l
ARMED SERVICES BOARD OF CONTRACT APPEALS
Petition of -- )
)
AWA Wilson JV ) ASBCA No. 61725-987
)
Under Contract No. W912QR-14-C-0010 )
APPEARANCE FOR THE APPELLANT: Mr. Mark Cochran
Principal
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Carlton A. Arnold, Esq.
Engineer Trial Attorney
U.S. Army Engineer District, Louisville
ORDER PURSUANT TO BOARD RULE l(a)(5)
DIRECTING CONTRACTING OFFICER TO ISSUE DECISION
AWA Wilson JV (A WA or contractor) filed a request, under Rule l(a)(5), for
an order directing the contracting officer (CO) to render a decision on an April 20,
2018 certified claim. A WA requested that the CO issue a decision within 30 days of a
Board order issuing an order. The United States Army Corps of Engineers
(government) has advised that a final decision on the claim will be issued by
December 18, 2018. We find the government's proposed date unreasonable and direct
the CO to issue a decision by October 24, 2018.
STATEMENT OF FACTS (SOF) FOR PURPOSES OF THE PETITION
1. AWA entered into Contract No. W912QR-14-C-0010, a firm fixed price
contract, with the government for work to be done at the Kingsolver/Pierce School in
Fort Knox, KY. Range and Civil Construction, LLC (RACC) was hired as the
earthwork subcontractor. (Bd. corr. ltr. dtd. August 15, 2018, ex. 4 at 1).
2. During its performance in 2014, RACC encountered what it described as
"unsuitable subsurface soils" in greater quantities than what it expected based on its
reading of the contract documents (Bd. corr. ltr. dtd. August 15, 2018, ex. 4 at l; pet. at 1).
3. By request for equitable adjustment (REA) dated March 30, 2015, AWA
requested a price adjustment based on the alleged unsuitable soils. In a response dated
May 14, 2015, the government stated that it did not believe the REA had merit, and, if
AWA wanted to pursue the action, it needed to provide an analysis. (Bd. corr. ltr. dtd.
August 15, 2018, ex. 4 at 41-42; pet. at 1).
4. AWA resubmitted the REA with additional analysis on July 5, 2016. The
REA proposal represented the direct and indirect costs associated with the unsuitable
soils and their impact on RACC and A WA. By correspondence dated January 5, 2016
the government denied the supplemental REA. (Bd. corr. ltr. dtd. August 15, 2018,
ex. 4 at 12, 82).
5. After receiving a "verbal request" for reconsideration of its prior decision,
the government again denied the REA again on June 27, 2017, reiterating its position
outlined in the January 5, 2017 denial (Bd. corr. ltr. dtd. August 15, 2018, ex. 4
at 85-86).
6. On October 9, 2017, RACC sent a letter to AWA, requesting that AWA
attempt to engage with the government to address the unsuitable soils issues (Bd. corr.
ltr. dtd. August 15, 2018, ex. 4 at 89).
7. A formal meeting was held on October 26, 2017, between AWA and the
government to discuss the issues in the REA. Two days later, AW A submitted a
mutual position memorandum to the government. A month later, on November 20,
2017, the government denied the position memorandum. (Pet. at 1).
8. RACC submitted a request to AWA on January 2, 2018, that it sponsor a
Contract Disputes Act (CDA) claim against the government under the contract.
Specifically, RACC requested a contracting officer's final decision (COFD) for the
unsuitable soils. (Bd. corr. ltr. dtd. August 15, 2018, ex. 4 at 1).
9. On April 20, 2018, AWA submitted its certified CDA claim in the amount of
$911,522 to the government. The claim requested a decision within 60 days of receipt.
(Bd. corr. ltr. dtd. August 15, 2018). On June 15, 2018, the CO advised that the
decision "may" be expected on or before December 18, 2018, due to the size,
complexity and need to review additional supporting data" (pet. at 1).
10. AWA filed its petition for a COFD on July 21, 2018 (id.).
11. By correspondence dated August 21, 2018, the government advised it
would issue its COFD on or before December 18, 2018 "[ d]ue to conflicts created by
pending litigation in another unrelated appeal..." (Bd. corr. ltr. dtd. August 21, 2018).
