NOTICE: This opinion is subject to motions for reargument under V.R.A.P. 40 as well as formal
revision before publication in the Vermont Reports. Readers are requested to notify the Reporter
of Decisions by email at: JUD.Reporter@vermont.gov or by mail at: Vermont Supreme Court, 109
State Street, Montpelier, Vermont 05609-0801, of any errors in order that corrections may be made
before this opinion goes to press.
2018 VT 123
No. 2017-413
In re Champlain Parkway Wetland Supreme Court
Conditional Use Determination
(Fortieth Burlington, LLC)
On Appeal from
Superior Court,
Environmental Division
April Term, 2018
Thomas S. Durkin, J.
Judith L. Dillon of Lisman Leckerling, P.C., Burlington, for Appellant.
Thomas J. Donovan, Jr., Attorney General, and Nicholas F. Persampieri, Assistant Attorney
General, Montpelier, for Appellee Agency of Natural Resources.
Jonathan T. Rose and Brian S. Dunkiel of Dunkiel Saunders Elliott Raubvogel & Hand, PLLC,
Burlington, for Appellee City of Burlington.
PRESENT: Reiber, C.J., Skoglund, Robinson, Eaton and Carroll, JJ.
¶ 1. EATON, J. This appeal arises following the decision of the Agency of Natural
Resources (ANR) extending the City of Burlington’s 2011 Conditional Use Determination (2011
CUD), which permitted the City to commence construction on the Champlain Parkway project.
Appellant Fortieth Burlington, LLC (Fortieth) contests ANR’s approval of the permit extension,
and the Environmental Division’s subsequent affirmance of that decision, on the basis that the City
failed to adhere to several project conditions outlined in the 2011 CUD and was required to
redelineate and reevaluate the wetlands impacted by the project prior to receiving an extension,
among other reasons. The Environmental Division dismissed Fortieth’s claims, concluding that
the project complied with the 2011 CUD’s limited requirements for seeking a permit extension
and that Fortieth’s other claims were collateral attacks against the underlying permit and were
impermissible. We affirm.
I. Facts and Procedural History
¶ 2. The relevant facts as found by the Environmental Division are as follows. In
September 2016, ANR granted the City’s request to extend the 2011 CUD for the Champlain
Parkway project. The 2011 CUD approved the proposed project impacts as described in the City’s
application, provided that the project complied with several conditions that were part of the permit.
¶ 3. There are three conditions of the CUD at issue here, Conditions A, D, and E.
Condition A requires the City to obtain the written approval of the Vermont wetlands office prior
to making “material or substantial changes” to the project. Condition D provides that:
All construction activities in the wetland and adjacent 50-foot
buffer zone shall be performed in compliance with Condition A and
shall be completed within five years of the date of this Conditional
Use Determination or this Conditional Use Determination will
terminate. The Secretary may grant an extension to this five-year
period. Any request for an extension must be received by the
Department at least 30 days prior to the end of the five-year period
in order to prevent the termination of this Conditional Use
Determination. A request for extension will be considered a minor
modification.
(Emphases added.) Finally, Condition E states that “[t]he wetland boundary determination is valid
for five years from the date of this determination” and that “[t]he delineation will need to be re-
evaluated by a qualified wetland consultant if the project is not constructed, or additional impacts
are proposed, after the five-year time period expires.” (Emphasis added.) The interplay between
these three conditions—namely whether the conditions are linked or to be applied separately—is
at the heart of this appeal. Fortieth challenges the City’s compliance with Conditions A, D, and
E; asserts that the project’s impacts have changed since ANR granted the original permit; and
2
argues that the City is required to redelineate and reevaluate the project’s impacts on nearby
wetlands prior to receiving an extension.
¶ 4. In September 2015, approximately three-and-a-half months before the 2011 CUD
was set to expire in January 2016, the City formally requested an extension to the 2011 CUD for
the project pursuant to Condition D. The request was timely according to Condition D’s
requirement that the application for an extension be filed at least thirty days prior to the end of the
2011 CUD’s five-year period. In its request, the City notified ANR that it had not commenced
construction on the project and that the City would like an extension of the original permit. The
City stated that the project’s wetland areas and impacts outlined in the original permit authorization
had not changed.
¶ 5. ANR issued a Notice of Amendment to the 2011 CUD, advising that the extension
request had been received on behalf of the City and setting the forty-five-day public comment
period required under the 2012 Vermont Wetland Rules. Fortieth filed comments, which included
Fortieth’s assertion that the extension request “did not include a redelineation or re-evaluation of
wetland H/I, or any field data regarding current conditions and boundaries” of the wetlands on the
project site as required by Condition E.1 Fortieth insisted that an extension of the CUD could not
be granted until the site had been reevaluated. Fortieth’s comments were based on Condition E’s
requirement that if the project was not constructed in the five years when the original CUD was
valid, then the wetland boundary delineation would need to be reevaluated after the five-year
period expired.
1
Wetland H/I is a thirteen-acre wetland complex with an adjacent fifty-foot buffer. It is
designated as a Class II wetland pursuant to Vermont Wetland Rule § 2.07. The City’s project has
various impacts on wetland H/I, such as a “shared-use path [that] will bisect the wetland,” which
were known at the time the 2011 CUD was granted.
3
¶ 6. In response to the comments, ANR agreed with Fortieth that redelineation of the
wetland boundary was necessary for the project extension and instructed the City to reevaluate the
wetlands on the project site. ANR later explained that this response to Fortieth’s comment was in
error—ANR maintained in its briefing and at oral argument before this Court that the City’s
request for an extension did not trigger Condition E’s requirements. ANR verified that Condition
D required the extension request to be filed before the five-year period expired, while Condition
E required the wetland to be reevaluated after the five-year period expired—the two conditions
were not linked.2 Nonetheless, in December 2015 and May 2016, the City redelineated and field
verified the wetlands that were included under the 2011 CUD, including “[p]reviously delineated
wetlands” and additional wetlands P and Q. ANR reviewed the information provided by the City
and determined that the redelineation of all wetlands on the project site was conducted
appropriately and that no changes would preclude the project from moving forward.
¶ 7. ANR granted the City’s extension request for the 2011 CUD, and extended all the
conditions of the 2011 CUD, including Conditions A, D, and E. Fortieth appealed ANR’s
Extension Decision to the Environmental Division, filing twelve questions in its Statement of
Questions.3 The majority of the questions related to the project’s impacts on wetland H/I and its
2
ANR’s current position is that “[t]he only requirement for obtaining extension of the
2011 CUD was that the City submit a timely request for an extension.”
3
The twelve questions submitted by Fortieth are as follows:
(1) Whether the project will result in an undue adverse impact to
protected functions and values of the significant wetland H/I, or
wetland buffer, and fails to comply with the Vermont Wetland
Rules?
(2) Whether the project complies with Vermont’s Wetland Statute,
10 V.S.A. sec. 913?
(3) Whether the City failed to comply with the terms and
conditions of the original CUD issued January 14, 2011, in failing
4
compliance with the Vermont Wetland Rules and Vermont wetland statute 10 V.S.A. § 913
(prohibiting certain activities in wetlands and wetland buffer zones). Questions 3 and 4 challenged
the City’s compliance with the 2011 CUD conditions because the City “fail[ed] to redelineate the
wetland boundary or re-evaluate the wetland delineation” and “provide a wetland delineation by a
to redelineate the wetland boundary or re-evaluate the wetland
delineation before it applied for its CUD extension?
