T.C. Memo. 2017-26
UNITED STATES TAX COURT
BASIC ENGINEERING, INC., Petitioner v.
COMMISSIONER OF INTERNAL REVENUE, Respondent
Docket No. 27691-13. Filed February 1, 2017.
L. Don Knight and Aaron P. Lloyd, for petitioner.
Bettina M. Nadler, for respondent.
MEMORANDUM FINDINGS OF FACT AND OPINION
PARIS, Judge: In a notice of deficiency dated August 22, 2013, respondent
determined Federal income tax deficiencies of $8,670,933.19 and $266,567.82 and
-2-
[*2] accuracy-related penalties under section 6662(a) of $1,734,186.64 and
$53,313.56 for petitioner’s 2009 and 2010 taxable years, respectively.1
The issues for decision are whether petitioner is: (1) eligible to account for
two of its contracts using the completed contract method of accounting and (2)
liable for accuracy-related penalties.
FINDINGS OF FACT
Some of the facts are stipulated and are so found. The first stipulation of
facts and the first supplemental stipulation of facts, and the exhibits attached
thereto, are incorporated herein by this reference. Petitioner, Basic Engineering,
Inc., was a Texas corporation with its principal place of business in Texas when it
timely filed its petition.
I. Overview of the Parties
Petitioner’s primary business is the engineering, designing, procuring,
refurbishing, and delivering of crude oil processing and refining systems to
customers in the petrochemical industry worldwide. Thomas Balke owned 51% of
petitioner and James Smith owned 49%; Mr. Balke and Mr. Smith also owned
Basic Equipment, Inc. (Basic Equipment), another Texas corporation, in the same
1
Unless otherwise indicated, all section references are to the Internal
Revenue Code in effect for the years at issue, and all Rule references are to the
Tax Court Rules of Practice and Procedure.
-3-
[*3] respective percentages. Mr. Balke was the president of both corporations
during the years in issue. Mr. Balke has over 30 years of experience in working
with oil refineries and refinery equipment; his international oil refinery business
experience first occurred in 1977.
This case concerns the accounting treatment for tax purposes of two of
petitioner’s contracts that were ongoing in 2009 and 2010: (1) petitioner’s
contract with Petromaxx Energy Group GmbH, later known as Petromaxx Energy
Group GmbH & Co KG, and later as Tagore Investments S.A. as universal
successor (collectively Petromaxx); and (2) petitioner’s contract with Amber
Energy S.A. (Amber). Since its incorporation in 2004 petitioner has accounted for
its long-term contracts using the completed contract method of accounting.
Respondent’s determinations that petitioner was ineligible to use the completed
contract method of accounting for the Petromaxx and Amber contracts led to the
deficiencies at issue.
II. The Petromaxx Contract
A. Basic Equipment-Petromaxx Agreement
Petitioner and Basic Equipment maintained relationships with salespersons
working outside the United States who searched for potential customers on their
behalf. In 2004 a salesman contacted a Basic Equipment representative to inform
-4-
[*4] him that the international entity Petromaxx was interested in building a small
oil refinery in Bulgaria with a 10,000 to 15,000 barrel per day (BPD) crude oil
topping unit. Mr. Balke, acting on behalf of Basic Equipment, offered to build
Petromaxx a new refinery, but Petromaxx wanted a refinery that was readily
available and wanted petitioner to find an existing refinery, disassemble it, and
refurbish various parts according to Petromaxx’s specifications. The newly
refurbished parts would then be reconstructed into a new refinery at Petromaxx’s
preferred international location.
Representatives for Basic Equipment and Petromaxx visited an existing oil
refinery in Nixon, Texas (Nixon refinery), that had equipment similar to the
equipment Petromaxx had initially described. After visiting the refinery Basic
Equipment made a proposal to refurbish the refinery’s parts and sell them to
Petromaxx, which would then construct an operating refinery. Basic Equipment
and Petromaxx ultimately reached an agreement on December 4, 2005 (Nixon
equipment agreement).
Under the terms of the Nixon equipment agreement, Basic Equipment
agreed to: design and manufacture one new 10,000 BPD atmospheric crude unit
and one reconditioned 17,000 BPD crude topping unit; provide Petromaxx with
designs and flow diagrams necessary to operate and perform maintenance on the
-5-
[*5] crude units; provide Petromaxx with plant operation manuals; and supervise
the commissioning of the crude units once they were assembled. In exchange,
Petromaxx agreed to pay Basic Equipment $21.5 million; Petromaxx initially paid
Basic Equipment $6,450,000 as a deposit on December 23, 2005.
Early in 2006 Petromaxx determined that it needed to build a larger
production capacity refinery than the Nixon refinery could provide and withdrew
the previous agreement.
B. Petitioner-Petromaxx Sale and Purchase Agreement
1. Background
After determining that the Nixon refinery would not meet its production
capacity needs, Petromaxx provided Mr. Balke with new scope of work
requirements. In an effort to find a refinery that would meet Petromaxx’s
production capacity requirements, Mr. Balke and a Petromaxx representative
visited a larger refinery with a 50,000 to 55,000 BPD capacity in California
(Cenco refinery). After examining the Cenco refinery, Mr. Balke offered to
refurbish and sell the refinery’s parts to Petromaxx, which would then construct an
operating refinery. At some point Mr. Balke made the decision to transfer the
-6-
[*6] order from Basic Equipment to petitioner.2 Basic Equipment transferred to
petitioner Petromaxx’s original $6,450,000 Nixon refinery deposit in installments
of $3 million on February 8, 2006, $3 million on March 8, 2006, and $450,000 on
March 28, 2006.
On March 22, 2006, petitioner purchased the Cenco refinery from JAS
Marketing, Inc. (JAS), for $18.9 million for use in the Petromaxx project.
Petitioner agreed to make its first payment to JAS on or before March 22, 2006,
with subsequent payments due monthly through August 22, 2007.
2. Sale and Purchase Agreement
Before executing a formal agreement, Petromaxx transferred to petitioner
$10,750,000 in addition to the $6,450,000 deposit Petromaxx paid to Basic
Equipment, which was subsequently transferred to petitioner. The advanced funds
were paid to petitioner in two equal installments of $5,375,000 on May 22 and
September 1, 2006.
On October 28, 2006, petitioner and Petromaxx executed a “Sale and
Purchase Agreement” (Petromaxx SPA) whereby Petromaxx agreed to purchase
certain crude oil processing units from petitioner. The Petromaxx SPA required
2
The exact date on which Mr. Balke made the decision to transfer the order
is not in the record.
-7-
[*7] petitioner to refurbish the oil processing units and to provide Petromaxx with
engineering specifications that Petromaxx would use to install the newly
refurbished units and construct an operating refinery.3 Once the Cenco refinery
was broken down and the necessary parts refurbished, petitioner was responsible
for delivering the refurbished units to its facility in Houston, Texas, and
Petromaxx was responsible for shipping the refurbished units from there to
Bulgaria. Petromaxx was also responsible for creating the refinery site in Bulgaria
and erecting and installing the newly refurbished units into a refinery. Once
Petromaxx had erected and installed the refurbished units, petitioner was required
to supervise the commissioning4 of the newly erected units. Upon successful
3
Petitioner subcontracted the engineering work to MM Inženjering LTD.
(Montmontaza), a subsidiary of Montmontaža PLC, a Croatian company, via an
agreement executed by the parties on January 9, 2007 (Montmontaza agreement).
Montmontaza was responsible for providing the information that Petromaxx
would need to construct the refinery in Bulgaria. To satisfy its responsibilities,
Montmontaza was to produce as-built documentation of the existing Cenco
refinery in its standing condition in California and check the then-existing plant
configuration against the future Bulgaria refinery site location. Doing so would
allow Montmontaza to produce the documentation that would be necessary for
Petromaxx to reconstruct the refurbished Cenco refinery in Bulgaria.
