AFFIRM as MODIFIED, and REVERSE and REMAND; Opinion Filed August 20, 2018.
In The
Court of Appeals
Fifth District of Texas at Dallas
No. 05-17-00583-CV
CITY OF LANCASTER, Appellant
V.
WHITE ROCK COMMERCIAL, LLC, Appellee
On Appeal from the 191st Judicial District Court
Dallas County, Texas
Trial Court Cause No. DC-14-06471
MEMORANDUM OPINION
Before Justices Bridges, Brown, and Boatright
Opinion by Justice Boatright
The City of Lancaster appeals a $4.7 million judgment rendered against it for breach of an
economic development contract with appellee White Rock Commercial, LLC. The City contends
that White Rock’s claim is barred by immunity. It also urges that the district court erred in granting
White Rock’s motion for partial summary judgment on the issue of liability, and it raises several
grounds for reversal related to the court’s damages award. We conclude that White Rock’s claims
are not barred by immunity and that the court did not err in granting White Rock’s motion for
partial summary judgment. However, we conclude that the court’s damages award is erroneous in
certain respects. We affirm, as modified, in part and reverse and remand, in part.
BACKGROUND
The Texas Constitution authorizes the Legislature to “provide for the creation of programs
and the making of loans and grants of public money” for “public purposes” that include the
“development and diversification of the economy of the state.” TEX. CONST. art. III, § 52-a (West
Supp. 2017). To this end, the Local Government Code empowers a municipality to “establish and
provide . . . programs for making loans and grants of public money . . . to promote state or local
economic development and to stimulate business and commercial activity in the municipality.”
TEX. LOC. GOV’T CODE ANN. § 380.001(a) (West 2005). White Rock’s claim is premised on the
City’s breach of a contract entered under the authority of this statute.
White Rock is a real estate developer. In 2007, it found out about an 83-acre site in
Lancaster that the City wished to develop. The City was willing to provide economic incentives to
promote the development. On August 13, 2007, White Rock entered two contracts that would
provide funds to help develop the property: (i) an “Incentive Agreement” with the Lancaster
Economic Development Corporation (the EDC),1 and (ii) an “Economic Agreement” with the City.
We will refer to the Economic Agreement as the 380 Agreement because it cites section 380.001
as the basis for the City’s authority to enter the Agreement.
In both contracts, White Rock agreed to design and construct infrastructural improvements
for a 1.4 million square-foot industrial park on the site. Such improvements were to be constructed
according to the City’s plans and specifications and were to include a new public regional storm
drainage and detention system, a wastewater or sanitary sewer system, a water delivery system,
off-site utility trunk connections, and streets. Both contracts made White Rock responsible for
1
The Lancaster EDC administers funds and projects using the $0.25 sales tax receipts dedicated to economic development pursuant to the
Development Corporation Act of 1979. The EDC has a board, separate from the City, composed of five members. The EDC is a separate taxable
entity from the City with its own budget and guidelines for expending funds.
–2–
funding the “Project Costs”—the actual costs incurred by White Rock to construct the
infrastructural improvements, plus a specified rate of interest—subject to reimbursement.
Each contract provided a different method of reimbursement. The Incentive Agreement
authorized four $450,000 payments from the EDC to White Rock, totaling $1.8 million, with the
first payment to be made ten days after commencement of the project. To trigger the remaining
payments, this agreement required White Rock to construct a “Qualified Building”—a building or
buildings on the project totaling at least 440,000 square feet—within thirty months of the City’s
final acceptance of the infrastructural improvements. White Rock would receive the remaining
three payments according to a schedule, with the final payment on August 1, 2009.
In contrast, the 380 Agreement was implemented through an “annual economic
development grant,” apportioned into twenty scheduled payments by the City. The payments were
to begin on October 1 following the first year that any office or industrial building constructed on
the property was issued a certificate of occupancy, and they were to continue for an additional
nineteen years. The grant was paid annually according to a formula based on the product of the
fair market value of the improvements multiplied by the City’s annual tax rate.
The parties disagree as to why there were two contracts. The City claims that the EDC had
insufficient funds to fully reimburse the projected costs budgeted for the project, which totaled in
excess of $3 million. In the City’s view, the 380 Agreement’s purpose was to reimburse White
Rock’s expected costs that were in excess of the $1.8 million to be paid under the Incentive
Agreement. White Rock counters that the contracts created different obligations and that the
Incentive Agreement provided additional incentives above the amounts to be paid under the 380
Agreement.
White Rock acquired the site in a private sale and completed the infrastructural
improvements on June 22, 2009. The City accepted these improvements nearly two months later.
–3–
White Rock also constructed a 442,000 square-foot distribution center. This was the Qualified
Building referenced in the Incentive Agreement. The EDC paid White Rock the four $450,000
installment payments required by the Incentive Agreement. The City issued a temporary certificate
of occupancy for this building on June 1, 2012, but it did not make any annual economic grant
payments under the 380 Agreement. White Rock sold the building at a loss, and its lender took the
undeveloped remainder of the property through a deed in lieu of a foreclosure transaction. This
remainder was thereafter developed by another developer.
White Rock sued the City in June 2014, alleging that it breached the 380 Agreement. White
Rock also filed a motion for partial summary judgment, urging that that the evidence established
the City’s liability for breach of contract and negated the City’s affirmative defenses. On January
28, 2015, the district court signed an order granting White Rock’s motion on all elements of its
breach of contract claim except for the amount of the damages, if any, to be determined at a later
date. The order also ruled that each of the City’s affirmative defenses failed as a matter of law.
The City subsequently filed a plea to the jurisdiction, claiming that it was immune from
White Rock’s breach of contract suit and that the 380 Agreement created a debt prohibited by the
Texas Constitution. The district court held a hearing on the City’s plea, and on June 30, 2016, the
court signed an order denying the plea. The court conducted a bench trial on White Rock’s
damages in November 2016. White Rock presented evidence that it had incurred Project Costs of
$ 2,677,288.79 and that its damages, after also adding the interest applicable under the 380
Agreement, totaled $4,726,217.53. On March 8, 2017, the court rendered judgment awarding
White Rock (i) actual damages consistent with the foregoing amounts, (ii) prejudgment interest of
$413,252.69, (iii) court costs, and (iv) postjudgment interest at the rate of 3.75%, compounded
annually. The City filed a motion for new trial and to set aside the court’s partial summary-
judgment order, which the court denied following a hearing. The City then appealed the judgment.
