NOT PRECEDENTIAL
UNITED STATES COURT OF APPEALS
FOR THE THIRD CIRCUIT
______________
Nos. 15-1086, 15-1127
______________
LORRAINE SMITH
Appellant in No. 15-1086
v.
SIDNEY KATZ; ALFRED MARSHALL
Sidney Katz, Appellant in No. 15-1127
______________
Appeal from the District Court
of the Virgin Islands
(D.C. No. 3-10-cv-00039)
District Judge: Honorable Curtis V. Gomez
______________
Argued May 17, 2016
Before: FUENTES,* VANASKIE, and RESTREPO, Circuit Judges
(Filed: June 27, 2017)
Rhea R. Lawrence, Esquire [ARGUED]
Lee J. Rohn, Esquire
Lee J. Rohn & Associates
1101 King Street
Christiansted, VI 00820
Counsel for Lorraine Smith
Robert L. King, Esquire [ARGUED]
*
Honorable Julio M. Fuentes assumed senior status on July 18, 2016.
Law Offices of Robert L. King
1212 Bjerge Gade, Suite 102
St. Thomas, VI 00802
Counsel for Sidney Katz
______________
OPINION**
______________
RESTREPO, Circuit Judge
Following a 5-day trial, a jury returned a verdict in this matter on June 18, 2012 in
favor of plaintiff, Lorraine Smith, and against defendant, Sidney Katz, awarding
compensatory damages in the amount of $1,290,000 due to injuries caused by a high
amount of mold spores in the air inside the building which Katz owned and where Smith
worked. The District Court ordered a remittitur of the damages awarded, but Smith
rejected the remittitur and demanded a new trial on damages only. See, e.g., Cortez v.
Trans Union, LLC, 617 F.3d 688, 716 (3d Cir. 2010) (citing Hetzel v. Prince William
Cnty., 523 U.S. 208, 211 (1998) (per curiam)) (“[A] court must afford a plaintiff the
option of a new trial when it attempts to reduce a jury award because it believes the
amount of the verdict is not supported by the evidence.”). Following the second trial on
damages, the jury on October 4, 2013 awarded Smith $55,000 in non-economic damages
and $20,000 in economic damages.
This disposition is not an Opinion of the full Court and, pursuant to I.O.P. 5.7, does not
**
constitute binding precedent.
2
On appeal, Smith claims the District Court erred in remitting the damages awarded
after the first trial, and in the alternative, that the District Court erred in denying her
motion for a new (third) trial on damages after the second trial. On cross-appeal, Katz
requests Judgment in his favor on the ground that the District Court erred in denying his
renewed motion for judgment as a matter of law after the first trial, or in the alternative,
that we should remand the case for a remittitur of the award after the first trial “to an
amount closer to the [$11,000.00] range,” see Katz’s Br. 28, or if we determine that the
second trial was warranted, that we affirm the jury’s award following the second trial on
damages.1 For the reasons explained below, we affirm the District Court’s Order denying
Katz’s motion for judgment as a matter of law and remitting the damages awarded
1
Katz also argues in his brief that the District Court erred in not granting his motion for a
new trial after the first trial. However, Katz clarifies that he “does not request a new
trial,” see Katz’s Br. 72, and his counsel made clear at oral argument that Katz is
requesting a reversal of the District Court’s denial of his motion for judgment as a matter
of law under Rule 50(b), or in the alternative, an affirmance of the District Court’s
verdict after the second trial on damages. He was quite clear at oral argument that he is
neither asking for, nor does he desire, a new trial, but that if we found it necessary to
grant Smith’s request for relief, in the alternative, for a new trial on damages only, then
the new trial should be on both liability and damages, as opposed to a new trial on only
damages. See id. (“Katz does not request a new trial, but if a new trial is ordered for
any reason, Katz requests that the trial be as to both liability and damages . . .”) (emph.
added); see also id. at 9 (Katz’s “Statement of Issues Presented” does not include an issue
as to a request on his part for new trial); id. at 28-29 (“Should this Court decide to not
grant Katz judgment as a matter of law, then, in the alternative, the district court’s
decision to remit was appropriate except that it did not remit enough . . . Katz does not
appeal the grant of the retrial nor the outcome of the retrial.”). Therefore, we understand
Katz’s arguments challenging the denial of his motion for new trial and any arguments he
makes where the appropriate relief would be a new trial, as arguments in the alternative,
should we deny both his request to reverse the denial of his motion as a matter of law and
vacate the Judgment entered following the (second) trial on damages. Since we affirm
the Judgment following the second trial, and Katz “does not request a new trial,” see id.
at 72, it is unnecessary to address his arguments supporting a request for new trial or for
which the appropriate relief would be a new trial.