4
The Petromaxx SPA defined commissioning as “a set of activities that shall
be performed by BUYER’s personnel as Supervised by BASIC’s on site field
engineer and witnesses by Qualified Engineer at BUYER’s Location in order to
determine that the Facility can be properly and safely operated in accordance with
the Technical Standards promptly after mechanical completion and pre-commis-
(continued...)
-8-
[*8] commissioning of the refinery, a qualified engineer would conduct
performance tests and issue a “final acceptance report and certificate” upon
successful testing. At that point, petitioner would have fulfilled all of its
obligations under the Petromaxx SPA and Petromaxx would assume full
responsibility for the refinery and its operation. In consideration for a complete,
satisfactory, and timely performance by petitioner of all of its obligations under
the Petromaxx SPA, Petromaxx agreed to pay petitioner $90.5 million.5
The Hardt Investment Group, headquartered in Vienna, Austria, controlled
the underlying funding of Petromaxx, and the parties negotiated the following
governing law provision in section 19.3.1 of the Petromaxx SPA:
This Agreement shall be governed by, and construed in accordance
with, the laws of the Republic of Austria including the UN
Convention on Contracts for the International Sale of Goods of 1980
(CISG). The Parties’ rights and obligations with respect to title to
and security interests in the Equipment shall be governed by the law
of the jurisdiction in which such Equipment is located.
4
(...continued)
sioning of the Facility”.
5
The total contract price included the $17.2 million previously paid to
petitioner--the $6,450,000 deposit paid to Basic Equipment (and transferred to
petitioner) and the two payments of $5,375,000 paid directly to petitioner.
-9-
[*9] 3. Amendment to Petromaxx SPA
After executing the Petromaxx SPA, Petromaxx once again determined that
it wanted to increase the capacity of its refinery. On October 6, 2007, almost one
year after the original contract was executed, petitioner and Petromaxx executed
an amendment to the Petromaxx SPA whereby petitioner agreed to refurbish
additional equipment that would allow Petromaxx to meet its capacity
requirements. Petromaxx agreed to pay an additional $31,750,000 to petitioner for
the additional equipment, bringing the total contract price to $122,250,000. In
October of 2007, at the time the parties executed the amendment to the Petromaxx
SPA, Petromaxx had made payments to petitioner totaling $72.4 million.6
C. Timeframe
For purposes of accounting for the Petromaxx contract, petitioner’s estimate
of the time the contract would take to complete is important. The Court will look
to the terms of the Petromaxx SPA and will consider testimony from Mr. Balke
and respondent’s expert witness, John Harris.
6
The parties executed subsequent amendments to the Petromaxx SPA
through August 13, 2008, but the subsequent amendments did not adjust the total
contract price.
- 10 -
[*10] 1. Petromaxx SPA
With respect to the Petromaxx project’s expected timeframe, section 3.2.2.
of the Petromaxx SPA provided:
Agreed Project Schedule. BASIC shall commence * * * [its work] in
accordance with the project schedule and management plan set forth
in Exhibit 3.2.2 (the “Preliminary Project Schedule”). Within one (1)
month after signing this Agreement, BASIC shall submit, for
BUYER’s review and approval, an updated and more detailed
schedule (as approved by Qualified Engineer and by BUYER, the
“Agreed Project Schedule”) amending the Preliminary Project
Schedule which sets forth the timing of completing the [Cenco
refinery] Units and of all other major elements of * * * [petitioner’s
obligations] as well as the interrelationship of such elements. Dates
included in the Agreed Project Schedule shall be the best estimates
available at the time of submission of the Agreed Project Schedule
but shall not be guaranteed dates of delivery or achievement of listed
milestones or objectives, except that Delivery of the last [Cenco
refinery] Unit is guaranteed to occur no later than twelve (12) months
after the signing of this Agreement.
Exhibit 3.2.2 to the Petromaxx SPA--the “Preliminary Project Schedule”--stated:
“[to be provided by BASIC]”; the rest of the page was blank. Petitioner did not
introduce into evidence a document purporting to be the preliminary project
schedule that it was to provide or an amended project schedule.
Although the Petromaxx SPA did not contain a project schedule, it required
petitioner to “use its best efforts” to deliver the last refurbished unit to its facility
in Houston, Texas, by April 30, 2007; however, if petitioner failed to deliver the
- 11 -
[*11] last unit by April 30, 2007, the Petromaxx SPA did not provide for penalties.
If petitioner failed to deliver the last unit on or before September 12, 2007,
petitioner would default under the terms of the Petromaxx SPA.7 These delivery
dates are the only performance dates specified in the Petromaxx SPA.8
7
Specifically, section 3.2.1 of the Petromaxx SPA provided:
BASIC shall use its best efforts to Deliver the [Cenco refinery] Units
listed as Phase One and as Phase Two in the Equipment Ledger
within five (5) months after signing of this Agreement. BASIC shall
use its best efforts to Deliver all other Units on or prior to the date
corresponding to such Unit set forth in the Project Schedule, and in
any event on or prior to April 30, 2007. The failure of BASIC to
deliver such Units on the foregoing dates shall not constitute a default
under this Agreement unless BASIC fails to use its best efforts.
Notwithstanding the foregoing, it shall be a default under this
Agreement if BASIC fails to Deliver the last Unit on or prior to
September 12, 2007 (“Final Delivery Date”).
Section 8.4 of the Petromaxx SPA provided that petitioner “shall diligently pursue
the performance of * * * [its work] and will achieve Delivery of all Equipment on
or prior to September 12, 2007”.
Sections 3.2.1 and 8.4 of the Petromaxx SPA conflict with section 3.2.2
with respect to the delivery of the units, as sections 3.2.1 and 8.4 state that
delivery of the last unit will occur on or before September 12, 2007, while section
3.2.2 states that delivery of the last unit will occur no later than 12 months after
the signing of the SPA on October 28, 2006. This inconsistency does not affect
the Court’s determination with respect to the two-year rule discussed infra.
8
The Montmontaza agreement also appears to coincide with the delivery
timeline specified in the Petromaxx SPA, as Montmontaza anticipated having all
drawings and documents completed by the middle of September 2007.
- 12 -
[*12] Importantly, the Petromaxx SPA did not include terms requiring Petromaxx
to ship the refurbished units from Houston, Texas, to Bulgaria by a specific date,
begin or finish creating the refinery site by a specific date, or begin or finish
installing and erecting the newly refurbished units into a refinery by a specific
date. Petitioner did not offer into evidence any documentation reflecting dates by
which petitioner or Petromaxx expected Petromaxx to begin or finish its
obligations.
Section 9.4.1 of the Petromaxx SPA provided: “Immediately after
notification that the erection and installation of the * * * [refinery site] has been
properly performed and completed, BASIC shall Supervise * * * [Petromaxx’s]
personnel in Commissioning of the Facility.” After successful commissioning, a
qualified engineer would conduct performance tests which “must in any case be
completed within sixty (60) days, or such other period as may be agreed in writing
by the Parties, from the date on which Commissioning has commenced.” Once the
qualified engineer was satisfied that the performance tests showed that the newly
installed and erected refinery met certain standards, he would issue a report. At
that point, petitioner would have fulfilled all of its obligations under the
Petromaxx SPA. The Petromaxx SPA did not contain an overall project
completion date.
- 13 -
[*13] With respect to the terms of payment, the Petromaxx SPA indicates that the
parties anticipated the final payment to become due on the earlier of: (1) 10
months after the “Final Delivery Date”, which was September 12, 2007, or (2) the
“Final Acceptance Date”, which was the date that the qualified engineer issued a
completion report.
Because the Petromaxx SPA did not specify dates by which Petromaxx
would ship the refurbished units, finish creating the refinery site, or finish
installing and erecting the newly refurbished units into a refinery, it is unclear
exactly when the parties expected the Petromaxx SPA to be completed.
