d 382, 383 (1964); see also Aurora East School District, 363 Ill. App. 3d
at 1055, 846 N.E.2d at 630 (the only defense to a section 19(g) petition is full payment of the
final award).
¶ 25 We note Mitsubishi was not without a remedy. Indeed, based on the fact it chose to
begin making payments to Sara of $1012.01 and not $1304.78 demonstrates it was aware of the
inconsistency from the beginning. With that knowledge, Mitsubishi could have moved pursuant
to section 19(f) of the Compensation Act to have the calculation corrected at the time the award
was issued. Section 19(f) provides the following:
“The decision of the Commission acting within its powers *** shall,
in the absence of fraud, be conclusive unless reviewed as in this
paragraph hereinafter provided. However, the Arbitrator or the
Commission may on his or its own motion, or on the motion of either
party, correct any clerical error or errors in computation within 15
days after the date of receipt of any award by such Arbitrator or any
decision on review of the Commission and shall have the power to
recall the original award on arbitration or decision on review, and
issue in lieu thereof such corrected award or decision. Where such
correction is made the time for review herein specified shall begin to
-9
run from the date of the receipt of the corrected award or decision.”
820 ILCS 305/19(f) (West 2012).
¶ 26 Mitsubishi also could have filed a petition pursuant to section 19(b) of the
Compensation Act for review of the award on the ground it exceeded the maximum statutory
amount. Section 19(b) provides, in relevant part, the following:
“The decision of the Arbitrator shall be filed with the
Commission which *** shall immediately send to each party *** a
copy of such decision, together with a notification of the time when it
was filed. *** Unless a petition for review is filed by either party
within 30 days after the receipt by such party of the copy of the
decision and notification of time when filed *** then the decision
shall become the decision of the Commission and in the absence of
fraud shall be conclusive.” 820 ILCS 305/19(b) (West 2012).
¶ 27 Here, however, it is undisputed Mitsubishi neither moved to correct the
computation of the award nor petitioned for its review. As stated, Mitsubishi may not now
contest its validity in the context of the section 19(g) proceeding. See Franz, 222 Ill. App. 3d at
1007, 584 N.E.2d at 539 (“A party cannot sit idly by, permitting an arbitrator’s decision to
become final, and then assert his claim in a collateral proceeding such as this one.”). As a result,
the trial court did not err in finding all future payments should continue to be paid at the
$1304.78 per week rate provided for by the award.
¶ 28 C. Calculation of Interest
¶ 29 The trial court awarded 9% interest pursuant to section 2-1303 of the Procedure
- 10
Code on all amounts due dating back to five years prior to the filing of Sara’s section 19(g)
application.
¶ 30 Section 2-1303 of the Procedure Code provides:
“Judgments recovered in any court shall draw interest at the rate of
9% per annum from the date of the judgment until satisfied ***.
When judgment is entered upon any award, report or verdict, interest
shall be computed at the above rate, from the time when made or
rendered to the time of entering judgment upon the same, and
included in the judgment. Interest shall be computed and charged
only on the unsatisfied portion of the judgment as it exists from time
to time. The judgment debtor may by tender of payment of judgment,
costs and interest accrued to the date of tender, stop the further
accrual of interest on such judgment notwithstanding the prosecution
of an appeal, or other steps to reverse, vacate or modify the
judgment.” 735 ILCS 5/2-1303 (West 2012).
¶ 31 Mitsubishi acknowledges interest is owed on the unpaid portions of the award.
Mitsubishi also states it has no issue with the 9% figure applying to any future outstanding
amounts. However, Mitsubishi disputes the application of section 2-1303 interest to amounts
owed prior to the trial court’s judgment. According to Mitsubishi, section 2-1303 interest is
“judgment” interest, which can only apply to judgments of the trial court and not decisions of the
Commission. Mitsubishi maintains any interest due should instead be recoverable only under
section 19(n) of the Compensation Act.
- 11
¶ 32 Section 19(n) provides, in relevant part, the following:
“After June 30, 1984, decisions of the Illinois Workers’
Compensation Commission reviewing an award of an arbitrator of
the Commission shall draw interest at a rate equal to the yield on
indebtedness issued by the United States Government with a 26-week
maturity next previously auctioned on the day on which the decision
is filed. Said rate of interest shall be set forth in the Arbitrator’s
Decision. Interest shall be drawn from the date of the arbitrator’s
award on all accrued compensation due the employee through the day
prior to the date of payments.” 820 ILCS 305/19(n) (West 2012).