3
following the first trial, and we affirm the Judgment following the retrial as well as the
District Court’s denial of Smith’s motion for new trial following the retrial.
I. 2
Smith initiated this action against Katz and Alfred Marshall in the Superior Court
of the Virgin Islands, and defendants removed the case to the District Court of the Virgin
Islands on April 18, 2010 based on diversity of citizenship.3 Smith’s Complaint alleged,
among other things, that Marshall and Katz, as lessors, negligently failed to use
reasonable care to protect from a harmful condition and also negligently failed to warn
Smith of this condition.4 According to Smith’s Complaint, she experienced medical
conditions, including exacerbation of pre-existing conditions, caused by a dangerous
condition in the Building, which included mold inside the Building, and that the high
amount of mold was due to the improper construction of the building, and a poor
ventilation system, which failed to properly remove the particulates from the Building.
On June 11, 2012, a jury trial commenced (“first trial”). At that trial, the evidence
indicated that on May 19, 1995, Katz and Marshall, doing business as A & S Realty,
2
We write exclusively for the parties and therefore set forth only those facts that are
necessary to our disposition.
3
On June 15, 2012, on Smith’s motion, all counts against Marshall were dismissed. See
Richards v. Marshall, 2013 WL 4028453, *1 (D. V.I. Aug. 1, 2013).
4
By Order filed May 10, 2010, the District Court granted Katz’s motion to consolidate
this case with Civil Action No. 09-0023, Richards v. Marshall, a case where multiple
plaintiffs sued Katz and Marshall, asserting that the mold spores in the Marshall Building
caused them to suffer various ailments. Following discovery in the consolidated cases,
pursuant to the District Court’s Order filed May 29, 2012, the two cases were tried
separately.
4
entered into a lease agreement with the Government of the Virgin Islands
(“Government”). The Government was leasing the building (“Marshall Building” or
“Building”) in St. Thomas as an office location for the Bureau of Internal Revenue
(“BIR”) of the Virgin Islands.5
Orlando Ramirez testified that he was hired by Katz to oversee a build-out of the
Building for the purpose of creating office space for the BIR. Following Ramirez’s
advice, Katz then hired Wilson Construction Company to help with the build-out, as well
as other contractors to install or renovate the plumbing, electricity, and air conditioning.
During his testimony, Ramirez acknowledged that the build-out did not include
many procedures that should have been followed to protect the structure of the Marshall
Building from water and excess moisture. According to Ramirez’s testimony, under his
agreement with Katz, Ramirez’s responsibilities included, but were not limited to,
overseeing the air conditioning and ductwork installation.
Sometime after the initial construction of the build-out had been completed and
the BIR employees had begun working in the Marshall Building, the Building was
flooded with rain water, and Katz had Ramirez build a retaining wall to attempt to keep
out any water in the future. Ramirez testified that although he would periodically inform
the BIR of work being performed, he neither sought nor needed the BIR’s permission
since he was working for Katz, the owner of the Building. He also acknowledged that
5
The parties do not dispute that Katz was the owner and landlord of the Marshall
Building at all relevant times for purposes of this case.
5
although he oversaw the building of a retaining wall, he failed to address the water that
had already flooded inside the Building.
Ramirez testified that in June 2008, Katz requested that Ramirez visit the Building
to look into a mold problem in the Building. Ramirez acknowledged there had been an
odor in the Building, and he referred Katz to Todd Donohue, a mechanical contractor
who worked with air conditioning and plumbing issues, to help address the problem.
Stephen Monsanto, the Operations Manager for the BIR from 1994 to 1998,
testified that he helped to negotiate the agreement to lease the Marshall Building. He
testified that as part of the negotiations, Katz agreed to perform the build-out needed for
the offices, and in fact, although the lease provided that the Government was responsible
to maintain the premises, all renovations and building structural decisions such as the
type of ductwork used, the air-conditioning, or the contractors used were ultimately made
by Ramirez, who worked for Katz. Monsanto testified that Katz was the individual
ultimately responsible for the build-out for the BIR’s office space.
