[Cite as New Riegel Local School Dist. Bd. of Edn. v. Bueherer Group Architecture & Eng. Inc., 2017-
Ohio-8521.]
IN THE COURT OF APPEALS OF OHIO
THIRD APPELLATE DISTRICT
SENECA COUNTY
NEW RIEGEL LOCAL SCHOOL
DISTRICT, BOARD OF EDUCATION,
CASE NO. 13-17-03
PLAINTIFF-APPELLANT,
-and-
STATE OF OHIO,
PLAINTIFF-APPELLEE,
v.
OPINION
THE BUEHRER GROUP
ARCHITECTURE & ENGINEERING,
INC., ET AL.,
DEFENDANTS-APPELLEES.
NEW RIEGEL LOCAL SCHOOL
DISTRICT, BOARD OF EDUCATION,
CASE NO. 13-17-06
PLAINTIFF-APPELLANT,
-and-
STATE OF OHIO,
PLAINTIFF-APPELLEE,
v.
OPINION
THE BUEHRER GROUP
ARCHITECTURE & ENGINEERING,
INC., ET AL.,
DEFENDANTS-APPELLEES.
Case No. 13-17-03 and 13-17-06
Appeal from Seneca County Common Pleas Court
Trial Court No. 15 CV 0115
Judgment Reversed, Cause Remanded
Date of Decision: November 13, 2017
APPEARANCES:
Christopher L. McCloskey and Tarik Kershah for Appellant
Shannon J. George and Matthew T. Davis for Appellee, Studer-
Obringer, Inc.
P. Kohl Schneider, Colleen A. Mountcastle and Melanie R. Irvin for
Appellee Charles Construction Services, Inc.
Marc A. Sanchez and Michael J. Frantz, Jr. for Appellee Ohio Farmer’s
Insurance Company
WILLAMOWSKI, J.
{¶1} Plaintiff-appellant New Riegel Local School District Board of
Education (“the School”) brings this appeal from the judgment of the Court of
Common Pleas of Seneca County granting the judgment on the pleadings filed by
defendants-appellees Studer-Obringer, Inc. (“SOI”), Charles Construction Services,
Inc. (“CCS”), and Ohio Farmers Insurance Company (“OFIC”). For the reasons set
forth below, the judgment is reversed.
-2-
Case No. 13-17-03 and 13-17-06
{¶2} This case arises from the construction of a new Kindergarten through
12th Grade School Facility Project (“the Project”) built as part of the Ohio Classroom
Facilities Assistance Program. Doc. 2. As a result of the Project, the School entered
into contracts with multiple contractors starting in February of 2000. Id. SOI
contracted with the school to serve as the general trades contractor for the Project.
Id. CCS contracted with the school to serve as the roofing contractor for the Project.
The School began occupying the school building on December 19, 2002, Doc. 88,
Ex. K. The State issued a Certificate of Completion transferring all of the interest
of the State in the Project to the School on March 3, 2004. Doc. 24.
{¶3} Over time, the School had issues with the facilities, including but not
limited to condensation and moisture intrusion allegedly caused by design and
construction errors. Doc. 2. A complaint was filed by the School on April 30, 2015.
Id. The complaint was brought in the name of the School with the State of Ohio
and OSFC as involuntary plaintiffs. Id. The complaint named the Buehrer Group
Architecture & Engineering, Inc., the Estate of Huber H. Buehrer (collectively
known as “the Buehrer Group”), SOI, CCS, and American Buildings Company as
defendants. Id. The complaint alleged that both SOI and CCS had breached its
contract by failing to conform to the requisite standard of care to perform in a
workmanlike manner. Id. SOI filed its answer to the complaint on July 13, 2015,
denying the allegations in the complaint and listing several affirmative defenses,
including the statute of repose. Doc. 34. CCS filed its answer to the complaint on
-3-
Case No. 13-17-03 and 13-17-06
July 31, 2015, also denying the allegations in the complaint and listing several
affirmative defenses including the statute of repose. Doc. 35.
{¶4} On February 10, 2016, the School filed an amended complaint in its
own name and that of the State. Doc. 62. The amended complaint raised the same
alleged breach of contract claims against SOI and CCS as the first complaint did.
Doc. 62. SOI filed its answer to the amended complaint on February 16, 2016. Doc.
65. CCS filed its answer to the amended complaint on February 23, 2016. Doc. 68.
Both answers denied the allegations of the amended complaint and raised the same
affirmative defenses. Doc. 62 and 65. On February 26, 2016, SOI filed a motion
for judgment on the pleadings pursuant to Civil Rule 12(C). Doc. 70. SOI claimed
that the claims raised by the School were time-barred by the statute of repose as set
forth in R.C. 2305.131(A)(1). Id. The School filed its memorandum in opposition
to this motion on March 4, 2016. Doc. 73. SOI then filed its reply to the
memorandum of the School. Doc. 75
{¶5} The School then filed a second amended complaint on June 10, 2016.
