In the United States Court of Federal Claims
No. 16-1691C
(Filed: March 14, 2018)
************************ *
* Judgment on the Pleadings;
Sovereign Immunity; Waiver;
CITY OF WILMINGTON, DELAWARE, *
Exhaustion; Clean Water Act, 33
* U.S.C. § 1323; Interest.
Plaintiff, *
*
v. *
*
THE UNITED STATES, *
*
Defendant. *
*
************************ *
Christopher D. Pomeroy and Paul T. Nyffeler, Aqualaw PLC, 6 S. 5th Street, Richmond,
VA 23219, and Luke W. Mette and Rosamaria Tassone, City of Wilmington Law Department, 800
N. French Street, 9th Floor, Wilmington, DE 19801, Of Counsel, for Plaintiff.
Chad A. Readler, Robert E. Kirchman, Jr., Deborah A. Bynum, Franklin E. White, Jr., and
Douglas T. Hoffman, U.S. Department of Justice, Civil Division, Commercial Litigation Branch,
P.O. Box 480, Ben Franklin Station, Washington, D.C. 20044, for Defendant.
_________________________________________________________
OPINION AND ORDER
_________________________________________________________
WILLIAMS, Judge.
The City of Wilmington, a municipal corporation of the State of Delaware (“Wilmington”),
brought the instant action to recover “reasonable service charges” under Section 1323 of the Clean
Water Act for control and abatement of stormwater pollution. Plaintiff assessed service charges
on five properties owned and operated by the Army Corps of Engineers within the Wilmington
city limits from January 4, 2011, through December 19, 2016. Defendant does not dispute that it
failed to pay those service charges.
Plaintiff moved this Court for partial judgment on the pleadings pursuant to Rule 12(c),
asserting that Defendant waived its right to contest issues it could have raised if it had brought an
administrative appeal under Wilmington City Code § 45-53(d)(7). Defendant did not bring an
administrative appeal, and while Defendant could still bring an administrative appeal, the
administrative tribunal can only adjust future fee assessments—not the past assessments at issue
here. Plaintiff argues that because Defendant could have challenged the stormwater fee
calculations “on the basis of site-specific, technical information” in an administrative appeal but
chose not to do so, it waived its right to raise such challenges here. Plaintiff asserts that this result
is compelled by either the Clean Water Act or the exhaustion doctrine.
The Court denies Plaintiff’s motion for partial judgment on the pleadings. The
administrative appeal provided for by the Wilmington City Code is permissive, rather than
mandatory. Accordingly, Defendant’s failure to submit an administrative appeal did not violate
the Clean Water Act, and the exhaustion doctrine does not preclude Defendant from challenging
the City’s assessments here.
Defendant also moved for partial judgment on the pleadings, asking this Court to find that
Plaintiff cannot recover interest as a matter of law. Defendant contends that Section 1323 does
not expressly waive sovereign immunity with respect to interest, and absent such an express
waiver, interest is unavailable. Further, Defendant contends that Plaintiff has misapplied its own
local law, which Defendant asserts does not provide for interest in this context.
The Court denies Defendant’s motion for partial judgment on the pleadings. The issue of
whether the Clean Water Act waives sovereign immunity with respect to interest is an issue of first
impression in this Circuit that is not amenable to judgment at this preliminary stage, given that the
parties dispute the meaning of the statute. Accordingly, while Defendant may renew its argument
at a later stage, Defendant’s motion is denied.
Background1
The City of Wilmington owns and operates a municipal storm sewer system that conveys
only stormwater, and a combined sewer system that conveys a combination of stormwater and
sanitary waste. Wilmington manages both systems with a goal of reducing stormwater pollutants
discharged into rivers, streams, lakes, and other bodies of water. Wilmington assesses fees on
property located within its city limits and places such fees in an enterprise fund used exclusively
for the provision of stormwater services and facilities. Wilmington City Code § 45-53.
Wilmington also assesses penalties and interest if property owners do not pay such fees in a timely
fashion.
Defendant owns and controls five properties within Wilmington’s jurisdiction that are at
issue in this lawsuit. Plaintiff claims that it assessed stormwater fees against these five properties
that in the aggregate totaled $1,577,368.40 as of December 16, 2016, plus interest of
$1,185,929.24. In response to Defendant’s motion for judgment on the pleadings, Plaintiff
concedes that it is not entitled to $124,790.21 in penalties that were included in this amount,
adjusting the principal it seeks to recover to $1,452,578.19. Pl.’s Opp’n 1. Defendant neither paid
the amounts assessed when it received invoices from Plaintiff in 2011 through 2016, nor invoked
the administrative appeal rights afforded it by the Wilmington City Code.
