STATE OF VERMONT
SUPERIOR COURT — ENVIRONMENTAL DIVISION
{
Williamson Building Permit Application { Docket No. 248-12-09 Vtec
Williamson NOV { Docket No. 184-11-10 Vtec
Williamson Belfry Application { Docket No. 185-11-10 Vtec
Town of Georgia v. Williamson { Docket No. 14-2-11 Vtec
Williamson Third Tier Application { Docket No. 55-4-12 Vtec
{
ALTERED1
Decision on Motion to Approve and Enforce Settlement Agreement
This decision was originally issued on November 1, 2012. The Court has been considering these
five (5) individual matters in a coordinated manner pursuant to Vermont Rules for Environmental Court
Proceedings Rule 2(b). In response to a recent motion filed by the Town of Georgia, the parties dispute
whether this decision is a final decision in any of these matters. To clarify and bring certainty to this
question, we alter the format of this decision. The conclusions of this decision remain unchanged.
The Town of Georgia (Town) filed a motion to approve and enforce a settlement
agreement executed on March 15, 2011 between the Town and Michael Williamson (Applicant).
Parties reached the settlement agreement after this Court ordered them to mediate the issues
involved in three appeals then pending, Docket Nos. 248-12-09 Vtec (Williamson Building
Permit Application), 184-11-10 Vtec (Williamson NOV), and 185-11-10 Vtec (Williamson Belfry
(Tower) Application). These disputes relate to construction involving a camp, deck, and tower2
on Applicant’s property. Applicant opposes the motion to approve and enforce, claiming that
the settlement agreement became null and void under its own terms when he failed to fulfill
one of its provisions.
In this proceeding, the Town is represented by Amanda S. E. Lafferty, Esq. and
Applicant is represented by Michael S. Gawne, Esq.
Factual Background
For the sole purpose of putting the pending motion in context, we recite the following
facts, which we understand to be undisputed unless otherwise noted:
1The altered portions of this decision are shown in italics and strikethrough text.
2Parties use the terms “tower” and “third tier” interchangeably in their briefs. As parties capitalize the
word “Tower,” we follow that practice in the remainder of this decision.
1
1. On March 15, 2011, as a result of a court-ordered mediation, the parties reached an
agreement, which they articulated in a document entitled “Settlement Agreement” (Agreement)
and filed with this Court. (Settlement Agreement, filed Mar. 23, 2011.) Both parties and their
respective attorneys signed the Agreement. The mediation itself occurred on February 16, 2011.
2. The Agreement resolved “all issues arising out of or related to” three appeals then
pending before the Environmental Division: Docket Nos. 248-12-09 Vtec (Williamson Building
Permit Application), 184-11-10 Vtec (Williamson NOV), and 185-11-10 Vtec (Williamson Tower
Application). Agreement at 1. The parties stipulated that that the Environmental Division
would stay3 all pending cases in accordance with the agreement. Agreement at 1, ¶ 2.
3. Among other terms, the Agreement required Applicant to confirm that the property at
issue was above the flood plain by obtaining a Letter of Map Amendment (LOMA) from the
Federal Emergency Management Agency (FEMA). Agreement at 1, ¶ 3. The Agreement states
that if Applicant failed to file the LOMA with the Town by May 16, 2011, “the stay shall be
lifted and this Agreement shall be null and void.” Id.
4. Paragraph 4 of the Agreement outlines steps necessary to secure a permit for the
proposed camp and deck; it notes that the Agreement separately addresses issues relating to the
proposed Tower. Agreement at 2–3, ¶ 4.
5. Applicant did not obtain and file a LOMA by May 16, 2011, but prior to May 16, 2011, he
initiated discourse with the Town about extending the deadline. In consultation with the Town,
he eventually submitted a Letter of Map Revision based on Fill (LOMR-F) in lieu of a LOMA,4
and on November 1, 2011 the Administrative Officer granted the permits referenced in
paragraph 4.