2
I
J DECISION
1
I When a CO receives a certified claim over $100,000, the Contract Disputes Act
(CDA), 41 U.S.C. §§ 7101-7109, requires that within sixty days of receipt of the
claim, the CO shall (a) issue a decision or (b) notify the contractor of the time within
which a decision will be issued. 41 U.S.C. § 7103(f)(2). The CDA also requires that
the decision of the CO on a contractor's claim "be issued within a reasonable
time ... taking into account such factors as the size and complexity of the claim and the
adequacy of information in support of the claim provided by the contractor."
41 U.S.C. § 7103(f)(3). Further, "[a] contractor may request the tribunal concerned to
direct a contracting officer to issue a decision in a specified period of time, as
determined by the tribunal concerned, in the event of undue delay on the part of the
contracting officer." 41 U.S.C. § 7103(f)(4). Board Rule l(a)(5) implements this
section providing that "[i]n lieu of filing a notice of appeal under paragraph (a)(l) or
(a)(2) of this Rule, the contractor may petition the Board to direct the contracting
officer to issue a decision in a specified period of time as determined by the Board."
Whether the time in which a CO states he or she will issue a decision is
reasonable must be determined on a case-by-case basis. Eaton Contract Services, Inc.,
ASBCA Nos. 52686, 52796, 00-2 BCA ,r 31,039 (finding eight months reasonable
given the volume of documentation, number of issues and time needed to gather
information due to relocation of personnel); Defense Systems Co., ASBCA No. 50534,
97-2 BCA ,r 28,981 (finding nine months reasonable when claimed amount exceeded
$71 million and narrative portion of the claim alone exceeded 162 pages);
Dillingham/ABB-SUSA, a Joint Venture, ASBCA Nos. 51195, 51197, 98-2 BCA
,r 29,778 (finding 14-16 months unreasonable for a small construction claim and an
impact claim that had been extensively analyzed and audited).
Here, the government argues that the CO intends to issue a decision on or
before December 18, 2018 due to conflicts created by pending litigation in another
appeal (SOF ,r 11 ). However, the Board has held that internal staffing matters are not
one of the factors used to determine a reasonable time under the CDA. Volmar
Constr., Inc., ASBCA No. 60710-910, 16-1 BCA ,r 36,519; See Fru-Con Construction
Corp., ASBCA No. 53544, 02-1 BCA ,r 31,729 (finding the scarcity of attorneys to
assist with the review of a contracting officer's final decision is a matter wholly and
exclusively within the control of the government).
There is no dispute as to whether the necessary documents were provided to the
CO. While the government initially claimed, in its initial letter to A WA stating it
would not issue a decision until December 2018, that it needed more time to review
additional information, it is unclear what that information is, given the extensive prior
REA submissions and discussions. Based on the available record, it appears the CO
has had access to most, if not all, of the same information since the revised REA was
3
submitted in July 2016. Additionally, the claim does not appear, on its face, to be
extraordinarily complex, requiring additional time to assess.
After considering the parties' arguments, we find that the government's
requested COFD issuance date of on or before December 18, 2018, is unreasonable.
The contractor submitted the initial REA on March 30, 2015. It then revised and
supplemented the REA in July 2016, and had meetings with the government to discuss
the REA. The certified claim was submitted on April 20, 2018. On June 15, 2018, the
CO responded to the contractor, alleging because the claim was too large and complex,
I
the CO may not issue a decision until December 18, 2018. It is not clear what
additional documentation the CO needed to review or how the matters in the claim
differed so greatly from REA, such that it became a more complex issue.
I Under the circumstances, we find the December 18, 2018 date for issuing a
final decision to represent undue delay. We believe that a reasonable time for the CO
to issue a final decision is October 24, 2018.
CONCLUSION
The Board hereby directs the CO to issue a decision on the contractor's claim
by October 24, 2018.
This Order completes all necessary action by the Board. If the CO fails to
comply with this Order, such failure will be deemed a decision by the CO denying the
claim, and the contractor may appeal to this Board or sue in the United States Court of
Federal Claims pursuant to the Contract Disputes Act, 41 U.S.C. §§ 7103(t)(5) and
7104.
Dated: September 17, 2018
dministrative Judge
Chairman
Armed Services Board
of Contract Appeals
(Signatures continued)
4
ORD OWEN C. WILSON
Administrative Judge Administrative Judge
Vice Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Order of the Armed Services
Board of Contract Appeals in ASBCA No. 61725-987, Petition of AWA Wilson JV,
rendered in conformance with the Board's Charter.
Dated:
JEFFREY D. GARDIN
Recorder, Armed Services
Board of Contract Appeals
5