–4–
ANALYSIS
The City raises six issues that challenge the judgment, including the district court’s
interlocutory orders that merged into the judgment.
I.
Plea to the Jurisdiction
The City urges that it is immune from White Rock’s suit. An assertion of governmental
immunity implicates a court’s subject matter jurisdiction, and such immunity is properly asserted
in a plea to the jurisdiction. Harris Cty. v. Annab, 547 S.W.3d 609, 612 (Tex. 2018). A movant
bears the burden in its plea to establish that it is entitled to immunity, and if it meets this burden,
the burden then shifts to the non-movant to establish, or at least raise a fact issue on, a waiver of
immunity. Lubbock Cty. Water Control and Improvement Dist. v. Church & Akin, L.L.C., 442
S.W.3d 297, 305 (Tex. 2014). Subject matter jurisdiction is a question of law that we review de
novo. Annab, 547 S.W.3d at 612. In the posture of this appeal from a final judgment following a
trial, we review the entire record, including the evidence admitted at trial, to the extent it bears on
the City’s jurisdictional argument. ATI Enters., Inc. v. Din, 413 S.W.3d 247, 250–51 (Tex. App.—
Dallas 2013, no pet.). With these standards in mind, we must determine whether immunity applies
and, if it does, we must defer to the Legislature’s decision to waive, or not to waive, such immunity.
Wasson Interests, Ltd. v. City of Jacksonville (“Wasson I”), 489 S.W.3d 427, 435 (Tex. 2016).
A. Applicability of Immunity
In its first issue, the City contends that it is immune from suit under the common law
doctrine of sovereign immunity. The City explains that political subdivisions of the State are
immune from suit unless the Legislature unambiguously waives immunity, and it contends that the
Legislature did not do so. And in its reply brief, the City asserts that its actions in entering into the
380 Agreement were governmental rather than proprietary. The distinction between governmental
and proprietary functions applies to breach of contract claims. Id. at 439. The City notes that
–5–
economic development corporations have sovereign immunity under chapters 504 and 505 of the
Local Government Code. It concludes that, because the City “acted in the same capacity as the
EDC” in entering into the 380 Agreement, “it was clearly and unequivocally carrying out a
governmental function consistent with case law.” However, the City provides no legal authority in
support of that conclusion. Chapters 504 and 505 apply to economic development corporations,
not municipalities, and we are aware of no judicial decision concluding that a municipality can
either act in the capacity of an economic development corporation, or carry out a governmental
function in that capacity.
White Rock contends that the City was never entitled to immunity because it engaged in a
proprietary rather than a governmental function. White Rock quotes the Texas Supreme Court in
Wasson I for the proposition that a proprietary function is one undertaken “’for the private
advantage and benefit of the locality and its inhabitants.” Id. at 433. White Rock notes that the 380
Agreement expressly provided that it “will further the objectives of the City, will benefit the City
and the City’s inhabitants and will promote local economic development and stimulate business
and commercial activity in the City.” White Rock contends that this shows that the City sought a
private advantage and benefit of the City and its inhabitants, that the City was engaging in a
proprietary rather than a governmental function, and that the City was therefore not entitled to
immunity under Wasson I.
That case, however, addressed section 101.0215 of the Civil Practice and Remedies Code,
which expressly identifies “street construction and design,” “sanitary and storm sewers,” and
“water and sewer service” as governmental functions and not proprietary functions. TEX. CIV.
PRAC. & REM. CODE § 101.0215(a)(3), (9), (32) (West Supp. 2017). Each of those functions was
expressly covered by the 380 Agreement. If section 101.0215 had not identified those functions as
either governmental or proprietary functions, we would apply a four-part test to determine whether
–6–
they were governmental, as the Texas Supreme Court did in an opinion issued after submission of
our case. Wasson Interests, Ltd. v. City of Jacksonville (“Wasson II”), ___ S.W.3d ___, No. 17-
0198, 2018 WL 2449184, at *6 (Tex. June 1, 2018). However, because the functions expressly
covered by the 380 Agreement are expressly identified in section 101.0215 as governmental
functions, we do not apply the Wasson II test. We are instead guided by section 101.0215’s
treatment of those functions. Wasson I, 489 S.W.3d at 439. We conclude that these functions are
what the Legislature has told us they are: governmental functions. Therefore, the City is immune
from suit absent a waiver by the Legislature. We sustain the City’s first issue.
B. Waiver of Immunity
In its second issue, the City contends that its immunity was not waived under Chapter 271
of the Local Government Code. A waiver of governmental immunity must be clear and
unambiguous. Oncor Elec. Delivery Co. LLC v. Dallas Area Rapid Transit, 369 S.W.3d 845, 849
(Tex. 2012). Under Chapter 271, “[a] local government entity that . . . enters into a contract subject
to this subchapter waives sovereign immunity to suit for the purpose of adjudicating a claim for
breach of the contract,” subject to certain terms and conditions not at issue here. TEX. LOC. GOV’T
CODE ANN. § 271.152 (West 2016). A “contract subject to this subchapter” includes “a written
contract stating the essential terms of the agreement for providing goods or services to the local
governmental entity that is properly executed on behalf of the local governmental entity.” TEX.
LOC. GOV’T CODE ANN. § 271.151(2)(A) (West 2016). We must look beyond the title of a written
contract to determine whether it satisfies Chapter 271’s waiver requirements. Church & Akin, 442
S.W.3d at 301.
The City argues that the 380 Agreement was not a “contract subject to this subchapter”
because it (i) lacked an essential term—the time of performance, City of Houston v. Williams, 353
S.W.3d 128, 138–39 (Tex. 2011)—and (ii) did not relate to the provision of goods or services.
–7–
1. Time of Performance
The City contends that its obligation to pay is “contingent on the completion of
performance by White Rock in an undetermined period of time,” citing section 5.3 of the
Agreement. The City relies on a decision from a sister court that held a contract to build a home
lacked several essential terms, including the size of the house contemplated, the price of the house
on a per-square-foot or other basis, or the time for completing construction. DKH Homes, LP v.
Kilgo, No. 03-10-00656-CV, 2011 WL 1811435, at *3 (Tex. App.—Austin May 11, 2011, no pet.)
(memo. op.). In response, White Rock points to section 7.1 of the Agreement, which authorizes
the City to terminate if White Rock does not take adequate steps to cure a default within thirty
days (or in the instance of a non-monetary default, within ninety days) after receiving notice from
the City, such default including a failure to commence or to complete construction of the project.
