Case: 17-60719 Document: 00514555575 Page: 1 Date Filed: 07/16/2018
IN THE UNITED STATES COURT OF APPEALS
FOR THE FIFTH CIRCUIT
United States Court of Appeals
No. 17-60719
Fifth Circuit
FILED
Summary Calendar July 16, 2018
Lyle W. Cayce
ENTERGY MISSISSIPPI, INCORPORATED, Clerk
Plaintiff - Appellee
v.
MARQUETTE TRANSPORTATION COMPANY, L.L.C.;
BLUEGRASS MARINE, L.L.C.,
Defendants – Appellants
Appeal from the United States District Court
for the Southern District of Mississippi
USDC No. 3:13-CV-879
Before DAVIS, COSTA, and ENGELHARDT, Circuit Judges.
PER CURIAM:*
A barge being pushed down the Mississippi River by a tow boat came
loose and hit a mooring dolphin structure, which is “a cluster of closely driven
piles used as a fender for a dock or as a mooring or guide for boats.” Entergy
Mississippi, which operates the dock as part of a fuel unloading facility near
Vicksburg, filed this maritime suit seeking the cost of repairs from the owner
* Pursuant to 5TH CIR. R. 47.5, the court has determined that this opinion should not
be published and is not precedent except under the limited circumstances set forth in 5TH
CIR. R. 47.5.4.
Case: 17-60719 Document: 00514555575 Page: 2 Date Filed: 07/16/2018
No. 17-60719
(Marquette Transportation) and operator (Bluegrass Marine) of the tow boat.
The district court found the Defendants liable at the summary judgment stage
and after trial awarded damages of just over $1 million. Defendants assert the
following grounds for reversal: (1) they should not have been liable because the
dolphin was unpermitted, (2) it was error to allow Entergy to amend its
pleading to increase the amount of damages sought, (3) the court should not
have used the damages amount from a related state suit, and (4) the
prejudgment interest was excessive. Finding no error, we AFFIRM.
I.
The towboat (also called a push boat) M/V ROBERT E. FRANE was
towing several barges down the Mississippi in high water conditions. The
current took the towboat and barges off their intended path, and the tow
allided with the Vicksburg Bridge, which knocked several barges loose. The
impact with the bridge caused one of the barges to allide with the mooring
dolphin outside the property leased by Entergy. Entergy hired Riverside
Construction Company, Inc. to repair the dolphin. High water on the river
prevented repairs from commencing for three years.
Shortly after the repairs began but well before they were completed,
Entergy sued Defendants. Entergy initially claimed damages “in excess of
$190,000.” Several years into the repair project, Entergy and Riverside
realized a mutual mistake about the scope of the repairs; Riverside believed
the contract price covered only the removal of the fender from the water and
inspection, but Entergy believed the price was for the entire repair including
rehanging the damaged fender on the dolphin structure. Entergy moved to join
Riverside to this suit, but Defendants successfully opposed. As a result, the
dispute over the cost of repairs between Riverside and Entergy proceeded in
state court.
2
Case: 17-60719 Document: 00514555575 Page: 3 Date Filed: 07/16/2018
No. 17-60719
Repair costs continued to mount, so Entergy was twice allowed to amend
its complaint to increase its damages. Defendants unsuccessfully sought
summary judgment on the ground that they were not liable because the
dolphin was an unpermitted obstruction. The court instead granted Entergy’s
motion seeking summary judgment on liability.
After those liability rulings in federal court, the state court held a bench
trial in the suit between Entergy and Riverside to determine the necessary and
reasonable cost of the repairs. That court found the reasonable cost to be
$1,005,048.34 and awarded Riverside a judgment for that amount, less money
already paid by Entergy. Entergy paid that judgment, and then sought this
amount, plus other associated costs, from Defendants in the district court.
The district court conducted a four-day bench trial on damages in
September 2016. A year later, it awarded Entergy a judgment for
$1,098,372.40 plus prejudgment interest at a rate of eight percent,
compounded annually from the date of the loss to the date of the judgment.
II.
Defendants first challenge the summary judgment ruling rejecting their
liability argument. They contend that Entergy’s failure to obtain a permit for
the dolphin means Defendants are not liable for causing the allision. 1
The general rule is that “[w]hen an unmanned barge strikes a stationary
object such as a dolphin[,] . . . the custodian of the barge has the burden to
prove that his negligence was not a proximate cause of the allision.” Pillsbury
Co. v. Midland Enters., Inc., 715 F. Supp. 738, 758 (E.D. La. 1989) (citing Koch-
Ellis Marine Contractors v. Sewerage & Water Bd. Of New Orleans, 218 F.2d
1 Entergy contends that the issue of permitting may not be appealed because it was
not raised in the pretrial order. But because the court had already rejected the defense as a
matter of law, Defendants did not need to engage in the futile step of raising the issue again
as part of the trial. See Ultraflo Corp. v. Pelican Tank Parts, Inc., 845 F.3d 652, 655 (5th Cir.
2017).
