IN THE COURT OF APPEALS OF THE STATE OF WASHINGTON
CORINA PUENTE, individually and as ) No. 76604-0-1
Personal Representative of the Estate )
of Javier Puente, deceased, ) DIVISION ONE
)
Appellant, )
)
v. )
)
RESOURCES CONSERVATION )
COMPANY INTERNATIONAL, a )
Delaware Corporation and a )
SUBSIDIARY of GE IONICS, INC., )
a Massachusetts Corporation, ) PUBLISHED OPINION
)
Respondent, )
Iti :6 WV ZZ 130 010Z
)
BAUGH INDUSTRIAL CONTRACTORS)
INC., a Washington Corporation; )
SKANSKA USA BUILDING, INC., a )
Delaware Corporation; STIRRETT- )
JOHNSEN,INC., a Washington )
Corporation; HARRIS GROUP, INC., a )
Washington Corporation; and NIPPON )
CHEMI-CON, a Japanese Corporation, )
)
Defendants. ) FILED: October 22, 2018
SCHINDLER, J. — Chemi-Con Materials Corporation(CMC)manufactures
anode aluminum foils for electrolytic capacitors. The manufacturing process
produces liquid boric acid. A boric acid evaporator system (BAES)converts the
180-degree liquid boric acid into distilled water for reuse in manufacturing anode
No. 76604-0-1/2
aluminum foil and into solid waste for disposal. In July 2012, CMC worker Javier
Puente suffered fatal injuries while performing maintenance work on the BAES
pump that had been installed in the environmental building of the facility in 2002.
Corina Puente individually and as the personal representative of the Estate of
Javier Puente (collectively, the Estate)filed a lawsuit against GE Ionics Inc. and
Resources Conservation Company International (collectively, RCCI)alleging
claims of negligence and liability under the Washington product liability act
(WPLA), chapter 7.72 RCW. The court ruled on summary judgment that the
lawsuit against RCCI is barred by the six-year statute of repose for claims arising
from construction, design, or engineering "of any improvement upon real
property." The Estate appeals the order granting summary judgment dismissal
of the lawsuit and the order denying reconsideration. We conclude the BAES
installed in the environmental building is not an improvement upon real property
and reverse and remand.
FACTS
Chemi-Con Materials Corporation(CMC)is a wholly owned subsidiary of
Nippon Chemi-Con Corporation (NCC). CMC manufactures anode aluminum
foils at its facility in Moses Lake, Washington. NCC uses the anode aluminum
foils to manufacture aluminum electrolytic capacitors.
The CMC manufacturing facility at Moses Lake operated in a building
originally built as a United States Air Force base hanger. CMC decided to
RCW 4.16.300.
2
No. 76604-0-1/3
expand the west bay building of the existing facility and add six new aluminum
formation machines to increase production.
Baugh Industrial Contractors Inc.2 was the general contractor for the
approximately $32.6 million "Large Phase 3"(LP3)"West Bay Expansion
Project." Baugh retained architect and engineering firm Harris Group Inc. to
design the expansion. Stirrett-Johnsen Inc. was the mechanical piping
subcontractor.
The LP3 West Bay Expansion Project began in 2000. In addition to the
six new aluminum formation machines in the main facility, the "environmental
building" was expanded to house utility systems and "support equipment,"
including "[c]ity water reverse osmosis" systems, deionization units, a phosphoric
acid recovery system, air compressors, and a new, larger boric acid evaporator
system (BAES). A BAES converts the liquid boric acid produced during the
manufacturing of anode aluminum foils into distilled water and into solid waste for
disposal. The distilled water is stored in a condensate tank and reused in the
manufacturing process.
Baugh entered into a contract with GE Ionics Inc. and Resources
Conservation Company International (collectively, RCCI)3 for the new BAES.
RCCI designs, builds, and sells industrial evaporator and wastewater treatment
systems worldwide:
RCCI produces detailed piping and instrumentation drawings and
Installation blueprints for its systems, procures the components that
comprise the system, and then works with the relevant general
contractor to ensure the system is constructed according to plan.
2 Skanska USA Building Inc. acquired Baugh In 2000.
3 In 2001, RCCI was doing business as"RCC Ionics.'
3
No. 76604-0-1/4
After construction is complete, RCCI provides startup assistance
and technical support services as the general contractor and the
customer work to bring the system online. RCCI does not
manufacture any components of its boric acid evaporator systems,
but instead provides design and specification services.