(4) Whether the City failed to file a complete and timely wetland
permit extension request where it failed to provide a wetland
delineation by a qualified wetland consultant during the growing
season and failed to include an updated Champlain Parkway Natural
Resource Map, [w]etland H/I impacts detail figure, wetland data
sheets and functional assessment, and wetland H/I photographs?
(5) Whether the project or project impacts on [w]etland H/I have
changed or increased, thereby requiring a new individual wetland
permit or major permit amendment, and review under the individual
permit standards, Section 9.5 of the Vermont Wetland rules?
(6) Whether the project and permit extension request fail[] to
qualify as a minor permit amendment?
(7) Whether a CUD extension request should have been granted?
(8) Whether the wrong version of the Vermont Wetland Rules was
applied to the original application, and whether and how that error
impacts the extension request?
(9) Whether the project complies with mitigation sequencing
under [§] 9.5(b) of the Vermont Wetland Rules?
(10) Whether reliance on anticipated stormwater improvements or
benefits arising from the project to the watershed generally can
render the adverse impacts to the water storage and stormwater
function of wetland H/I not undue?
(11) Whether the functions and values of wetlands J, K, and N, are
significant and require a wetland permit prior to impacts to those
wetlands?
(12) Whether the project will result in an undue adverse impact to
[w]etlands J, K, and N?
5
qualified wetland consultant” based on an updated assessment of wetland H/I prior to applying for
its CUD extension. Question 7 broadly asked, “[w]hether a CUD extension request should have
been granted.” Questions 11 and 12 requested that the City assess the project’s impacts on
additional wetlands J, K, and N prior to seeking an extension. Fortieth later sought to amend
Questions 11 and 12 to assess whether the project would have negative impacts on newly
discovered wetland P.
¶ 8. After Fortieth filed its Statement of Questions, the parties filed multiple motions,
which the court addressed in its April 14, 2017 decision. In that decision, the court dismissed
Questions 1-6 and 8-10, and it directed Fortieth to submit a clarified Question 7. The order also
granted Fortieth’s request to withdraw Questions 11 and 12 and denied Fortieth’s request to amend
those questions. Fortieth submitted a clarified Question 7 with six subparts, which largely
reiterated Fortieth’s original questions.4 After denying several motions to reconsider and
4
Fortieth’s clarified Question 7 contained subparts (a)-(f):
(a) Whether the extension . . . will result in a violation of the
Vermont Water Quality Standards . . . ?
(b) Whether the extension . . . complies with the Vermont Wetland
Rules?
(c) Whether the extension . . . complies with the Vermont Wetland
Statute, 10 V.S.A. § 913?
(d) Whether the extension . . . will have an undue adverse impact
on the protected functions and values of significant wetlands?
(e) Whether the extension . . . meets the requirements for granting
an extension under the Vermont Wetland Rules[] and the 2011 CUD
permit?
(f) Whether the extension . . . was insufficient and incomplete and
should have been denied because it did not evaluate impacts to
additional significant wetlands, including [w]etlands G and Y, not
identified as being impacted in the 2011 CUD, and where such
impacts have not been evaluated and there has been no
demonstration that these wetland impacts will not result in an undue
6
conducting an evidentiary hearing in September 2017, the Environmental Division dismissed the
rest of the questions and issued a judgment order.
¶ 9. In its decision, the Environmental Division explained that the CUD is “functionally
akin” to a final permit decision, which generally may not be challenged in a subsequent
proceeding. The court ultimately dismissed Questions 1, 2, 6, 8, 9, 10, and clarified Question 7
and its subparts (a)-(e) because, in its view, these questions sought to collaterally attack the 2011
CUD by attempting to tie issues related to the underlying permit to the extension request.
¶ 10. In addressing Questions 3, 4, 5, and 7(f),5 the Environmental Division construed
the 2011 CUD permit Conditions A, D, and E as separate provisions. Regarding Questions 3, 4,
and 7(f), the court concluded that, while the City was required to comply with both Condition D
(extension request) and Condition E (redelineating project impacts), the time frames for complying
with Condition D and Condition E were different. Based on the plain language of the Conditions,
the court concluded that the City was required to seek a permit extension under Condition D before
the 2011 CUD’s five-year expiration date and was required to redelineate the wetland boundary
under Condition E after the five-year expiration date. Regarding Question 5, the court explained
that, based on the plain language of the CUD, the City’s extension request was a “minor
modification” rather than a “material or substantial change,” and therefore it did not trigger review
of the project by the Vermont wetlands office under Condition A. Based on these conclusions, the
Environmental Division approved ANR’s grant of an extension for the project. Fortieth now
appeals the Environmental Division’s decision to this Court.
adverse impact to the functions and values of these significant
wetlands or a violation of the Water Quality Standards?
5
Question 7(f) asked whether the time extension request was insufficient and incomplete
as it did not evaluate impacts to additional wetlands not identified as impacted in the 2011 CUD.
To the extent this subpart asked for the court to require a reassessment of potential new wetlands,
this is similar to Questions 3 and 4, which sought to require redefinition of the wetland boundaries
prior to seeking an extension request.
7
¶ 11. Fortieth lists a number of arguments on appeal. Most notably, Fortieth contends
that the Environmental Division erred when it: (1) incorrectly applied the motion-for-summary-
judgment standard rather than the motion-to-dismiss standard in dismissing Fortieth’s appeal; (2)
failed to apply the rules of statutory and permit construction correctly when interpreting the City’s
2011 CUD conditions and dismissing Questions 3, 4, 5, and 7(f); (3) dismissed Fortieth’s
remaining Questions 1-10 and amended Question 7; and (4) denied Fortieth’s motion to alter
Questions 11 and 12 to add inquires related to project impacts on wetland P. We affirm the
Environmental Division’s decisions on all counts.
II. Standard of Review
¶ 12. We review the court’s factual findings for clear error and its findings of law de
novo. In re Vill. Assocs. Act 250 Land Use Permit, 2010 VT 42A, ¶ 7, 188 Vt. 113, 998 A.2d
712. Thus, we review the Environmental Division’s grant of the City’s motion to dismiss and its
interpretation of the 2011 CUD permit conditions without deference. In re Confluence Behavioral
Health, LLC, 2017 VT 112, ¶ 12, __ Vt. __, 180 A.3d 867 (reviewing Environmental Division’s
interpretation of permit conditions de novo); Skaskiw v. Vt. Agency of Agric., 2014 VT 133, ¶ 6,
198 Vt. 187, 112 A.3d 1277 (“We review decisions on a motion to dismiss de novo under the same
standard as the trial court and will uphold a motion to dismiss for failure to state a claim if it is
beyond doubt that there exist no facts or circumstances that would entitle the plaintiff to relief.”
(quotation omitted)).
