Feeley Construction Permits

Court: Vermont Superior Court
Date filed: 2011-01-03
Citations:
Copy Citations
Click to Find Citing Cases
Combined Opinion
                                   STATE OF VERMONT

                               ENVIRONMENTAL COURT

                                           }
In re: Feeley Construction Permits         }
        Nos. 19687 & 21006                 }         Docket Nos. 4-1-10 Vtec & 5-1-10 Vtec
        (Appeals of Doane)                 }
                                           }

                              Decision and Order on
      Appellees’ Renewed Motion for Summary Judgment to Dismiss as Untimely

       In January of 2010, Appellants Frederick and Heike Doane (Appellants) filed the

above-captioned appeals from two concurrently issued decisions of the Development

Review Board (DRB) of the Town of Colchester, ruling that Appellants’ attempted

appeals of two zoning permits issued to Appellees Richard and Theresa Feeley

(Appellees) were untimely.       Appellants are represented by Robert T. Gaston, Esq.;

Appellees are represented by Matthew T. Daly, Esq.             The Town is represented by

Thomas G. Walsh, Esq., but has not taken an active role regarding the pending motions.

       In Docket No. 4-1-10, Appellants seek to appeal the DRB’s decision regarding

permit #19687, issued on August 15, 2005 (the 2005 Permit), which authorized Appellees

to construct a replacement shed, replacement set of stairs, and new decks on their

property. In Docket No. 5-1-10, Appellants seek to appeal the DRB’s decision regarding

permit #21006, issued on June 26, 2008 (the 2008 Permit), which authorized Appellees to

construct a second replacement deck and set of stairs on their property. As noted in this

Court’s June 16, 2010 decision in this matter, at 14, “[b]ecause Appellants filed their

notices of appeal with the DRB years after the expiration of the appeal periods, both

appeals are untimely and must be dismissed unless some other circumstance justifies

the filing of a late appeal of either permit.”



                                                 1
      Appellees initially moved for summary judgment to dismiss both appeals as

untimely. The Court’s June 16, 2010 decision analyzed Appellants’ apparent three main

arguments and ruled that material facts were in dispute, or at least had not then been

provided to the Court, to allow the Court to dismiss either appeal on summary

judgment.    The decision gave the parties an opportunity to provide the missing

information and to renew the motion, so as to avoid an unnecessary trial to establish

essentially uncontested facts. The facts as stated in the June 16, 2010 decision are

repeated here as necessary, augmented by the additional information presented in

connection with the parties’ renewed motion memoranda.



Factual and Procedural Background

      Appellees own a parcel of property located at 73 Irish Cove in Colchester,

containing a seasonal dwelling or camp building that Appellees use during the summer

months.     Appellees’ property is located on the shore of Lake Champlain in the

Shoreland overlay zoning district. Appellees’ camp building is located close to the

elevation of the lake and is reached by a stairway leading down from the higher

elevation of the roadway; the camp building itself is not visible from the higher

elevation. Access to Appellees’ property is by a private, dead-end road marked “Irish

Cove,” leading from Marble Island Road, the nearest public road.1

      Appellants currently own a parcel of property on the shore of Lake Champlain

adjacent to and northerly of Appellees’ parcel, having the address of 1021 Marble Island

Road, and containing a house constructed in 2008 that Appellants use during the

summer months.      Material facts have not been provided as to the date on which


1
       Neither party has provided a map or diagram showing the private and public
roadways in the area nor the location of the 73 Irish Cove parcel, building, or driveway
in relation either to Appellants’ present property at 1021 Marble Island Road or to
Appellants’ former condominium unit at 1067 Marble Island Road.
                                           2
Appellants acquired this property.2 Access to Appellants’ property is directly from

Marble Island Road. In 2005, Appellants owned a condominium unit (Unit #4) located

in a condominium development having the overall address of 1067 Marble Island Road.

Appellants acquired the condominium unit in June of 2005 and were regularly present

at the condominium unit during its remodeling from June of 2005 through January of

2006.

        On August 11, 2005, Appellees submitted zoning permit application #19687 (the

2005 Application), seeking to replace an existing set of stairs leading along the south

side of the camp building from the road down to the camp building; to replace an

existing 6’ x 7’ shed with a new 8’ x 10’ shed adjacent to the stair landing and to

construct an 8’ x 10’ deck over the top of the new shed; and to construct a new 10’ x 17’

deck to the south3 of the camp building itself, with two steps leading down from it to

the ground surface.

        Appellees attached five diagrams or drawings to the 2005 Application form: one

diagram depicting the existing layout of the property; two diagrams depicting plan

views of the proposed layout, setbacks, and construction; one drawing showing the

west or lake side elevation of the proposed new shed and the upper portion of the

stairs; and one drawing showing the south side elevation of the whole property from

the road down to the lake, including the new stairs, the new shed, the new decks, and

the existing camp building.    Appellees signed the application “certify[ing] that all

information, including attachments, in this application are complete, true and accurate.”

