NATIONAL PRESORT SERVICES, INC.,
Plaintiff - Counter Defendant - Appellee,
v.
ACS STATE AND LOCAL SOLUTIONS, INC.; ET AL,
Defendants,
ACS STATE AND LOCAL SOLUTIONS, INC.,
Defendant - Counter Claimant - Appellant.
Appeal from the United States District Court
for the Northern District of Texas
USDC No. 3:03-CV-338-K
Before JONES, Chief Judge, and DeMOSS and OWEN, Circuit Judges.
PER CURIAM:*
In this diversity case a prime contractor, ACS State and Local Solutions, Inc.,
terminated in part its subcontract with National Presort Services, Inc. The district court
granted partial summary judgment that ACS breached an obligation to reimburse National
*
Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not be
published and is not precedent except under the limited circumstances set forth in 5TH CIR. R. 47.5.4.
Presort for the cost of unused supplies and storage fees. Following a jury verdict favorable
to National Presort on its damage claims and ACS’s breach-of-contract counterclaim, the
district court entered final judgment in National Presort’s favor. We VACATE the summary
judgment with regard to National Presort’s breach-of-contract claim and REMAND the case
to the district court for further proceedings.
I
ACS’s predecessor-in-interest, Lockheed Martin IMS, Inc., contracted with the Office
of the Attorney General for the State of Texas (OAG) to provide certain services in
connection with collection and distribution of child support payments (the prime contract).
Lockheed subsequently subcontracted some of its duties under the prime contract to National
Presort. The subcontract incorporated by reference all the provisions of the prime contract:
2.0 PRIME CONTRACT
Notwithstanding any other provision of this Agreement, this Agreement is a
subcontract under the Prime Contract and each and every provision of the
Prime Contract and any amendments thereto shall extend to and be binding
upon SUBCONTRACTOR as part of this Agreement. With respect to any
references in the Prime Contract to CONTRACTOR and OAG for purposes
and applicability to this Subcontract, CONTRACTOR shall mean and include
SUBCONTRACTOR, and OAG shall mean and include CONTRACTOR.1
The subcontract also provided a method of resolving any conflict or inconsistency among the
various documents governing the parties’ relationship, giving the terms of the prime contract
precedence over the terms of the subcontract:
1
Emphasis added.
2
1.0 APPLICABLE DOCUMENTS
1.1 Interpretation
Attachments I-IV are attached to and form a part of this Agreement. In the
event of any conflict or inconsistency in the definition or interpretation of any
word, responsibility, schedule, or the contents or description of any task,
deliverable, goods, service, or other work, or otherwise, between the Prime
Contract and the body of this Agreement and the Exhibits thereto, or between
such documents, such conflict or inconsistency shall be resolved by giving
precedence to the documents according to the following priority:
First ATTACHMENT I: The PRIME CONTRACT between
CONTRACTOR and STATE for the Texas State Disbursement
Project
Second ATTACHMENT II: The Office of the Attorney General, State
of Texas Request for Proposal (RFP) for the State Disbursement
Unit Services, its Amendments and the written answers to
questions regarding the RFP
Third The body of this AGREEMENT
Fourth National Presort Services’ STATEMENT OF WORK, Exhibit 1
Fifth National Presort Services’ PAYMENT PROVISIONS, Exhibit 2
ACS subsequently acquired Lockheed and shortly thereafter gave National Presort
notice that it was terminating some of National Presort’s responsibilities under the
subcontract pursuant to paragraph MM of the prime contract. This provision, which was
incorporated into the subcontract pursuant to section 2.0, provides:
MM. Termination of the Contract
1. Convenience of the State of Texas
OAG reserves the right to terminate the contract at any time, in whole
or in part, if the OAG determines that a termination is in the State’s
interest. The OAG will terminate the contract by providing the
Contractor with sixty (60) calendar days advance written notice
specifying the extent of termination and the effective date. In the event
of such a termination, the Contractor shall, unless otherwise mutually
3
agreed upon in writing, cease all affected work immediately upon the
effective date of termination. OAG shall be liable for payments for
terminated services performed under the contract up to the effective
date of termination. Payment for such services will be made in
accordance with Sections VIII.D and IX. The OAG shall have no other
liability; including no liability for any costs associated with the
termination including, but not limited to, implementation cost (such as
facilities acquisition and build out), acquisition cost for infrastructure
items (such as equipment, computer hardware and software),
termination and settlement of leases and subcontracts, storage and
transportation, and personnel relocation.2
The subcontract also contains its own provision governing contract termination. The
subcontract provides that ACS can terminate the subcontract at any time, for any reason,
provided ACS reimburses National Presort for the costs of supplies and storage that National
Presort has incurred in connection with the subcontract:
8.0 Termination
CONTRACTOR shall have the right to terminate this Agreement, independent
of any OAG right to terminate.