White Rock urges that this provision obligated it to perform within a reasonable time, citing case
law that a contract is not “too indefinite to be enforced . . . so long as the language used fixes an
ascertainable fact or event by which the term of the duration of the contract can be determined.”
Brittian v. Gen. Tel. Co. of Sw., 533 S.W.2d 886, 891 (Tex. Civ. App.—Fort Worth 1976, writ
dism’d). It alternatively contends that the law will imply a reasonable time where no time for
performance is stated in the contract, citing Moore v. Dilworth, 179 S.W.2d 940, 942 (Tex. 1944).
Whether a contract has all the essential terms to be an enforceable agreement is a question
of law. Ferachi v. Cady, No. 2-07-355-CV, 2009 WL 1506899, at *4 (Tex. App.—Fort Worth
May 28, 2009, pet. denied) (mem. op). The material terms are determined on a case-by-case basis,
and each contract should be considered separately to determine its material terms. Fischer v. CTMI,
L.L.C., 479 S.W.3d 231, 237 (Tex. 2016). In this case, we conclude that the law implied a
reasonable time for White Rock to complete performance of its contractual obligations. Absent
such an interpretation, section 7.1’s provision regarding the cure of a default, and the termination
–8–
following a failure to cure, would never apply. This interpretation would render section 7.1
meaningless, in contravention of the principle that courts attempt to avoid such a construction.
Vest v. Gulf Ins. Co., 809 S.W.2d 531, 533 (Tex. App.—Dallas 1991, writ denied). For this reason,
we conclude that the Agreement stated its essential terms.
2. Goods or Services
We next consider whether the 380 Agreement was for the provision of “services,” a term
not defined in Chapter 271. The Texas Supreme Court has held that the term “is broad enough to
encompass a wide array of activities,” and “includes generally any act performed for the benefit
of another.” Kirby Lake Dev., Ltd. v. Clear Lake City Water Auth., 320 S.W.3d 829, 839 (Tex.
2010) (citation and internal quotation marks omitted). The services provided “need not be the
primary purpose of the agreement.” Id. However, section 271 does not extend to “‘contracts in
which the benefit that the local governmental entity would receive is an indirect, attenuated one.’”
Id. (quoting Berkman v. City of Keene, 311 S.W.3d 523, 527 (Tex. App.—Waco 2009, pet. denied)
(brackets omitted)); cf. Church & Akin, 442 S.W.3d at 303 (“When a party has no right under a
contract to receive services, the mere fact that it may receive services as a result of the contract is
insufficient to invoke chapter 271’s waiver of immunity.”).
The City urges that White Rock, as the owner of the property, was required by the City’s
subdivision ordinance to construct the infrastructural improvements at issue, though the City
provides no citation to the applicable ordinance. The City claims that its ordinance required this
infrastructure, once built, to be turned over to the City to maintain in perpetuity. In the City’s view,
it merely financed White Rock’s construction of the infrastructural improvements that White Rock
was already required by law to install. The City’s plea attached an affidavit of the City
Manager/Chief Budget Officer, who averred that the City did not receive a direct benefit from the
–9–
project. The City also urges that it was White Rock who benefitted from the infrastructure in the
form of an increase in its property’s value.
In support of its position, the City relies on cases holding that contracts were not for the
provision of services because their benefit to the municipality was attenuated. Berkman involved
child welfare services that were at most a benefit to the state given that the city in that case had no
independent obligation to provide for the welfare of children who were wards of the state. 311
S.W.3d at 527. In East Houston Estate Apartments, L.L.C. v. City of Houston, a city loaned federal
and private funds to a property owner to rehabilitate an apartment complex within the city. 294
S.W.3d 723, 726, 736–37 (Tex. App.—Houston [1st Dist.] 2009, no pet.). While the city might
benefit in a general way from refurbished apartments and low-income housing, our sister court
concluded that nothing in the contract obligated the property owner to provide any municipal
service directly to the city. Id. at 736. Rather, the city was simply a conduit of federal funds and a
facilitator of the project. Id.
In City of Canton v. Zanbaka, USA, LLC, a city economic development corporation
contracted with the owner of “Duke’s Travel Plaza” to fund a sewer line and lift station to its travel
plaza located along Interstate 20. No. 12-12-0006-CV, 2013 WL 3377436, at *1 (Tex. App.—
Tyler July 3, 2013, pet. denied) (mem. op. on reh’g). Despite the contract’s stated purpose of
providing new economic opportunities for the city, our sister court concluded that the contract’s
“tangible objective” was to provide funding for a sewer line and lift station to Duke’s real property.
Id. at *3. Any benefits to the EDC that would flow from this objective were indirect. Id.
In response to the City, White Rock relies on Kirby Lake, in which the supreme court held
that section 271.152 waived a water control and improvement district’s immunity. 320 S.W.3d at
838–40. In that case, residential developers contracted with the district to build water and sewer
facilities—i.e., water and sewer lines—according to the district’s specifications. Id. at 832. The
–10–
contracts required the developers to lease the constructed facilities to the district free of charge
until the district purchased them. Id. The district agreed to reimburse the developers for 70% of
their construction costs once it received voter-approved bond funds. Id. at 832–33. However, under
applicable state regulations, the developers assumed the risk that the voters would never authorize
public funds for acquiring the facilities. Id. at 832, 836. Based on the developers’ obligation to
“construct, develop, lease, and bear all risk of loss or damage to the facilities,” the supreme court
held that the contracts entailed services provided directly to the district. Id. at 839.
White Rock also cites Dallas Area Rapid Transit v. Monroe Shop Partners, Ltd., 293
S.W.3d 839 (Tex. App.—Dallas 2009, pet denied), disapproved on other grounds by Zachry
Constr. Corp. v. Port of Houston Auth. of Harris Cty., 449 S.W.3d 98, 110 n.54 (Tex. 2014). In
that case, we concluded that a contract that called for DART to sell, and for Monroe to purchase
and develop, a historically significant property was a contract to provide services. Id. at 840–41.
The contract required Monroe to accept a separate assignment of DART’s responsibility of
complying with the state’s restrictions flowing from the historic nature of the property. Id. at 841.
These facts, coupled with the contract’s provisions that required various approvals from DART,
brought the contract within the scope of section 271.152. Id.
In this case, the 380 Agreement expressly stated that it would benefit the City by growing
its economy. There is also evidence that the City projected that it would receive a net $12.4 million
benefit from the project. Nevertheless, under the reasoning of Berkman, East Houston Estate, and
Zanbaka, this benefit to the City is too attenuated for the section 271.152 waiver to apply. Cf.