2       This fact may be material to Appellants’ standing in 2005 to have brought any
appeal to the DRB regarding Appellees’ property.
3       By comparison of the 2005 application with the 2008 application, it appears that
the 2005 deck was the one on the south side of the camp building, at the foot of the
stairs. The 2005 application did not propose any construction on the north side of the
camp building, and showed the side setback from the north property line to the camp
building as measuring 57 feet. It did not show an existing 12’ x 12’ deck to the north of
the camp building, at issue in the 2008 application.
                                           3
       The Zoning Administrator approved the 2005 Application on August 15, 2005,

granting permit #19687 (the 2005 Permit). Material facts are in dispute as to whether

Appellees posted notice of the 2005 Permit within view from the public right-of-way

most nearly adjacent to the subject property, as required by 24 V.S.A. § 4449(b); facts are

also disputed regarding what Appellees were advised to do by the Zoning

Administrator, if anything, regarding the posting requirements in 2005.

       The 2005 Permit stated that “[c]onstruction shall not commence before 8/30/05,”

that is, during the fifteen-day appeal period for an appeal to be taken to the DRB under

24 V.S.A. § 4465(a). Interested persons seeking to appeal the Zoning Administrator’s

issuance of the 2005 Permit therefore had until August 30, 2005, to file a timely appeal

with the DRB; no such appeal was filed within the fifteen-day period.

       At some time prior to October 11, 2005, Appellees completed the proposed work.

Material facts have not been provided to the Court as to Appellants’ opportunity to

observe any construction or presence of outdoor structures at Appellees’ property,

either from the land or from the lake, during mid-August to mid-October of 2005,

except that they were present at their 1067 Marble Island Road condominium in the

summer and fall of 2005. At no time during construction pursuant to the 2005 Permit

did Appellants seek to take a late appeal of the 2005 Permit to the DRB, nor did

Appellants raise the issue at that time that the posting of the notice of permit was

deficient.

       On October 11, 2005, the Zoning Administrator inspected the completed work

and issued a Certificate of Occupancy/Compliance to Appellees under § 11.04 of the

Zoning Regulations.4 24 V.S.A. § 4449(a)(2). No party appealed or attempted to appeal

the Zoning Administrator’s action in issuing the Certificate of Occupancy/Compliance,

either in October of 2005 or since that time.

4       The Town of Colchester Zoning Regulations                    are    available    at
http://colchestervt.gov/PlanningZ/zoningregs.shtml.
                                                4
      Material facts have not been provided to the Court as to Appellants’ presence at

or use of their 1067 Marble Island Road condominium unit at any time during either

2006 or 2007. Material facts have not been provided to the Court as to Appellants’

opportunity to observe the presence of outdoor structures at Appellees’ property, either

from the land or from the lake, during the period from mid-October of 2005 through the

end of 2005, or at any time in 2006, or at any time in 2007, or during the first half of

2008. During the summer of 2008, Appellants continued to use the condominium at

1067 Marble Island Road while their 1021 Marble Island Road house was under

construction on their property adjacent to Appellees’ property.

      On June 25, 2008, Appellees submitted zoning permit application #21006, seeking

approval to “construct/replace deck – accessible + stairs.” From the application and its

attached documents it appears that this application related to a proposal to remove an

existing 12’ x 12’ deck located to the north of the camp building, between it and the

north side property line, and to install a 12’ x 36’ ± deck between the north side of the

camp building and the north property line, with a tall “privacy fence” along the

property line, and a short solid fence along the westerly side of the deck. Appellees

attached four documents to the 2008 application form: one diagram depicting the then-

existing layout of the property; one diagram depicting the proposed layout of the new

north side deck, the location of the old deck to be removed, and the proposed privacy

fencing and low fencing; a hand-drawn east elevation showing the proposed fencing,

and a hand-written description of some of the proposed work. Appellees signed the

application “certify[ing] that all information, including attachments, in this application

are complete, true and accurate.”

      The Zoning Administrator approved the application on June 26, 2008, granting

permit #21006 (the 2008 Permit). Material facts are in dispute as to whether Appellees

posted notice of the 2008 Permit within view from the public right-of-way most nearly

adjacent to the subject property, as required by 24 V.S.A. § 4449(b); facts are also
                                            5
disputed regarding what Appellees were advised to do by the Zoning Administrator, if

anything, regarding the posting requirements in 2008.