III. Motion-to-Dismiss Standard
¶ 13. First, Fortieth alleges that the court erred in granting the City’s motion to dismiss
because it failed to apply the appropriate standard. Fortieth contends that the court incorrectly
held Fortieth to the standard for opposing summary judgment motions and relieved the City of the
8
greater burden under the motion-to-dismiss standard. As a result, Fortieth claims that it was
prevented from introducing facts or discovering evidence that might support its appeal.
¶ 14. As explained above, this Court reviews a motion to dismiss de novo under the same
standard as the trial court. Skaskiw, 2014 VT 133, ¶ 6. We will uphold a dismissal “for failure to
state a claim if it is beyond doubt that there exist no facts or circumstances that would entitle the
plaintiff to relief.” Id. (quotation omitted). “We assume as true all facts as pleaded” by the
nonmoving party, and “accept as true all reasonable inferences derived therefrom, and assume as
false all contravening assertions in the [moving party’s] pleadings.” Birchwood Land Co. v.
Krizan, 2015 VT 37, ¶ 6, 198 Vt. 420, 115 A.3d 1009. Because we review the Environmental
Division’s decision granting the City’s motion to dismiss de novo, whether the Environmental
Division applied the correct legal standard is not relevant to this appeal.
IV. Interpretation of 2011 CUD Conditions
¶ 15. Next, we consider whether the Environmental Division erred in construing the 2011
CUD conditions and dismissing Fortieth’s Questions 3, 4, 5, and 7(f). As explained above, we
review the Environmental Division’s interpretation of the CUD conditions de novo. Confluence
Behavioral Health, LLC, 2017 VT 112, ¶ 12. We construe permit conditions according to the
established rules governing statutory construction. Agency of Nat. Res. v. Weston, 2003 VT 58,
¶ 16, 175 Vt. 573, 830 A.2d 92 (mem.). In doing so, we first look to the plain meaning of the
words used by the drafters to determine their original intent. Id. If the plain meaning of the
language is clear, we “accept[] the plain meaning of the words because we presume that they
express the underlying intent.”6 Id.
¶ 16. On appeal, Fortieth asserts two theories to support its contention that the City
violated the 2011 CUD permit conditions. First, Fortieth contends that Conditions D and E must
6
Generally, we give some level of deference to ANR interpretations of rules promulgated
by the agency and/or terms that are within the agency’s area of expertise. In re Korrow Real Estate
9
be read together, such that the City was required to redelineate the wetland boundaries implicated
by the project prior to applying for a permit extension. Second, Fortieth asserts that the City’s
request for an extension constitutes a “material or substantial change” under Condition A and
therefore the City required the “written approval of the Vermont Wetlands Office” prior to
obtaining an extension. As we explain below, under the language of this permit, the only relevant
consideration regarding a request for an extension under Condition D is the timeliness of the
request. The request for a permit extension was made more than thirty days before the expiration
of the five-year CUD period, and thus was timely under the 2011 CUD permit. Accordingly, there
exists no set of facts upon which Fortieth could prevail on this issue, and we affirm the court’s
dismissal of Questions 3, 4, 5, and 7(f).
A. Conditions D and E
¶ 17. First, Fortieth argues that the City must redelineate and reevaluate the wetlands on
the project site pursuant to Condition E prior to seeking an extension of the 2011 CUD under
Condition D. We disagree; the plain language of the 2011 CUD requires the timely filing of an
extension application to be considered for a project extension, nothing more.
¶ 18. The permit language at issue provides the following. Condition D governs project-
extension requests. Condition D mandates that “[a]ll construction activities in the
wetland . . . shall be completed within five years” of the CUD. If the project requires an extension
beyond that five-year time period, Condition D simply provides that “[a]ny request for an
extension must be received by the Department at least 30 days prior to the end of the five-year
period in order to prevent the termination of [the 2011 CUD].” (Emphasis added.) If this
requirement is met, “[t]he Secretary may grant an extension to this five-year period.” Condition
LLC Act 250 Permit Amendment Application, 2018 VT 39, ¶¶ 21-22, __Vt. __, 187 A.3d 1125
(outlining when court owes deference to agency interpretations of policy or terms). Here, where
we are construing the permit conditions based on their plain language and ANR’s expertise is not
implicated, we owe no deference to the agency’s permit determination.
10
E is a separate provision that governs delineation of the project’s wetland boundaries. Condition
E explains that the project’s “wetland boundary determination is valid for five years from the date
of [the 2011 CUD].” However, “[t]he delineation will need to be re-evaluated by a qualified
wetland consultant if the project is not constructed, or additional impacts are proposed, after the
five-year time period expires.” (Emphasis added.)
¶ 19. Upon reviewing the conditions outlined above, the Environmental Division
concluded that the CUD conditions were “clear on their face”: the City was not required to conduct
a new wetland delineation prior to applying for an extension of the City’s five-year term because
the procedures for receiving a time extension under Condition D were separate from Condition E’s
requirement that the City redelineate the wetland boundary. We agree.
¶ 20. Based on the plain language of Conditions D and E, we conclude that the City was
not required to redelineate the wetland boundaries prior to seeking a permit extension for the
project. First, the language of these conditions indicates that they were intended to be read
separately. The language of Condition D is simple: the only condition to seeking an extension is
timeliness. If the application for an extension is timely submitted within thirty days of the CUD’s
expiration date, then “[t]he Secretary may grant an extension to this five-year period.” While the
2011 CUD requires the City to comply with all conditions, nowhere does the 2011 CUD specify
compliance with Condition E as a prerequisite to seeking a time extension under Condition D.
Such a reading would be contrary to the plain language of the CUD. Had the extension provision
been meant to be intertwined with Condition E, as the dissent suggests, it would have been a simple
matter to include such language within Condition D. It is not for us to rewrite the CUD in a way
that might seem more advisable to some, but rather to construe it according to its plain language
when, as here, that language is clear.
¶ 21. Second, while the City is required to comply with both Conditions D and E, these
provisions have a timeline. Under Condition D, which expressly governs project extensions, the
11
City must apply for a project extension at least thirty days before the CUD’s five-year expiration
date to avoid termination. In contrast, Condition E, which requires re-assessment of the wetland
boundaries, only becomes applicable after the initial five-year permit has expired. Therefore,
under the 2011 CUD conditions, the City was required to comply with Condition D and seek an
extension before Condition E’s requirements were triggered. In theory, this would relieve projects
that were not approved for an extension, either due to untimely filings or due to the Secretary’s
denial of their application, from unnecessarily undergoing the redelineation process. Therefore,
under the 2011 CUD, applying for a permit extension was not conditioned upon re-assessing the
project’s wetland boundaries.
¶ 22. Applying these permit conditions to the case at hand, Condition D simply required
the City to seek a permit extension at least thirty days prior to the CUD’s termination date in
January 2016, which it did. As such, ANR was correct in granting the City’s permit-extension
request because the City was not required to comply with Condition E prior to filing for an
extension.7
¶ 23. Fortieth argues that comparing the 2010 Vermont Wetland Rules (VWR) to the
most recent version of the rules supports its position that the two provisions were intended to be
linked.8 However, the 2010 VWR were still in force when the 2011 CUD was issued and when
7
Although ANR initially seemed to agree with Fortieth’s construction of these provisions
in a “Response Summary” issued by the agency, ANR has since changed its position and stated
that the City was not required to conduct a redelineation of the wetland boundaries for the project
prior to obtaining the extension. Neither the fact that ANR originally indicated a redelineation
was necessary nor the fact that ANR has changed position on this issue is relevant to our review
of the CUD permit language.