Plaintiff filed its Complaint on December 22, 2016, and Defendant filed its Answer on
April 24, 2017. By motion dated October 4, 2017, the parties jointly asked the Court to permit
them to file motions for partial judgment on the pleadings and to stay discovery until the motions
1
This background is derived from the parties’ respective motions for judgment on the
pleadings. This background should not be construed as findings of fact.
2
are resolved. The Court granted the parties’ motion by Order dated October 5, 2017, and briefing
on the motions for partial judgment on the pleadings concluded on December 21, 2017.
Discussion
Jurisdiction and Legal Standards
The Court has jurisdiction over this action pursuant to the Tucker Act, 28 U.S.C. § 1491
(2012). The Tucker Act waives sovereign immunity and provides this Court with jurisdiction over
specific categories of claims against the United States, including those claims “founded either upon
the Constitution, or any Act of Congress or any regulation of an executive department . . . in cases
not sounding in tort.” § 1491(a)(1). “[T]he claimant must demonstrate that the source of
substantive law he relies upon can fairly be interpreted as mandating compensation by the Federal
Government for the damages sustained.” United States v. Mitchell, 463 U.S. 206, 216-17 (1983)
(internal citation and quotation marks omitted). Section 1323(a) of the Clean Water Act “may
fairly be interpreted to mandate the payment of money by the government” because it mandates
that the United States “shall” pay “reasonable service charges.” DeKalb Cty., Georgia v. United
States, 108 Fed. Cl. 681, 695-96 (2013) (explaining that the word “shall” generally makes a statute
money-mandating).
RCFC 12(c) provides that “[a]fter the pleadings are closed—but early enough not to delay
trial—a party may move for judgment on the pleadings.” The Court will only grant a motion for
judgment on the pleadings where “it appears to a certainty” that the nonmoving party “is entitled
to no relief under any state of facts which could be proved in support of [its] claim.” Owens v.
United States, 851 F.2d 1404, 1407 (Fed. Cir. 1988) (internal citation and quotation omitted). The
Court must “assume each well-pled factual allegation to be true and indulge in all reasonable
inferences in favor of the nonmovant.” Id. “A motion for judgment on the pleadings should be
denied unless it appears to a certainty that [the nonmoving party] is entitled to no relief under any
state of facts which could be proved in support of [its] claim.” Johns-Manville Corp. v. United
States, 12 Cl. Ct. 1, 14 (1987) (internal citations omitted). See also Xianli Zhang v. United States,
640 F.3d 1358, 1376 (Fed. Cir. 2011) (affirming judgment on the pleadings in favor of defendant
where the Court found that the governing statute subjected the plaintiff to the taxes at issue and it
was not entitled to a tax refund as a matter of law).
Defendant is Not Precluded from Challenging Plaintiff’s Fee Assessments in This Forum
Plaintiff asks the Court to rule that Defendant cannot “contest [Plaintiff’s] stormwater
calculation based on site-specific, technical information, namely land surveys, gross parcel area,
total impervious area, type of surface material, and similar evidence” that could have been
considered in an appeal under the Wilmington City Code § 45-53(d)(7). Pl.’s Mot. 2.2 Plaintiff
2
Plaintiff differentiates between “site-specific” challenges to the charges and challenges
based on Plaintiff’s “general methodology,” and asserts that only the latter can be challenged in
this forum. Regardless of whether its motion is granted, Plaintiff acknowledges it must prove that
“the properties’ stormwater charges are based on some fair approximation of the proportionate
contribution of the properties to stormwater pollution” and Defendant could still contest “whether
Wilmington City Code § 45-53 provides some fair approximation of the proportionate contribution
of stormwater pollution by vacant properties like the properties at the center of this litigation.”
3
raises two interconnected arguments in support of its position. First, Plaintiff argues that Section
1323(a) of the Clean Water Act obligates the Government to comply with local administrative
procedures and that the Government violated this provision by failing to file an administrative
appeal that Plaintiff claims was mandated by the local Wilmington Code. Second, Plaintiff argues
that the exhaustion doctrine prohibits Defendant from raising arguments here that it could have—
but did not—raise in an administrative appeal. The Court is not persuaded by either argument.