        The 2008 Permit stated that “[c]onstruction shall not commence before 7/11/08,”

that is, during the fifteen-day appeal period for an appeal to be taken to the DRB under

24 V.S.A. § 4465(a).   Interested persons seeking to appeal the Zoning Administrator’s

issuance of the 2008 Permit therefore had until July 11, 2008, to file a timely appeal with

the DRB; no such appeal was filed within the fifteen-day period.

        Within a month of receiving the 2008 Zoning Permit, Appellees completed the

proposed work. Material facts have not been provided to the Court as to Appellants’

opportunity to observe any construction or presence of outdoor structures at Appellees’

property during June and July of 2008, either from the land or from the lake, other than

the fact that Appellants were residing at their 1067 Marble Island Road condominium

unit while their 1021 Marble Island Road house was being constructed in the summer of

2008.   At no time during Appellees’ construction pursuant to the 2008 Permit did

Appellants seek to take a late appeal of the 2008 Permit to the DRB, nor did Appellants

raise the issue at that time that the posting of the notice of permit was deficient.

         On July 24, 2008, the Zoning Administrator inspected the completed work and

issued a Certificate of Occupancy/Compliance to Appellees. No party appealed the

Zoning Administrator’s action in issuing the Certificate of Occupancy/Compliance,

either in the summer of 2008 or since that time.

        Material facts have not been provided to the Court as to Appellants’ opportunity

to observe the presence of the outdoor structures at Appellees’ property, either from the

land or from the lake, during the period from August of 2008 through the filing of this

appeal in October of 2009. After receiving information in mid-March of 2009 that Mr.

Feeley had alleged that Mr. Doane was cutting trees in the Shoreland setback, Mr.

Doane inspected the Feeley property in late March of 2009; he characterized his state of

mind at that inspection to the DRB as having been “surprised” by how large the decks
                                              6
and stairs were. In re: Property of Richard & Theresa Feeley, Permit Nos. 19687 and

21006, Findings of Fact, at 2 (Town of Colchester DRB Dec. 9, 2009). Appellants did not

attempt to file a late appeal of either permit between Mr. Doane’s observations in March

of 2009, and October 15, 2009, when the present two appeals were filed with the DRB.

       On September 24, 2009, Appellants met with the Director of Planning and

Zoning and the Zoning Administrator for the Town of Colchester, having provided

them a few days in advance of the meeting with a five-page “Historic Outline” with

twelve attached exhibits. Approximately two pages of the outline dealt with the history

of the Feeley construction and its asserted noncompliance with the Zoning Regulations

and with the Town’s “Shoreland District Stairs Interpretation.”5 Approximately two

pages of the outline dealt with the so-called “false accusations” from Mr. Feeley that

Appellants had cut trees in the Shoreland zoning district, which had resulted in a 2007

and a 2009 notice of violation, both of which were later withdrawn by the Town after

investigation.    The “Conclusion” section of the “Historic Outline” document

characterized the document as an “aid” to the scheduled September 24, 2009 meeting,

“merely highlighting interactions between” the Doanes, the Feeleys, and the Town’s

representatives. To the extent that the document requested any action by the Zoning

Administrator at all, that request was stated in full, at 4–5, as follows:

       The predominant point sought is the disparity in the manner in which the
       Town has related to Mr. and Mrs. Doane and Mr. Feeley. The Town has
       not hesitated to charge Mr. and Mrs. Doane with violations based on little
       or no evidence whatsoever while at the same time providing Mr. and Mrs.
       Feeley with building permits with little or no apparent investigation in a
       short period of time without proper notice to the public or hearing before
       the [DRB], notwithstanding the inadequacies of their permit application
       and the extant violations resulting from the permitted construction. In
       short, Mr. Feeley has falsely charged Mr. and Mrs. Doane with violations

5      This “interpretation” is stated in a July 6, 2005 memorandum from Brenda M.
Green, Director of the Planning and Zoning Department of the Town of Colchester, to
the Planning and Zoning Staff.
                                              7
      while Mr. Feeley’s property stands in continuing violation. What can be
      done?
      Two weeks after the September 24, 2009 meeting, the Town’s attorney wrote to

Appellants on behalf of the Town, referring to the issues discussed at the meeting and

raised in the Historical Outline. The letter informed Appellants that “[p]ursuant to the

exclusivity-of-remedy provision of § 4472(d), the Town and all interested parties are

precluded from challenging the Feeley[s’] previous permits . . . [a]s no one took issue

with the permits . . . by filing an appeal within the appeal periods,” making them “final

and binding.” Letter from Thomas G. Walsh, Colchester Town Attorney, to Appellants

(Oct. 8, 2009).    The letter also stated that the 2005 and 2008 Certificates of

Occupancy/Compliance had not been appealed and had become final, also precluding

Appellants from challenging the two underlying permits.           Id.   Even if the town

attorney’s letter can be considered an action of the zoning administrator and therefore

appealable to the DRB under 24 V.S.A. § 4465(a), the letter only explains why the

permits cannot now be appealed. The letter does not refer to or deny any request for

revocation of either permit or any request for enforcement of the Zoning Regulations.