8
The 2017 VWR cited by Fortieth has recently been superseded by a new set of VWR,
effective August 15, 2018. Those rules include similar provisions allowing the Secretary to issue
a CUD or order (§ 9); determine whether any wetland is a Class II or Class III wetland (§ 8); or
initiate a rulemaking process to classify a wetland as Class I or to lower the classification to a Class
I wetland (§§ 4.3, 7). Vermont Wetland Rules §§ 4.3, 7, 8, 9, Code of Vt. Rules 12 030 026 (2018)
[hereinafter 2018 VWR], https://dec.vermont.gov/sites/dec/files/documents/wsmd_
VermontWetlandRules_2018.pdf [https://perma.cc/G494-DC44]. As such, the language at issue
12
the City sought a permit extension. As such, the language of the 2018 VWR does not control our
interpretation of the 2011 CUD conditions. To the extent that the 2018 VWR is instructive, these
changes lend further support to our interpretation that Conditions D and E were not linked when
the 2011 CUD and this extension were granted.
¶ 24. The 2010 VWR, which was in effect at the time the 2011 CUD issued, simply
explains that:
[a]n individual wetland permit shall remain valid for one year from
the date of issuance unless the Secretary specifies a longer period
not to exceed five years. The Secretary may extend a permit for up
to a total of ten years beyond the date of issuance of the original
permit.
Vermont Wetland Rules § 9.1 (2010) [hereinafter 2010 VWR]
https://dec.vermont.gov/sites/dec/files/documents/WSMD_VermontWetlandRules_2010_7_16.p
df [https://perma.cc/YRJ2-ZTXK]. Under this version of the VWR, there are no qualifications
limiting the Secretary’s ability to extend the original permit for up to ten years beyond the original
issuing date. In contrast, the more recent 2018 VWR provides an expanded version of this
language:
The Secretary may extend a permit for up to a total of ten years
beyond the date of issuance of the original permit if the permittee
re-evaluates and re-delineates the wetland resources impacted by the
authorized activity and the Secretary determines there will be no
impact to Class I or Class II wetland or buffer beyond those impacts
permitted under the original permit. If any additional wetland or
buffer will be impacted, an amendment must be applied for,
concurrent with a permit extension.
2018 VWR § 9.1 (emphasis added). The language in the 2018 VWR specifies that redelineating
project boundaries and determining whether additional impacts will occur is a prerequisite to
requesting and obtaining a permit extension. If there are changes to the project or its impacts, the
here remains consistent between the 2017 and 2018 versions of the VWR, and we refer to the more
recent 2018 VWR throughout.
13
2018 VWR requires the developer to apply for a project amendment concurrent with the extension
application. This clause reiterates that the developer must know about any changes in the project
and plan accordingly prior to applying for an extension. However, none of these specifications
were included in the 2010 VWR.
¶ 25. At the time that the 2011 CUD permit issued and the City applied for an extension
in 2015, there were no rules providing an expanded definition regarding the interplay between
Conditions D and E. The plain language of Conditions D and E in the 2011 CUD provided a clear
timeline for the extension application and redelineation process. The fact that the VWR was later
revised to clarify these rules merely demonstrates that the language at issue was insufficient to
communicate this practice at the time that the 2010 VWR was in place. It would be unfair to
impose the enhanced standard crafted for the 2018 VWR retrospectively to the 2011 CUD, and we
decline to do so here.
¶ 26. Fortieth further argues that the extension cannot be granted without a redelineation
of the project’s wetland boundaries because the project will enter its five-year extension period
without valid boundaries. Fortieth is concerned that unknown project impacts may harm various
wetlands on and around the project site. This argument is without merit because the City is not
excused from compliance with Condition E, or any other permit condition, simply because it
receives a permit extension—the City is still required to redelineate the wetland boundaries after
the initial five-year permit lapses. Changes in the wetland boundaries or harmful impacts from the
project, such as those alleged by Fortieth, would be discovered through this process and
appropriate steps could be taken if additional impacts arise. For example, if the result of Condition
E’s “checkup” on the project’s wetland boundaries indicated that the boundaries had changed
significantly, then ANR could initiate new delineation proceedings under Section 8 of the VWR,
which allows “a person” to petition the Secretary to evaluate and classify a wetland as a Class II
14
or Class III wetland. 2018 VWR § 8.1. If a new wetland was identified in these proceedings, then
ANR could address any project impacts to that new wetland through a new permitting proceeding.9
B. Conditions A and D
¶ 27. We also agree with the Environmental Division that the City’s request for an
extension was not a “substantial or material change” under Condition A of the CUD. Condition
A provides that “[n]o material or substantial changes shall be made in the project without the
written approval of the Vermont Wetlands Office.” (Emphasis added.) However, Condition D
specifies that “[a] request for extension will be considered a minor modification.” (Emphasis
added.) The CUD does not further define “minor modification,” and neither the wetland statutes
nor the VWR define the term. As such, the plain language of the CUD conditions governs our
inquiry. The plain language of the two provisions clearly indicates that a request for an
extension—a “minor modification”—under Condition D does not rise to the level of a “material
or substantial change” contemplated under Condition A. Therefore, we conclude that merely
requesting a time extension under Condition D does not require written approval from the Vermont
wetlands office.
¶ 28. In sum, we conclude that: (1) seeking an extension under Condition D of the 2011
CUD was not preconditioned on reevaluating the wetland boundaries under Condition E; and (2)
seeking a permit extension under Condition D is a “minor modification” rather than a “material or
substantial change” under Condition A and therefore does not require additional review by the
Vermont wetlands office. Accordingly, the Environmental Division was correct to dismiss
Questions 3, 4, 5, and 7(f).
9
Here, the project did undergo redelineation and reevaluation of the wetlands, and ANR
deemed that no changes would preclude the project from moving forward.
15
V. Collateral Attacks on 2011 CUD
¶ 29. Because we conclude that seeking a permit extension under Condition D does not
implicate permit Conditions A or E, Fortieth may not appeal ANR’s grant of an extension as an
avenue to collaterally challenge the City’s compliance with these peripheral conditions or to
challenge the underlying 2011 CUD.
¶ 30. Where a land permit decision has become final, a party cannot later collaterally
attack that final decision through a separate proceeding. Levy v. Town of St. Albans Zoning Bd.
of Adjustment, 152 Vt. 139, 141, 564 A.2d 1361, 1363 (1989). This rule applies to municipal
zoning permits through 24 V.S.A. § 4472(d), which specifically bars collateral attacks to final
permit decisions. In re Lathrop Ltd. P’ship, 2015 VT 49, ¶¶ 54-55, 199 Vt. 19, 121 A.3d 630. The
bar against collateral attacks also applies to Act 250 permits, In re Taft Corners Assocs., Inc., 160
Vt. 583, 593, 632 A.2d 649, 654 (1993), and has been applied to ANR permit decisions, In re
Unified Buddhist Church, Inc., 2006 VT 50, ¶ 13, 180 Vt. 515, 904 A.2d 1139 (mem.).