Louis Willis, who became the Director of the BIR in June 2000, testified that there
was “always” water on the floor in parts of the Marshall Building which “came from the
hills” outside the Building. (JA 807) He testified that in 2002 or 2003, there was
“tremendous flooding” in the Building from water which “came from the top floor down
to the bottom” amounting to “about 10 to 12 inches of water.” (JA 807.) After Willis
spoke with Katz, Katz through Ramirez built a retaining wall, which “solved the major
water problem,” but parts of the building “always had drippings of water.” (JA 808-09.)
Willis further testified that at some point the landlord paid for “blocks” to substitute for
6
sheetrock walls to protect the employees at the BIR from being robbed. (JA 809.) When
the sheetrock walls were taken out, moisture was observed at the bottom of the sheetrock.
As a result of the moisture problems with the Building, Willis did not want to renew the
lease.
Katz acknowledged that the lease provided that “[a]ll installations, alterations,
additions or improvements upon the leased premises, made or required to be made under
this lease by lessor, including all pipes, ducts, conduits, equipment, wiring, air-
conditioners, light fixtures, paneling, partitions, railings, galleries, and the like, shall
become and remain the property of the lessor” and that Katz was the lessor. (JA 1537.)
He also testified that he believed that, under the lease, the BIR was not responsible for
any structural elements of the Building, and indeed, the lease provided that the BIR could
not make any changes to the exterior of the Building. Katz further testified that the lease
made him responsible for the foundation of the Building and the structural soundness of
the Building.
Smith testified that she began working for the BIR at the Marshall Building in
June 2006, and she continued to work in the Building until June 9, 2009. The evidence
indicates that prior to working for the BIR, she had been diagnosed with asthma in 2001,
and that when she was treated in 2001, she reported a history at that time of asthma
during the previous three years.
Smith testified that a few months after she started working for the BIR at the
Marshall Building she began experiencing symptoms, including sore throat, ear
infections, and problems breathing and that her symptoms worsened while she worked in
7
the Marshall Building. In June 2008, while working in the Building, she smelled what
she described as a “strong stench” and “damp odor,” she felt her eyes burning, she began
“gasping for breath at times,” and she felt “nauseated” to the point where she vomited.
(JA 293-94.) Evidence indicated that other BIR employees also experienced symptoms
that day to the point where the employees left the Building. The evidence further
indicated that Smith went to the ER of a nearby hospital seeking medical treatment, as
did other employees that day.
The record reveals that Smith saw numerous doctors for treatment of her
symptoms while she was working for the BIR. Drs. Audria Thomas, Adam M. Shapiro,
and Stephen Grundfast testified at the first trial that they treated Smith during the time
she worked for the BIR. The testimony indicates that well prior to working for the BIR,
Smith had been diagnosed with emphysema and Chronic Obstructive Pulmonary Disease
(“COPD”) as well as asthma, and that although she was a smoker for approximately 10 to
15 years from about the age of 15 years old, she had stopped years prior to working for
the BIR. Evidence from treating doctors indicated that her symptoms were aggravated by
the existence of mold in her work environment at the Marshall Building.
Dr. Grundfast, a specialist in pulmonary medicine and internal medicine, testified
that he first examined Smith in September 2008, and he diagnosed her with asthma and
shortly thereafter determined that she did not have emphysema. He further testified that
mold and especially high mold concentration “definitely affect[s] asthma patients in a
negative way.” (JA 1238.) Dr. Grundfast also agreed with Katz’s counsel during
questioning that Smith had exacerbation of her asthma symptoms on June 2, 2008.
8
Smith also called fact witnesses Barbara Richards, Elsa Mulraine, Janice
Melchior, Luis Morales, Marie Vanterpool, Raymond George, and Leon Monsanto to
corroborate her testimony about her health problems and about the conditions at the
Marshall Building. Ms. Mulraine and Ms. Melchior, for example, testified as to the water
entering the Building when it rained, moisture in the Building, and that the employees
had to exit the building on June 2, 2008, when the odor was particularly strong causing
symptoms such as coughing and tearing. Mr. George testified that, although Smith had
some problems with breathing prior to working at the Building, after Smith began
working at the Marshall Building she began coughing more and her trouble breathing
became noticeably worse.