      On October 15, 2009, more than four years after the 2005 Permit and its related

2005 Certificate of Compliance were issued, more than a year after the 2008 Permit and

its related 2008 Certificate of Compliance were issued, and approximately seven months

after observing the finished construction, Appellants filed two identical “applications

for appeal” (notices of appeal) with the DRB: one seeking to appeal the 2005 Permit and

one seeking to appeal the 2008 Permit.6


6       This Court’s June 16, 2010 decision referred to the absence of these notices of
appeal to the DRB as being missing material facts. In response to that decision, in their
filing internally dated July 22, 2010, and filed with the Court on July 26, 2010, Appellees
attached new copies of the two DRB decisions and copies of Appellants’ two notices of
their appeals from the DRB to this court (which, of course, the Court already had).
They did not provide copies of the notices of appeal filed to the DRB seeking appeal of
                                            8
      However, neither notice of appeal purported to be an appeal to the DRB from

any decision of the Zoning Administrator, whether declining to take enforcement action

or declining to initiate revocation proceedings.    Instead, under ¶ 6 of each notice,

entitled “Appeal Type,” which gives options for either “appeal of decision of Zoning

Administrator” or “[appeal of] Notice of Violation,” both of the boxes available to check

off for the two types of appeal were left blank. Rather, also within ¶ 6 “Appeal Type”

(but on the line for “[p]rovision of zoning ordinance in question”), Appellants stated

“Appeal of Building Permit # 19687” (for the 2005 Permit) and stated “Appeal of

Building Permit # 21006” (for the 2008 Permit).

      On November 13, 2009, Appellants, now represented by counsel, filed a pre-

hearing memorandum with the DRB. The memorandum laid out Appellants’ argument

that Appellees’ failure to post the proper notice of the issuance of the permits

automatically rendered the permits null and void; and laid out various “omissions and

misstatements” in both permit applications. The memorandum argued that “if the

material facts had been fully disclosed, . . . the Town would have been warranted in

denying the building permits” and that the “omissions and misstatements provide the

Town with . . . grounds for revoking the permits.” The “Conclusion” section of the pre-



the Zoning Administrator’s decisions, which is what the June 16, 2010 decision had
stated was necessary in order for the Court to determine the scope of Appellants’
appeal to the DRB. Attorney Daly’s letter to the Court filed August 24, 2010, reiterated
that his office had “filed the Notices of Appeal” together with the July 22, 2010 filing;
however, these were not the notices of appeal to the DRB found necessary by the Court.
       Similarly, although Attorney Gaston’s letter filed with the Court on August 23,
2010, stated that “[e]nclosed herewith are copies of the two Appeals to the DRB by
Appellants,” in fact the documents that were attached were two copies of the appeal of
the 2005 Permit and no copy of the notice of appeal of the 2008 Permit. Upon request of
the Court staff in connection with this renewed motion, on December 14, 2010,
Appellants filed a copy of the notice of appeal to the DRB filed by Appellants regarding
the 2008 Permit; it is identical to the notice of appeal to the DRB of the 2005 Permit
except for the difference in permit number.
                                           9
hearing memorandum stated that “both of the appeal permits are null and void and

should be revoked under controlling law”; that “[d]oing nothing renders the

Regulations meaningless”; and that “[t]o lend meaning, enforcement i[s] required.”

This memorandum did not appear to make any specific request for enforcement action,

except to the extent that Appellants may have thought of revocation of the permits as a

type of enforcement.

      The DRB held a consolidated hearing on the two appeals on November 18, 2009.7

The DRB issued concurrent decisions on December 9, 2009 (the 2009 DRB Decisions),

ruling that both appeals were untimely under 24 V.S.A. § 4465(a), and that “all parties,

including the Town, are bound per [24 V.S.A. § 4472(d)].” In re: Property of Richard &

Theresa Feeley, Permit Nos. 19687 and 21006, Findings of Fact, at 3 (Town of Colchester

DRB Dec. 9, 2009).

      Appellants appealed the 2009 DRB Decisions to this Court in the present appeals.

The notices of appeal filed with this Court state that each appeal “is taken against

[Appellees] and the Town of Colchester for failing to follow and enforce the Town’s

Zoning Regulations.” Appellants filed the following ten questions as their statement of

questions in each appeal:

      1.     Did [Appellees’] notice of permit fail to meet the statutory
      requirement because it was not within view from the public right-of-way
      closest to [Appellees’] property?
      2.     Did the Town lack jurisdiction to take any action following the
      defective notice?
      3.     Because of the lack of the statutory required notice, will
      [Appellants’] rights of constitutional due process or fundamental
      administrative fairness be denied if they are not allowed to proceed with
      their appeal?