In the event the CONTRACTOR terminates the contract for any reason, The
[sic] CONTRACTOR shall reimburse the SUBCONTRACTOR for the cost of
all unused envelopes, printed forms, paper and other materials, including all
such items not yet produced but under contract for production. Reimbursable
cost shall include costs of storage of such materials and costs of their
disposal.3
After receiving the notice of partial termination, National Presort sought
reimbursement based on section 8.0 of the subcontract. National Presort sued for breach of
2
Emphasis added.
3
Emphasis added.
4
contract when ACS refused to pay the full amount National Presort claimed was due for
supplies and storage. ACS denied liability based on paragraph MM of the prime contract,
contested the reasonableness of the amount of damages sought, filed a breach-of-contract
counterclaim based on National Presort’s allegedly substandard performance, and requested
a declaration that ACS is not liable for any damages. ACS asserted that section 8.0 is
inapplicable to a partial termination of the subcontract, and even if it were applicable, the
terms of the prime contract, including paragraph MM, take precedence over the terms of the
subcontract.
With the district court’s permission, National Presort filed a motion for partial
summary judgment on the eve of trial, asserting the subcontract is unambiguous and the
parties intended section 8.0 to apply to any termination of the subcontract. The next day, the
district court granted the motion for partial summary judgment, holding that section 8.0
controlled termination of the subcontract and ACS breached its express obligation to
reimburse National Presort for the specified expenses. The court determined that paragraph
MM is inapplicable because (1) ACS provided no rationale for its authority to terminate the
subcontract “in the State’s interest,” (2) the prime contract’s provisions are relevant only in
the event of an inconsistency with the subcontract, (3) section 8.0 controls because it is more
specific, and (4) application of paragraph MM would render section 8.0 meaningless. The
court also gave ACS seventeen days to file a motion to reconsider the summary judgment
order, recognizing that ACS did not have an adequate opportunity to respond to the motion.
5
The case then proceeded to a jury trial on National Presort’s damages, attorney’s fees,
and ACS’s breach-of-contract counterclaim. The jury was instructed that ACS breached the
subcontract. The jury returned a verdict rejecting ACS’s counterclaim and awarding
National Presort $112,000 in actual damages, $130,000 in attorney’s fees for trial court
proceedings, and $35,000 in attorney’s fees for any appellate proceedings. Shortly
thereafter, ACS asked the court to reconsider summary judgment on the breach-of-contract
issue, arguing that it did not breach the contract because (1) paragraph MM takes precedence
over section 8.0 under the express terms of the subcontract, (2) section 8.0 is inapplicable
to a partial termination of the subcontract, (3) there was at least some evidence that
termination was in the State of Texas’s interest, and (4) ACS offered to pay for some of
National Presort’s claimed expenses. ACS further complained that the district court’s failure
to give ACS at least ten days to respond to the summary judgment motion as required by
FED. R. CIV. P. 56(c) was harmful error.
After considering the motion for reconsideration and supporting evidence, the district
court denied the motion. The district court reiterated its conclusion that, under section 1.1
of the subcontract, the prime contract’s provisions only come into play if there is a conflict
between the terms of the prime contract and the subcontract. The court then concluded that
section 8.0 does not conflict with paragraph MM because the latter only applies to the
OAG’s ability to terminate the prime contract and does not “speak to” the relationship
between National Presort and ACS. Although the court conceded that it was error to rule on
6
the summary judgment motion before ACS had an adequate opportunity to respond, the court
concluded the error was cured by giving ACS an opportunity to file its motion for
reconsideration and present responsive evidence.