Dr. Howard M. Weiner, an environmental exposure expert, testified that results of
air samplings for mold spores in the Marshall Building in June 2008 revealed a
“significant problem with mold” with elevations of up to 47,000 spores per cubic meter,
“which is a great deal since in your home you would expect about 300 to 500.” (JA 676-
77.) Dr. Weiner explained that “[m]old doesn’t just appear like that,” but rather, there
was “a chronic source of moisture intrusion into the building that allowed for the mold to
grow as much as it did.” (JA 677-78.) The doctor further explained that the high level of
mold was due to “water coming in the building because the building envelope is not
doing what it’s supposed to, and/or because of the air-conditioning, the HVAC, heating,
ventilation, air-conditioning system also not working.” (JA 678.)
The doctor further confirmed that “[w]hen you are in a damp environment or a
moldy environment, you will have aggravation of your respiratory tract, so that your nose
9
can get itchy, runny, stuffy, sneezy,” “[i]f you have asthma, then your symptoms can be
aggravated,” and “[e]ven if you’re not allergic, you can get your eyes to be itching,
tearing,” and you can have symptoms such as headaches, sinus pressure, and swollen
glands. (JA 680-81.) He further testified that, irrespective of “other exposures” (JA
693), if an individual is exposed for an extended period of time to an environment with
the mold sampling such as those found in the Marshall Building, such circumstances
“will predictably make all of your symptoms worse.” (JA 694.)
James Thibodeau, a structural engineer, testified that there was a “huge hill”
behind the Building and that prior to the retaining wall, the rain water caused the
Building to flood. (JA 882-83.) He further testified that the gutters on both sides of the
Marshall Building would fill up causing moisture that goes through the foundation wall.
Thibodeau indicated that the design and installation of the air conditioning system in the
Building was faulty and against industry standards since it merely recirculated the
moisture and other contaminants in the Building. He testified that the ductwork installed
in the Building was a “cheap, inexpensive duct system that’s susceptible to deterioration”
and that in this case the “ductwork collapsed from deterioration.” (JA. 933.) He also
testified that the moisture that came up through the floor caused deterioration of the tile
floor, and there was also deterioration of the sheetrock throughout the Building,
particularly in the subterranean first-floor space. Thibodeau concluded that “the structure
[of the Building] was performing poorly” (JA 948), noting that there were no water
management membranes on the outside of the foundation walls, which was a structural
defect.
10
The jury returned a verdict on June 18, 2012 against Katz, awarding Smith
$390,000 in economic damages and $900,000 in non-economic damages. On July 16,
2012, Katz filed a Renewed Motion for Judgment as a Matter of Law, or in the
Alternative, For New Trial, as well as a Motion for Remittitur. On March 22, 2013, the
District Court denied Katz’s requests for judgment as a matter of law and for new trial,
and granted Katz’s request for remittitur. See Smith v. Katz, 2013 WL 1182074 (D. V.I.
Mar. 22, 2013). The Court found that the jury’s awards for economic and non-economic
losses were “‘clearly unsupported’ by the evidence and exceed[ed] the amount needed to
make the plaintiff whole.” Id. at *15 (quoting Starceski v. Westinghouse Elec. Corp., 54
F.3d 1089, 1100 (3d Cir. 1995)). The District Court further found that awards of $50,000
for economic losses and $100,000 for noneconomic losses were “in keeping with the
evidence” and applicable law.6 Id.
On April 10, 2013, Smith filed a “Notice that Plaintiff Does Not Accept the
Remittitur and Demands a New Trial on Damages,” which the District Court construed as
a motion for new trial in light of the remittitur. On July 30, 2013, the Court granted
Smith’s request and ordered a trial on the issue of damages to be held on September 30,
2013 (“second trial”).
Following the second trial, on October 4, 2013 the jury awarded Smith $20,000 in
economic damages and $55,000 in non-economic damages. Smith thereafter filed a
6
On April 8, 2013, Katz prematurely filed a Notice of Appeal from the District Court’s
March 22, 2013 rulings, and this Court granted Smith’s Motion to Dismiss the Appeal for
Lack of Jurisdiction by Order filed Sept. 25, 2013.
11
motion for new trial. The District Court denied the request for a new trial on December
11, 2014, see Smith v. Katz, 2014 WL 7004995 (D. V.I. Dec. 11, 2014), and Judgment
was entered in Smith’s favor in the amount of $75,000, in accordance with the jury’s
award following the second trial.