7     Appellants have provided a DVD copy of the local cable television’s electronic
recording of the hearing, which the Court has reviewed solely to determine the scope of
the DRB hearing, as this is a de novo appeal.
                                          10
      4.    Were there omissions or misstatements of material fact by
      [Appellees] or their agent in their application (or at any hearing) which
      would have warranted refusing the permit?
      5.    Because of such omissions or misstatements of fact, is the subject
      permit revocable at any time?
      6.     Was this appeal timely as to the [A]ppellants’ notice to the Town of
      violations by [Appellees]?
      7.    Did the Town, through its representatives, fail to follow and
      enforce its own zoning regulations?
      8.      Did [Appellees] violate the Town’s Zoning Regulations?
      9.      Should the permit be revoked and the property restored to its prior,
      or a legitimate, state?
      10.   Should this matter be remanded to the Town for a full hearing and
      consideration?


Appellees’ Motion for Summary Judgment

      Under the statutory scheme governing appeals to this Court, actions of the

Zoning Administrator, including appeals of notices of violation issued by zoning

administrators, may be directly appealed only to the DRB.8 24 V.S.A. § 4465. The form

“application for appeal” filled out by Appellants in each of the present two cases

reflects this jurisdiction by listing two options to be checked off under ¶ 6 “Appeal

Type”: either “appeal of decision of Zoning Administrator” or “[appeal of] Notice of

Violation.”

      Only decisions of the DRB (or other municipal panel) may be appealed directly

to this Court. 24 V.S.A. § 4471. In a de novo appeal such as this, the Court sits in place

of the DRB to consider what was before the DRB, applying the substantive standards


8
       As well as their jurisdiction over direct appeals from actions of a zoning
administrator, DRBs also have jurisdiction to perform the reviews of development
applications and variances listed in 24 V.S.A. § 4460(e), not at issue in the present
appeals.
                                           11
that were applicable before the DRB. V.R.E.C.P. 5(g); 10 V.S.A. § 8504(h); see, e.g., In re

Maple Tree Place, 156 Vt. 494, 500 (1991) (stating that the “court is limited to

consideration of the matters properly warned as before the local board” (citing In re

Torres, 154 Vt. 233, 235 (1990)); In re: Kibbe Zoning Permit, No. 173-8-07 Vtec, slip op. at

1–2 (Vt. Envtl. Ct. Nov. 6, 2008) (Wright, J.).



       Scope of Appellants’ Applications for Appeal to the DRB

       Neither “application for appeal” (notice of appeal) that Appellants filed with the

DRB even purported to be an appeal from any action of the Zoning Administrator. Nor

do the applications for appeal mention any request made by Appellants asking the

Zoning Administrator to take any action to revoke the permits, or to take any

enforcement action against Appellees for failure to comply with the Zoning

Regulations.     Rather, under ¶ 6 of each application regarding “Appeal Type,”

Appellants stated “Appeal of Building Permit # 19687” (for the appeal of the 2005

Permit) and stated “Appeal of Building Permit # 21006 (for the appeal of the 2008

Permit). Each notice of appeal stated the following three reasons under ¶ 7, entitled

“REASON FOR APPEAL”

       1) defective notice of appeal period (for decision by administrative
       officer – see 24 VSA sec 4464)
       2) misstatement of material fact on application warranting refusal of
       permit (Town of Colchester Zoning Regulations, Article 11.08)
       3) Violation of Town of Colchester Zoning Regulations
In its decisions on both appeals, the DRB itself characterized the appeals as being

attempted appeals of the original 2005 and 2008 Permits, and not as being appeals from

any subsequent request made asking the Zoning Administrator either to revoke the

permits or to take enforcement action against Appellees. In re: Property of Richard &

Theresa Feeley, Permit Nos. 19687 and 21006, Findings of Fact, at 3 (Town of Colchester


                                              12
DRB Dec. 9, 2009).

      Accordingly, all that was before the DRB, and therefore all that is before this

Court in this de novo appeal, is Appellants’ attempted late appeal of the 2005 Zoning

Permit and their attempted late appeal of the 2008 Zoning Permit.



      Revocation – Questions 4, 5, and 9 of the Statement of Questions

      If Appellants ever requested the Zoning Administrator to commence revocation

proceedings, such a request does not appear to have been ruled on by the Zoning

Administrator or appealed from the Zoning Administrator to the DRB. It therefore is

beyond the scope of this appeal, in which the Court only has jurisdiction to consider

what was properly before the DRB.