The contract between Baugh and RCCI identifies RCCI as the "Seller."
The contract states the Seller shall provide "the design, procurement,
manufacturing, and delivery of Boric Acid Evaporator System."
Exhibit B identifies the scheduled delivery dates for the components for
the BAES, including tanks to collect and store the liquid boric acid produced
during the manufacturing process, a heat exchanger and recirculation pump, a
"heater shell," and a 4-to 5-story or 50- to 60-foot-tall evaporator tank or "vapor
body" to be located outside the environmental building.
Exhibit C identifies the technical design specifications for the BAES:
Vendor agrees to supply the design, procurement, manufacturing,
and delivery of the Boric Acid mechanical vapor recompression
type evaporator system designed for 32 gpmmaverage flow and 40
gpm peak flow per the design conditions listed in RFP[51 05-
870/Q/2003 and per the scope of supply that includes, but is not
limited to the following:
1. Complete evaporator assembly....
2. Heat Exchangers
3. Pumps
4. Liquid/solid separation equipment
5. Compressors
6. Control valves and in-line instruments
7. All interconnecting piping and ductwork up to owner interface
Gallons per minute.
5 Request for proposal.
4
No. 76604-0-1/5
8. Support structure for furnished equipment. RCC[I]to provide
the vapor body support legs, upper access platform, and
ladder.' RCC[I]to provide support legs for heater. RCC[I]to
provide 4'x30' maintenance platform for heater including
access ladder.
9. All manual valves
10. Painting....
11. Motors — High Efficiency....
12. Noise insulation system. RCC[1]to provide noise insulation
blankets for both compressors to achieve performance of 86-
88 dBAI61@ 3ft.
13. Control panels and PLC control system
14. Design engineering and drawings
15. Erection supervision, training, and start-up assistance as
required and requested from Contractor and/or Owner.
16. Testing to verify equipment fabrication, operation, and
process guarantees
17. All electrical and control equipment will be ULMirated....
18. Flow Transmitters will be used in place of magnetic flow
meters due to the low conductivity of the fluids.
CMC issued a certificate of completion for the LP3 West Bay Expansion
Project on August 23, 2002. The "Project Completion Report" describes the work
completed and the new equipment installed. The report identifies the BAES as a
new "major process" system that is "rmiajor equipment installed as part of the
LP3 west bay expansion project." The RCCI BAES "Maintenance Manual"
6 Decibels.
Programmable logic controller.
° Underwriters Laboratory.
5
No. 76604-0-1/6
contains "the equipment manufacturers' instructions for installation and
maintenance" of the BAES.
On July 23, 2012, CMC shut down the Moses Lake "manufacturing plant"
for "routine maintenance." Sixty-four-year-old Javier Puente had been a CMC
1
maintenance department employee for more than 10 years and had been
responsible for maintenance of the BAES for "many years? Before performing
maintenance on the BAES recirculation pump located in the environmental
building, the CMC employees drained the liquid from the BAES. Puente and the
other maintenance workers removed the bolts that attached the BAES
recirculation pump to the piping system. Puente was "standing near the joint
between the pump and the piping system" when a large volume of 180-degree
"boric acid solution" burst onto him. Puente died two days later from thermal
burns to 80 percent of his body.
Corina Puente individually and as the personal representative of the
Estate of Javier Puente (collectively, the Estate)filed a lawsuit against GE Ionics
Inc. and Resources Conservation Company International (collectively, RCCI)
alleging claims of negligence and liability under the Washington products liability
act(WPLA), chapter 7.72 RCW.9 The Estate alleged RCCI is a "product
manufacturer." The Estate alleged RCCI negligently installed equipment,
provided defective designs and equipment, did not design a reasonably safe
9 When the Estate filed the lawsuit, RCCI was doing business as"GE Power & Water.'
The Estate also sued Baugh, Skanska USA, the Harris Group, Stirrett-Johnsen, and CMC parent
company NCC.
6
No. 76604-0-1/7
BAES, breached express and implied warranties, and did not provide adequate
warnings.
A chemical engineer expert retained by the Estate concluded the BAES
designed by RCCI was "inherently dangerous."