On appeal, ACS challenges the summary judgment on its merits and also argues the
summary judgment order must be vacated and a new trial ordered because of the district
court’s procedural error.4
II
The Federal Rules of Civil Procedure allow a party responding to a motion for
summary judgment ten days to present argument and evidence in opposition to the motion.5
This court strictly enforces the ten-day notice requirement and has vacated summary
judgments and remanded for further proceedings when the district court did not provide
notice prior to granting summary judgment even if “‘summary judgment may have been
proper on the merits.’”6 As the district court acknowledged in its order on ACS’s motion for
reconsideration, the court erred by granting National Presort’s motion for partial summary
judgment without giving ACS at least ten days to respond. However, “the harmless error
4
ACS has not appealed the jury’s award of damages, the adverse jury finding on its breach-of-
contract counterclaim, or the district court’s adverse summaryjudgment on ACS’s claims for business
reputation damages and declaratory relief.
5
FED. R. CIV. P. 56(c).
6
Leatherman v. Tarrant County Narcotics Intelligence & Coordination Unit, 28 F.3d 1388,
1397-98 (5th Cir. 1994) (quoting Judwin Props., Inc. v. U.S. Fire Ins. Co., 973 F.2d 432, 437
(5th Cir. 1992)) (involving sua sponte summary judgment granted without at least ten-days notice
as required by rule 56(c)).
7
doctrine applies to lack of the notice required by Rule 56(c).”7 Failure to provide adequate
notice is harmless when the non-moving party either admits that it had no additional evidence
to present or had an opportunity to present additional evidence and that evidence does not
raise a genuine issue of material fact.8
In this case, the district court gave ACS seventeen days after summary judgment was
granted to present argument and evidence. Any error in failing to give notice was therefore
harmless, and we will proceed to the merits of the parties’ contentions.
III
We review a summary judgment de novo, applying the same standard applied by the
district court.9 Summary judgment is proper if no genuine issue of material fact exists and
the moving party is entitled to judgment as a matter of law.10 The parties agree that Texas
substantive law applies in this diversity case.11
Under Texas law, separate agreements may be incorporated by reference into a signed
7
Powell v. United States, 849 F.2d 1576, 1580 (5th Cir. 1988).
8
Id.
9
Allstate Ins. Co. v. Disability Servs. of the Sw., Inc., 400 F.3d 260, 262-63 (5th Cir. 2005).
10
FED. R. CIV. P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986).
11
See Erie R.R. Co. v. Tompkins, 304 U.S. 64 (1938); Thrash v. State Farm Fire & Cas. Co.,
992 F.2d 1354, 1356 (5th Cir. 1993) (“In a diversity case state law provides the elements of the
plaintiff’s case.” (citation omitted)).
8
contract.12 No particular language is required to incorporate a document by reference; all
that is necessary is that the parties’ intent is plainly expressed.13 “When a document is
incorporated into another by reference, both instruments must be read and construed
together.”14
Our initial inquiry is whether the subcontract is ambiguous with regard to termination.
In arguing that section 8.0 is the sole governing termination provision, National Presort
repeatedly refers to parol evidence of what the parties intended with respect to termination
of the subcontract and submitted evidence that the terms of section 8.0 were specifically
negotiated by the parties. Generally speaking, parol evidence cannot render an unambiguous
contract ambiguous.15 “Whether a contract is ambiguous is a question of law for the court
to decide by looking at the contract as a whole in light of the circumstances present when the
contract was entered.”16 A contract is not ambiguous if the language can be given a certain,
12
Trico Marine Servs., Inc. v. Stewart & Stevenson Technical Servs., Inc., 73 S.W.3d 545,
549 (Tex. App.–Houston [1st Dist.] 2002, orig. proceeding).