2. Mr. Balke’s Testimony
Mr. Balke testified that 3-D laser scanning technology was introduced to his
industry in the early to mid-2000s. This technology allowed existing refineries to
be scanned before their deconstruction and produced blueprints and models of the
assembled refineries timelier than the traditional method of measurement and
modeling. These blueprints and models could then be shipped elsewhere to assist
in the preparation of the new site for construction. According to Mr. Balke
petitioner was an early adopter of this technology, and he intended petitioner to
use it in completion of the Petromaxx SPA.
- 14 -
[*14] In theory, by using the increased efficiency of the 3-D scanning, multiple
stages of the refurbishing and reconstruction processes could proceed in tandem.
Mr. Balke used the phrase “parallel processing” to describe this system of
operation. The logistics of this theory operated in the following manner: Each
stage of the dismantling project would be scanned and modeled, and the model
would be sent to the purchaser; then, simultaneously, petitioner would begin
dismantling and refurbishing the scanned sections of the refinery while the
purchaser used the models to prepare the new site for the refinery’s specific
reconstruction requirements. Despite the theory’s temporal benefits, Mr. Balke
testified that he was aware of only two other companies in petitioner’s industry
currently using a parallel processing system.
3. Respondent’s Expert Witness Testimony
Respondent called John R. Harris, PE, to testify as an expert witness on the
process of creating, constructing, and operating refineries. The Court recognized
Mr. Harris as such an expert and received into evidence his expert witness report,
in which he stated his opinion regarding a reasonable estimate of time it would
take to complete the Petromaxx refinery project.
Mr. Harris opined that a three-year timeframe to complete the Petromaxx
project was “optimistic but possible.” To arrive at his conclusion, Mr. Harris
- 15 -
[*15] noted that the only performance date specified in the Petromaxx SPA was
September 12, 2007, the date by which petitioner was required to deliver the
equipment. Because the Petromaxx SPA did not specify dates by which the
remaining components of the Petromaxx refinery project would begin and finish,
Mr. Harris was required to make assumptions and estimate how long the
remaining components would take, which he summarized as follows:
One must make an estimate of the reasonable time required to ship the
equipment, acquire the balance of the equipment, supplies and
services necessary to complete a refinery. Foreign shipping to an
inland port in the developing world is difficult to estimate. Six
months seems like an optimistic period to have everything in place in
Bulgaria, assuming no delays in long lead-time equipment, no local
shortages of necessary supplies or scarcity of skilled labor.
Following Owner acquisition of the equipment, and presuming
finished engineering proceeds timely, final erection of the refinery
could hardly be expected in less than one year. If commissioning
proceeds promptly and few problems are found, this task should take
6 weeks, followed by another month for a performance run on the
refinery.
Mr. Harris did not take petitioner’s parallel processing system into
consideration in reaching his conclusions with respect to the Petromaxx SPA’s
timeframe. Instead, Mr. Harris’ conclusion was based on traditional industry
practices, and Mr. Balke agreed with Mr. Harris’ conclusion to the extent he had
relied on traditional industry practices. Mr. Balke disagreed with Mr. Harris’
overall conclusion that the Petromaxx project would take at least three years to
- 16 -
[*16] complete because Mr. Harris did not consider how much time 3-D laser
imaging or petitioner’s parallel processing system would save.
D. Project Outcome
Ultimately, the Petromaxx refinery project was not completed. At some
point during the course of the project, Petromaxx lost its financing and was unable
to pay petitioner. At the time of trial, the dismantled units from the Cenco refinery
were still in petitioner’s construction yard in Texas.
III. The Amber Contract
A. Background
While petitioner was working on the Petromaxx refinery project, a
representative from the Hardt Investment Group contacted Mr. Balke to inform
him that Amber was interested in purchasing a 100,000 BPD refinery and
assembling it in Pakistan. Mr. Balke informed the representative that he was
aware of a 100,000 BPD refinery in Turkey (Ataº refinery) that would meet
Amber’s production capacity requirements. Toplam Mühend¥sl¥k ve Taahhüt
Ýthalat Ýhracat L¥m¥ted ª¥rket¥ (Toplam), a company incorporated in Turkey,
contracted to supply the Ataº refinery units.9
9
Toplam obtained title to the then-existing Ataº refinery units on April 21,
2008. BP, Shell, and Marmara Petrol owned the refinery site and have since
(continued...)
- 17 -
[*17] B. Petitioner-Amber Sale and Purchase Agreement
On July 17, 2008, petitioner and Amber executed a “Sale and Purchase
Agreement” (Amber SPA). The Amber SPA required petitioner to identify and
negotiate purchase orders with third-party vendors to procure oil processing units
for use in the Amber project, refurbish those units, and deliver the newly
refurbished units to a designated location. To satisfy those obligations, petitioner
purchased the Ataº refinery units from Toplam for $18 million via a “Supply
Agreement” executed on July 24, 2008 (Toplam supply agreement). Under the
terms of the Toplam supply agreement, Toplam agreed to dismantle the Ataº
refinery and deliver the dismantled units to a specified location in Turkey in a
condition that would allow them to be refurbished on site. Petitioner then
subcontracted with third parties to perform the refurbishing work that was
specified in the Amber SPA; the refurbishing work would occur while the Ataº
units were at the Ataº refinery site in Turkey.10 Upon completion of the work in
9
(...continued)
converted the location to an oil products terminal and storage facility.
10
Although the Toplam supply agreement allowed for the refurbishing work
to take place at the Ataº site, the units were ultimately moved to Northern Cyprus
and refurbished there.
- 18 -
[*18] Turkey, Amber was responsible for transporting the newly refurbished units
to a site in Pakistan.11
The Amber SPA required petitioner to obtain a fluid catalytic cracker unit
(FCCU)12 for use in the Amber project. Petitioner agreed to acquire, dismantle,
and transport the FCCU to its Houston, Texas, facility for refurbishing work.
Petitioner purchased an FCCU from a third party in Wichita, Kansas, for use in the
Amber project.
The Amber SPA also required petitioner to provide Amber with engineering
specifications and drawings that Amber would use to install the newly refurbished
units and construct an operating refinery. Amber was responsible for creating and
preparing the refinery site and erecting and installing the newly refurbished units
if it elected to do so.13 If Amber chose to erect and install the refurbished units,
petitioner was required to supervise the commissioning of the newly erected
11
The location at which Amber was to construct a refinery was subject to
change at Amber’s sole discretion. The available documentary evidence does not
reflect a final location determination.
12
Fluid catalytic cracking, a type of secondary unit operation, is primarily
used in producing additional gasoline in the refining process.
13
Under the terms of the Amber SPA, Amber was not required to install and
erect a refinery. If Amber elected not to install, erect, and commission the
refinery, the total contract price was to be reduced by only $75,000 out of the total
contract price of $100 million.
- 19 -
[*19] refinery. Upon successful commissioning of the refinery, a qualified
engineer would conduct performance tests and issue a “final acceptance report and
certificate” upon successful testing. At that point, petitioner’s obligations under
the Amber SPA would end and Amber would assume full responsibility for the
refinery and its operation. In consideration for a complete, satisfactory, and timely
performance by petitioner of all of its obligations under the Amber SPA, Amber
agreed to pay petitioner $100 million.
The Amber SPA contained the following governing law provision:
This Agreement shall be governed by, and construed in accordance
with, the laws of the State of Texas, including Article 2 of the
Uniform Commercial Code, except to the extent that the Parties’
rights and obligations with respect to title to and security interests in
the Equipment may be governed by the law of the jurisdiction in
which such Equipment is located.
C. Timeframe
For purposes of accounting for the Amber contract, petitioner’s estimate of
the time the contract would take to complete is important. The Court will look to
the terms of the Amber SPA and will consider testimony from Mr. Balke and
respondent’s expert witness, John Harris.