      Questions 4, 5, and 9 of the Statement of Questions in each appeal, dealing with

whether Appellants made omissions or misstatements of material fact in the application

process which would have warranted refusing the permit, and therefore whether either

permit should be revoked under § 11.08 of the Zoning Regulations, are therefore

beyond the scope of these appeals, and must be dismissed. Because they are beyond the

scope of these appeals, the Court need not reach the question of whether or how § 11.08

of the Zoning Regulations is affected by 24 V.S.A. § 4455 (2009) and V.R.E.C.P. 3(9),

giving this Court jurisdiction to revoke a municipal permit for, among other things,

misrepresentation of material fact, but requiring such revocation to be done “on petition

by the municipality and after notice and opportunity for hearing.” 24 V.S.A. § 4455.



      ”Enforcement” – Questions 7 and 8 of the Statement of Questions

      Apparently in connection with their argument that both permits should be

revoked, Appellants brought to the Zoning Administrator’s attention their claims that

the deck proposed in the 2008 permit encroached farther into the north side setback

than did the previous deck that was being removed, and that therefore a permit for that
                                           13
large a deck should not have been granted and should be revoked. They also brought

to the Zoning Administrator’s attention their claims that the stairways, landings and

decks proposed in the 2005 permit exceeded the allowable dimensions for stairways

and platforms in the Shoreland District Stairs Interpretation, and that therefore a permit

for the stairs, shed, and two decks should not have been granted and should be

revoked. Questions 7 and 8 of the Statement of Questions broadly ask whether

Appellees violated the Zoning Regulations and whether the Town, through its

representatives, failed to “follow and enforce” the Zoning Regulations.

       If permits are granted in error by a zoning administrator, but those permits

become final without a timely appeal, they cannot be challenged in any later

proceeding,   including an enforcement proceeding.         24 V.S.A. § 4472(d); City of S.

Burlington v. Dep’t of Corrs., 171 Vt. 587, 588-89 (2000) (ruling that 24 V.S.A. § 4472(d)

prevents any sort of collateral attack on a zoning decision that has not been timely

appealed); Levy v. Town of St. Albans, 152 Vt. 139, 142 (1989) (ruling that

24 V.S.A. § 4472(d) prevents a collateral attack on a final zoning decision even if that

“decision was void ab initio”). The DRB, in the first instance, and this Court, in this de

novo appeal, lack jurisdiction to entertain an untimely appeal. 24 V.S.A. § 4472(d); see

also, e.g., Boutwell v. Town of Fair Haven, 148 Vt. 8, 10 (1987) (citing Harvey v. Town of

Waitsfield, 137 Vt. 80, 82 (1979)) (“The failure to effect a timely appeal extinguishes

subject matter jurisdiction.”). The absence of a timely appeal prevents the DRB or the

Court from considering the merits of an appeal, even if the administrative officer issued

a permit in error or without the statutory or regulatory authority to do so. See In re Taft

Corners Assocs., 162 Vt. 638, 639 (1994) (mem.) (citing Town of Charlotte v. Richmond,

158 Vt. 354, 357-58 (1992); Levy, 152 Vt. at 142 (1989)) (If a timely appeal of a decision of

the zoning administrator is not taken, the trial court is barred under 24 V.S.A. § 4472(d)

from asserting jurisdiction “even if the administrator’s ruling was ultra vires.”); see also

In re Tekram Partners, 2005 VT 92, ¶ 8, 178 Vt. 628 (stating that courts have “‘strictly
                                             14
enforced’ [the] exclusivity-of-remedy provision to ensure timely review of all zoning

disputes, thereby assuring parties of finality”).

       Such a property may be nonconforming due to the error of the zoning

administrator, as defined in the statute, 24 V.S.A. §§ 4303(13)–(16), but the

nonconformity is thereafter governed by and may be regulated and expanded only

under the municipal provisions regulating nonconformities required by 24 V.S.A.

§ 4412(7).

       In the present case, unless and until Appellants are granted leave to take a late

appeal of either permit, it would be premature to determine whether either permit was

granted in error. Further, as no appeal or attempted late appeal has been filed from the

Zoning Administrator’s issuance of the 2005 and the 2008 Certificates of

Occupancy/Compliance, the reasoning in Tekram prevents the Town from issuing a

Notice of Violation or taking other enforcement action. 2005 VT 92, ¶¶ 7–13 (holding

that when a certificate of occupancy has been issued for a project that is in violation of a

zoning ordinance, that certificate serves as an “approval” of the violations so that 24

V.S.A. § 4472(a) precludes the municipality from bringing a later enforcement action.).



       Accordingly, Question 7 of the Statement of Questions is DISMISSED. To the

extent that Question 8 of the Statement of Questions relates to whether the construction

proposed by either permit application meets the requirements of the Zoning

Regulations in effect at the time the application was made, it must await a

determination of whether a late appeal may be taken of either permit; otherwise, to the

extent that Question 8 relates to any possibility of the Town’s taking any enforcement

action, it is also DISMISSED.