¶ 31. Here, we are presented with an appeal from an ANR decision granting a time
extension to an existing wetland CUD issued by ANR. The 2011 CUD was an act or decision
made by ANR pursuant to Chapter 37 of Title 10, which could have been appealed within thirty
days pursuant to Chapter 220 of Title 10. When no appeal was made, the 2011 CUD became final.
Merely requesting an extension for the 2011 CUD does not alter the 2011 CUD other than to
extend the CUD dates. Here, Fortieth’s challenges to the project’s compliance with Conditions A
and E reach beyond the extension determination, asserting that the project’s impacts have
substantially changed and that new wetland boundaries will be affected by the project.10 Because
10
Although it is not relevant to our analysis of the City’s permit extension request, we
note Fortieth has other avenues to raise these challenges. First, the City is still required to comply
with Condition E, which functions as a mandatory “checkup” to see whether the boundaries have
changed if the project is not started within five years of the original permit issuance. If the
information provided as part of the “checkup” suggests the wetland boundaries have changed
significantly, then ANR could initiate new delineation proceedings under Section 8 of the current
16
these allegations are not relevant to the limited scope of the extension request determination, these
challenges are collateral to the matter at hand and we do not consider them.
¶ 32. Similarly, we conclude that the Environmental Division properly dismissed the
remainder of the questions raised by Fortieth (Questions 1, 2, 6, 8, 9, 10, and clarified Question
7(a)-(e)) because they are issues that were finally decided in the original 2011 CUD and cannot be
collaterally attacked on appeal.11 See Lathrop Ltd. P’ship, 2015 VT 49, ¶¶ 54-55; Unified
Buddhist Church, Inc., 2006 VT 50, ¶ 13; Taft Corners Assocs., 160 Vt. at 593, 642 A.2d at 654;
Levy, 152 Vt. at 142, 564 A.2d at 1363. Having failed to participate in those proceedings or appeal
the 2011 CUD, Fortieth cannot raise those issues on appeal here, when the Court is simply
addressing the City’s compliance with Condition D’s extension procedures. To the extent Fortieth
alleges those questions relate to the extension at issue, they are duplicative of Questions 3, 4, 5,
and clarified Question 7(f), which we address above, and should be dismissed for the same
reasons.12
VWR and could address any project impacts to that new wetland through a new permitting
proceeding. Additionally, both the wetlands statute and VWR allow interested parties to petition
ANR for classification proceedings. See 10 V.S.A. § 914(a); 2018 VWR §§ 8.1-8.5. Decisions
of ANR in such proceedings are appealable to the Environmental Division and the Court. 10
V.S.A. §§ 8504-8505; 2018 VWR § 8.4. Additionally, the City is not excused from compliance
with Condition A. If the Agency determines that the City needs a wetland permit for the alleged
changes asserted by Fortieth, then the City will be required to apply for one before constructing
the project. The Agency may initiate an investigation or enforcement proceeding and, assuming
Fortieth can demonstrate standing, Fortieth may have the opportunity to ask to participate in those
proceedings. 10 V.S.A. § 8020. The viability of these options and Fortieth’s likelihood of success
in pursuing these alternate avenues is beyond the scope of this opinion; we note them merely to
demonstrate that there are other ways to monitor the project’s impacts on local wetlands.
11
Questions 1, 2, 9, and 10 attempt to challenge the project’s compliance with the Vermont
Wetland Rules and statutes; Question 6 challenges whether the 2011 CUD was allowed to define
a project extension request as a “minor modification”; and Question 8 challenges whether the
correct version of the Vermont Wetland Rules was applied when the 2011 CUD was originally
created. Clarified Question 7 subparts (a) through (e) merely reiterate these challenges.
12
Fortieth argues that the Environmental Division erroneously relied on “suggested facts”
in ANR’s memoranda about “separate proceeding[s] for re-evaluating wetland boundaries.”
Fortieth contends that: (1) “there is no separate process” for reevaluating the wetland boundaries,
17
VI. Motion to Amend Related to Wetland P
¶ 33. Finally, we conclude that the Environmental Division correctly denied Fortieth’s
motion to amend the Statement of Questions to raise issues related to wetland P because those
issues are not relevant to the time-extension request. Fortieth contends that wetland P is located
close to, and is hydrologically connected to, wetland H/I. Because of the asserted connection
between wetland P and wetland H/I, Fortieth argues that the discovery of wetland P requires a
more comprehensive review of the wetland impacts of the project prior to an extension request
being granted. However, as explained above, the 2011 CUD does not require redelineation or
reevaluation of the wetland prior to granting an extension request. The project may receive an
extension request under Condition D without these additional measures. A reevaluation of the
wetland delineation is required under Condition E after the original five-year permit has lapsed.
The potential impacts to wetland P should not be considered in a request that solely asks for a time
extension of the 2011 CUD, but may be germane concerning other permit conditions. Therefore,
the court was correct in dismissing Fortieth’s request to amend is Statement of Questions to add
questions related to wetland P.
and (2) the availability of alternative mechanisms for challenging the 2011 CUD does not excuse
the City from complying with the CUD conditions here. However, this argument is without merit
because the availability of alternative proceedings are not relevant to determining whether the City
complied with the limited requirements for a permit extension under Condition D. We provide
examples of these alternate mechanisms to explain how Fortieth would appropriately challenge
these apparent areas of concern. See supra, ¶ 31 n.10.
Similarly, Fortieth’s argument that the court erred in “ruling the operational [stormwater]
permit can substitute for a wetland permit or authorization from the Vermont Wetlands Program”
is beyond the scope of our analysis of the City’s permit extension request. Regulatory processes
for reviewing substantial or material changes to the project are not relevant to our analysis of the
project’s compliance with Condition D, and we decline to consider them. Accordingly, appellees’
joint motion asking this Court to take judicial notice of documents related to ANR’s stormwater
program and Fortieth’s stormwater permit is denied as moot.
18
VII. Conclusion
¶ 34. In sum, we conclude the following. First, Questions 3, 4, 5, and 7(f) were properly
dismissed because, based on the plain language of the 2011 CUD Conditions, (1) the City may
seek a permit extension under Condition D without redelineating and reevaluating the project’s
wetland boundaries under Condition E, and (2) the City’s request for a project extension under
Condition D is a “minor modification” rather than a “material or substantial change” and thus does
not require review by the Vermont wetlands office under Condition A. Second, to the extent that
these Questions collaterally attack the permit’s validity for reasons other than its compliance with
Condition D, such attacks are impermissible. The remainder of Fortieth’s Questions (1, 2, 6, 7(a)-
(e), 8, 9, and 10) constituted impermissible collateral attacks on the underlying 2011 CUD permit
and as such were properly dismissed. Finally, the City appropriately denied Fortieth’s request to
amend its Question 11 and 12 to add questions related to wetland P because such issues were
beyond the scope of proceedings related to a permit extension under Condition D.