6. Paragraph 4 of the Agreement concludes, “If the Administrative Officer issues such a
permit or permits, and the permit is not appealed, then this Agreement shall become binding
and enforceable.” Agreement at 2, ¶ 4.
7. Paragraph 5 of the Agreement provides:
3 The Agreement uses the term “stay” to refer to putting litigation on hold, but it is the practice of this
Court to use the term “continuance” for such situations. We apply the term “stay” in the context of
delaying the implementation of an act or decision of a decision-making body or a prohibition on an
applicant taking actions to further a contested development.
4 Applicant obtained a LOMA and sent it to the Town on May 31, 2011, but FEMA subsequently
rescinded it on June 7, 2011. Shortly thereafter, Applicant initiated contact with the Town and suggested
the substitution of a LOMR-F for the LOMA.
2
In full settlement of all claims by either party for damages, attorney’s fees, costs of
litigation, or fines related to the construction of the Camp, Deck[,] and/or Tower
accruing up to the date of this Agreement, twenty days after the issuance of a permit
and passage of the appeal period5 described in paragraph 4, [Applicant] shall pay to the
Town the sum of Seven Thousand Dollars. On that date, Williamson Building Permit
Application, Docket No. 248-12-09 Vtec and Williamson Tower Application, 185-11-10
Vtec shall be dismissed by stipulation of the Parties.
Agreement at 2, ¶ 5.
8. Paragraph 6 of the Agreement outlines a separate process for resolving the Tower
permit dispute. It provides, among other things, that should the Town deny the Tower
approval, then Applicant may appeal that denial; if the denial is ultimately affirmed, then any
related fines would accrue beginning from the date of the settlement agreement.
9. During the period of time when Applicant and the Town communicated regarding
potential deadline extensions and substitutes for the LOMA, Applicant began inquiring
“whether the Town would be willing to reduce the fine” in the Agreement. (Applicant’s Mem.
in Opp’n to Mot. to Approve and Enforce Settlement Agreement at 2, filed July 19, 2012.)
Despite repeated requests, the Town consistently declined to reduce the fine.
10. By its appeal to this Court, the Town alleges that Applicant has failed to pay $7,000 to
the Town as per paragraph 5 of the Agreement.
Discussion
Pending before the Court is the Town’s motion to approve and enforce the Settlement
Agreement executed after court-ordered mediation in March 2011. The Town argues that the
Agreement was an arms-length transaction fully executed by both parties and their attorneys,
and that Applicant’s failure to submit a LOMA by May 16, 2011 does not void the Agreement,
because the Town accepted Applicant’s late submission of a substitute LOMR-F and ultimately
approved the permits. Because we conclude that the Agreement is enforceable and that
Applicant’s failure to pay the agreed-upon fines constitutes a breach, we GRANT the Town’s
motion to approve and enforce the Agreement.
5 This refers to a portion of the Agreement outlining what would happen in the event that a person other
than the Agreement’s signatories appealed any eventual decision to issue the permit. No third party
appealed the Town’s decision in this case.
3
I. Whether the Settlement Agreement is Enforceable or Null and Void
The question before the Court is whether the Agreement in its entirety became null and
void upon Applicant’s failure to submit a LOMA by May 16, 2011. The facts and circumstances
in this case suggest that the Agreement did not become void because the Town’s actions in
accepting a late LOMR-F in place of the LOMA constituted a mere waiver of the timing and
form for flood plain certification. The rest of the Agreement remains intact and enforceable.
It is by now axiomatic that “[w]here there is a covenant to perform a certain thing at a
certain time, if performance of another thing, or performance at a different time, be accepted in
lieu of the other, it is an answer to an action for the nonperformance of the thing stipulated.”