- 20 -
[*20] 1. Amber SPA
With respect to the Amber SPA’s timeframe, section 3.2.1 of the Amber
SPA provided:
BASIC shall commence * * * [its work] in accordance with the
Project Schedule and shall use its best efforts to ensure that * * * [its
work is] performed in accordance with the Project Schedule. Dates
included in the Project Schedule are the best estimates available on
the date of this Agreement but are not guaranteed dates of delivery or
achievement of listed milestones or objectives, except that Delivery
of all items comprising the * * * [complete package of crude oil
processing and refining equipment] is guaranteed to occur no later
than the Delivery Deadline [November 15, 2010]. Modifications to
the Project Schedule shall only be made with the prior written
approval of * * * [Amber].
A project schedule was not attached to the Amber SPA, and petitioner did
not offer into evidence a project schedule or any other documentation that would
reflect dates by which the parties expected the various components of the project
to be completed.
Although the Amber SPA did not contain a project schedule, the agreement
required petitioner to deliver the last unit “no later than” November 15, 2010.
Petitioner was entitled to bonus payments if the delivery date for the units
occurred before November 15, 2010, and subject to penalties if the delivery date
occurred after November 15, 2010.
- 21 -
[*21] Importantly, just like the Petromaxx SPA the Amber SPA did not include
terms requiring Amber to ship the refurbished units by a specific date, begin or
finish creating the refinery site by a specific date, or begin or finish installing and
erecting the newly refurbished units into a refinery by a specific date. Petitioner
did not introduce into evidence any documentation reflecting dates by when
petitioner or Amber expected Amber to begin or finish its obligations.
If Amber elected to erect the refinery, petitioner was required to provide at
least one field engineer to supervise the commissioning process. After successful
commissioning, a qualified engineer would conduct performance tests which
“must in any case be completed within sixty (60) days, or such other period as may
be agreed in writing by the Parties, from the date on which Commissioning has
commenced.” Once the qualified engineer was satisfied that the performance tests
showed that the newly installed and erected refinery met certain standards, he was
to issue a report. At that point, petitioner’s obligations under the Amber SPA
would end and Amber would assume full responsibility for the refinery and its
operation. The Amber SPA did not specify an overall project completion date.
With respect to the terms of payment, the Amber SPA indicated that the
parties anticipated the final payment’s becoming due on the earlier of: (1) 10
months after the “Delivery Date”, which was the date on which petitioner
- 22 -
[*22] delivered the refurbished units to its facility in Houston, Texas, or (2) the
“Final Acceptance Date”, which was the date on which the qualified engineer
issued a completion report.14
Because the Amber SPA, like the Petromaxx SPA, did not specify dates by
when Amber was required to ship the refurbished units, finish creating and
preparing the refinery site, or finish installing and erecting the newly refurbished
units into a refinery, it is unclear exactly when the parties expected the Amber
SPA to be completed.
2. Mr. Balke’s Testimony
Mr. Balke testified that the Amber refinery project was simpler from a
logistics perspective than the Petromaxx refinery project and was likely to be
finished faster than Petromaxx, starting from each respective contract’s start date.
In addition he pointed to the Amber SPA, which refers to the possibility that
petitioner would use 3-D laser scanning and modeling. As with the Petromaxx
SPA, Mr. Balke’s intent was for petitioner to use parallel processing in fulfilling
the contract obligations of the Amber SPA.
14
Although the Amber SPA provided for delivery of all units to Houston,
Texas, the parties stipulated that petitioner and Amber never intended for the Ataº
refinery units to be shipped from Turkey to Houston. See infra note 15.
- 23 -
[*23] 3. Respondent’s Expert Witness Testimony
Mr. Harris opined that a 4-1'2-year timeframe to complete the Amber
refinery contract was “optimistic but possible.” In arriving at his conclusion, Mr.
Harris noted that the “Amber plant is double the size of the * * * [Petromaxx]
plant, involving more work and time.” Mr. Harris also noted that the only
performance date specified in the Amber SPA was with respect to petitioner’s
delivery obligations; petitioner was required to deliver the equipment by
November 15, 2010, roughly 28 months after the date on which the Amber SPA
was executed. Because the Amber refinery project did not specify dates by which
the remaining components of the Amber SPA would begin and finish, Mr. Harris
was required to make assumptions and estimate the time it would take to complete
the remaining tasks, which he summarized as follows:
One must make an estimate of the reasonable time required to ship the
equipment, acquire the balance of the equipment, supplies, and
services necessary to * * * complete the Amber refinery in Pakistan.
Foreign shipping in the developing world is difficult to estimate.
Seven months seems like an optimistic period to have everything in
place in Pakistan, assuming no delays in long lead-time equipment,
no local shortages of necessary supplies or scarcity of skilled labor.
Following Owner acquisition of the equipment, and presuming
finished engineering proceeds timely, final erection of the refinery
could hardly be expected in less than 18 months. If commissioning
proceeds promptly, and few problems are found, this task should take
- 24 -
[*24] two months, following by another two months for a performance run
on the refinery.[15]
As with the Petromaxx SPA, Mr. Harris’ overall conclusion with respect to
the Amber SPA’s timeframe did not take petitioner’s parallel processing system
into consideration.
D. Project Outcome
On the same day that petitioner and Amber executed the Amber SPA they
also executed a “Side Letter” to the Amber SPA whereunder the parties agreed
that the due date for certain installment payments would be extended because
Amber had not yet obtained sufficient financing to effect payment for the
installments. After approximately 18 months, on January 18, 2010, the parties
agreed to cancel the Amber SPA and release themselves from all responsibilities
and liabilities under the SPA’s terms. At the time of trial, the FCCU was still in
15
Mr. Harris’ opinion was formed, in part, on the basis of moving the Ataº
refinery from Turkey and the FCCU from Wichita to petitioner’s facility in
Houston for cleaning and inspection and then shipping those refurbished parts to
Pakistan. While the FCCU unit was to be transported from Wichita to Houston,
and then from Houston to Pakistan, the parties stipulated that petitioner and
Amber never intended for the dismantled Ataº refinery to be shipped from Turkey
to Houston even though delivery to Houston was specified in the Amber SPA.
The stipulation was executed by the parties after the filing date of the expert
report.
- 25 -
[*25] petitioner’s construction yard in Texas, and the Ataº refinery units were still
in Northern Cyprus.
IV. Petitioner’s Federal Income Tax Returns
From 2005 to 2010 petitioner accounted for the Petromaxx and Amber
contracts using the completed contract method of accounting; each return was
prepared and signed by the same certified public accountant (CPA). A taxpayer
using the completed contract method of accounting recognizes all income and
expenses associated with a contract only in the contract’s completion year. See
sec. 1.460-4(d), Income Tax Regs. Petitioner’s position is that neither contract
was completed. Because petitioner accounted for the contracts using the
completed contract method of accounting, it did not report income or expenses
associated with either contract during the years at issue or earlier because the
contracts were not completed. Petitioner’s schedule of all of its contracts for
2007-2010 was provided to respondent. This information was not reported on its
income tax returns. The schedules reflected petitioner’s annual contract revenue,
estimated total contract prices, annual contract expenses, and estimated total
contract expenses for the Petromaxx and Amber projects as follows:
- 26 -
[*26] Petromaxx project
Estimated total
Annual Estimated total Annual contract
Year revenue contract price expenses expenses
Before 2007 $20,395,917 $122,250,000 $16,316,738 $97,800,000
2007 49,708,361 122,250,000 39,766,687 97,800,000
2008 31,978,623 122,250,000 25,582,819 97,800,000
2009 866,631 122,250,000 709,295 97,800,000
2010 192,707 122,250,000 154,174 97,800,000
Total $103,142,239 $82,529,713
Amber project
Estimated total
Annual Estimated total Annual contract
Year revenue contract price expenses expenses
Before 2007 -- -- -- --
2007 -- -- -- --
2008 $33,252,634 $101,000,000 $26,667,954 $81,000,000
2009 1,418,775 101,000,000 1,137,835 81,000,000
2010 31,585 101,000,000 25,325 81,000,000
Total $34,702,994 $27,831,114
Respondent determined that petitioner was ineligible to use the completed
contract method of accounting for the Petromaxx and Amber SPAs. The notice of
deficiency reflected alternative accounting positions for petitioner’s projects.