With respect to Plaintiff’s first argument, Section 1323(a) of the Clean Water Act provides
that the Federal Government:
shall be subject to, and comply with, all Federal, State, interstate, and local
requirements, administrative authority, and process and sanctions respecting the
control and abatement of water pollution in the same manner, and to the same extent
as any nongovernmental entity including the payment of reasonable service
charges. The preceding sentence shall apply (A) to any requirement whether
substantive or procedural (including any recordkeeping or reporting requirement,
any requirement respecting permits and any other requirement, whatsoever), (B) to
the exercise of any Federal, State, or local administrative authority, and (C) to any
process and sanction, whether enforced in Federal, State, or local courts or in any
other manner.
33 U.S.C. § 1323(a). According to Plaintiff, by referring to “local requirements, administrative
authority, and process” and “procedural” requirements, the statute subjects Defendant to all local
requirements, including the administrative appeal procedures in Section 45-53(d)(7) of the
Wilmington City Code.
The Wilmington City Code provides for the assessment of a “[s]torm water charge,”
defined as “the monthly charge for storm water management assessed to a parcel within the city
based on the use of the parcel on the last day of the month of the billing period.” Wilmington City
Code § 45-53(a). The Code further mandates that “[a]ll parcels that are within the city's corporate
boundaries, shall be assessed a monthly storm water charge as per the provisions of this article.”
§ 45-53(d). The Wilmington City Code provides for an administrative appeal of the assessment
as follows:
An owner of a parcel for which a storm water charge has been assessed, may
appeal for that parcel: (1) the calculation of the storm water charge; (2) the
assigned storm water class; (3) the assigned tier, if applicable; and (4) the
eligibility for a credit. The appellant must file the appeal in writing to the
commissioner of the department of public works.
The appellant shall submit a land survey prepared by a registered surveyor
showing dwelling units, gross parcel area, total impervious area, type of surface
material, as appropriate, and any other information that the commissioner shall
Pl.’s Mot 1-2. Further, Plaintiff agrees that Defendant could introduce “technical, site-specific
information” as “evidence to show that Wilmington’s runoff coefficient for Vacant properties is
an unfair approximation of Vacant properties’ proportional contribution to stormwater.” Pl.’s
Reply 15 n.5.
4
specify. The commissioner may waive in writing the submission of a land survey.
An appeal may be filed at any time, but any adjustment to the assessment in
favor of the appellant shall only be applied prospectively. No retroactive
adjustments to the storm water charge will be made in favor of the appellant.
a. The burden of proof shall be on the appellant to demonstrate, by
clear and convincing evidence the validity of the appeal.
§ 45-53(d)(7) (emphasis added).
Defendant failed to avail itself of the administrative appeal process provided by the
Wilmington City Code. Because Plaintiff asserts that the Wilmington City Code mandated an
appeal procedure which Defendant did not invoke, Plaintiff contends that Defendant violated the
Clean Water Act. Due to Defendant’s failure to utilize the Wilmington City Code appeal
procedure, Plaintiff asks this Court to enter an extreme procedural ruling and hold that Defendant
waived its right to address issues before this Court that it could have addressed in that
administrative appeal. This Court rejects Plaintiff’s claim that “[b]y failing to appeal the
stormwater calculation, the owner loses the right to challenge the calculation of past charges.”
Pl.’s Br. 7. Such a draconian result is not dictated by the statutory framework here.
Although the Government is subject to local requirements, the Wilmington City Code does
not require a property owner to pursue an administrative appeal. Rather, that appeal right is
permissive. The Wilmington City Code clearly provides that a property owner “may” appeal an
assessment. The Code does not suggest a party would waive its right to defend against an
assessment if it did not utilize the administrative appeal process. Accordingly, the Clean Water
Act does not preclude Defendant from challenging the assessment in this forum because it failed
to invoke the Wilmington City appeal process.
In the alternative, Plaintiff invokes the exhaustion doctrine, which precludes “judicial relief
for a supposed or threatened injury until the prescribed administrative remedy has been
exhausted.” McKart v. United States, 395 U.S. 185, 193 (1969) (internal quotation and citation
omitted). Plaintiff contends that because Defendant failed to file an administrative appeal,
Defendant cannot make arguments in this Court that it could have raised in such administrative
appeal. This Court declines to apply the exhaustion doctrine in the manner Plaintiff suggests.
Where “Congress has not clearly mandated the exhaustion of particular administrative remedies,
the exhaustion doctrine is not jurisdictional, but is a matter for the exercise of ‘sound judicial
discretion.’” Maggitt v. West, 202 F.3d 1370, 1377 (Fed. Cir. 2000) (citing McCarthy v. Madigan,
503 U.S. 140, 146 (1992)). Here, the Wilmington City Code did not require that a property owner
pursue an administrative appeal as a prerequisite to defending against or challenging the City’s
assessment in this Court.