Church & Aiken, 442 S.W.3d at 306–07 (indirect benefits to water district from lessee’s increased
profits could not, alone, convert lessee’s efforts to promote its own business into services to water
district). However, the circumstances of this case demonstrate that White Rock’s agreement to
construct the infrastructural improvements was itself a direct benefit to the City, as were the
–11–
facilities constructed in Kirby Lake. 320 S.W.3d at 838–40. Although the City contends that its
subdivision ordinance independently required White Rock to construct the facilities at issue, the
record evidences that White Rock would not have done so but for the City’s solicitations.
Specifically, Hopkins testified that White Rock initially refused to develop the property but
changed its mind after the City offered the incentives set forth in both the 380 Agreement and the
Incentive Agreement. The City’s agreement to pay White Rock for such construction is further
evidence of a contract for services. See Church & Aiken, 442 S.W.2d at 304 (“[T[he waiver will
typically apply only to contracts in which the governmental entity agrees to pay the claimant for
the goods or services that the claimant agrees to provide to the governmental entity.”).
In sum, the 380 Agreement entailed services provided directly to the City, thereby waiving
its immunity under section 271.152. Accordingly, we need not decide whether the Agreement was
also a contract for providing goods. We overrule the City’s second issue.
C. Enforceability of Debt
The City’s third issue contends that the 380 Agreement created a void debt that the district
court lacked jurisdiction to enforce. The City cites two constitutional provisions that prohibit it
from incurring a debt unless at the same time (i) a provision is made for annually assessing and
collecting a sufficient sum to pay the debt’s interest, and (ii) a sinking fund is created of at least
two percent of the debt. TEX. CONST. art. XI, §§ 5, 7 (West Supp. 2017); see McNeill v. City of
Waco, 33 S.W. 322, 324 (Tex. 1895) (concluding that “debt,” as used in article 11, means any
pecuniary obligation imposed by contract except for obligations to be satisfied out of current
revenues or out of some fund within the municipality’s immediate control). We are not persuaded
by the City’s argument. The constitutional provision authorizing Local Government Code section
380.001 provides that a “grant made as provided by this section”—that, as in this case, is not
secured by a pledge of ad valorem taxes or financed by the issuance of bonds payable from such
–12–
taxes—“does not constitute or create a debt for the purpose of any provision of this constitution.”
TEX. CONST. art. III, § 52-a. Thus, the grant made under the 380 Agreement was not a debt for
purposes of the foregoing constitutional provisions.
The City alternatively relies on section 3.3 of the Agreement, in which it agreed “to use
available funds . . . to reimburse DEVELOPER for Project Costs.” The City interprets this
provision to mean that its obligation was contingent on its appropriation of funds in its annual
budget to pay the grant. Related to this point, the City Manager/Chief Budget Officer averred in
an affidavit, attached to the City’s plea, that the City did not appropriate any funds for fiscal years
2012 through 2016 to pay the grant.
The interpretation of an unambiguous contract, including whether a contractual provision
creates a condition precedent to performance, is a question of law for the court. Lambrecht &
Assocs., Inc. v. State Farm Lloyds, 119 S.W.3d 16, 26 (Tex. App.—Tyler 2003, no pet.). “[T]o
make performance specifically conditional, a term such as ‘if’, ‘provided that’, ‘on condition that’,
or some similar phrase of conditional language must normally be included.” Solar Applications
Eng’g, Inc. v. T.A. Operating Corp., 327 S.W.3d 104, 109 (Tex. 2010) (citation and internal
quotation marks omitted). Though such phrases are not required, their absence is probative of the
parties’ intent to make a covenant—i.e., to agree to act or refrain from acting in a certain way—
rather than to impose a condition precedent. Id. at 108–09. In the absence of conditional language,
and to the extent another reasonable interpretation of the contract is possible, we will construe the
terms as a covenant in order to prevent a forfeiture. Id. at 109. In this case, the 380 Agreement
contains no such condition, nor does it contain other language that suggests the parties intended to
condition the City’s performance under the Agreement on its appropriation of funds to pay the
grant. We therefore disagree with the City’s interpretation of section 3.3.
–13–
The City also cites section 2.2 of the Agreement, which provides that “DEVELOPER’s
performance . . . shall not result in the creation of any claim against CITY for money or
performance, any lien, charge, encumbrance or security interest upon any asset of CITY.” White
Rock responds that the Agreement, when read in its entirety, makes clear that the City was
obligated to reimburse White Rock’s costs and that section 2.2 cannot reasonably be construed
otherwise. We agree with White Rock’s interpretation. Section 2.2 addresses only White Rock’s
performance under the Agreement, as opposed to the City’s nonperformance if its own obligations.
Moreover, sections 1.13 and 3.3 of the Agreement expressly obligate the City to reimburse White
Rock’s costs, though these sections differ whether such reimbursement is to be in full. Upon
reviewing the Agreement in its entirety, we conclude that section 2.2 did not bar White Rock’s
claim against the City. We overrule the City’s third issue.
II.
Breach of Contract
The City’s fourth issue challenges the sufficiency of the evidence to support White Rock’s
breach of contract claim. The City refers to both legal and factual sufficiency, but the crux of its
complaint is that the district court erred in granting White Rock’s motion for partial summary
judgment. Cf. City of Keller v. Wilson, 168 S.W.3d 802, 823 (Tex. 2005) (“[T]he test for legal
sufficiency should be the same for summary judgments, directed verdicts, judgments
notwithstanding the verdict, and appellate no-evidence review.”). White Rock, the movant, bears
the burden of proving that no material fact issue exists on the elements of its claim and that it is
entitled to judgment as a matter of law. TEX. R. CIV. P. 166a(c). We review a challenge to a
traditional summary judgment de novo. Provident Life & Accident Ins. Co. v. Knott, 128 S.W.3d
211, 215 (Tex. 2003). We view the evidence in the light most favorable to the City, the non-
movant, indulging every reasonable inference in the City’s favor, and resolving any doubts against
the motion. Lightning Oil Co. v. Anadarko E&P Onshore, LLC, 520 S.W.3d 39, 45 (Tex. 2017).
–14–
A. Conditions Precedent
The City asserts that White Rock’s summary-judgment motion did not establish the
occurrence of what it labels as four conditions precedent to the City’s obligation to pay the
economic development grant. The performance of a condition precedent is an essential element of
a plaintiff’s breach of contract claim. Lidawi v. Progressive Cty. Mut. Ins. Co., 112 S.W.3d 725,
734 (Tex. App.—Houston [14th Dist.] 2003, no pet.).