Porter v. Stewart, 2 Aikens, 417, 427 (1828). Waiver is “the voluntary relinquishment of a
known right.” North v. Simonini, 142 Vt. 482, 485 (1983). Waiver occurs where one party in an
executory contract continues performance under the contract knowing that the other party has
failed to perform under the term. Lemnah v. Am. Breeders Serv., Inc., 144 Vt. 568, 578–79
(1984). It may be express or manifested by conduct. Id. at 579. Waiver requires no new
consideration. Bates v. German Commercial Accident Co., 87 Vt. 128, 128 (1913). Here, the
disputed clause required Applicant to certify that the property at issue was above the flood
plain. For this certification, the Town accepted a late LOMR-F in place of the LOMA originally
due by May 16, 2011. This conduct manifested an intent to waive the deadline for—and specific
form of—FEMA’s flood plain certification.
Of course, waiver is a concept that usually arises as a defense where a party waives a
provision then subsequently seeks to enforce it. The defense is based upon the principle that it
would be fraud to allow one party to mislead the other by giving the impression that it had
waived a provision of the contract, then later seeking to enforce that very provision. See In re
Delligan’s Estate, 111 Vt. 227, 288 (1940).
Here, however, it is not the Town that seeks to hold Applicant to the LOMA provision
that it waived; rather, it is the Applicant who seeks to use his technical breach of the LOMA
provision to declare the agreement null and void. Applicant argues that, “[w]hile the parties
have attempted to reach a substitute settlement agreement whereby a LOMR-F [would be]
submitted to the Town by October 31, 2011, they never reached an agreement.” Id. at 5.
4
Applicant emphasizes that he “never procured a LOMA, much less by May 16, 2011,” and he
therefore maintains that the Agreement is null and void by its own terms. Id.6
Waiver may be express or manifested by conduct. Applicant admits that he
“eventually submitted to the Town a copy of a LOMR-F (in lieu of a LOMA), and the Town
granted the approvals identified in Paragraph 4 of the Settlement Agreement.” (Applicant’s
Mem. in Opp. to Mot. to Approve and Enforce Settlement Agreement at 4, filed July 19, 2012.)
Paragraph 4 of the Agreement states that if the Town issues the permits identified in that
paragraph, “then this Agreement shall become binding and enforceable.” Agreement at 2, ¶ 4.
We regard the Town’s conduct in issuing the permits referenced in paragraph 4 of the
Agreement as the clearest possible manifestation that the Town accepted the late LOMR-F in
lieu of the LOMA, regardless of whether the parties memorialized this waiver in writing.
Just as in a typical waiver-as-a-defense situation it would be wrong to allow one party to
mislead the other by waiving a contractual provision then later enforcing the same, here it
would be wrong to allow Applicant to enjoy the permits that the Town issued after waiving the
details of the LOMA provision, then use the technical breach of that very provision as grounds
for voiding the Agreement and escaping payment of agreed-upon fines. The Town could and
did waive the technical details of the FEMA flood plain certification in issuing the permits in
paragraph 4 of the Agreement. The rest of the Agreement remains intact and enforceable.
II. Review for Unconscionability
The parties do not dispute that this Court has jurisdiction to enforce the Agreement, the
underlying appeals for which are still pending on our docket. See Petition of Telesystems
Corp., 148 Vt. 411, 412–13 (1987) (determining that a trial court has jurisdiction to enforce a
settlement agreement in an action still pending and active on the court’s docket, even when the
terms of the agreement are not yet incorporated into an order). Before doing so, however, a trial
court retaining jurisdiction must review the terms of the settlement agreement so as to
6 In his supplemental reply brief, Applicant states, “[W]hile the parties attempted to reach a new settlement
agreement whereby the Town would agree to accept a LOMR-F in lieu of a LOMA and to extend the date of its
procurement, [Applicant] also wanted the Town to reduce, if not eliminate, the fine. Since the Town was
unwilling to do so, a new agreement was never reached.” Applicant’s Supplemental Mem. In Opp. To Mot. To
Approve and Enforce Settlement Agreement at 1, filed August 10, 2012.) (emphasis added). The fact that the
Town agreed to waive the technical requirements of the flood plain certification but did not additionally
agree to modify an essential term of the contract by reducing or eliminating the agreed-upon fee is
immaterial.