II.7
On cross-appeal, Katz argues that the District Court erred in denying his Rule
50(b) renewed motion for judgment as a matter of law after the first trial.8 Smith
responds that we should affirm the denial of Katz’s renewed motion. We agree with
Smith in this regard and affirm the denial of Katz’s motion.
We exercise plenary review over the District Court’s denial of judgment as a
matter of law. Eshelman v. Agere Sys., Inc., 554 F.3d 426, 433 (3d Cir. 2009). Thus, we
exercise the same standard as the District Court. Lightning Lube, 4 F.3d at 1166.
A motion for judgment as a matter of law “should be granted only if, viewing the
evidence in the light most favorable to the nonmovant and giving it the advantage of
every fair and reasonable inference, there is insufficient evidence from which a jury
7
The District Court of the Virgin Islands had diversity jurisdiction pursuant to 48 U.S.C.
§ 1612(a) and 28 U.S.C. § 1332. We exercise appellate jurisdiction pursuant to 28 U.S.C.
§§ 1291 and 1294(3).
8
A post-trial motion for judgment as a matter of law made pursuant to Fed. R. Civ. P.
50(b) “must be preceded by a Rule 50(a) motion sufficiently specific to afford the party
against whom the motion is directed with an opportunity to cure possible defects in proof
which otherwise might make its case legally insufficient.” Brokerage Concepts, Inc. v.
U.S. Healthcare, Inc., 140 F.3d 494, 519 n.18 (3d Cir. 1998) (quoting Lightning Lube,
Inc. v. Witco Corp., 4 F.3d 1153, 1173 (3d Cir. 1993)).
12
reasonably could find liability.” Avaya Inc. v. Telecom Labs, Inc., 838 F.3d 354, 373 (3d
Cir. 2016) (quoting Lightning Lube, 4 F.3d at 1166). The Supreme Court explained:
Credibility determinations, the weighing of the evidence, and
the drawing of legitimate inferences from the facts are jury
functions, not those of a judge. Thus, although the court
should review the record as a whole, it must disregard all
evidence favorable to the moving party that the jury is not
required to believe.
Reeves v. Sanderson Plumbing Prods., Inc., 530 U.S. 133, 150-51 (2000) (citation
omitted). “[J]udgment as a matter of law should be granted sparingly.” Avaya Inc., 838
F.3d at 373 (quoting Goodman v. Pa. Tpk. Comm’n, 293 F.3d 655, 665 (3d Cir. 2002)).
Smith alleged that Katz was negligent for failure to use reasonable care to protect
from a harmful condition and also that Katz was negligent in failing to warn of a
dangerous condition.9 The “foundational elements of negligence” under the law in the
Virgin Islands are: “(1) a legal duty of care to the plaintiff, (2) a breach of that duty of
care by the defendant (3) constituting the factual and legal cause of (4) damages to the
plaintiff.” Machado v. Yacht Haven U.S.V.I., LLC, 61 V.I. 373, 380 (2014) (premises
liability action against landowner). “[T]he touchstone of premises liability in the Virgin
Islands is foreseeability – if a possessor could anticipate that the conditions on its
property would result in injury to those foreseeably using the property, the possessor can
be held liable for those injuries.”10 Id. at 394.
9
All other claims against the defendants were dismissed before the end of trial and are
not at issue on appeal.
10
“In the context of a negligence claim based on a premises-liability theory, [the
Supreme Court of the Virgin Islands] has eliminated the traditional common-law
13
Katz argues that the evidence was insufficient to support a finding that he was
liable, and he argues that the Second Restatement of Torts should have been applied, but
in any event, that the evidence does not support that he had a duty with regard to the
build-out. However, as Smith points out in her brief, in arguing the Rule 50 motion in the
District Court, Katz’s counsel conceded the following position: “It would be admitted
that had Mr. Katz did, did [sic] the construction, that he would have owed a duty to
do the construction in a reasonable manner” (JA 1612 (emph. added)). Cf. United
States v. Sussman, 709 F.3d 155, 162 (3d Cir. 2013) (observing that concession made by
defendant in district court supported a finding of waiver of specific sufficiency of the
evidence argument, and that “the waiver binds him on this appeal”); United States v.
Lloyd, 10 F.3d 1197, 1209 (6th Cir. 1993) (concession made by defendant’s attorney in
district court was binding on appeal).