- 27 -
[*27] Under either position, respondent determined that petitioner was not eligible
to report income under the completed contract method of accounting. Respondent
determined that the Petromaxx SPA should have been reported as a manufacturing
contract and that petitioner should have accounted for the Petromaxx SPA using
the accrual method of accounting.16 As his alternative position, respondent
determined that petitioner must account for both contracts using the percentage of
completion method because petitioner could not have estimated their completion
within the two-year period beginning on the respective contract commencement
dates. See sec. 460(e).
As discussed infra, the determination of whether either contract is a
manufacturing contract or a construction contract is irrelevant because the section
460 default provision applies. Thus, the following facts and calculations are
derived from respondent’s alternative position, i.e., that petitioner was required to
account for both contracts using the percentage of completion method.17
16
Although respondent’s pretrial memorandum asserts that both the
Petromaxx and Amber contracts are manufacturing contracts, the notice of
deficiency determines that only the Petromaxx contract is a manufacturing
contract. Respondent did not amend his answer to assert otherwise.
17
Because the deficiency and penalty amounts reflected on the face of the
notice of deficiency are based on respondent’s primary position, the adjustments
discussed infra will not match the deficiency and penalty amounts reflected on the
(continued...)
- 28 -
[*28] The percentage of completion method of accounting requires taxpayers to
recognize income and expenses throughout the duration of a contract on the basis
of the percentage of the contract that is actually completed. Accordingly,
respondent’s alternative position adjusted petitioner’s gross receipts and cost of
goods sold figures for the Petromaxx and Amber SPAs on the basis of the
percentage that the contracts were completed in 2009 and 2010.
To determine the percentages of the Petromaxx and Amber SPAs that were
completed, respondent used the schedule of contracts petitioner had provided; in
accordance with section 460(b), respondent added the annual expenses petitioner
had actually incurred and then divided those totals by the estimated total contract
costs. For 2009 respondent determined that petitioner had completed
approximately 84.23% of the Petromaxx SPA18 and approximately 34.33% of the
Amber SPA,19 and for 2010 respondent determined that petitioner had completed
17
(...continued)
face of the notice of deficiency.
18
Petitioner had incurred $82,375,539 of actual expenses between 2005 and
2009. Petitioner estimated the total contract costs to amount to $97.8 million.
Actual expenses of $82,375,539 divided by an estimated total contract cost of
$97.8 million equals 84.23%.
19
Petitioner had incurred $27,805,789 of actual expenses between 2005 and
2009. Petitioner estimated the total contract costs to amount to $81 million.
(continued...)
- 29 -
[*29] approximately 84.39% of the Petromaxx contract and approximately 34.36%
of the Amber contract.
Respondent then multiplied the percentage each contract was completed by
the estimated total contract price to arrive at the amounts petitioner should have
recognized as income had it accounted for the contracts using the percentage of
completion method of accounting. For 2009 respondent adjusted petitioner’s
gross receipts by $137,644,475.20 Because petitioner did not report any income or
expenses from the Petromaxx or Amber contract from 2005 to 2009, the 2009
adjustment accounts for all income that petitioner should have recognized between
19
(...continued)
Actual expenses of $27,805,789 divided by an estimated total contract cost of $81
million equals 34.33%.
20
For the Petromaxx SPA, respondent multiplied the $122,250,000 estimated
total contract price by an 84.23% completion percentage to arrive at a
$102,971,175 gross receipts adjustment for income from the Petromaxx SPA from
2005 to 2009. For the Amber SPA, respondent multiplied the $101 million
estimated total contract price by a 34.33% completion percentage to arrive at a
$34,673,300 gross receipts adjustment. In total, these adjustments amount to
$137,644,475.
- 30 -
[*30] 2005 and 2009 under the percentage of completion method of accounting.21
For 2010 respondent adjusted petitioner’s gross receipts by $225,900.22
Respondent allowed corresponding adjustments for cost of goods sold and
made an adjustment for a section 481(b) limitation credit for 2009 to further
reduce petitioner’s tax liability. The adjustments in the notice of deficiency give
rise to the deficiencies and penalties currently at issue. Petitioner challenges the
deficiencies and penalties, arguing that it was entitled to account for the
Petromaxx and Amber SPAs using the completed contract method of accounting.
As of the date of the notice of deficiency, August 22, 2013, petitioner had neither
21
Following a change of accounting method, the Commissioner may make
any necessary adjustments to prevent taxable income from being duplicated or
omitted as a result of the change under sec. 481(a). For purposes of sec. 481(a)
adjustments, once there has been a change in the method of accounting, no statute
of limitations applies to the Commissioner’s authority to correct errors on old tax
returns. See Mingo v. Commissioner, 773 F.3d 629, 636 (5th Cir. 2014), aff’g
T.C. Memo. 2013-149.
22
For the Petromaxx SPA, respondent multiplied the $122,250,000 estimated
total contract price by an 84.39% completion percentage to arrive at $103,166,775.
After subtracting the gross receipts adjustment for 2009 of $102,971,175
respondent arrived at a total adjustment for the Petromaxx SPA of $195,600 for
2010. For the Amber SPA, respondent multiplied the $101 million estimated total
contract price by a 34.36% completion percentage to arrive at $34,703,600. After
subtracting the gross receipts adjustment for 2009 of $34,673,300 respondent
arrived at a total adjustment for the Amber SPA of $30,300 for 2010. These
adjustments total $225,900.
- 31 -
[*31] reported any of the Petromaxx or Amber contract income nor claimed
deductions for any of the contract expenses.
OPINION
I. Burden of Proof
Generally, the Commissioner’s determinations set forth in a notice of
deficiency are presumed correct, and the taxpayer bears the burden of showing the
determinations are in error. Rule 142(a); Welch v. Helvering, 290 U.S. 111, 115
(1933). If a taxpayer’s method of accounting does not clearly reflect income,
section 446(b) allows the Commissioner to change the taxpayer’s method of
accounting to one that does clearly reflect income. The Commissioner is granted
broad discretion in determining whether an accounting method clearly reflects
income, and that determination is entitled to more than the usual presumption of
correctness. See Commissioner v. Hansen, 360 U.S. 446, 467 (1959); The Howard
Hughes Co., LLC v. Commissioner, 142 T.C. 355, 376, aff’d, 805 F.3d 175 (5th
Cir. 2015); Shea Homes, Inc. v. Commissioner, 142 T.C. 60, 84 (2014), aff’d, 834
F.3d 1061 (9th Cir. 2016). The question of whether a particular accounting
method clearly reflects income is a question of fact to be determined on a case-by-
case basis. See The Howard Hughes Co., LLC v. Commissioner, 142 T.C. at 376;
- 32 -
[*32] Shea Homes, Inc. v. Commissioner, 142 T.C. at 85; Ansley-Sheppard-
Burgess Co. v. Commissioner, 104 T.C. 367, 371 (1995).
To prevail, the taxpayer must establish that the Commissioner abused his
discretion in changing the method of accounting. Mingo v. Commissioner, 773
F.3d 629, 635 (5th Cir. 2014), aff’g T.C. Memo. 2013-149; The Howard Hughes
Co., LLC v. Commissioner, 142 T.C. at 376; Shea Homes, Inc. v. Commissioner,
142 T.C. at 85. The taxpayer bears a heavy burden of proof, and the Commis-
sioner’s determination is not to be set aside unless shown to be plainly arbitrary.
Mingo v. Commissioner, 773 F.3d at 635; Ansley-Sheppard-Burgess Co. v.