13
See Owen v. Hendricks, 433 S.W.2d 164, 166-67 (Tex. 1968) (discussing the doctrine of
incorporation by reference for purposes of the statute of frauds where one document is signed and
another pertaining to the same transaction is unsigned).
14
In re C & H News Co., 133 S.W.3d 642, 645-46 (Tex. App.–Corpus Christi 2003, orig.
proceeding).
15
Friendswood Dev. Co. v. McDade & Co., 926 S.W.2d 280, 283 (Tex. 1996) (“McDade’s
interpretation, however, is parol evidence, and parol evidence of intent cannot be admitted for the
purpose of creating an ambiguity.”); R&P Enters. v. LaGuarta, Gavrel & Kirk, Inc., 596 S.W.2d 517,
518-19 (Tex. 1980).
16
Coker v. Coker, 650 S.W.2d 391, 394 (Tex. 1983); Friendswood Dev., 926 S.W.2d at 282.
9
definite legal meaning or interpretation in light of the surrounding circumstances.17 Even
considering the evidence National Presort submits concerning negotiation of section 8.0,
sections 1.1, 2.0 and 8.0 of the subcontract and paragraph MM of the prime contract are
unambiguous;18 therefore, we construe the subcontract as a matter of law without reference
to parol evidence.19
We disagree with the district court’s conclusion that the language in the prime
contract, including paragraph MM, is inapplicable absent a conflict with the terms in the
subcontract. Section 2.0 of the subcontract unambiguously incorporates by reference all of
the provisions in the prime contract, and nothing in section 8.0 or any other provision of the
subcontract excludes the termination provision in paragraph MM. Section 2.0
unambiguously provides that all of the provisions of the prime contract as incorporated into
the subcontract are to be construed by substituting ACS when the prime contract references
the OAG and National Presort when the prime contract references ACS. Therefore, the
language in paragraph MM is for all intents, constructions and purposes an express provision
17
Coker, 650 S.W.2d at 393; Sun Oil Co. v. Madeley, 626 S.W.2d 726, 731 (Tex. 1981)
(stating that when construing a contract, the court may consult surrounding circumstances to
determine whether the contract’s language is ambiguous; if the language is unambiguous, the court
can then confine itself to the writing, and parol evidence is not admissible to render a contract
ambiguous if it is not ambiguous on its face).
18
Cf. Wood Motor Co. v. Nebel, 238 S.W.2d 181, 184-85 (Tex. 1951) (concluding that an
agreement with two termination clauses was not ambiguous; one clause resulted in termination
without notice on the happening of specified events and the other provided for termination by either
party without notice).
19
See Coker, 650 S.W.2d at 393.
10
of the subcontract, regardless of whether it conflicts with another term in the subcontract.
Further, paragraph MM and section 8.0 can be harmonized and given effect, both
generally and as applied in this case, without rendering either provision meaningless.20
Section 8.0 allows ACS to terminate the subcontract for any reason without notice,
independent of whether the OAG has terminated the prime contract in whole or part. If ACS
terminates the subcontract without notice, it must reimburse National Presort for the
specified expenses. Paragraph MM, on the other hand, provides temporal and substantive
limitations on ACS’s right to terminate the subcontract. First, ACS must determine that
termination is in the State of Texas’s interest. Second, ACS must give at least sixty days
written notice. The notice period is essentially a proxy for a reasonable period of time for
National Presort to consume existing supplies and recover expenses through performance of
the contract. If ACS satisfies paragraph MM’s preconditions to termination, ACS is thus
relieved of liability for any expenses. There is nothing inconsistent about section 8.0 and
paragraph MM. The contract may be terminated by satisfying either one. If paragraph
MM’s preconditions have been satisfied, ACS did not breach the contract. If those
conditions have not been satisfied, section 8.0 will control.
The district court concluded that paragraph MM was not applicable to the relationship
between National Presort and ACS, and therefore did not consider whether ACS’s partial
termination of the subcontract complied with paragraph MM’s conditions. We cannot
20
See Nebel, 238 S.W.2d at 184-85.
11
determine, based on the record before us, whether paragraph MM’s requirements were met.
We VACATE the judgment and REMAND this case to the district court for further
proceedings.