Moreover, “viewing the evidence in the light most favorable to [Smith] and giving
it the advantage of every fair and reasonable inference,” see Avaya, 838 F.3d at 373
(quoting Lightning Lube, 4 F.3d at 1166), there was sufficient evidence to support a
conclusion that Katz had a duty of care to construct the build-out and perform the other
construction undertaken by Katz in a reasonable manner, that Katz breached that duty,
and that plaintiff suffered injuries factually and legally caused by Katz’s breach. Viewed
distinction between invitees, licensees, and trespassers, and has instead concluded ‘that
the foreseeability of harm is the touchstone of [a land possessor’s] duty.’” Antilles Sch.,
Inc. v. Lembach, 64 V.I. 400, 409 (2016) (quoting Machado, 61 V.I. at 384). While
Smith was characterized as an invitee at trial, the District Court correctly charged the jury
that the foreseeability test needed to be satisfied to support a liability finding, and indeed,
the jury ultimately found the existence of the requisite foreseeability.
14
in the proper light, there was sufficient evidence to support the conclusion that the work
performed by Katz, through Ramirez and other contractors, was performed unreasonably,
and included structural defects and, at times, noncompliance with industry standards, in
such a manner that included the failure to properly account for water intrusion and excess
moisture resulting in “a chronic source of moisture intrusion into the building that
allowed for the mold to grow as much as it did” (JA 678). Among other things, Ramirez
testified that he “didn’t pay attention to” whether the Building was subterranean, and he
acknowledged that there were multiple procedures related to protecting the structure from
water and moisture that “need[ed] to be followed” when doing the work in this case that
were not followed. (JA 414-17.) Finally, the evidence was sufficient to support the
conclusion that Smith incurred harm proximately caused by Katz’s breach of duty in this
case.11
III.
Smith argues that the District Court erred when it remitted the damages award
after the first trial, and she requests that the first verdict be reinstated. “[T]he remittitur is
well established as a device employed when the trial judge finds that a decision of the
jury is clearly unsupported and/or excessive.” Cortez, 617 F.3d at 715-16 (quoting
Spence v. Bd. of Educ. of Christina Sch. Dist., 806 F.2d 1198, 1201 (3d Cir. 1986)).
11
Although the District Court applied the res ipsa loquitur doctrine in denying Katz’s
motion, see Smith, 2013 WL 1182074, at *11-13, we see no need to apply that doctrine
under these circumstances in affirming the denial of Katz’s motion since there was
sufficient evidence for a jury to conclude that the very high concentration of mold spores
in the air in the Marshall Building due to the defective construction by Katz proximately
caused at least an exacerbation of Smith’s condition.
15
“The trial judge’s decision to grant or withhold a remittitur cannot be disturbed
absent a manifest abuse of discretion.” Starceski, 54 F.3d at 1100; see Spence, 806 F.2d
at 1201. Therefore, “[o]ur role in reviewing the District Court’s decision to remit the
damage award here is ‘severely limited.’” Evans v. Port Auth. of N.Y. and N.J., 273 F.3d
346, 354 (3d Cir. 2001) (citing Gumbs v. Pueblo Inter’l, 823 F.2d 768, 771 (3d Cir.
1987)). “The district judge is in the best position to evaluate the evidence presented and
determine whether or not the jury has come to a rationally based conclusion.” Spence,
806 F.2d at 1201. Therefore, “[w]e must give the benefit of every doubt to the judgment
of the trial judge.” Evans, 273 F.3d at 354 (quoting Gumbs, 823 F.2d at 773).
Here, the jury concluded that Katz was liable to Smith in the amount of
$1,290,000, comprised of $390,000 in economic losses and $900,000 in non-economic
losses. Upon Katz’s motion, the District Court ordered remittitur of the damages award
to $150,000, comprised of $50,000 in economic losses and $100,000 in non-economic
losses. In particular, the Court found that the jury’s awards for economic and non-
economic damages were “clearly unsupported by the evidence and exceed[ed] the
amount needed to make the plaintiff whole.” Smith, 2013 WL 1182074, at *15 (citing
Starceski, 54 F.3d at 1100) (internal quotations omitted). Smith’s attempt to justify the
size of the jury’s award after the first trial by reference to the record is unpersuasive. On
the record before us, we cannot say that the Court abused its discretion in ordering
16
remittitur of the jury’s awards for economic and non-economic damages in this case. The
District Court’s decision to grant remittitur was well within the discretion reserved to it.12
IV.
