STATE OF VERMONT
ENVIRONMENTAL COURT
In re: Appeal of Watker, et al. }
}
} Docket No. 143-9-01 Vtec
}
}
Decision and Order on Appellants= Motion for Reconsideration
Appellants appealed from a decision of the Development Review Board (DRB) of the City of
Barre, granting resubdivision approval to Appellee-Applicant Fecteau Residential Homes, Inc.
Appellants are represented by L. Brooke Dingledine, Esq.; Appellee-Applicant is represented by
John F. Nicholls, Esq.; the City is represented by Oliver L. Twombly, Esq. The Court decided all
issues in the case by summary judgment in a decision issued on December 12, 2001; Appellants
request consideration of their memorandum in opposition to summary judgment, although it was
filed beyond the time allotted by the November 13, 2001 scheduling order.
The law does not favor decisions by default. Therefore, we proceed to reexamine each of the
issues in the motion for summary judgment, in light of Appellants= Memorandum in Opposition
to Summary Judgment.
Question 1 of the Statement of Questions
The purpose statement of zoning or subdivision regulations is not independently enforceable; it
must be carried out through the regulatory provisions of the regulations. Accordingly, summary
judgment remains entered on this question in favor of Appellee-Applicant.
Question 2 of the Statement of Questions
If Appellee-Applicant undertook grading, clearing, construction or other [site] improvement,
such activity might well violate ' 21-21 of the Subdivision Regulations and provide the basis for
an enforcement action. However, no provision in the Regulations allows a permit application to
be held up pending such an enforcement action. Compare 10 V.S.A. ' 8011. Accordingly,
summary judgment remains entered on this question in favor of Appellee-Applicant.
Questions 3 & 4 of the Statement of Questions
Appellants raise the question of whether this subdivision should have been classified as major
rather than minor. As this is a de novo proceeding, the issue is not whether the DRB mis-
classified it or changed its position during the hearing. Rather, the issue is whether the
subdivision objectively falls into the > minor= subdivision category.
Both major and minor subdivisions must meet the definitional requirements that they not
adversely affect adjoining property and that they not conflict with the Master Plan, Zoning
Ordinance, Capital Budget and Plan, Official Map, or Zoning Regulations. A subdivision is
minor if it contains no more than four lots and does not require a new street or the extension of
municipal improvements. This subdivision contains no more than four lots. All four lots have
access to the existing Elliott Street; therefore it does not require a new street. The snowplow
turnaround extension is not required for the subdivision or for the safety, health or welfare of the
public, although it has been requested by the City for the convenience of its snow plowing
trucks. As no extension of municipal improvements is required for the subdivision, it meets all
the criteria for treatment as a > minor= subdivision. Accordingly, summary judgment remains
entered on this question in favor of Appellee-Applicant.
Question 5 of the Statement of Questions
Section 21-37(d) of the Subdivision Regulations requires Appellee-Applicant to apply for all
municipal and state permits required of the subdivision, and to submit copies of those
applications to the now-DRB. The regulations do not require that such applications be submitted
in advance of the subdivision application or as a precondition for the DRB to consider the
subdivision application. Accordingly, summary judgment remains entered on this question in
favor of Appellee-Applicant.
Further, the regulations do not require an applicant to submit proof as to which municipal or state
permits may also be required for the subdivision. In the present case, Appellee-Applicant was not
required to apply for an Act 250 permit and the subdivision application could proceed in the
absence of such an application. However, the DRB required verification (presumably, that no
such permit was required) from the Act 250 program to be submitted to the Zoning
Administrator. Such verification may be a prudent step for a municipality to take; it does not
invalidate the application.
Neither party provided ' 21-39(d)(5) of the Subdivision Regulations. While the DRB found that
Class III wetlands existed on the property, there was no showing that a state or federal wetlands
or Army Corps of Engineers permit was required; nor, even if one is required, that it be obtained
in advance of the subdivision application or as a precondition for the DRB to consider the
subdivision application. Accordingly, summary judgment remains entered on this question in
favor of Appellee-Applicant.
Question 6 of the Statement of Questions
The notice required to be sent under ' 21-37(e) to adjoining landowners and to the Regional
Planning Commission appears to have been sent and published as required for the June hearing.
Moreover, Mr. Watker appeared at the hearing; no prejudice has been shown for that reason and
because the appeal to this Court is de novo on all issues. Accordingly, summary judgment
remains entered on this question in favor of Appellee-Applicant.
Question 7 of the Statement of Questions
While this question would ordinarily raise a question of fact for the hearing; Appellants have not
come forward in their opposition to summary judgment with any disputed material facts with
regard to this question. Rather, they only adduce the fact that an Army Corps of Engineers permit
may be required. That fact does not raise an inference that the subdivision approval failed to give
due regard to the preservation and protection of existing water bodies and other natural
resources. That is, if an Army Corps of Engineers permit or a state wetlands permit is required,
those federal or state permits may be relied upon by the City to provide the required level of
protection. Accordingly, summary judgment remains entered on this question in favor of
Appellee-Applicant.
Accordingly, based on the foregoing, Appellants= Motion for Reconsideration of the grant of
summary judgment in favor of Appellee-Applicant is DENIED. Appellee-Applicant= s Motion
for Summary Judgment remains granted, and the December 12, 2001 decision remains in effect,
having concluded the appeal.
Done at Barre, Vermont, this 29th day of January, 2002.
___________________
Merideth Wright
Environmental Judge