1
[I]t is my opinion that Defendant RCCI designed the BAES, knowing
that the hazard of hot boric acid solution would exist and that the
recirculation pump would need to be removed for maintenance
periodically, and did not provide any way to block the hazard of hot
boric acid solution when workers removed the recirculation pump
for maintenance. It is my opinion that Defendant RCCI designed a
product that was inherently dangerous because Defendant RCCI
knew that the BAES included wearable parts that would require
maintenance (e.g., the recirculation pump), and they did not include
double block and bleed mechanisms so that the pump could be
safely removed without workers being exposed to the hazard of hot
boric acid solution.11°1
RCCI filed a motion for summary judgment dismissal on the grounds that
the six-year construction statute of repose barred the lawsuit. RCW 4.16.300
states actions or claims arising from construction of an improvement upon real
property are subject to the six-year construction statute of repose. RCW
4.16.310 bars claims that accrue within six years of substantial completion.
RCCI argued the BAES is an improvement upon real property because it was
Integral to the function of the environmental building.
In opposition to summary judgment, the Estate argued the construction
statute of repose did not bar the lawsuit because the record established the
BAES was part of the manufacturing process, not an improvement upon real
property.
"CMC replaced the BAES that RCCI designed after Puente was severely injured.
7
No. 76604-0-1/8
The court entered an "Order Granting Defendant Resources Conservation
Company International's Motion for Summary Judgment Pursuant to
Construction Statute of Repose." The court denied the motion for
reconsideration. The order denying reconsideration states the court finds RCCI
I
are "engineers entitled to the protection of the construction statute of repose in
RCW 4.16.300 and 4.16.310 against Plaintiffs claims herein," the claims "arise
out of construction activities related to improvements upon real property," and the
claims "accrued after the expiration of the construction statute of repose in RCW
4.16.300 and 4.16.310."
The Estate appeals the summary judgment order of dismissal and the
order denying the motion for reconsideration.11
ANALYSIS
The Estate contends the court erred in ruling that the BAES is an
improvement "upon real property" barred by the construction statute of repose.
We review an order of summary judgment dismissal de novo and engage
In the same inquiry as the trial court. Kofmehl v. Baseline Lake, LLC, 177 Wn.2d
584, 594, 305 P.3d 230(2013). Summary judgment is appropriate when there is
no genuine Issue as to any material fact and the moving party is entitled to
judgment as a matter of law. CR 56(c); Kofmehl, 177 Wn.2d at 594. A material
fact is one upon which the outcome of the litigation depends. Owen v. Burlington
N. Santa Fe R.R., 153 Wn.2d 780,789, 108 P.3d 1220(2005). We consider all
II The court also dismissed the lawsuit against the general contractor Baugh, Skanska
USA, the construction project architect and engineer the Harris Group, the mechanical piping
subcontractor Stirrett-Johnsen, and CMC parent company NCC as barred by the six-year statute
of repose. The Estate does not appeal the order dismissing these defendants.
8
No. 76604-0-1/9
facts and make all reasonable factual inferences in the light most favorable to the
nonmoving party. Young v. Key Pharms., Inc., 112 Wn.2d 216,226,770 P.2d
182(1989). Summary judgment should be granted only "if reasonable minds
could reach only one conclusion from the evidence presented." Estate of Becker
v. Avco Corp., 187 Wn.2d 615,621, 387 P.3d 1066(2017); Allen v. State, 118
Wn.2d 753, 760, 826 P.2d 200(1992).
"A statute of repose terminates the right to file a claim after a specified
time even if the injury has not yet occurred." Maior League Baseball Stadium
Pub. Facilities Dist. v. Huber, Hunt & Nichols-Kiewit Constr. Co., 176 Wn.2d 502,
511,296 P.3d 821 (2013). The construction statute of repose bars all claims
arising from construction of"any improvement upon real property" that has not
accrued within six years after substantial completion. RCW 4.16.300,.310.
RCW 4.16.300 states:
RCW 4.16.300 through 4.16.320 shall apply to all claims or causes
of action of any kind against any person, arising from such person
having constructed, altered or repaired any improvement upon real
property, or having performed or furnished any design, planning,
surveying, architectural or construction or engineering services, or
supervision or observation of construction, or administration of
construction contracts for any construction, alteration or repair of
any improvement upon real property. This section is specifically
intended to benefit persons having performed work for which the
persons must be registered or licensed under RCW 18.08.310
[(architects)], 18.27.020 [(contractors)], 18.43.040[(engineers and
land surveyors)], 18.96.020[(landscape architects)], or 19.28.041
[(electricians)), and shall not apply to claims or causes of action
against persons not required to be so registered or licensed.