Finally, Smith argues, in the alternative, that she is entitled to a new (third) trial on
damages.13 By Order filed December 11, 2014, the District Court denied Smith’s motion
for a new trial. See Smith v. Katz, 2014 WL 7004995 (3d Cir. 2014). We review the
District Court’s denial of a motion for a new trial for abuse of discretion except to the
extent that the Court’s denial was based on the “application of a legal precept, in which
12
Although on cross-appeal Katz argues that the District Court correctly granted
remittitur but did not reduce the award enough, this argument is largely academic since
Smith rejected the District Court’s conditional remittitur and invoked her right to demand
a new trial (on damages only) as an alternative to the reduction in the award made by the
District Court, see, e.g., Cortez, 617 F.3d at 716 (citing Hetzel, 523 U.S. at 211) (where a
court exercises its discretion to reduce a jury award because it believes the amount of the
award is inconsistent with the evidence in the case, such a reduction is necessarily
conditional since the court must offer a new trial as an alternative in order to avoid
depriving the plaintiff of her Seventh Amendment right to a jury trial). Obviously, a
more reduced award by the District Court would not have altered Smith’s decision to
request a new trial on damages in lieu of accepting the Court’s remittitur. Therefore, we
need not address Katz’s argument in that regard.
13
On appeal, Smith concedes “retrial on the issue of damages was appropriate.” See
Appellant Br. 46. Indeed, at the District Court level, Smith filed a “Notice that Plaintiff
Does Not Accept the Remittitur and Demands a New Trial on Damages,” prompting the
Court to Order a trial on the issue of damages. Thus, although Smith’s appeal brief
curiously appears, at times, to imply that it was inappropriate to hold a damages only
trial, a damages only trial is what she had asked for in the District Court, and ultimately,
that is what she asks for again here, in the alternative, on appeal. See id. at 56; (“The
Court should . . . order a new trial on damages”); id. at 31 (“Alternatively, Smith is
entitled to a new trial on damages”); Appellant Third Step Br. 54 (“Smith is entitled to a
new trial on damages”).
17
case the standard of review is plenary.” Brand Marketing Grp. LLC v. Intertek Testing
Servs., N.A., 801 F.3d 347, 366 (3d Cir. 2015) (quoting Lighting Lube, 4 F.3d at 1167).
On appeal, Smith argues that the District Court erred and a new trial is warranted
based on the exclusion of certain expert testimony on causation at the second trial, as well
as allegedly inadequate jury instructions. With regard to the challenged exclusion of
evidence, the District Court explained that while “it is clear that this testimony would
have fallen outside the scope of a damages trial[,] . . . Smiths’ experts were not excluded
or limited in their testimony for that reason alone.” Smith, 2014 WL 7004995, at *3.
Rather, “Smith’s experts were primarily limited in their testimony due to late or
insufficient expert disclosures under Federal Rule of Civil Procedure 26.” Id.
Initially, it is noted that, especially in light of the fact that Smith requested the
second trial on damages only, Smith cannot now properly complain to the extent that the
District Court excluded evidence on liability. Further, under Rule 26(a)(2), a party must
provide required expert testimony disclosures in accordance with the Court’s orders and
Rule 26(a)(2).14 “The trial court’s exclusion of testimony because of the failure of
counsel to adhere to a pretrial order will not be disturbed on appeal absent a clear abuse
of discretion.” Konstantopoulos v. Westvaco Corp., 112 F.3d 710, 719 (3d Cir. 1997)
(quoting Semper v. Santos, 845 F.2d 1233, 1238 (3d Cir. 1988)). Here, the District Court
issued scheduling orders setting the deadlines for the parties’ respective expert
14
Under Fed. R. Civ. P. 26(a)(2)(D), the expert disclosures required under Rule 26 must
be made “at the times and in the sequence that the court orders,” or absent a stipulation or
court order, such disclosures must be made “at least 90 days before the date set for trial or
for the case to be ready for trial.”
18
disclosures, and those deadlines were not altered following the Order for a new trial on
damages. See Smith, 2014 WL 7004995, at *3. Smith failed to comply with the Court’s
Scheduling Order’s expert disclosure deadlines and failed to comply with Rule 26(a)(2).