Affirmed.
FOR THE COURT:
Associate Justice
¶ 35. ROBINSON, J., dissenting in part. The 2010 Conditional Use Determination
issued to the City of Burlington by the Water Quality Division of the Department of Environmental
Conservation, Agency of Natural Resources, contains the following conditions:
D. All construction activities in the wetland and adjacent 50-foot
buffer zone shall be performed in compliance with Condition A and
shall be completed within five years of the date of this Conditional
Use Determination or this Conditional Use Determination will
terminate. The Secretary may grant an extension to this five-year
period. Any request for an extension must be received by the
Department at least 30 days prior to the end of the five-year period
in order to prevent the termination of this Conditional Use
19
Determination. A request for extension will be considered a minor
modification.
E. The wetland boundary determination is valid for five years
from the date of this determination. The delineation will need to be
re-evaluated by a qualified wetland consultant if the project is not
constructed, or additional impacts are proposed, after the five-year
time period expires.
¶ 36. The majority’s suggestion that these two provisions are unrelated and operate
independently, even if a permit extension would extend the CUD more than five years beyond the
original boundary delineation, would lead to nonsensical consequences. A contrary construction—
one that would require a reevaluation of the wetland before the extension can be granted beyond
the five-year period during which the boundary determination is valid—is more consistent with
the language and structure of the permit and better promotes the purposes of the wetland-protection
laws.13 The parties’ own conduct throughout the permit extension process and prior to the appeal
to the Environmental Division, as well as ANR’s subsequent amendment of its rules, reinforce that
approval of the City’s extension request is contingent on completion of a reevaluation of the
wetland by a qualified wetland consultant. Accordingly, I respectfully dissent from that portion
of the majority’s decision relating to its conclusion that these two provisions operate independently
and holding that the City may secure an extension without reevaluating the wetland boundaries.14
I. The Majority’s Construction of the Statute Is Untenable
¶ 37. We should not construe a permit condition in a way that renders the permit
nonsensical. See Agency of Nat. Res. v. Handy Family Enters., 163 Vt. 476, 482, 660 A.2d 309,
13
My argument is limited to cases like this in which the proposed permit extension would
extend the permit beyond the period when the boundary delineation underlying that permit was
valid—in this case, five years. Nothing about my argument suggests that a permit extension within
the period in which the boundary delineation remains valid requires a reevaluation of the wetland
boundary.
14
In particular, I would reverse the Environmental Division’s judgment as to Questions 3,
4, 5, 11, and 12. I join the majority’s affirmance with respect to Questions 1, 2, 6, 7, 8, 9 and 10
for the reasons stated by the majority.
20
312 (1995) (“We see no reason to depart from normal statutory construction techniques in
interpreting permit conditions.”); Dep’t of Taxes v. Montani, 2018 VT 21, ¶ 24, __ Vt. __, 184
A.3d 723 (explaining that courts should avoid constructions that “produce absurd or illogical
consequences”). A construction of the 2010 CUD that treats Condition E as irrelevant to an
extension request pursuant to Condition D would do just that. Because (1) pursuant to Condition
E and the Vermont Wetland Rules (VWR), the wetland boundary determination is invalid after
five years, and (2) the boundaries of the wetland are integral to the permit, a CUD extended
pursuant to Condition D without redelineated boundaries would no longer apply to a validly
delineated area and thus would be meaningless. I expand on each of these points below.
¶ 38. First, by its plain terms, Condition E provides that the wetland boundary
determination upon which the 2010 CUD was predicated “is valid for five years from the date of
this determination.” There is nothing unclear about this provision. After five years, the subject
wetland, assuming it still exists, no longer has valid or established boundaries.
¶ 39. This requirement is consistent with the VWR in effect at the time. Those rules
require that “[t]he presence of a wetland and the boundary between a wetland and upland shall be
delineated by the methodology set forth in the Federal Manual for Identifying and Delineating
Jurisdictional Wetlands, as amended, and supplemental guidance documents issued by the U.S.
Army Corps of Engineers.” Vermont Wetland Rules § 3.2(a), Code of Vt. Rules 12 030 026 (2010)
[hereinafter 2010 VWR], https://dec.vermont.gov/sites/dec/files/documents/WSMD_Vermont
WetlandRules_2010_7_16.pdf [https://perma.cc/YRJ2-ZTXK]. The Army Corps of Engineers
has issued guidance indicating that jurisdictional determinations, including wetlands delineations,
are valid for five years “unless new information warrants revision of the determination before”
that time. U.S. Army Corps of Eng’rs, No. 05-02, Regulatory Guidance Letter on Expiration of
Geographic Jurisdictional Determinations of Waters of the United States ¶ 3(a) (June 14, 2005),
21
https://usace.contentdm.oclc.org/utils/getfile/collection/p16021coll9/id/1246 [https://perma.cc/W
3CK-RQQD]].
¶ 40. The five-year limitation on the validity of wetland delineations makes sense;
wetlands are dynamic in their scope and character. As the Army Corps of Engineers explained in
its Regulatory Guidance Letter, “[s]ince wetlands and other waters of the United States are affected
over time by both natural and [human-caused] activities, local changes in jurisdictional boundaries
can be expected to occur. As such, jurisdictional determinations cannot remain valid for an
indefinite period of time.” Id. ¶ 2(a). In fact, the Army Corps of Engineers guidance acknowledges
that in some cases rapidly changing environmental conditions may merit reverification sooner than
five years after the original delineation. Id. ¶ 3(a). Given that the delineation of a Class I or Class
II wetland drives the findings underlying a wetland CUD and determines the scope and
requirements of the CUD itself, it makes sense that the permit limits the validity of the wetland
delineation in this case to five years.
¶ 41. Second, the delineation of the wetland that is the subject of the CUD is integral to
both the findings underlying the permit and the terms of the permit. This is apparent from the
2010 CUD itself.
¶ 42. The Secretary’s findings of fact for the 2010 CUD relate to a specifically delineated
area of wetland: a thirteen-acre wetland complex in a ravine along Englesby Brook. The findings
describe the character of the subject wetland, the flora found there, the protected functions of the
wetland, and the functions that are not present or are present at such a minimal level as not to be
protected functions. They consider the impact of the project on the described wetland and its
protected functions. The findings reflect the Secretary’s conclusions that the project will not lead
to any undue adverse impacts and that the project “cannot practicably be located outside the
wetland and buffer zone or on another site owned, controlled or available to satisfy the basic
project purpose.” They further state, “if the project is constructed according to the specifications
22
of the application and accompanying site plans, and the conditions of this Conditional Use
Determination, the resulting wetland and buffer zone alteration is not expected to result in any
violations of the Vermont Water Quality Standards.” These findings are specific to a wetland with
validly established boundaries. The Secretary’s assessment of the impact of the project as
proposed on the wetland’s protected functions, and the determination that the proposed use cannot
practicably be located outside the wetland and buffer zone, require consideration of the location
and impacts of the project relative to the location, characteristics, and boundaries of that specific
wetland.