                                             15
       Late Appeals of the 2005 or the 2008 Zoning Permit – Questions 1, 2, 3, 6 and 10

       Appellants are seeking to take late appeals of the 2005 and 2008 Zoning Permits

under 24 V.S.A. § 4465, more than four years late in the case of the 2005 Zoning Permit

and more than one year late in the case of the 2008 Zoning Permit, and in both cases

some seven months after Appellant Frederick Doane observed the completed outdoor

decks, stairway and shed that are the subject of the two permits. Appellants claim that

Appellees failed to post either permit within view from the public right-of-way most

nearly adjacent to the subject property, as required by 24 V.S.A. § 4449(b).9 Appellants

argue both that Appellees’ alleged failure to post rendered each permit “null and void,”

and that Appellees’ alleged failure to post automatically justifies Appellants’ filing late

appeals of both permits.

       Appellants rely on In re Torres, 154 Vt. 233 (1990) to argue that a lack of

subsequent posting under 24 V.S.A. § 4449(b) renders a duly-issued zoning permit

automatically “null and void.” Torres does not have such an automatic effect, and

cannot be extended to support Appellants’ position. Indeed, such a result would be

entirely unworkable, would encourage subsequent litigation between neighbors over

whether and how landowners posted their zoning permits, and would undermine the

principles of finality of zoning permits established in § 4472(a) and (d) and in Levy and

its progeny.

       Unlike the present cases, in which the permits were properly issued by the

Zoning Administrator without a prior hearing and which only required subsequent


9
       Material facts are in dispute as to the circumstances of Appellees’ posting of the
permits, including whether and where they were posted, and whether Appellees were
given any erroneous information by the Zoning Administrator or other Town official
causing them to take any specific action regarding posting the permits. Nevertheless,
the Court will proceed to analyze the requirements Appellants must satisfy to take a
late appeal, because if they are not met, it will be unnecessary to take evidence on the
circumstances of Appellees’ posting of the permits.
                                            16
posting rather than any prior notice or warning, Torres dealt with a type of permit

requiring a prior warned hearing by the ZBA.           In Torres, the Zoning Board of

Adjustment (ZBA) had only considered (and had granted) an application for a home

occupation permit. In the appeal brought by neighbors, the trial court ruled that the

application did not qualify as a home occupation but instead required conditional use

approval. However, the court proceeded to consider the merits of conditional use

approval rather than remanding it to the ZBA to be properly warned and considered in

the first instance for conditional use approval by the ZBA.         The Supreme Court

determined that the notice and hearing requirements that were a prerequisite on

application to the ZBA could not have been dispensed with by the ZBA, and therefore

that the trial court, sitting in place of the ZBA, also could not dispense with them.

Torres, 154 Vt. at 235-36. When read together with Levy and subsequent cases citing

Levy, it is apparent that Torres does not automatically invalidate actions of a zoning

administrator; instead, to challenge such actions an appeal must be taken to the DRB.

In the present case, even if Appellees failed to post as required by statute, the permits,

as actions of the Zoning Administrator, would not be automatically null and void if

they were not properly appealed.

      Therefore, the Court must turn to the methodology for determining whether

Appellants can file a very late appeal of either the 2005 Permit or the 2008 Permit.

Although their notice of appeal and statements of questions do not cite 10 V.S.A.

§ 8504(b)(2)(C), which now allows the Court to determine whether “some other

condition exists which would result in manifest injustice if the person’s right to appeal

was disallowed,” Question 3 of the Statement of Questions essentially raises this

argument in the terms stated in zoning cases prior to the adoption of the statute.10 If


10    Appellees argue that the Court should not consider whether Appellants’ appeal
meets the statutory requirement, because the notice of appeal was not accompanied by
a motion for party status under § 8504(b)(2) as required by V.R.E.C.P. 5(d)(2). However,
                                           17
Appellants had no actual or record notice of the issuance of either zoning permit until

mid-March of 2009, the Court must determine “whether due process or fundamental

administrative fairness requires” them to “be allowed to contest the permit,

notwithstanding the strong policy interests in finality.” In re Hignite, 2003 VT 111, ¶ 8,

176 Vt. 562 (mem.).11

       The statutory standard of “manifest injustice,” 10 V.S.A. § 8504(b)(2)(C), is even

more stringent than the findings of either “good cause” or “excusable neglect” required

for taking a late appeal to court under V.R.A.P. 4(d). See In re Geddes Planned Unit

Development, Docket No. 231-11-09 Vtec, slip op. at 7-8 (Vt. Envtl. Ct. April 20, 2010)