1. Completion of Infrastructure
The City contends that White Rock failed to give notice that it completed the infrastructural
improvements. While the 380 Agreement obligated White Rock to complete the improvements,
the contract’s terms did not require White Rock to give notice of such completion. White Rock’s
summary-judgment motion attached an affidavit by Hopkins, along with supporting
documentation, to show that (i) White Rock completed the improvements on June 22, 2009, and
(ii) the City delivered a letter of acceptance on August 13 of the same year.2 The City’s opposing
summary-judgment evidence did not contradict these facts.
2. Certificate of Occupancy
The City also complains that White Rock failed to show that a “final” certificate of
occupancy was issued for a building on the project site. As described previously, section 5.3 of the
Agreement required the City, following the issuance of a certificate of occupancy on any
“Improvement[ ]”—defined elsewhere in the contract as an office or industrial building—to
commence economic development grant payments. The Hopkins affidavit attached a “temporary”
certificate of occupancy issued by the City on June 1, 2012, for the “Mobis” building constructed
on the property. The “temporary” designation on the certificate has no significance given that the
2
The City objected to White Rock’s summary-judgment evidence. However, the district court did not rule on these objections, and they are
not asserted in the City’s appeal brief as a basis for reversal.
–15–
380 Agreement does not require a “final” certificate. White Rock’s summary-evidence thus
demonstrates that the certificate-of-occupancy requirement was met. The City’s summary-
judgment evidence did not contradict this fact.
3. Project Costs
The City complains that White Rock did not submit a written report itemizing all Project
Costs within ninety days following the end of the fiscal year in which the infrastructural
improvements were completed, as was required by section 4.6 of the Agreement. The City
contends that it did not receive such a report until December 2015, when White Rock produced a
report in response to the City’s discovery requests. The City also points to Hopkins’s trial
testimony that he did not know whether White Rock submitted a report reflecting and itemizing
its Project Costs. In the City’s view, its obligation to pay White Rock never arose because White
Rock failed to provide the cost report required by section 4.6. White Rock disputes the City’s
claims and urges that the City’s brief omits Hopkins’s trial testimony that he believed White Rock
had in fact submitted a cost report “with some level of itemization.”
We begin by considering the City’s assertion that section 4.6 gave rise to a condition
precedent. This provision contains no language that would suggest such a condition. Solar
Applications, 327 S.W.3d at 109. However, section 7.2 of the Agreement provides that, “in the
event” White Rock fails to furnish the City any required documentation within thirty business days
following a written request from the City, “then” White Rock shall be in default. Section 7.3, in
turn, suspends the City’s obligation to pay any installment while White Rock is in default.
Moreover, section 7.1 permits the City to terminate the Agreement “if” White Rock does not take
adequate steps to cure its default within a specified period of time after receiving notice of the
default. In the event of a termination, section 7.3 provides that White Rock shall forfeit any
remaining payments under the Agreement. Taken together, the foregoing provisions establish a
–16–
condition subsequent—“a condition referring to a future event, upon the happening of which the
obligation becomes no longer binding upon the other party, if he chooses to avail himself of the
condition.” Cmty. Health Sys. Prof. Servs. v. Hansen, 525 S.W.3d 671, 682 (Tex. 2017) (citation
and internal quotation marks omitted). A condition subsequent excuses an already binding
agreement, id. at 683, and unlike a condition precedent, it is an affirmative defense on which the
defendant bears the burden of proof, see Commercial Union Ins. Co. of Am. v. Stanmike Inv. Co.,
475 S.W.2d 295, 297 (Tex. Civ. App.—Waco 1971, writ ref’d n.r.e.) (concluding that burden was
on insurer to plead, prove, and establish occurrence of condition subsequent in order to avoid
liability); Knoff v. U.S. Fid. & Guar. Co., 447 S.W.2d 497, 500–01 (Tex. Civ. App.—Houston [1st
Dist.] 1969, no writ) (concluding same); Blue Bonnet Life Ins. Co. v. Reynolds, 150 S.W.2d 372,
374 (Tex. Civ. App.—Eastland 1941, writ ref’d) (concluding same).
The City’s answer did not plead White Rock’s non-compliance with section 4.6, though it
pled that White Rock did not comply with all applicable provisions of the contract. In addition, the
City’s summary-judgment opposition made no attempt to establish (i) such noncompliance, or
(ii) that the City availed itself of the condition subsequent set forth above. Since the City failed to
raise a fact question regarding this affirmative defense, section 4.6 did not foreclose the rendition
of partial summary judgment in White Rock’s favor.
4. Value of Improvements
Under section 5.3 of the Agreement, the formula for determining each economic
development grant payment is based in part on “the fair market value of the industrial distribution
and office improvements (as determined by the Dallas County Appraisal District).” The City urges
in its appeal brief, as it did in the litigation below, that White Rock’s notice of such value was a
condition precedent to the City’s contractual obligations. Related to this argument, the City’s
Economic Development Director averred in a supporting affidavit that White Rock did not notify
–17–
the City of the value of the building for which the certificate of occupancy was issued. We disagree
with the City’s contention that section 5.3 gave rise to a condition precedent. This section does not
require White Rock to provide notice of the improvements’ value, nor does it condition the City’s
obligation to pay on its receipt of such notice. Solar Applications, 327 S.W.3d at 109. Accordingly,
White Rock’s purported noncompliance with this provision did not preclude the rendition of a
partial summary judgment in its favor.
B. Affirmative Defenses
The City also asserts that fact issues regarding its affirmative defenses foreclosed the
rendition of summary judgment against it, though it provides no additional briefing on this point.
We have already addressed most of the City’s defenses asserted in its summary-judgment
opposition—specifically, governmental immunity, whether the 380 Agreement creates an
unconstitutional debt, and conditions precedent. The sole remaining defense that we have not
addressed is the City’s assertion that the 380 Agreement was an illegal tax abatement because it
required payments in excess of ten years on property not located in a “reinvestment zone,” in
contravention of section 312.204 of the Tax Code. TEX. TAX CODE ANN. § 312.204(a) (West
2015).3 This section applies only to agreements to exempt property from taxation. Id. The 380
Agreement was not such an agreement; it instead obligated the City to make grant payments
directly to White Rock. Accordingly, section 312.204 does not apply here.