Commissioner, 104 T.C. at 370-371 (citing Thor Power Tool Co. v. Commis-
sioner, 439 U.S. 522, 532-533 (1979)). But the Commissioner may not change a
taxpayer’s method of accounting from an incorrect method to another incorrect
method; nor may the Commissioner change a taxpayer’s method of accounting
where a taxpayer’s method of accounting is clearly an acceptable method and
clearly reflects income. The Howard Hughes Co., LLC v. Commissioner, 142
T.C. at 376; Shea Homes, Inc. v. Commissioner, 142 T.C. at 85.
II. Long-Term Contracts
Section 460 governs how taxpayers report income from long-term contracts.
Section 460(f)(1) defines a long-term contract as “any contract for the
- 33 -
[*33] manufacture, building, installation, or construction of property if such
contract is not completed within the taxable year in which such contract is entered
into.” The Amber and Petromaxx SPAs were both for the “manufacture, building,
installation, or construction of property”, and neither contract was completed
within the taxable year in which it was entered into. Thus, the contracts are long-
term contracts under section 460.
A. Percentage of Completion Method
Generally, taxpayers who receive income from long-term contracts must
account for that income using the percentage of completion method of accounting.
Sec. 460(a). This method essentially requires a taxpayer to recognize income and
expenses throughout the duration of a contract. See sec. 460(b); see also The
Howard Hughes Co., LLC v. Commissioner, 142 T.C. at 382; Shea Homes, Inc. v.
Commissioner, 142 T.C. at 85. As argued here, however, two exceptions to this
rule may apply: section 460(f)(2) excludes certain manufacturing contracts and
section 460(e)(1)(B) excludes certain construction contracts. As discussed infra,
the Court need not determine whether the Petromaxx and Amber SPAs are for
manufacturing or construction because neither exception applies; section 460
requires petitioner to use the percentage of completion method of accounting for
both contracts.
- 34 -
[*34] B. Exception for Certain Manufacturing Contracts
Respondent’s primary position is that the Petromaxx SPA is a
manufacturing contract and that it fails to meet the section 460(f)(2) requirements
to be treated as a long-term contract. Accordingly, respondent asserts, petitioner is
required to use the accrual method of accounting. Petitioner disagrees, arguing
that section 460(f)(2) is inapplicable because the contracts are construction
contracts--not manufacturing contracts.
Manufacturing contracts are generally not treated as long-term contracts,
meaning the long-term contract accounting rules of section 460 would not apply.
See sec. 460(f)(2). However, if a contract involves the manufacture of (A) any
unique item of a type not normally included in the finished goods inventory of the
taxpayer or (B) any item which normally requires more than 12 calendar months to
complete, then the contract is treated as a long-term contract and is subject to
section 460. See sec. 460(f)(2)(A) and (B).
At issue are two contracts--each for the disassembly, transportation,
refurbishing, assembly, and certification of a new oil refinery. Petitioner
introduced sufficient evidence, corroborated by the testimony of Mr. Balke,
showing that the processes involved normally require more than 12 calendar
months to complete. Respondent’s expert, Mr. Harris, agreed, stating that the
- 35 -
[*35] assembly process alone “could hardly be expected in less than one year.”
Assuming without finding that these contracts are for the manufacture of two oil
refineries, each would fall under the section 460(f)(2)(B) requirement that it be
treated as a long-term contract under section 460 and thus generally accounted for
using the percentage of completion method of accounting.
The Commissioner may not change a taxpayer’s method of accounting from
an incorrect method to another incorrect method. The Howard Hughes Co., LLC
v. Commissioner, 142 T.C. at 376; Shea Homes, Inc. v. Commissioner, 142 T.C. at
85. Because the evidence clearly establishes that even if the Petromaxx SPA were
a manufacturing contract, the length of the contract would render section 460(f)(2)
properly applicable and would generally require petitioner to use the percentage of
completion method of accounting, the Court finds respondent’s manufacturing
position for the Petromaxx SPA incorrect.
C. Exception for Certain Construction Contracts
In some instances taxpayers may account for income from certain
construction contracts under a method of accounting other than the percentage of
completion method, such as the completed contract method. See sec. 460(e); The
Howard Hughes Co., LLC v. Commissioner, 142 T.C. at 382. Section
460(e)(1)(B) provides an exception to the percentage of completion method of
- 36 -
[*36] accounting for certain long-term contracts that meet the following
requirements: (1) the contract is a construction contract; (2) the taxpayer
estimates, at the time the contract is entered into, that it will be completed within
the two-year period beginning on the contract commencement date (the two-year
rule); and (3) the taxpayer’s average annual gross receipts for the three taxable
years preceding the taxable year in which the contract is entered into do not
exceed $10 million. A taxpayer who satisfies all three requirements is eligible to
account for such a contract using the completed contract method of accounting;
failure to meet any one of the three requirements will render the exception
inapplicable.23
Petitioner accounted for the Petromaxx and Amber SPAs using the
completed contract method. Respondent determined that petitioner was ineligible
to use the completed contract method. The parties disagree over whether (1) the
contracts were “construction contracts” under section 460 and (2) the two-year
rule was satisfied. Assuming without finding that these contracts are construction
contracts, and bearing in mind the well-settled principle that statutes granting tax
exemptions or deferments must be strictly construed, see The Howard Hughes
23
Sec. 460(e)(1)(A) provides an additional exception to the percentage of
completion method of accounting for home construction contracts. Petitioner does
not contend that it qualifies for this exception.
- 37 -
[*37] Co., LLC v. Commissioner, 805 F.3d at 181, the Court finds that petitioner
did not satisfy the two-year rule with respect to either contract. Petitioner,
therefore, was not eligible to account for the Petromaxx or Amber SPA using the
completed contract method of accounting.
III. Two-Year Rule
A. Legal Framework
To be eligible for the construction contract exception to the percentage of
completion method, the taxpayer must estimate, at the time the contract is entered
into, that it will be completed within the two-year period beginning on the contract
commencement date. See sec. 460(e)(1)(B)(i). The statute requires the Court to
first determine the contract commencement dates of the Petromaxx and Amber
SPAs and then determine whether petitioner could have reasonably estimated--at
the time the respective contracts were entered into--that the projects would be
complete within two years from their respective commencement dates. Sec.
460(e)(1)(B); see also sec. 1.460-1(f)(4), Income Tax Regs.
1. Contract Commencement Date
For purposes of section 460, the term “contract commencement date” means
the first date on which any costs (other than bidding expenses or expenses
incurred in connection with negotiating the contract) allocable to the contract are
- 38 -
[*38] incurred.24 Sec. 460(g); sec. 1.460-1(b)(7), Income Tax Regs. A cost is
“incurred” for the taxable year in which all the events have occurred that establish
the fact of the cost, the amount of the cost can be determined with reasonable
accuracy, and economic performance has occurred with respect to the cost. Sec.
1.460-1(b)(8), Income Tax Regs. (“Incurred has the meaning given in § 1.461-
1(a)(2) (concerning the taxable year a liability is incurred under the accrual
method of accounting), regardless of a taxpayer’s overall method of accounting.”).
2. Two-Year Estimate
With respect to estimating the length of a contract under section 460,
section 1.460-1(f)(4)(i), Income Tax Regs., provides:
A taxpayer must use a reasonable estimate of the time required to
complete a contract when necessary to classify the contract (e.g., to
determine whether * * * the two-year completion rule for exempt
construction contracts * * * is satisfied * * *). To be considered
reasonable, an estimate of the time required to complete the contract
must include anticipated time for delay, rework, change orders,
technology or design problems, or other problems that reasonably can
be anticipated considering the nature of the contract and prior
experience. A contract term that specifies an expected completion or
delivery date may be considered evidence that the taxpayer
24
The contract commencement date is not necessarily the same date as the
date that the contract is entered into. The regulations provide separate definitions
for the two times. Secs. 1.460-1(b)(7) (defining contract commencement date),
(c)(2) (defining the date that the contract is entered into), Income Tax Regs. And
para. (c)(2) contemplates situations where a taxpayer attempts to change his
Federal tax consequences through creative scheduling of these dates.