Because Defendant was not required to pursue the City’s appeal process, “[w]hether the
doctrine of exhaustion should be invoked” is a matter for the Court’s discretion and requires a
case-by-case analysis of the competing interests of the parties. Maggitt, 202 F.3d at 1378.
Invoking the exhaustion doctrine here would mean that a property owner’s argument against the
City’s assessment of stormwater charges would “go unheard.” Id. at 1377. Here, the Clean Water
Act mandates that a property owner pay the City “reasonable” stormwater charges, and application
of the exhaustion doctrine would bar the property owner—the United States—from challenging
5
the reasonableness of those charges in numerous respects. As such, Defendant would suffer
serious prejudice in a manner not contemplated by the statute by being forced to pay whatever
charges the City assessed without recourse.
Plaintiff asserts that invoking the exhaustion doctrine would further Plaintiff’s interest in
protecting its administrative authority and promote judicial economy because the administrative
appeal process would have minimized the parties’ litigation costs by “resolving factual details at
the administrative level.” Pl.’s Reply 11. While the City has articulated a legitimate interest that
might prove to be paramount in some circumstances, that interest pales in comparison to
Defendant’s interest in being able to litigate the City’s entitlement to the assessment. Additionally,
the Wilmington administrative appeal would not have provided Defendant the remedy it seeks in
this forum because the Wilmington City Code only grants prospective relief and does not permit
parties to appeal fees that were already assessed. Wilmington City Code § 45-53(d)(7).
Accordingly, the Court concludes that Defendant’s interests outweigh Plaintiff’s in this case, and
declines to apply the exhaustion doctrine.3
Plaintiff’s Entitlement to Interest is Not Amenable to Judgment on the Pleadings
Defendant contends that Plaintiff cannot recover interest because the United States has not
waived its sovereign immunity with respect to claims for interest under the Clean Water Act.
Plaintiff acknowledges the longstanding rule that the waiver of sovereign immunity “for pre- and
post-judgment interest must be separate and distinct from the general waiver of sovereign
immunity upon which the suit is based.” Pl.’s Opp’n 2 (citing Marathon Oil Co. v. United States,
374 F.3d 1123, 1126-27 (Fed. Cir. 2004)). However, Plaintiff argues that the Clean Water Act
unambiguously waives the United States’ sovereign immunity regarding interest. The statute
provides in relevant part:
Each department, agency, or instrumentality of the executive, legislative, and
judicial branches of the Federal Government (1) having jurisdiction over any
property or facility, or (2) engaged in any activity resulting, or which may result, in
the discharge or runoff of pollutants, and each officer, agent, or employee thereof
in the performance of his official duties, shall be subject to, and comply with, all
Federal, State, interstate, and local requirements, administrative authority, and
3
Defendant also makes a sweeping argument that the exhaustion doctrine is inapplicable as
a matter of law because “it is [Plaintiff] and not the United States that is seeking a judicial remedy.”
Def.’s Resp. 9 (citing Palladian Partners, Inc. v. United States, 783 F.3d 1243, 1255 (Fed. Cir.
2015)). Defendant’s reliance on Palladian is misplaced, as Palladian did not question whether the
exhaustion doctrine could be invoked against a Defendant. Moreover, the exhaustion doctrine may
apply to matters sought to be raised as a defense, as well as to a plaintiff’s direct claim. See, e.g.,
McGee v. United States, 402 U.S. 479, 485-86 (1971) (in criminal prosecution for failing to appear
for draft induction, petitioner was prohibited from raising a defense that he was exempt from the
draft as a conscientious objector, where he failed to exhaust administrative remedies); United
States v. California Care Corp., 709 F.2d 1241, 1248-49 (9th Cir. 1983) (healthcare providers were
foreclosed from raising defense against Government suit for return of Medicare overpayments due
to their failure to exhaust administrative remedy for challenging the Government’s overpayment
determination).
6
process and sanctions respecting the control and abatement of water pollution in
the same manner, and to the same extent as any nongovernmental entity including
the payment of reasonable service charges.
* * *
This subsection shall apply notwithstanding any immunity of such agencies,
officers, agents, or employees under any law or rule of law.
33 U.S.C. § 1323(a) (emphasis added).
Although the question of whether Plaintiff can recover interest from the Federal
Government is purely a legal issue, the Court declines to resolve the issue at this preliminary stage
of proceedings as it raises a thorny issue of first impression in this Court. “A motion for judgment
on the pleadings should be denied unless it appears to a certainty that [the nonmoving party] is
entitled to no relief under any state of facts which could be proved in support of [its] claim.” Johns-
Manville Corp., 12 Cl. Ct. at 14 (internal citations omitted).