In conclusion, upon viewing the summary-judgment evidence in the light most favorable
to the City, we conclude that the district court did not err in granting White Rock’s motion for
partial summary judgment. We overrule the City’s fourth issue.
3
The City also pled failure of consideration, but it did not assert this defense in its opposition to White Rock’s summary-judgment motion.
–18–
III.
Damages
A. Credit for Sums Paid Under Incentive Agreement
The 380 Agreement and the Incentive Agreement both required that White Rock be
reimbursed “in full.” However, both contracts also “anticipated” that Project Costs would exceed
reimbursements and provided that White Rock was responsible for paying these excess costs.
Under the City’s interpretation of the agreements, the $1.8 million paid in satisfaction of the
Incentive Agreement must be credited against any balance that the City owes under the 380
Agreement. Its fifth issue contends that the district court erred in refusing to apply such a credit
here.
During its cross examination of Hopkins, the City attempted to establish that it was entitled
to a $1.8 million credit, as set forth above, plus an additional credit for impact fees that it had
waived. White Rock objected to this line of questioning on the basis that the City had not pled the
affirmative defense of offset. See SAS & Assocs., Inc. v. Home Mktg. Servicing, Inc., 168 S.W.3d
296, 301 (Tex. App.—Dallas 2005, pet. denied) (noting that offset is an affirmative defense). The
district court sustained White Rock’s objection, thereby foreclosing any trial by consent regarding
this defense.
The City contends that the court’s ruling was erroneous because the defense of offset does
not apply here. This defense, also referred to as setoff, has its roots in English bankruptcy law,
which permitted a defendant to raise a debt that the plaintiff owed the defendant as a defense or
counterclaim. Bandy v. First State Bank, Overton, Tex., 835 S.W.2d 609, 618 (Tex. 1992). The
right of setoff allows parties that owe each other money from different transactions, referred to as
“mutual debts,” to apply their debts to each other. Sommers v. Concepcion, 20 S.W.3d 27, 35 (Tex.
App.—Houston [14th Dist.] 2000, pet. denied). In the City’s view, this defense does not apply to
–19–
sums paid by a third-party, in this case, the Lancaster EDC, as opposed to sums paid by the debtor
itself.
White Rock agrees that its specific objection at trial regarding the City’s failure to plead
offset was not a proper objection. It instead contends for the first time on appeal that the affirmative
defense of payment, also not pled by the City, applies here. TEX. CIV. P. 94. It argues that we
should uphold the district court’s ruling on any valid ground, i.e., the City’s failure to plead
payment, even though the court’s ruling was based on the City’s failure to plead offset. See State
Bar of Tex. v. Evans, 774 S.W.2d 656. 658 n.5 (Tex. 1989) (“[E[ven where the trial court errs in
sustaining a specific untenable objection, an appellate court should uphold the ruling if there is
any other ground for doing so, even though not urged below.”). We agree with White Rock.
Assuming the district court erred in sustaining White Rock’s objection based on the City’s failure
to plead offset, the court’s ruling was nevertheless proper based on the City’s failure to plead
payment. See Garner v. Fidelity Bank, N.A., 244 S.W.3d 855, 861 (Tex. App.—Dallas 2008, no
pet.) (“Absence of a proper plea of payment renders evidence as to payment inadmissible.”). We
overrule the City’s fifth issue.
B. Evidentiary Issues
In its sixth issue, the City asserts that several of the district court’s evidentiary rulings were
erroneous. The admission or exclusion of evidence is committed to the trial court’s sound
discretion. Interstate Northborough P’ship v. State, 66 S.W.3d 213, 220 (Tex. 2001). The City
urges that the court erred by admitting into evidence a file (Plaintiff’s Exhibit 9) containing vendor
invoices and other documentation relating to Project Costs incurred by White Rock. The City
contends that the invoices lacked a proper foundation and were inadmissible hearsay. We disagree.
Exhibit 9 was accompanied by an affidavit, signed by Hopkins, which averred that White Rock
(i) incorporated each of the invoices into its business records, and (ii) regularly relied on the
–20–
accuracy of the invoices. Hopkins also averred that White Rock confirmed the accuracy of the
invoices prior to incorporating them into its own records, thereby establishing the invoices’
trustworthiness. Hopkins provided additional testimony at trial that supported the statements made
in his affidavit. Based on the foregoing evidence, we conclude that White Rock laid a proper
predicate for the admission of Exhibit 9 under the hearsay exception for records of regularly
conducted activity. Morris v. Branch Banking and Trust Co., No. 05-15-01249-CV, 2017 WL
3634334, at *8 (Tex. App.—Dallas Aug. 24, 2017, pet. denied) (mem. op.). The court did not err
in overruling the City’s objection to the admission of this exhibit.
The City also claims that the court erred by admitting a chart into evidence (Plaintiff’s
Exhibit 8) that tallied the invoice amounts from Exhibit 9 and identified the Project Costs category
to which each invoice related. Exhibit 8 reflected that the costs incurred by White Rock totaled
$2,677,288.79. The City argues that this exhibit lacked a sufficient predicate and was inadmissible
hearsay. We again disagree. A predicate under this rule requires the offering party to show that the
underlying documents are admissible, that they are voluminous, and that they were made available
to the opposing party for inspection and use in cross-examination. Leander v. Fin & Feather Club
ex rel. Parten, No. 06-10-00135-CV, 2012 WL 75815, at *7 (Tex. App.—Texarkana Jan. 11, 2012,
no pet.) (mem. op.). As explained previously, the records underlying Exhibit 8 were admissible.
The records were approximately 800 pages, and Hopkins testified that they were an “enormous
amount of data.” White Rock’s counsel also represented to the court that the business records
affidavit proving Exhibit 9 was on file at least fourteen days before trial in compliance with Texas
Rule of Evidence 902(10)(A), thereby establishing that they were made available to the City for
inspection and cross-examination. We thus conclude that the court did not err overruling the City’s
objection to the admission of Exhibit 8.