Doc. 88. This complaint added OFIC as a defendant as the surety for SOI, but did
not make any changes to the claims against SOI. Id. SOI filed its answer to the
second amended complaint on June 20, 2016. Doc. 93. On June 23, 2016, SOI
renewed its motion for judgment on the pleadings pursuant to Civil Rule 12(C).
Doc. 95. The School filed its memorandum in opposition to the motion on July 13,
2016. Doc. 102. A reply was filed by SOI on July 20, 2016. Doc. 107. On August
-4-
Case No. 13-17-03 and 13-17-06
24, 2016, the trial court granted SOI’s motion for judgment on the pleadings. Doc.
116. This judgment was based upon the statute of repose as set forth in R.C.
2305.131. Id.
{¶6} CCS filed its answer to the second amended complaint on June 28,
2016. Doc. 102. After the trial court had granted both SOI’s and The Buehrer
Group’s motions for judgment on the pleadings based upon the statute of repose,
CCS filed its own motion for judgment on the pleadings also based upon the statute
of repose. Doc. 124. The School filed a response to CCS’s motion on September
28, 2016. Doc. 126. On October 31, 2017, the trial court granted CCS’s motion for
judgment on the pleadings. Doc. 129.
{¶7} OFIC filed its answer to the second amended complaint on August 15,
2016. Doc. 113. Following the dismissal of SOI as a party, OFIC filed a motion
for judgment on the pleadings on September 6, 2016. Doc. 119. OFIC argued that
since SOI was dismissed, OFIC was no longer liable as the surety for SOI and must
also be dismissed. Id. The School filed its response to OFIC’s motion on September
9, 2016. Doc. 120. In the same entry that granted CCS’ motion for judgment on
the pleadings, the trial court also granted OFIC’s motion for judgment on the
pleadings and both parties were dismissed. Doc. 129.
{¶8} On January 25, 2017, the School filed its notice of appeal from the
judgment dismissing SOI as a party. Doc. 134. This judgment was assigned
appellate case number 13-17-03. The School also filed its notice of appeal from the
-5-
Case No. 13-17-03 and 13-17-06
judgment dismissing CCS and OFIC. Doc. 143. This judgment was assigned
appellate case number 13-17-06. The other judgments were assigned case numbers
13-17-04 (dismissal of case against the Buehrer Group) and 13-17-05 (dismissal of
the State as a party). On appeal, the School raises the following assignments of
error.
First Assignment of Error
The trial court erred in dismissing [the School’s] breach of
contract claims against [SOI], [CCS], and [The Buehrer Group],
by finding that the Ohio Statute of Repose, R.C. 2305.131, barred
[the School’s] claims for breach of contract.
Second Assignment of Error
The trial court erred in dismissing the claims against [SOI] and
[CCS] as those contracts were entered with [the State] and
general limitations periods do not apply to the State of Ohio.
Third Assignment of Error
The trial court erred in finding that [the School] does not have
authority to bring its action in the name of [the State].
Fourth Assignment of Error
The trial court erred in dismissing [the School’s] claims against
[OFIC], as surety for [SOI], on the basis that [the School’s] surety
bond claim against [OFIC] was barred by the virtue of the
dismissal of the claims against [SOI].
As the third assignment of error applies only to the State, we need not address that
assignment of error in this opinion. It will be addressed in Appellate Case No. 13-
17-05.
-6-
Case No. 13-17-03 and 13-17-06
{¶9} In the first assignment of error, as it applies to SOI, the School claims
that the trial court erred in dismissing with prejudice the claims against SOI. The
dismissal was granted by the trial court pursuant to the statute of repose which limits
actions for damages based upon defective and unsafe conditions in improvements
to real property.
(A)(1) Notwithstanding an otherwise applicable period of
limitations specified in this chapter or in section 2125.02 of the
Revised Code and except as otherwise provided in divisions
(A)(2), (A)(3), (C), and (D) of this section, no cause of action to
recover damages for bodily injury, an injury to real or personal
property, or wrongful death that arises out of a defective and
unsafe condition of an improvement to real property and no cause
of action for contribution or indemnity for damages sustained as
a result of bodily injury, an injury to real or personal property,
or wrongful death that arises out of a defective and unsafe
condition of an improvement to real property shall accrue against
a person who performed services for the improvement to real
property or a person who furnished the design, planning,
supervision of construction, or construction of the improvement
to real property later than ten years from the date of substantial
completion of such improvement.
***
(G) As used in this section, “substantial completion” means the
date the improvement to real property is first used by the owner
or tenant of the real property or when the real property is first
available for use after having the improvement completed in
accordance with the contract or agreement covering the
improvement, including any agreed changes to the contract or
agreement, whichever occurs first.
R.C. 2305.131.