(Wright, J.); In re: Jim Sheldon Excavating, Inc., Docket No. 54-4-09 Vtec, slip op. at 3-4

(Vt. Envtl. Ct. June 8, 2009) (Wright, J.) (determination of good cause requires the Court

to find that the moving party is not at fault in failing to file a timely appeal while


that rule applies by its terms to “claims and challenges of party status,” that is, to issues
of a party’s standing to bring an appeal, not to claims that the appeal itself was
untimely when filed with the DRB.
11
        Appellants cite In re: Tuttle Street Right-of-Way, Docket No. 98-5-06 Vtec (Vt.
Envtl. Ct. Dec. 28, 2006) (Wright, J.), aff’d In re Young’s Tuttle Street ROW, 2007 VT 118,
182 Vt. 631 (mem.), in support of their argument that the Court should grant them leave
to file an untimely appeal. However, in that case, slip op. at 8, the Court ruled that the
fact that the petitioner had failed to appeal a 1996 action of the ZBA precluded her from
raising that issue in the 2006 case before the Court, in particular because she had not
“shown why she could not have sought to take a late appeal of the 1996 action [any]
earlier than the present 2004 petition.”
        In the present case, material facts are in dispute as to why Appellants did not
seek to appeal any earlier than mid-October of 2009, including as to Appellants’
opportunity to observe the construction from 2005 through 2008, as well as whether
Appellants would have met the other requirements of standing at the time of either
permits’ issuance. That is, even if Appellants show that they were unaware of the 2005
and 2008 permits when those permits were issued, the Court must nevertheless
determine “whether due process or fundamental administrative fairness,” Hignite, 2003
VT 111, ¶ 8, requires it to allow an untimely appeal of the permits, or whether “manifest
injustice” would occur in the absence of such an untimely appeal. 24 V.S.A.
§ 8504(b)(2)(C).
                                             18
determination of excusable neglect requires the Court to find that the fault was

excusable, based on consideration of: 1) the danger of prejudice to the non-moving

party; 2) the length of delay; 3) the reason for delay and whether it was within the

moving party’s control; and 4) whether the moving party acted in good faith). Even

under an excusable neglect or good cause standard, an appellant seeking to take a late

appeal must explain the delay, including any reasons why an appeal was not filed as

soon as possible after the appellant became aware of the possible need or opportunity

for an appeal. See Sheldon Excavating, Docket No. 54-4-09 Vtec, slip op. at 5.

       In the present case, material facts are disputed, or have not yet been presented,

that could resolve Questions 3 and 6 of the Statement of Questions. In particular,

Appellants have not shown why they did not attempt to file a late appeal of either

permit during the time that construction was ongoing pursuant to either permit, have

not shown what efforts they made to become aware of construction on Appellees’

property prior to mid-March of 2009, and especially have not shown why they waited

seven months (thirteen or fourteen times the normal appeal period) to attempt to file

the appeals with the DRB. In the absence of any explanation that amounts to manifest

injustice if the appeal were not allowed, both appeals are untimely.        In addition,

Appellants have not shown that, in 2005, the construction of the south side stairway,

decks, and shed on Appellees’ property had any “physical or environmental impact on

their interests” that would have given them standing to bring the appeal of the 2005

Permit, even had they seen any posted notice from the public road.               24 V.S.A.

§ 4465(b)(3).



       Accordingly, based on the foregoing, it is hereby ORDERED and ADJUDGED

that Appellees’ Renewed Motion for Summary Judgment is GRANTED in favor of

Appellees to DISMISS Questions 4, 5, 7, and 9 of the Statement of Questions in each

appeal, and to DISMISS Question 8 to the extent that it relates to the possibility of the
                                           19
Town’s taking any enforcement action.       Appellees’ Renewed Motion for Summary

Judgment is DENIED in that some material facts are in dispute as to Questions 1, 2, 3, 6,

and 10 of the Statement of Questions, and in that Question 8, as it relates to whether the

construction proposed by either permit application meets the requirements of the

Zoning Regulations in effect at the time the application was made, must await the

determination of whether either of the appeals was timely.

      A telephone conference has been scheduled (see enclosed notice).            At the

conference, the parties should be prepared to discuss setting a schedule for mediation in

this and the newly filed Act 250 case involving the same parties, as well as to determine

the time required for any evidentiary hearing necessary to determine whether

Appellants should be allowed to file a late appeal of either permit. In particular, the

parties should be prepared to discuss whether Questions 3 and 6 as to the timeliness of

either appeal should be heard and resolved first, that is, to determine whether

Appellants should be given leave to take the late appeals, even assuming that the

posting did not meet the requirements of the state statute.



      Done at Berlin, Vermont, this 3rd day of January, 2011.




                           _________________________________________________
                                 Merideth Wright
                                 Environmental Judge




                                           20