5
“minimize the possibility that unconscionable terms of settlement are accorded the force and
effect of a judgment order.” Id. at 413.
The proper inquiry for unconscionability is whether there exists evidence of
“overreaching on the part of one of the parties such as that which results from an inequality in
bargaining power or under other circumstances in which there is an absence of meaningful
choice . . . together with contract terms which are unreasonably favorable to that party.” Maglin
v. Tschannerl, 174 Vt. 39, 45–46 (2002). Although Applicant’s opposition memorandum
recounts his efforts to convince the Town that the agreed-upon fine was too high, he does not
allege that the fine provision—or any other provision of the Agreement—rises to the level of
unconscionability. We have completed our own review of the Agreement, and we cannot find
any terms that could be deemed unconscionable. Even if Applicant could have obtained more
favorable settlement terms, basic principles of contract law forbid us—absent a showing of
unconscionability—from remaking parties’ contracts. See Grievance of Graves, 147 Vt. 519, 523
(1986) (the court must interpret, rather than remake or ignore, contract language). Both parties
were represented by counsel at the mediation. They signed the agreement a month after the
mediation, leaving ample time to review its terms. We regard the agreement as conscionable
and enforceable. We therefore GRANT the Town’s motion to approve the settlement
agreement.
III. Whether Applicant Breached the Settlement Agreement
Paragraph 5 of the Agreement states:
In full settlement of all claims by either party for damages, attorney’s fees, costs of
litigation, or fines related to the construction of the Camp, Deck[,] and/or Tower
accruing up to the date of this Agreement, twenty days after the issuance of a permit
and passage of the appeal period described in paragraph 4, [Applicant] shall pay to the
Town the sum of Seven Thousand Dollars.
Agreement at 2, ¶ 5. Over 20 days have passed since the Town issued the permit described in
paragraph 4 of the Agreement, the period for appeals by third parties expired without any such
appeal, and Applicant has not paid the $7,000 fine. Applicant therefore breached the
Agreement. As noted in footnote 4 above, the Agreement provides a separate process for
resolving the dispute related to the Tower. See Agreement at 3, ¶ 6.
6
Conclusion
For the reasons detailed above, we GRANT the Town’s motion to approve and enforce
the parties’ Settlement Agreement. We conclude that the Town’s waiver of the technical
requirements of the FEMA floodplain certification leaves the remainder of the Settlement
Agreement binding upon the parties, and we approve the Agreement’s terms as conscionable.
Pursuant to the parties’ Settlement Agreement, Applicant shall pay to the Town the sum of
Seven Thousand Dollars within twenty days of the date of this decision. Once this payment is
made, the parties may timely file a stipulation for dismissal of the matters indicated in
paragraph 5 of the Agreement.
Based on the terms of the Settlement Agreement, the following two (2) matters are hereby
DIMISSED: Williamson Building Permit Application, Docket No. 248-12-09 Vtec and Williamson
Tower Application, 185-11-10 Vtec. A Judgment Order accompanies this Decision and this decision
completes all proceedings in these two matters.
A hearing has been previously noticed in Williamson Third Tier Application, Docket No. 55-4-12
Vtec. The hearing is scheduled for May 14, 2013, to take place in the Vermont Superior Court, Franklin
Civil Division, St. Albans, Vermont. This hearing is limited to this single matter. The other two matters
remaining before the Court, Williamson NOV, Docket No. 184-11-10 Vtec and Town of Georgia v.
Williamson, Docket No. 14-2-11 Vtec are hereby placed on inactive status to await the outcome of the
proceedings in Williamson Third Tier Application, Docket No. 55-4-12 Vtec.
Done at Burlington, Vermont this 13th day of March, 2013.
Thomas G. Walsh,
Environmental Judge
7