–21–
In addition, the City urges that the court erred in overruling its objection, on relevancy
grounds, to Hopkins’s testimony regarding section 1.13 of the Agreement. Hopkins testified that
this section “created an expectation that we were going to be reimbursed in full for our cost, plus
8% per annum interest.” Hopkins’s testimony related to the disputed issue of whether
“reimbursement in full” under the 380 Agreement included the sums previously paid in satisfaction
of the Incentive Agreement. The City contends that both agreements are unambiguous and that the
previously paid sums are part of White Rock’s “full” reimbursement, thereby reducing the amount
owed by the City. If the City is correct that the contracts are unambiguous, then Hopkins’s
testimony could not establish otherwise. See David J. Sacks, P.C. v. Haden, 266 S.W.3d 447, 450
(Tex. 2008) (noting that parol evidence is not admissible to give an unambiguous contract a
meaning different than what the contract’s language imports). However, as we have explained
above, the City’s failure to plead the defense of payment precludes our consideration of whether
the court’s damages award should have been reduced by the amount of the sums paid under the
Incentive Agreement. On this record, we cannot conclude that any error in admitting Hopkins’s
testimony probably caused the rendition of an improper judgment. TEX. R. APP. P. 44.1(a)(1). We
overrule the City’s sixth issue with regard to the purported evidentiary errors that it asserts.
C. Legal and Factual Sufficiency
The City’s sixth issue also raises several challenges under the rubric of legal and factual
sufficiency. The parties each submitted proposed findings of fact and conclusions of law, but the
district court made no findings. The City does not contend that the court erred in this respect, and
we will therefore consider this case as one in which neither party requested findings of fact or
conclusions of law. In this scenario, we will imply all facts necessary to support the court’s
judgment. Shields Ltd, P’ship v. Bradberry, 526 S.W.3d 471, 480 (Tex. 2017). If the reporter’s
record is filed on appeal, as it was here, “implied findings may be challenged on factual-and legal-
–22–
insufficiency grounds in the same manner ‘as jury findings or a trial court’s [express] findings of
fact.’” Id. (quoting Roberson v. Robinson, 768 S.W.2d 280, 281 (Tex. 1989) (per curiam)). In
reviewing legal sufficiency, we must credit favorable evidence that supports the verdict, if
reasonable jurors could, and disregard contrary evidence unless reasonable jurors could not. City
of Keller, 168 S.W.3d at 827. In contrast, a factual sufficiency review requires us to weigh all of
the evidence and to set aside findings only if they are so against the great weight and preponderance
of the evidence to be clearly wrong and unjust. Ortiz v. Jones, 917 S.W.2d 770, 772 (Tex. 1996).
1. Hopkins’s Testimony
The City challenges the sufficiency of the evidence based on Hopkins’s failure to explain
“what formula [he] used to calculate the damages and/or interest accrued.” Hopkins testified that
White Rock incurred Project Costs of $2,677,288. The court admitted into evidence White Rock’s
Exhibits 8 and 9 which, as explained above, documented these costs. With the exception of the
evidence submitted by White Rock regarding its insurance costs, which we address below, we
conclude that the court could reasonably infer that the foregoing costs were Project Costs subject
to reimbursement. We also conclude that the court’s award of such costs was not contrary to the
great weight and preponderance of the evidence.
We next examine the sufficiency of the evidence to support the court’s award of the interest
that accrued on the Project Costs. Section 1.13 of the Agreement provides for (i) interest “imputed
or accrued at the rate of eight percent (8%) per annum, calculated from the Project Commencement
to Completion” plus (ii) interest “after Completion at the rate of eight (8%) per annum,
compounded annually.” Hopkins testified that, upon adding interest, White Rock’s damages
totaled $4,726,217.53. Based on this testimony, $2,048,929.53 in interest had accrued as of the
date of trial on the $2,677,288 in Project Costs incurred by White Rock. Hopkins did not explain
–23–
how this amount of interest was calculated, nor did White Rock’s exhibits contain any such
explanation.
Hopkins has a Finance degree and is a Certified Public Accountant, though he was not
offered as an expert witness. The City notes that Hopkins was unable on cross examination to
calculate the amount of interest on a hypothetical lesser sum—i.e., if White Rock’s Project Costs
were reduced by the $1.8 million previously paid by the Lancaster EDC. During this line of
questioning, Hopkins testified that the interest amount actually submitted by White Rock “had
already been calculated ahead of today.” Based on this testimony, we conclude that the court could
reasonably determine that White Rock’s interest calculations were correct. We also conclude that
the interest award was not contrary to the great weight and preponderance of the evidence
2. Lump Sum Award
Section 5.3 of the Agreement obligated the City to make annual economic development
grant payments over a twenty-year period. These payments were based on the fair market value of
the infrastructural improvements, as determined by DCAD, multiplied by the tax rate annually
adopted by the City. The City argues that the court’s lump-sum award does not conform to this
provision, given that the provision does not contain an acceleration clause. It also urges that no
evidence was admitted regarding the fair market value of the improvements and that the contract’s
payment formula, based on future property assessments and future tax rates, precluded the award
of a lump sum.
White Rock acknowledges that section 5.3 provided the mechanism through which the City
was supposed to reimburse White Rock’s costs, but it contends that the City’s material breach
permitted White Rock to recover a lump sum representing the total amount owed by the City. As
support, White Rock cites Republic Bankers Life Insurance Co. v. Jaeger, in which the Texas
Supreme Court held that “[t]he measure of damages in an action for breach of contract by
–24–
repudiation is the total of all accrued payments plus interest, plus the present value of all unaccrued
payments that the plaintiff would have received if the contract had been performed.” 551 S.W.2d
30, 31 (Tex. 1976) (per curiam).
We agree with White Rock that the City’s breach in this case permitted White Rock to
recover a lump sum award. Cf. Long Trusts v. Griffin, 222 S.W.3d 412, 415 (Tex. 2006) (per
curiam) (noting that, after defendant’s material breach of contract, plaintiff may cease performance
and sue for breach). We decline to consider whether White Rock should have offered evidence of
the present value of the annual grant payments that had not yet accrued at that time. The City did
not raise this issue at trial, nor does it complain on appeal that White Rock should have offered
evidence of a discounted lump sum.
3. Non-Reimbursable Costs
The City urges that four types of costs incurred by White Rock were not reimbursable
Project Costs under the terms of the Agreement. Under section 1.13, Project Costs were the costs
incurred to “plan, design, permit, and construct” the infrastructural improvements, except for costs
expressly excluded by the Agreement. The City claims that White Rock’s reimbursable costs
totaled $2,049,200.98, not the $2,677,288 sum awarded by the district court.
Legal fees
Hopkins testified that White Rock’s evidence of costs included the legal fees that it
incurred related to the project. In Hopkins’s experience, it is customary and advisable to incur such
fees when constructing infrastructural improvements. The City notes that the Agreement contains
no specific reference to legal fees, but it fails to explain why these fees were unnecessary to plan,
design, permit, and construct the infrastructural improvements. We conclude that the foregoing
evidence supports the court’s implied finding that White Rock’s legal fees were within the scope
–25–
of section 1.13. We also conclude that this implied finding was not contrary to the great weight
and preponderance of the evidence.