¶ 43. Likewise, the terms of the permit itself depend on established wetland boundaries
for their effect. The permit only purports to allow impacts within the wetland and buffer zone. It
requires all construction activities “in the wetland and adjacent 50-foot buffer zone” to be
performed in compliance with the City’s proposals and submissions.
¶ 44. So if Condition D and Condition E are unrelated and operate independently such
that the grant of a permit extension more than five years from the operative wetland delineation is
not conditioned on a redelineation, then the Secretary could simply issue an order extending the
expiration date of an existing CUD, even though that permit was based upon boundaries that were,
as a matter of law pursuant to the terms of the CUD itself, no longer valid.15
¶ 45. At the time of the Secretary’s extension of the permit, the wetland, assuming it
continued to exist, would lack any valid boundaries—making any purported findings about the
impacts of the project within the wetland or its buffer nonsensical. Where does the wetland end?
15
I note that’s not what happened here. In this case, the City did secure a reevaluation of
the wetland boundaries, the extended permit included revised findings to reflect that fact, and the
extended permit established that the wetland boundaries would be valid for five more years. Only
when the permit was on appeal to the Environmental Division did the Secretary assert that the
reevaluation of the wetland boundaries was not actually a requirement for the permit extension in
the first place.
23
Where does the buffer lie? How can we know what a project’s impacts on the wetland actually
are when we don’t fully know where the wetland is?
¶ 46. Moreover, the scope of such a permit would be impossible to assess: the CUD
would authorize specified development within a purportedly specified wetland, and would
condition the CUD on compliance with certain requirements within the wetland and buffer, but
the exact location of the wetland and buffer would be unknown. How would the City, the
Secretary, or anyone else know if the City violated the permit by conducting impermissible
activities within the wetland or buffer when the boundaries of the wetland and buffer are
undetermined? It makes no sense.
II. A Construction Harmonizing Conditions D and E Better Aligns with the Language and
Structure of the Permit
¶ 47. In construing the permit, the majority fails to grapple with the clear and unequivocal
language of Condition E, providing that the boundary determination that defines the subject
wetland and is the foundation for the CUD is no longer valid after five years. See State v. Tierney,
138 Vt. 163, 165, 412 A.2d 298, 299 (1980) (“In construing a statute, this Court considers it as a
whole, and, if possible, gives effect to every word, clause and sentence.”). In contrast, a
construction of the CUD pursuant to which the City must conduct a reevaluation before the
Secretary can grant the extension is consistent with all of the language in the CUD. Contrary to
the majority’s suggestion, ante, ¶ 21, the fact that Condition D sets a deadline for an application
for an extension does not mean that the Secretary’s exercise of discretion in granting a requested
extension is limitless, or that the pending invalidity of the wetland boundary determination is
irrelevant.
¶ 48. The majority focuses on the fact that the request for extension must be filed at least
thirty days prior to the permit expiration, reads the permit to contemplate a reevaluation of the
boundary after the five-year time period marking the validity of the delineation expires, and
24
concludes that therefore these two conditions apply during distinct time periods. Ante, ¶ 21. But
there are two different five-year limitations in play here: the expiration of the CUD if the project
is not completed within five years and the five-year limitation on the validity of the wetland
boundary determination. Had the initial permit period been only three years, then no delineation
would be required for an extension of the permit for another two years. More important, Condition
D requires that an extension request be filed at least thirty days before expiration of the permit “in
order to prevent the termination of this Conditional Use Determination.” This language makes it
clear that the City’s timely filing of the request is necessary and sufficient to forestall the CUD’s
expiration, and that the Secretary is not required to actually issue a ruling extending the CUD
before its initial expiration date in order to prevent the permit’s termination. But the permit
contains no language requiring a ruling on the extension request in any particular time frame.
¶ 49. Given these considerations, the most sensible way to understand the interaction
between Conditions D and E is that the CUD requires the permittee to file an extension request at
least thirty days prior to the expiration of the CUD in order to, in effect, toll the expiration of the
permit, but requires reevaluation of the wetland boundaries before the Secretary may approve the
extension if doing so extends the CUD beyond the five-year validity of the boundary
determination.16 This construction harmonizes and gives effect to all of the terms of the permit.
¶ 50. The majority’s construction of the CUD also fails to consider the CUD as a whole.
On the majority’s view, the permit provides no guidance as to how the Secretary is to exercise the
discretion afforded under Condition D, and affords no avenue for reviewing the reevaluation
required by Condition E in the context of this permit proceeding.
16
Given this analysis, I reject Fortieth’s argument that the City’s failure to secure a
completed reevaluation of the wetland boundaries and buffer before the City requested an
extension of the CUD is fatal to the City’s request. By filing a timely request for extension, the
City effectively ensured that the existing CUD would not terminate pending further proceedings;
but the Secretary could not approve the extension without the required reevaluation of the wetland
boundaries.
25
¶ 51. Condition D does not require the Secretary to approve a timely filed request for
extension; instead, the Secretary’s authority to grant an extension is discretionary under the terms
of the CUD. Condition D does not expressly identify the factors that guide the Secretary’s exercise
of discretion. If the only relevant consideration were the timeliness of the request for an extension,
the permit would mandate an extension upon timely filing. It does not; it is discretionary.
Understood in light of Condition E and the purposes of the CUD in the first place, important
considerations include whether the existing delineation will become invalid before or during the
extended period of the permit, and whether the required reevaluation undermines the critical
findings that the project will have no undue adverse impact on the protected functions of the
wetland.
¶ 52. At the same time, understood as a free-floating requirement untethered to a permit
extension, Condition E appears to create an important but unreviewable requirement. If the
reevaluation is not a condition precedent to approval of a CUD extension beyond the period in
which the boundary determination is valid, how is that reevaluation reviewable in the context of
the CUD proceeding? The majority suggests that because the requirements of Condition E apply
in any event, a permittee will be required to undertake a reevaluation. If the reevaluation discloses
changes in the wetland boundaries or new harmful impacts from the projects, the Secretary could
initiate a new delineation proceeding pursuant to Section 8 of the Vermont Wetland Rules.
Vermont Wetland Rules § 8, Code of Vt. Rules 12 030 026 (2018) [hereinafter 2018 VWR],
https://dec.vermont.gov/sites/dec/files/documents/wsmd_VermontWetlandRules_2018.pdf [https
://perma.cc/G494-DC44].17 If the new delineation identified a new wetland, the majority asserts,
the Secretary could then address any project impacts to that new wetland through a new permitting
proceeding.
17
As noted in the majority, ante, ¶ 23 n.8, a new set of VWR took effect on August 15,
2018.
26
¶ 53. This answer to the question of how the redelineation pursuant to Condition E may
be reviewed is flawed on multiple levels. First, it’s not at all clear procedurally how the Secretary
could initiate a new permitting proceeding regarding this project at some unspecified date in the
future, especially if the project is partially or even completely constructed. Second, the majority
describes a path for dealing with entirely new wetlands (initiate a new permitting proceeding) that
would not make sense in the context of changes to the contours of wetlands that have already been
identified and made the subject of permitting proceedings. And finally, initiation of the review
process described by the majority falls entirely to the Secretary. 2018 VWR § 8.1. The review
process posited by the majority would not only be clunky and circuitous; it would leave established
parties to this permitting proceeding without a mechanism to challenge the conclusions of the
reevaluation in the context of this permit.