In determining whether a District Court abused its discretion in this context, we
consider: (1) the prejudice or surprise in fact of the party against whom the excluded
witnesses would have testified; (2) the ability of that party to cure the prejudice; (3) the
extent to which waiver of the rule against calling unlisted witnesses would disrupt the
orderly and efficient trial of the case or other cases in the court; and (4) bad faith or
willfulness in failing to comply with the District Court’s Order. Konstantopoulos, 112
F.3d at 719. In addition, we consider the importance of the excluded testimony. Id.
Considering these factors, we conclude the District Court did not abuse its
discretion in excluding the expert testimony. Smith had ample opportunity to meet the
applicable expert disclosure requirements under the District Court’s pretrial Order and
Rule 26. While Smith characterizes the excluded expert testimony as significant, we
note, as did the District Court, that the District Court did not exclude all of the testimony
from Drs. Shapiro and Grundfast. The Court allowed these doctors to testify as treating
physicians but prevented them from putting forward expert opinion causation testimony
in that Smith failed to timely designate them as expert witnesses or provide other required
disclosures regarding their expert opinion testimony in a timely fashion. Smith provided
no adequate justification for failing to make the timely mandatory disclosures on expert
witnesses, despite the fact that Rule 26(a)(2) unambiguously required those disclosures.
“[W]e have generally upheld trial courts’ imposition of sanctions excluding witnesses
19
because of the district court’s need for broad leeway to manage its cases.” In re Paoli
R.R. Yard PCB Litig., 35 F.3d 717, 792 (3d Cir. 1994) (citations omitted). The District
Court did not abuse its discretion in barring the expert opinion testimony.
Smith further argues that “[o]n retrial, the jury should have been instructed that
Katz’ negligence caused the exposure” and that the “jury should have then been
instructed to make its damages findings based on the extent of Smith’s injuries that were
proximately caused by the exposure.” See Appellant Br. 47. Generally, we review jury
instructions for abuse of discretion, but we exercise plenary review “when the question is
whether a district court’s instructions misstated the law.” De Asencio v. Tyson Foods,
Inc., 500 F.3d 361, 366 (3d Cir. 2007) (quoting United States v. Dobson, 419 F.3d 231,
236 (3d Cir. 2005)). “[W]hen we consider jury instructions[,] we consider the totality of
the instructions and not a particular sentence or paragraph in isolation.” Id. (quoting
United States v. Coyle, 63 F.3d 1238, 1245 (3d Cir. 1995)). “The charge, taken as a
whole and viewed in light of the evidence, must fairly and adequately submit the issues in
the case to the jury.” Tigg Corp. v. Dow Corning Corp., 962 F.2d 1119, 1123 (3d Cir.
1992) (quoting Link v. Mercedes-Benz of N. Am., 788 F.2d 918, 920 (3d Cir. 1986)). In
applying this standard, we must keep in mind that “[n]o litigant has a right to a jury
instruction of its choice, or precisely in the manner and words of its own preference.”
Douglas v. Owens, 50 F.3d 1226, 1233 (3d Cir. 1995).
The District Court pointed out to the jury that “here the essential element that
we’re talking about is proof of damages,” (JA 2988). The Court explained:
20
[I]t has already been found that the defendant Sidney Katz
was negligent in his failure to use reasonable care to protect
Lorraine Smith from a harmful condition, and that Mr. Sidney
Katz failed to warn of a harmful condition, and that his
negligence in both those respects was the proximate cause of
some injury to Lorraine Smith.
Your task is not to determine whether or not Mr. Katz
was the cause of some injury. Your task is to determine what,
if any, damages would be appropriate for some injury that the
plaintiff Lorraine Smith suffered.
(JA 2989.) The Court further instructed: “You must consider the extent of Lorraine
Smith’s injuries and what sum of money you believe will fairly, justly and reasonably
compensate her for all of the injuries she sustained as a result of the defendant’s conduct.
No more, no less.” (JA 2990.) Thus, as the Court explained to the jury, “[i]f the plaintiff
had a physical condition that was made worse by the defendant’s negligence, you must
award damages that will reasonably and fairly compensate the plaintiff for the effect on
that condition.” (JA 2993.) The District Court’s charge in this case, taken as a whole and
viewed in light of the evidence, fairly and adequately presented the issues in the case to
the jury.
V.
For the foregoing reasons, we affirm the District Court’s Order denying Katz’s
motion for judgment as a matter of law and remitting the damages awarded following the
first trial, and we affirm the Judgment entered following the retrial and the District
Court’s denial of Smith’s motion for a new trial.
21