- 39 -
[*39] reasonably expects to complete or deliver the subject matter of the
contract on or about the date specified, especially if the contract
provides bona fide penalties for failing to meet the specified date. If
a taxpayer classifies a contract based on a reasonable estimate of
completion time, the contract will not be reclassified based on the
actual (or another reasonable estimate of) completion time. A
taxpayer’s estimate of completion time will not be considered
unreasonable if a contract is not completed within the estimated time
primarily because of unforeseeable factors not within the taxpayer’s
control, such as third-party litigation, extreme weather conditions,
strikes, or delays in securing permits or licenses.
Section 1.460-1(f)(4)(i), Income Tax Regs., provides that the taxpayer’s
estimate of the time required to complete a contract must be “reasonable”. Where,
as here, the parties disagree as to whether the two-year rule for exempt
construction contracts has been satisfied, the Court will consider all of the facts
and circumstances of a particular case to determine whether the taxpayer’s
estimate was reasonable. Further, the Court must look back to the time the
contract was entered into to decide whether the estimate was reasonable. See sec.
460(e)(1)(B)(i).
Often, a written contract objectively manifests the taxpayer’s expectations at
the time the taxpayer enters into the contract. However, the regulations do not
require the Court to make its determination with respect to the two-year rule on the
basis of the contract alone, and the dates specified in the contract are not
dispositive. See sec. 1.460-1(f)(4)(i), Income Tax Regs. (“A contract term that
- 40 -
[*40] specifies an expected completion or delivery date may be considered
evidence that the taxpayer reasonably expects to complete or deliver the subject
matter of the contract on or about the date specified[.]” (Emphasis added.)). The
facts and circumstances of this case require the Court to make a decision with
respect to the two-year rule on the basis of the contracts and the supporting
documentation in the record, Mr. Balke’s testimony, and Mr. Harris’ expert
testimony because they are the only evidence available for the Court to consider
for both the Petromaxx and Amber SPAs.
B. Petromaxx SPA
1. Contract Commencement Date
Although petitioner and Petromaxx formally executed the Petromaxx SPA
on October 28, 2006, the first date on which petitioner incurred costs allocable to
the Petromaxx SPA (other than bidding expenses or expenses incurred in
connection with negotiating the contract) was March 22, 2006, when petitioner
purchased the Cenco refinery for use in the Petromaxx SPA. Thus, for purposes of
section 460, the contract commencement date of the Petromaxx SPA was March
22, 2006. See sec. 460(g); sec. 1.460-1(b)(7) and (8), Income Tax Regs.
- 41 -
[*41] 2. Two-Year Estimate
a. Parties’ Arguments
The parties disagree as to whether petitioner reasonably estimated that the
Petromaxx SPA could have been completed within two years from the contract
commencement date of March 22, 2006. Respondent relies on the terms of the
Petromaxx SPA and Mr. Harris’ expert testimony that three years is an optimistic
estimate of the time required to complete a project similar to the Petromaxx
refinery project. Petitioner contends that its 3-D laser scanning and parallel
processing system allowed it to reasonably estimate that the Petromaxx SPA
would be completed within two years. Further, petitioner argues that Mr. Harris
did not consider petitioner’s parallel processing system when determining how
long it would take the parties to complete the Petromaxx refinery project and that
he was altogether unfamiliar with parallel processing.
b. Terms of the Petromaxx SPA
The two-year rule requires the Court to look at petitioner’s expectations at
the time it entered into the contract. See sec. 460(e)(1)(B). While dates specified
in a contract are not dispositive, the Court will first look to the terms of the
Petromaxx SPA to help determine petitioner’s expectations at the time it entered
into the SPA, October 28, 2006.
- 42 -
[*42] Section 1.460-1(f)(4)(i), Income Tax Regs., provides that a contract term
that specifies an expected completion or delivery date may be considered evidence
that the taxpayer reasonably expects to complete or deliver on or about that date,
especially if the contract provides bona fide penalties for failing to meet the
specified date. The only provision in the Petromaxx SPA that references a specific
date is with respect to petitioner’s delivery obligations. Petitioner was to “use its
best efforts” to deliver the last unit by April 30, 2007, but failure to do so would
not result in penalties; rather, petitioner would only default under the Petromaxx
SPA if it failed to deliver the last unit by September 12, 2007. The Petromaxx
SPA references a project schedule. However, the project schedule attached to the
Petromaxx SPA stated only “[to be provided by BASIC]”; the remainder of the
page was blank, and petitioner did not introduce into evidence any documents that
purport to be a project schedule.
Petitioner’s contractual obligations were not complete upon delivery of the
last refurbished unit. The parts then had to be shipped from Texas to Bulgaria and
assembled according to petitioner’s detailed modeling, and the newly assembled
refinery had to be commissioned under petitioner’s supervision and a final
acceptance report and certificate obtained upon successful testing. Only then
would petitioner’s contractual obligations be fulfilled. And the Petromaxx
- 43 -
[*43] SPA did not specify dates by when these remaining obligations were to be
complete.
Respondent introduced an expert witness report into evidence. In that
report Mr. Harris estimated how long the remaining components of the Petromaxx
refinery project would take, i.e., how long it would take to ship the delivered units
from Texas to Bulgaria; how long it would take to assemble the refinery once
Petromaxx was in possession of all of the equipment; and how long it would take
to commission and performance test the newly assembled refinery. Mr. Balke
agreed with Mr. Harris’ conclusions to the extent they were based on traditional
industry practices.
Once petitioner delivered the final unit, Petromaxx had to ship the units to
Bulgaria; Mr. Harris opined that six months was an optimistic estimate of only the
time required to ship the units to Bulgaria, which did not include the time required
to assemble the new refinery. Once Petromaxx acquired all of the equipment, it
had to assemble the refinery; Mr. Harris estimated that the assembly process alone
“could hardly be expected in less than one year.” Once Petromaxx assembled the
refinery, petitioner was required to supervise the commissioning process; Mr.
Harris estimated that the commissioning process would take six weeks. After the
commissioning process was complete, a qualified engineer was to conduct
- 44 -
[*44] performance tests and issue a final report upon successful testing; Mr. Harris
estimated that performance testing would take approximately one month. At that
point petitioner would have finally completed all of its obligations under the
Petromaxx SPA.
Even if the Court concludes that April 30, 2007 (the best efforts date)--and
not September 12, 2007 (the default date)--is the relevant delivery date despite the
Petromaxx SPA’s not calling for penalties if petitioner did not deliver the units by
then, the Petromaxx project still could not have been completed within two years
from March 22, 2006, the contract commencement date. The time between the
contract commencement date and the best efforts date was 13 months; once the
units were delivered, it would take 6 months to ship them from Texas to Bulgaria.
Upon receipt of all of the units, it would take Petromaxx 12 months to assemble
the refinery; and once the refinery was assembled, it would take approximately 2-
1'2 months to commission and conduct performance tests. In total, a project
similar to the Petromaxx refinery project would take over 33 months to complete
using traditional industry practices.
The Petromaxx SPA indicates that petitioner and Petromaxx anticipated the
final payment’s becoming due on the earlier of: (1) 10 months after the “Final
Delivery Date”, which the Petromaxx SPA defined as September 12, 2007, or (2)
- 45 -
[*45] the “Final Acceptance Date”, which was defined as the date on which the
qualified engineer issued a completion certificate.25 Assuming traditional industry
practices, this provision puts the completion date more than two years after the
contract commencement date. The Petromaxx SPA does not require the qualified
engineer to issue a completion certificate by a certain date, and 10 months after the
September 12, 2007, “Final Delivery Date” is July 12, 2008, which is more than
two years after the March 22, 2006, contract commencement date.