-7-
Case No. 13-17-03 and 13-17-06
{¶10} The School argues that the statute of repose does not apply because
they are bringing suit for breach of contract, not for a tort and the statute of repose
does not apply to breach of contract claims. In support of this argument the School
cites to Kocisko v. Charles Shutrump & Sons Co. et al., 21 Ohio St.3d 98, 488
N.E.2d 171 (1986), which held that the statute of repose did not apply in that case
because it was a breach of contract case, not a tort case and the statute of repose
does not apply to a contract case.1 In Kocisko, the church took occupancy of the
building on October 25, 1970. The roof of the building leaked from the date of its
installation. The church then filed suit on November 6, 1981. The church brought
suit for breach of contract alleging that the defendants failed to install the roof in a
workmanlike manner. The Supreme Court of Ohio affirmed the judgment of the
appellate court reversing summary judgment on the grounds that the statute of
repose did not apply to cases based upon a breach of contract. Id. at 99. The School
argues that since the current statute contains similar language to the one addressed
by Kocisko, the same rule should be applied.
{¶11} A clear reading of the statute does not support this conclusion. The
statute specifies that NO cause of action for damages to real property, resulting from
the improvement to that real property, can be brought after 10 years from the time
1
This court notes that the case was based upon a prior version of R.C. 2305.131 that is no longer in effect,
but that the language is similar to the current version.
-8-
Case No. 13-17-03 and 13-17-06
the improvements were substantially completed. R.C. 2305.131. The statute does
not limit it to claims for torts only. Regardless of what the School labels this claim,
the School is trying to collect damages resulting from an improvement, i.e. the
Project, to real property. The statute specifically prohibits this. Thus, it would
appear that the statute specifically denies the claims in this case. However, the
Ohio Supreme Court has interpreted this language as applying to tort claims only.
We are required to follow the ruling of the Supreme Court unless either the
legislature or the Supreme Court chooses to modify it. Given the Supreme Court’s
holding in Kocisko, we find that the statute of repose does not apply to claims for
breach of contract.
{¶12} The School premised its claims as breach of the terms in the contract.
“In reviewing whether a motion to dismiss should be granted, we accept as true all
factual allegations in the complaint.” Perrysburg Twp. v. Rossford, 103 Ohio St.3d
79, 2004-Ohio-4362, 814 N.E.2d 44, ¶ 5. “Under de novo analysis, we are required
to ‘accept all factual allegations of the complaint as true and draw all reasonable
inferences in favor of the nonmoving party.’” Pearsall v. Guernsey, 3d Dist.
Hancock No. 5-16-25, 2017-Ohio-681, ¶ 9 (citations omitted). Viewing the
allegations in a light most favorable to the School, we must find that the trial court
erred in granting the motion to dismiss on the pleadings pursuant to the statute of
repose. As the Supreme Court stated in Kocisko, “this court expresses no opinion
as to the merit of any of the plaintiff’s claims.” Kocisko, supra at 99. This court
-9-
Case No. 13-17-03 and 13-17-06
merely holds that judgment on the pleadings in this case, as pled, is inappropriate.2
For that reason, the first assignment of error is sustained as it applies to SOI and
CCS.
{¶13} The School argues in its fourth assignment of error that the trial court
erred in dismissing OFIC as surety for SOI. The decision to dismiss OFIC was
based upon the fact that SOI had been dismissed from the case. The reasoning of
the trial court that a surety cannot be liable if there is no valid claim against the
principal is correct. However, as we have determined that the trial court erred in
granting judgment on the pleadings based upon the statute of repose, SOI is once
again a party against whom a valid claim may lie. The result of this is that OFIC is
once again the surety for a party and should not have been dismissed from the case.
For this reason, the fourth assignment of error is sustained.
{¶14} In the second assignment of error, the School says that the trial court
erred in dismissing the claims pursuant to the statute of repose because the contracts
were entered with the State and the limitation does not apply to the State. Since this
court has determined that the statute of repose does not apply to the alleged breaches
of contract, this assignment of error is moot and need not be addressed by this court.
2
This court does not make any determination as to whether or not this case actually is based upon a breach
of contract. The only issue before this court is whether viewing the pleadings in a light most favorable to the
plaintiff, a viable cause of action could exist. Since it is arguable that this is a breach of contract case, the
granting of judgment on the pleadings was not appropriate.
-10-
Case No. 13-17-03 and 13-17-06
App.R. 12(A)(1)(c). Additionally, for the reason set forth above, the third
assignment of error will not be addressed in this opinion.
{¶15} Having found error prejudicial to the Appellant in the particulars
assigned and argued, the judgment of the Court of Common Pleas of Seneca County
is reversed and the matter is remanded for further proceedings in accord with this
opinion.
Judgment Reversed
And Cause Remanded
ZIMMERMAN and SHAW, J.J., concur.
/hls
-11-