Section 1323(a) of the Clean Water Act makes the Government “subject to” and requires
it to “comply with” Federal, State, and local requirements “in the same manner, and to the same
extent as any nongovernmental entity.” Here, the United States is a property owner in the City of
Wilmington subject to that locality’s Code and is required to pay reasonable stormwater charges
in the same manner and to the same extent as any nongovernmental entity.
Section 45-53 of the Wilmington City Code, which authorizes stormwater charges, is
contained in Article II (“Sewers, Sanitary and Storm Water Rates and Charges”) of Chapter 45
(“Utilities”) of the Wilmington City Code. The interest provision, Wilmington City Code § 45-
176(c), entitled “Water and sewer charges; interest, penalties and costs; limitation of actions,” is
contained in Article III, entitled “Water Supply and Service Regulations.” The interest provision
provides in relevant part that:
if any water facilities charges or water usage charges, or sewer system charges, or
any combination thereof, imposed pursuant to the provisions of this article and of
article II of this chapter are not paid when due . . . interest shall become due and
payable as of the first day of each month on the total amount of any such unpaid
charges, but not including any penalties imposed, at the annual rate of 24 percent
on the total amount of charges unpaid for up to one year and at the annual rate of
36 percent on the total amount of charges unpaid for more than one year . . .
Wilmington City Code § 45-176(c) (emphasis added).
The parties dispute whether this Code provision applies to the assessment at issue.
Defendant contends that this provision “does not apply to storm water” related charges, which
Defendant asserts are not “facilities charges,” “water consumption,” or “sewer charges.” Def.’s
Mot. 7-8. Plaintiff replies that “‘[s]ewers’ is a generic term that broadly encompasses conveyance
of both of the referenced types of water – ‘sanitary’ wastewater (i.e., sewage) and storm water,”
7
and the Code permits interest to be assessed for stormwater charges against all property owners
that fail to pay charges on time. Pl.’s Opp’n 9, 11.4
Given the parties’ dispute as to whether stormwater charges under the Wilmington City
Code § 45-53 constitute “water facilities charges or water usage charges, or sewer system charges,
or any combination thereof” under Wilmington City Code § 45-176(c), and thus, are subject to
interest on the unpaid stormwater charges at issue, Defendant’s motion for judgment on the
pleadings fails.
This Court recognizes that the United States District Court for the Northern District of New
York found that the Clean Water Act does not permit the recovery of prejudgment interest against
the United States. However, that Court was not called upon to address the language of the Clean
Water Act requiring the Federal Government to be treated in the same fashion as nongovernmental
entities, and the parties there did not dispute whether the interest provision of the local law applied
to the charges at issue. New York State Dep’t of Envtl. Conservation v. U.S. Dep’t of Energy, 772
F. Supp. 91, 93, 104-05 (N.D.N.Y. 1991) (granting partial motion to dismiss). To this Court’s
knowledge, no other federal court has addressed whether the Clean Water Act waives the
Government’s sovereign immunity with respect to interest.
Conclusion
Plaintiff’s motion for partial judgment on the pleadings is DENIED, and Defendant’s
motion for partial judgment on the pleadings is DENIED.
The parties shall file a joint proposed schedule for further proceedings by March 23, 2018.
This schedule shall include deadlines for discovery, dispositive motions, as well as proposed trial
dates, and the location of trial.
s/Mary Ellen Coster Williams
MARY ELLEN COSTER WILLIAMS
Judge
4
Plaintiff also cites an internal Government memorandum, which it claims suggests the
Navy and DOD believed that while “[i]nterest, penalties, or late fees” levied prior to the
amendment of the Clean Water Act in January 2011, were not payable because the statute does not
apply retroactively, interest levied subsequent to the amendment could be payable. In this
memorandum, dated April 9, 2012 and entitled “Payment of Reasonable Stormwater Service
Charges,” the Navy’s Deputy Director for Energy and Environmental Readiness advised Navy
installations that:
A stormwater fee, charge, or assessment found to be reasonable under these criteria
is payable even if it denominated a tax. Note that Clean Water Act amendments
are not retroactive; only those reasonable service charges assessed after January 4,
2011 may be paid by DoD facilities. Interest, penalties, or late fees levied after
January 4, 2011 for stormwater charges assessed prior to January 4, 2011 are also
not payable.
Pl.’s Opp’n Ex. A, at 2.
8