¶ 54. Understanding the permit conditions as requiring a reevaluation of the wetland
boundaries if an extension will extend the CUD beyond the period of time when the existing
boundary delineation is valid avoids these pitfalls. It provides considerations to guide the
Secretary’s discretionary decision whether to extend the CUD pursuant to Condition D, and
recognizes a framework for enforcing, reviewing, and making relevant the reevaluation required
pursuant to Condition E in the context of this permitting proceeding.
¶ 55. Finally, a CUD extension that simply adopted the terms of the underlying permit
but inserted a new effective date could completely write the reevaluation requirement of Condition
E out of the permit; if the delineation is only valid for five years from the date of the permit, then
substituting a new permit date by way of extension would effectively discharge the reevaluation
requirement.
III. The Underlying Statute and Regulations Reinforce This Construction
¶ 56. Requiring a reevaluation before extending the permit beyond the period during
which the prior boundary delineation is valid also best promotes the purposes of the wetland-
27
protection laws. The VWR make the policy underlying the statute and associated rules clear,
expressly stating that “[i]t is the policy of the State of Vermont to identify and protect significant
wetlands and the values and functions which they serve in such a manner that the goal of no net
loss of such wetlands and their functions is achieved.” 2010 VWR § 1.1.18 In pursuit of this
policy, the wetlands protection statute expressly prohibits activities in a significant wetland or
buffer zone of a significant wetland “except in compliance with a permit, conditional use
determination, or order issued by the Secretary.” 10 V.S.A. § 913(a). It defines “[s]ignificant
wetland” to include any Class I or Class II wetland, id. § 902(11), and “[b]uffer zone” as “an area
contiguous to a significant wetland that protects the wetland’s functions and values,” id. § 902(9).
The statute establishes a buffer zone for Class I wetlands that “extend[s] at least 100 feet from the
border of the wetland, unless the Department determines otherwise,” and for Class II wetlands that
“extend[s] at least 50 feet from the border of the wetland unless the Secretary determines
otherwise.” Id. § 902(9). The VWR, past and present, reinforce the statutory requirements. See
2010 VWR § 9.1 (prohibiting activity in a Class I or Class II wetland or associated buffer zone
“unless it is an allowed use or authorized by a permit, conditional use determination, or order
issued by the Secretary”).19
¶ 57. Given the dynamic nature of wetlands, see U.S. Army Corps of Eng’rs, Regulatory
Guidance Letter ¶¶ 2(a)-3(a), if the Secretary can extend a CUD for activity in a wetland when the
boundaries of the wetland are not validly established, there is a reasonable likelihood that activity
within significant wetlands or protected buffer zones that the VWR prohibits unless permitted will
18
Both superseding revisions to the VWR maintained this statement of purpose. See 2018
VWR § 1.1; Vermont Wetland Rules § 1.1, Code of Vt. Rules 12 030 026 (2017) [hereinafter 2017
VWR], https://dec.vermont.gov/sites/dec/files/documents/wsmd_Vermont_Wetland_Rules_2017
.pdf [https://perma.cc/H4SP-L857].
19
Both superseding revisions to the VWR reflect this statutory requirement. See 2018
VWR § 9.1; 2017 VWR § 9.1.
28
be allowed without any review of its impacts. Such a result would squarely undermine the purpose
and intent of the statutory and regulatory scheme.
IV. The History of This Proceeding and Subsequent Changes to the VWR Reinforce This
Understanding
¶ 58. The conduct of all parties to this proceeding prior to the Secretary’s change of
position before the Environmental Division reinforces that the construction adopted in this dissent
best captures the intent of the permit and the expectations of all parties involved based on the terms
of the permit and the statutory framework. Although my analysis does not rest in any part on the
2017 (and now the 2018) revisions to the VWR, the suggestion that the revision imposed more
onerous requirements, rather than providing greater clarity as to the existing scheme, is
inconsistent with the record.
¶ 59. The only representation the City’s agent included in requesting an extension of the
2010 CUD was that “[t]he proposed project’s wetland areas and impacts outlined in the original
permit authorization have not changed. The proposed project will result in unavoidable impacts
to 20,620 [square feet] of Class II wetland and 33,585 [square feet] of buffer zone along Englesby
Brook.” The City’s agent apparently understood the changes to the wetland areas and impacts, or
lack thereof, as considerations pertinent to its request to extend the CUD.
¶ 60. Fortieth likewise understood the changes, or lack thereof, to the wetland boundaries
as relevant, commenting to the Wetlands Program Manager that the City’s representation that the
wetlands areas and impacts had not changed was unsupported by “any field summaries, data
sheets, maps, site visit memoranda, photographs, or other documents demonstrating that” a
wetland consultant evaluated the wetland to be protected by the CUD.
¶ 61. And the Secretary acknowledged that a redelineation of the wetlands on the project
site was required by Condition E, requesting additional information from the City to support its
claim that the wetland areas and wetland impacts approved in the original CUD had not changed.
29
The Secretary continued the proceeding until the City’s consultants were able to reevaluate the
wetlands on the site and provide updated delineations; agency staff participated in site visits with
the City’s consultant; previously delineated wetlands were redelineated and field-verified; and
delineations were provided for two additional wetlands found on the project site. The Secretary’s
ultimate approval of the CUD rested on findings that expressly took into account the redetermined
boundaries. In short, the Secretary proceeded exactly as required by the CUD and the applicable
statutes and rules.
¶ 62. My analysis of the CUD does not turn on this history. Our job is to construe the
permit as written and intended, regardless of the parties’ understandings. But it’s telling that all
three of these stakeholders apparently shared the same understanding of the relationship between
a request to extend the permit and the need to reevaluate the wetland boundary—even though this
understanding was directly counter to the City’s interests and involved a regulatory regime
administered by the Secretary. To the extent that the majority describes the 2017 amendments to
the VWR as providing an “enhanced” standard, ante, ¶ 25, I believe that characterization is belied
by this record.
¶ 63. The 2017 rules, adopted well before the proceedings at the Environmental Division
were done, make it crystal clear that the Secretary may only extend a permit “if the permittee re-
evaluates and redelineates the wetland resources impacted by the authorized activity and the
Secretary determines there will be no impact to Class I or Class II wetland or buffer beyond those
impacts permitted under the original permit.” 2017 VWR § 9.1.20 In so providing, for all the
reasons set forth above, the rules do not create a more onerous burden for a permittee seeking an
extension; rather, they make even clearer the longstanding requirements of the VWR. See Doe v.
Vt. Office of Health Access, 2012 VT 15A, ¶ 26, 191 Vt. 517, 54 A.3d 474 (“We presume that the
20
The superseding 2018 VWR maintain this requirement. 2018 VWR § 9.1.
30
Legislature intended to change the meaning of a statute when it amends it, but we will recognize
clarification of the law where the circumstances clearly indicate it was intended.” (quotation
omitted)).
¶ 64. For the above reasons, I respectfully dissent.
¶ 65. I am authorized to state that Justice Skoglund joins this dissent.
Associate Justice
31