RCW 4.16.310 states,"All claims or causes of action as set forth in RCW
4.16.300 ... which ha[ve] not accrued within six years after such substantial
completion of construction ... shall be barred." There is no dispute the Estate
9
No. 76604-0-1/10
filed the lawsuit against RCCI more than six years after substantial completion of
the CMC LP3 expansion project.
RCCI and the Estate dispute whether the BAES is an "improvement upon
real property" under RCW 4.16.300 that is barred by the six-year statute of
repose. RCW 4.16.310.
The Washington Supreme Court decision in Condit v. Lewis Refrigeration
Co., 101 Wn.2d 106, 676 P.2d 466(1984), controls. In Condit, the court rejected
the analysis but affirmed the result in Yakima Fruit & Cold Storage Co. v. Central
Heating & Plumbing Co., 81 Wn.2d 528, 503 P.2d 108(1972), and Pinneo v.
Stevens Pass, Inc. 14 Wn.App. 848,545 P.2d 1207(1976). Condit, 101 Wn.2d
at 109-10. The court in Condit concluded the statute of repose, RCW 4.16.300,
applies only to claims "against any person, arising from such person having
constructed, altered or repaired any improvement upon real property" and
specifically,"construction activities, including designing, planning, surveying,
architectural, or construction or engineering services." Condit, 101 Wn.2d at 110.
Because "(e]ach of these activities relates to the process of building a structure,"
the court rejected the analysis in Yakima Fruit and Pinneol2 as contrary to the
intent of the statute. Condit 101 Wn.2d at 109-10. The court held the statute
"focuses on individuals whose activities relate to construction of the
12 In Yakima Fruit, the court looked to the "manner, purpose and effect of annexation to
the freehold" to determine "whether Improvements or Installations on the realty retain their
character as personalty or become a part of the realty.' Yakima Fruit 81 Wn.2d at 530-31. In
Pinneo, the court cited Sienloch v. Iroauois Minim Co., 106 Wash.632,636, 181 P. 51 (1919), to
conclude an improvement upon real property is a'betterment of a permanent nature which added
to the value of the property as real property.' Einneo, 14 Wn. App. at 851.
10
No. 76604-0-1/11
improvement, rather than those who service or design items within the
improvement." Condit, 101 Wn.2d at 110.
With respect to "those who service or design items" installed within a
building, the court observed that "if these individuals were protected, they could
easily avoid product liability law, if they desired, by simply bolting, welding the
equipment or fastening it in some other manner to the building." Condit 101
Wn.2d at 110-11. The court held,"Mechanical fastenings may attach a machine
to the building, but they do not convert production equipment into realty or
integrate machines into the building structure, for they are not necessary for the
building to function as a building." Condit, 101 Wn.2d at 111.
The court concluded the engineering and design of the conveyer belt and
refrigeration unit that caused the injury to the plaintiff was not an improvement
upon real property. Condit 101 Wn.2d at 112. But instead, the conveyor belt
and refrigeration unit were engineered and designed as part of the
"manufacturing process taking place within the improvement." Condit, 101
Wn.2d at 112.
Rather than designing an improvement on real property,
respondent was engineering and designing accoutrements to the
manufacturing process taking place within the improvement. As
such, they are more properly subject to product liability law and its
statute of limitations.
Condit, 101 Wn.2d at 112.
The decisions in Pinneo and Yakima Fruit are consistent with the analysis
adopted in Condit and further amplified in 1519-1525 Lakeview Boulevard
11
No. 76604-0-1/12
Condominium Ass'n v. Apartment Sales Corp., 144 Wn.2d 570,29 P.3d 1249
(2001).
In Pinneo, the operator of the Stevens Pass ski area retained a contractor
to replace and install a ski lift. Pinneo, 14 Wn. App. at 849. Yakima Fruit
involved the repair of a building refrigeration system integrated into the structure
of the building such that the system could not be removed from the building with
either the system or the building remaining intact. Yakima Fruit, 81 Wn.2d at
529-31. The repair required the removal of an entire floor of the building
structure. Yakima Fruit, 81 Wn.2d at 529.