According to the arbitrator’s decision, the section 19(n) interest rate in this case was 0.97%.
¶ 33 The determinative question is whether section 2-1303 interest can reach back and
apply from the date of the arbitrator’s award once a trial court enters judgment on a section 19(g)
application.
¶ 34 We find guidance in this court’s decision in Radosevich v. Industrial Comm’n, 367
Ill. App. 3d 769, 856 N.E.2d 1 (2006). In Radosevich, the claimant applied for a section 19(g)
judgment and argued interest under section 2-1303 should be awarded from the date of the
award. Radosevich, 367 Ill. App. 3d at 777, 305, 856 N.E.2d at 8. We recognized a claimant is
entitled to section 19(n) interest on all awards of arbitrators and decisions of the Commission.
Radosevich, 367 Ill. App. 3d at 777, 856 N.E.2d at 8. Such interest is “ ‘drawn from the date of
the arbitrator’s award on all accrued compensation due the employee through the day prior to the
date of payments.’ ” Radosevich, 367 Ill. App. 3d at 777, 856 N.E.2d at 8 (quoting 820 ILCS
- 12
305/19(n) (West 2004)). However, a claimant is entitled to section 2-1303 interest once the
award is reduced to an enforceable judgment by the trial court. Radosevich, 367 Ill. App. 3d at
778, 856 N.E.2d at 9; Sunrise Assisted Living, 2015 IL App (2d) 140037, ¶ 32, 35 N.E.3d 189
(citing Radosevich approvingly).
¶ 35 With regard to whether section 2-1303 interest could reach back and apply from
the date of the arbitrator’s award, Radosevich stated the following:
“A claimant is entitled to section 2-1303 interest if and when
the arbitrator’s award or Commission’s decision becomes an
enforceable judgment. When an employer fails or refuses to pay a
final award[,] *** a claimant may file a petition pursuant to section
19(g) of the Act to reduce the award to an enforceable judgment in
the circuit court for entry of judgment. [Citation.] Section 2-1303
provides that judgments shall draw interest at the rate of 9% per
annum from the date of judgment, and ‘[w]hen judgment is entered
upon any award, report or verdict, interest shall be computed at the
above rate, from the time when made or rendered to the time of
entering judgment upon the same, and included in the judgment.’
[Citation.] Once a claimant implements section 19(g) of the Act, a
resulting order of the circuit court is an enforceable judgment, and
section 2-1303 interest is properly awarded from the date of the
arbitrator’s award through the date judgment was entered on that
award. In addition, any prospective payments due pursuant to the
- 13
section 19(g) judgment that are untimely shall also be subject to
section 2-1303 interest.” Radosevich, 367 Ill. App. 3d at 778, 856
N.E.2d at 8-9.
¶ 36 Indeed, the following plain language of section 2-1303 supports such an
interpretation: “[w]hen judgment is entered upon any award, report or verdict, interest shall be
computed at the above rate, from the time when made or rendered to the time of entering
judgment upon the same, and included in the judgment.” (Emphasis added.) 735 ILCS 5/2-1303
(West 2012). Thus, prior to the section 19(g) petition, Mitsubishi could have satisfied the
deficiency and owed just the section 19(n) interest rate. See Sunrise Assisted Living, 2015 IL
App (2d) 140037, ¶ 35, 35 N.E.3d 189 (finding section 2-1303 interest was not appropriate
because the employer paid the amount due and section 19(n) interest prior to the section 19(g)
petition being filed). However, “[o]nce a claimant implements section 19(g) of the
[Compensation] Act because the employer has failed to pay, a resulting order of the circuit court
is an enforceable judgment, and section 2-1303 interest is properly awarded from the date of the
arbitrator’s award through the date that judgment was entered on that award.” Sunrise Assisted
Living, 2015 IL App (2d) 140037, ¶ 33, 35 N.E.3d 189.
¶ 37 In this case, Mitsubishi did not seek to correct the award or petition for its review.
Instead, Mitsubishi chose to pay an amount less than what was awarded, which created a
deficiency. That deficient amount was subject to section 19(n) interest up until Sara filed her
section 19(g) application. At that point, section 2-1303 interest applied. Applying the statute of
limitations, as discussed above, results in section 2-1303 interest on the outstanding amounts
beginning five years prior to the date Sara filed her section 19(g) application. Thus, the trial court
- 14
did not err in determining section 2-1303 interest applied to the circumstances of this case.
¶ 38 III. CONCLUSION
¶ 39 For the reasons stated, we affirm the trial court’s judgment.
¶ 40 Affirmed.
- 15