3
Case: 17-60719 Document: 00514555575 Page: 4 Date Filed: 07/16/2018
No. 17-60719
at 772 & n.3 (5th. Cir. 1955)), aff’d, 904 F.2d 317 (5th Cir. 1990). That
describes this incident, but Defendants cite the Pennsylvania rule, which can
shift the burden to Entergy. The Pennsylvania rule applies when the
stationary object is not authorized to be in the water, in which case the party
violating the statute must “show not only that its conduct was not a
contributing cause of the collision, but that it could not have been a cause of
the collision.” Fla. E. Coast Ry. Co. v. Revilo Corp., 637 F.2d 1060, 1064 (5th
Cir. 1981) (citing The Pennsylvania, 86 U.S. 125, 138 (1873)). The
Pennsylvania rule applies whether the object struck is a bridge or a vessel. Fla.
E. Coast Ry. Co., 637 F.2d at 1064.
Defendants contend that Entergy violated the Rivers and Harbors Act of
1899, 33 U.S.C. § 403 (2012), by having unpermitted dolphins in the river. The
Act expressly prohibits any structures, including dolphins, from being built
“except on plans recommended by the Chief of Engineers and authorized by
the Secretary of the Army.” 33 U.S.C. § 403. Defendants presented permits
obtained from the Army Corps of Engineers pertaining to the property going
back to 1965. None of them explicitly cover the dolphin fender system. See id.
Contrary to Defendants’ assertion, the district court did assume The
Pennsylvania applied and shifted the burden to Entergy. It held that “[e]ven
if the [Corps] never condoned the dolphin fender system, the Pennsylvania rule
will not shield the defendants for their negligent actions.” This is because the
crew of the M/V ROBERT E. FRANE was aware of the dolphin’s existence and
location, and Defendants provided no evidence that the dolphin “actually
obstructed navigation, that it was inherently dangerous, or that any change in
its design or placement would have prevented the collisions.” Dow Chem. Co.
v. Dixie Carriers, Inc., 463 F.2d 120, 122 (5th Cir. 1972). The allision was
caused by the M/V ROBERT E. FRANE’s previous allision with the Vicksburg
4
Case: 17-60719 Document: 00514555575 Page: 5 Date Filed: 07/16/2018
No. 17-60719
Bridge; the captain of the ship admitted as much. The district court properly
held Defendants liable. Id.
III.
Defendants next argue that the district court abused its discretion in
allowing Entergy to twice amend its complaint to increase the amount of
damages it sought. It is not clear that Entergy even had to amend as the
original complaint requested damages “in excess of $190,000.” But assuming
Entergy needed to increase the amount it sought, the district court did not err
in allowing it to do so. “The court should freely give leave when justice so
requires.” Fed. R. Civ. P. 15(a). The leave should be granted “unless the
movant has acted in bad faith or with a dilatory motive, granting the motion
would cause prejudice, or amendment would be futile.” Jebaco, Inc. v. Harrah’s
Operating Co., Inc., 587 F.3d 314, 322 (5th Cir. 2009) (citations omitted). There
was good reason for the amendment as Entergy and Riverside had a
misunderstanding about the scope of the repairs and river conditions
substantially delayed the start of the work.
IV.
Defendants raise a couple challenges to the damages award. They first
argue it was improper to rely on the state court’s determination of the
reasonable cost of repairs. We do not have to decide the application of issue
preclusion because the district court noted after its review of the evidence that
it would reach the same result even if not legally bound by the state court
ruling. We find no clear error in that determination. See Todd Shipyards
Corp. v. Turbine Serv., Inc., 674 F.2d 401, 405 (5th Cir. 1982) (noting that
damage awards are reviewed for clear error).
The district court also did not err in refusing to deduct depreciation from
its award. “[W]here the repairs do not extend the useful life of the property as
it existed just before the collision, there should be no deduction for
5
Case: 17-60719 Document: 00514555575 Page: 6 Date Filed: 07/16/2018
No. 17-60719
depreciation.” Brunet v. United Gas Pipeline Co., 15 F.3d 500, 505 (5th Cir.
1994) (quoting Freeport Sulphur Co. v. S.S. Hermosa, 526 F.2d 300, 305-06 (5th
Cir. 1976)). The repaired portion of Entergy’s dolphin fender system will still
need to be replaced whenever the whole structure is replaced; the new
materials used to repair the dolphin thus did not change the time frame of that
replacement. Depreciation was not required.
V.
Defendants’ final argument is that the district court erred in awarding
prejudgment interest from the date of the allision. “[I]nterest from the date of
loss has long been allowed, of course, in admiralty for property loss.” Alcoa S.S.
Co. v. Charles Ferran & Co., 443 F.2d 250, 256 (5th Cir. 1971) (internal
quotations omitted). The award of interest is, however, ultimately a matter of
discretion. Id. Even if there were reasons that might have allowed the trial
court to limit the time period for prejudgment interest, we find no abuse of
discretion in its following the normal rule. 2
***
The judgment of the district court is AFFIRMED.
2 Entergy requests sanctions against Defendants. This appeal does not rise to the level
of frivolity that warrants sanctions under Fed. R. App. P. 38.
6