In Lakeview, the Washington Supreme Court considered the class of
persons affected by the statute, noting that the statute applies to claims of any
kind against any person arising from that person having constructed, altered, or
repaired any improvement upon real property or from having performed or
furnished a limited set of delineated services for the construction, alteration, or
repair of any improvements on real property. Lakeview, 144 Wn.2d at 578 (citing
RCW 4.16.300). In further defining the class of persons affected by the statute,
the court drew a number of distinctions between contractors who are within the
class of persons affected by the statute and manufacturers who are not.
Lakeview, 144 Wn.2d at 578-79.
As relevant here, the court noted (1) manufacturers are subject to product
liability laws that have their"own statutes of limitation" tied to the "useful life of
the product,"(2)contractors "make a unique product designed to deal with the
12
No. 76604-0-1/13
distinct needs of a particular piece of real estate "13(3)contractors "build
improvements upon real estate in an ever-chanqinq environment"and (4)
manufacturers "do not contribute to the structural aspects of real estate
improvements? Lakeview, 144 Wn.2d at 579.14
Here, the record establishes the BAES equipment located in the
environmental building, including the pump Puente was working on at the time of
his fatal injury, was integral to the operation of the production lines and the
manufacturing process. CMC vice president Joseph Akers testified the BAES is
essential to the manufacturing process:
Q. And the — and tell us again what the purpose or the
intent of that entire system is.
A. To evaporate the boric waste stream.
Q. Because if you didn't do that what would be the
consequence?
A. We couldn't operate the facility.
Q. Okay.... And,just to follow up, why Isn't it that you
couldn't operate the facility if you didn't have this system in place?
A. Because our process utilizing the boric acid to form
our product it has that waste stream and that waste stream we can't
just dump anywhere, we have to treat it based on a permit that
we're issued.
Q. I see. Okay. So if that system shuts down the plant
shuts down?
A. Yes.
Q. And I believe you say, I just want to make sure, that
the system that we see ... is it fair to say it's crucial to the
operation of the plant?
A. Yes.
Q. And this is what you're referring to if that system goes
down then the plant has to go down for a little while, correct?
A. Yes.
13 RCCI argues it produces unique equipment for every site, but the unique design Is
driven by the manufacturing process, not by the distinct needs of a particular piece of real estate.
14 Emphasis added.
13
No. 76604-0-1/14
Q. I think you said earlier — I think you were answering
questions because of the critical nature, the Boric Acid Evaporator
System. What did you mean by that?
A. Without the Boric Evaporator System operating, we
can't operate the production lines.
The Supreme Court in Condit and Lakeview has been very clear that in
order for a mechanical system within a building constructed on real property to
be integral so as to constitute an "improvement upon real property,'the system
must actually be integrated into and a part of the structure itself. Condit, 101
Wn.2d at 112; Lakeview, 144 Wn.2d at 578-79; RCW 4.16.300. The record
establishes the BAES equipment located in the environmental building was not
Integral to the environmental building structure. Rather, the equipment was
simply "house[d]" within the environmental building. Akers testified part of the
LP3 project was to expand the environmental building to "house additional
equipment," including the BAES:
Q. So tell — what sort of additions to the physical plant
took place out there, modifications to the physical plant took place
out there as part of the LP3 expansion?
A. So in production we added of course the six additional
formation lines with all the equipment that's related to that on the
production side. We added additional cooling capabilities, so
cooling towers and air cooled heat expansion changers, the
environmental building was expanded to house the additional
equipment used to either supply product to production or to handle
the waste in production.
Q. So had there — I have heard talk of this
environmental building, was there always an environmental building
in existence In some fashion since the time you got there in '95?
A. Yes.
Q. But what happened in 2000 is that it was expanded?
A. Correct.
Q. And what was the purpose of why was it expanded?
A. To house the additional equipment needed to treat
the additional formation lines.
14
No. 76604-0-1/15
Q. So it's fair to say that that vapor body that we see
there is part of an entire system?
A. Correct.
Like the conveyor belt and freezer tunnel system in Condit we conclude the
BAES is an "accoutrement[)to the manufacturing process taking place within the
improvement." Condit 101 Wn.2d at 112.
We reverse and remand.
WE CONCUR:
4/aV
15