Insurance costs
Section 6.1 of the Agreement obligated White Rock or its contractor, at its “sole expense,”
to obtain insurance while constructing the infrastructural improvements. White Rock’s evidence
included the construction-related insurance costs that it had incurred. The City contends that
section 6.1’s “sole expense” requirement excluded White Rock’s insurance costs from
reimbursement. We agree based on the plain language of this provision. We therefore conclude
that no evidence supports a finding awarding reimbursement of White Rock’s insurance costs.
Title fees
The City contends that White Rock’s costs incurred from a title company were a non-
reimbursable “soft cost.” As support, it cites the testimony of Dipak Patel, a City Project Manager
whom the City proffered as an expert witness for the purpose of comparing the costs submitted by
White Rock to the Agreement’s definition of Project Costs. The City relies on Patel’s testimony
that title costs are a “soft cost” and that, based on his experience, the title costs incurred in this
case “seem[ ] to be a little bit” high. Patel declined to concede that title companies are always
unnecessary to the development of infrastructural improvements, and the City points to no other
evidence to support its position. Viewing the evidence in the light most favorable to the court’s
implied findings, we conclude that the court could reasonably determine that White Rock’s title
fees were necessary to the development of the infrastructural improvements. We also conclude
that the court’s implied findings were not contrary to the great weight and preponderance of the
evidence.
–26–
Installation of gas line
White Rock’s evidence also included invoices related to the construction of a gas line. The
City contests these costs based on the Agreement’s exclusion of costs related to the “private public
infrastructure to serve each building.” Pertinent to this exclusion, the City cites Patel’s testimony
that he believed the line in question related only to the building constructed on the property, as
opposed to the infrastructural improvements. The documentation in White Rock’s Exhibit 9
regarding this cost refers to the “installation of gas utilities at Southpoint[e] Corporate Center,”
which the record elsewhere shows was the name of the office park to be developed on the 83-acre
tract. Exhibit 9 also contains internal White Rock correspondence assigning the foregoing costs to
“infrastructure” on the basis that the gas line “is in the street, and [it] provides gas to all of the
future buildings.” (Emphasis added). This evidence suggests that the line in question was not
installed to serve a particular building, thus rendering the foregoing exclusion inapplicable. We
conclude that the evidence reasonably supports the court’s implied finding. We also conclude that
this implied finding was not contrary to the great weight and preponderance of the evidence.
4. Interest
The City raises four complaints regarding the court’s award of interest.
Accrual date for prejudgment interest
The City contests the court’s selection of June 17, 2014—the date that White Rock filed
its original petition—as the commencement date for calculating prejudgment interest. Prejudgment
interest accrues from the earlier of: (1) 180 days after the date a defendant receives written notice
of the claim, or (2) the date suit is filed, and until the day before the judgment. Long v. Castle Tex.
Prod. Ltd. P’ship, 426 S.W.3d 73, 77 (Tex. 2014). The City argues for a different rule here based
on its claim that White Rock did not submit a demand for damages or an itemized cost report until
December 2015. We decline to apply a different rule given our prior determination that White
–27–
Rock’s obligation to submit an itemized cost report was a condition subsequent that the City never
triggered.
Effect of $1.8 million payment
The City also contends that the court erred in awarding interest on an amount of damages
not reduced by the $1.8 million payment referenced above. We need not consider this argument
given our prior holding that the City’s failure to plead the affirmative defense of payment
forecloses our consideration of whether the court erred in refusing to credit the payment against
the damages award.
Duplicative interest
In addition, the City argues that the district court erred in awarding prejudgment and
postjudgment interest “in that interest is contemplated in the Agreement and the [c]ourt cannot
compound both interest rates on the award of damages.” The City cites no supporting authority,
and its bare assertion of error is insufficient for this Court to analyze the merits of its position See
TEX. R. APP. P. 38.1(i) (providing that brief must contain a clear and concise argument for the
contentions made, with appropriate citations to authorities).
Accrual date for postjudgment interest
The judgment awarded postjudgment interest beginning on February 23, 2017, even though
the judgment was not signed until March 8, 2017. The City contends that this was error. We agree
because postjudgment interest accrues from the judgment date through the date the judgment is
satisfied. Long, 426 S.W.3d at 77.
In conclusion, we sustain the City’s sixth issue regarding the court’s erroneous award of
insurance costs and regarding its award of postjudgment interest based on an erroneous accrual
date. We otherwise overrule the City’s sixth issue.
–28–
CONCLUSION
The district court did not err in denying the City’s plea to the jurisdiction and in granting
White Rock’s motion for partial summary judgment. However, the court’s damages award was
erroneous in certain respects, as set forth above. We reverse in part and remand this cause to the
district court for the limited purpose of determining (i) the amount of insurance costs, which we
have held must be excluded from the court’s damages award, and (ii) the calculation of
prejudgment interest based on the revised damages award. We modify the judgment to reflect that
postjudgment interest shall accrue from March 8, 2017, the date of the judgment. We otherwise
affirm the judgment as modified.
/Jason Boatright/
JASON BOATRIGHT
JUSTICE
170583F.P05
–29–
Court of Appeals
Fifth District of Texas at Dallas
JUDGMENT
CITY OF LANCASTER, Appellant On Appeal from the 191st Judicial District
Court, Dallas County, Texas
No. 05-17-00583-CV V. Trial Court Cause No. DC-14-06471.
Opinion delivered by Justice Boatright.
WHITE ROCK COMMERCIAL, LLC, Justices Bridges and Brown participating.
Appellee
In accordance with this Court’s opinion of this date, the judgment of the trial court is
AFFIRMED, as modified, in part and REVERSED and remanded, in part. We REVERSE that
portion of the trial court’s judgment that awarded reimbursement of appellee’s insurance costs.
We remand this case to the trial court for the purpose of determining (i) the amount of appellee’s
insurance costs to be excluded from the damages award, and (ii) the calculation of prejudgment
interest based on the revised damages award. We modify the judgment to reflect that
postjudgment interest shall accrue from March 8, 2017, the date of the judgment. In all other
respects, the trial court’s judgment is AFFIRMED.
It is ORDERED that each party bear its own costs of this appeal.
Judgment entered this 20th day of August, 2018.
–30–