Under section 1.460-1(f)(4)(i), Income Tax Regs., dates specified in the
Petromaxx SPA are not dispositive in determining whether petitioner, at the time it
entered into the Petromaxx SPA, could have reasonably expected to complete the
Petromaxx project within two years from its commencement date. Accordingly,
the Court will next consider Mr. Balke’s testimony.
c. Mr. Balke’s Testimony
Petitioner acknowledges the lack of specificity in the Petromaxx SPA and
the lack of formal documentation such as a project schedule but argues that the
“parties intended for Petromaxx to begin building the * * * [refinery]
25
Although this provision of the Petromaxx SPA refers to terms of payment
and not performance, i.e., refurbishing, shipping, constructing the refinery,
commissioning, or performance testing, the Court will address this terms of
payment provision for the sake of completeness.
- 46 -
[*46] infrastructure while Petitioner was refurbishing the refinery” even though
the Petromaxx SPA is silent on the matter.26
The Petromaxx SPA is governed by Austrian law, including the United
Nations Convention on Contracts for the International Sale of Goods (CISG), Apr.
11, 1980, 1489 U.N.T.S. 59.27 The CISG embodies a liberal approach to contract
26
Specifically, petitioner’s reply brief states:
As is apparent from the contracts themselves and the testimony
at trial, Petitioner operates in a flexible and informal manner; the lack
of formal documentation of a project schedule does not prove that the
parties did not have an understanding that the * * * [refinery site]
should be completed while the refinery is being refurbished, simul-
taneously instead of subsequently. Petitioner offered testimony as a
fact witness, under oath, which is the best available evidence of its
customary business practices. Mr. Balke has established his criteria
as an experienced professional in his line of work. His testimony is
supported by the efforts taken by Petitioner to provide specifications
to Petromaxx using laser imaging at considerable cost to Petitioner.
Procuring those images immediately and providing such images at an
unusually early stage in the construction process corroborates the
testimony that the parties intended for Petromaxx to begin building
the * * * [refinery] infrastructure while Petitioner was refurbishing
the refinery.
27
CISG art. 1(1) “applies to contracts of sale of goods between parties
whose places of business are in different States: (a) when the States are
Contracting States; or (b) when the rules of private international law lead to the
application of the law of a Contracting State.” For purposes of the CISG, a party’s
place of business is the one having “the closest relationship to the contract and its
performance, having regard to the circumstances known to or contemplated by the
parties at any time before or at the conclusion of the contract.” Id. art. 10(a).
(continued...)
- 47 -
[*47] interpretation. Under the CISG a contract of sale may be proven by any
means, including witnesses; it need not be evidenced by writing and is not subject
to any other requirement as to form. Id. art. 11. Article 8 of the CISG provides:
(1) For the purposes of this Convention statements made by and
other conduct of a party are to be interpreted according to his intent
where the other party knew or could not have been unaware what the
intent was.
(2) If the preceding paragraph is not applicable, statements made by
and other conduct of a party are to be interpreted according to the
understanding that a reasonable person of the same kind as the other
party would have had in the same circumstances.
(3) In determining the intent of a party or the understanding a
reasonable person would have had, due consideration is to be given to
all relevant circumstances of the case including negotiations, any
practices which the parties have established between themselves,
usages and any subsequent conduct of the parties.
Article 8 of the CISG allows broader standards of evidence outside the
executed documents, including statements made or a party’s conduct, to determine
the intent of a party. Petitioner’s position is that even though the Petromaxx SPA
27
(...continued)
Under the Petromaxx SPA, Petromaxx’s “place of business” for purposes of the
CISG is in Bulgaria, as the refinery was to be assembled there. Petitioner’s “place
of business” for purposes of the CISG is in the United States, as petitioner
refurbished the Cenco refinery parts in the United States. Both Bulgaria and the
United States ratified the CISG. Thus, the CISG applies because there is a
contract for the sale of goods between parties whose places of business are in
different contracting States.
- 48 -
[*48] and related documents are silent with respect to anticipated performance
dates and parallel processing, petitioner’s conduct reflected the parties’ intent to
implement petitioner’s parallel processing system.
Even if the Court looks outside the terms of the Petromaxx SPA and
considers statements and conduct of the parties, petitioner did not introduce any
such evidence to support Mr. Balke’s self-serving testimony that would allow the
Court to conclude that the parties in fact agreed to implement a parallel processing
system. Petitioner did not introduce any evidence that Petromaxx “knew or could
not have been unaware what the intent was” with respect to the project’s time line.
See CISG art. 8(1). Further, because petitioner’s parallel processing system was
not the traditional way of operating in the industry, Petromaxx would not have
known or had reason to know that it should be performing its contractual
obligations simultaneously with petitioner. See id. Petitioner did not introduce
any evidence to show that Petromaxx made statements to petitioner or acted as if
the parties were conducting operations using a parallel processing system. See id.
art. 8(2) and (3). Mr. Balke further testified that he agreed with most of Mr.
Harris’ conclusions because they were based on traditional practices within the
industry. That testimony provides further support to the conclusion that
Petromaxx did not have any reason to be aware of petitioner’s expectations with
- 49 -
[*49] respect to Petromaxx’s timing for beginning and completing its contractual
obligations. See CISG art. 8(2) and (3).
Petitioner did not produce any other witnesses, provide the Court with any
documentary evidence that would reflect a meeting of the minds between the
parties to use a parallel processing system, or even explain how much time parallel
processing would save; instead petitioner relied solely on Mr. Balke’s unsupported
testimony. Although Mr. Balke has over 30 years of experience in working with
oil refineries and refinery equipment, including international dealings, he did not
provide a single concrete example of a project similar to the Petromaxx SPA
where the parties conducted operations using a parallel processing system and
which was complete within two years from its commencement date.28 Petitioner’s
28
The increased efficiency vel non of the parallel processing system does not
rescue petitioner’s expectations here. Assuming without finding that the best
efforts date is the relevant date, the two-year clock began running on March 22,
2006; the best efforts date was April 30, 2007; the parts needed to be transported
from Texas to Bulgaria, taking six months; and commissioning and testing the
refinery required an additional 2-1'2 months--leaving slightly more than two
months until the end of the two-year period for Petromaxx to assemble the refinery
according to petitioner’s detailed models. And respondent’s expert found that
through the use of traditional industry techniques, reassembly might be attained in
12 months. As discussed supra, none of these projections account for delay,
rework, or technology or design problems caused by implementing a new 3-D
scanning and modeling process. See sec. 1.460-1(f)(4)(i), Income Tax Regs.
Therefore, even if parallel processing could reduce a one-year construction project
to approximately two months, a reasonable estimate necessarily requires inclusion
(continued...)
- 50 -
[*50] actions of purchasing the Cenco refinery and beginning the refurbishing
process do not prove the intent or knowledge of Petromaxx to equally perform its
responsibilities. Petitioner simply has not introduced sufficient evidence to show
that its expectations with respect to the Petromaxx refinery project’s timeframe
differed from those projected by Mr. Harris according to traditional industry
practices or objectively manifested in the Petromaxx SPA.
d. Conclusion
The Commissioner is granted broad discretion in determining whether an
accounting method clearly reflects income, and that determination is entitled to
more than the usual presumption of correctness. Commissioner v. Hansen, 360
U.S. at 467; The Howard Hughes Co., LLC v. Commissioner, 142 T.C. at 376;
Shea Homes, Inc. v. Commissioner, 142 T.C. at 84. Petitioner simply has not met
its burden to prove that respondent’s determination was clearly arbitrary.
Respondent’s position that petitioner did not reasonably estimate that the
Petromaxx refinery project could be completed within two years is supported by
the documentation that is available for the Court to review, primarily the
28
(...continued)
of time for such unanticipated issues. Id. Petitioner offered no explanation other
than the unsupported testimony of Mr. Balke that he believed the contract could
have been completed within two years.
- 51 -
[*51] Petromaxx SPA and its amendments, and by Mr. Harris’ expert testimony.
Petitioner attempts to rebut respondent’s determination with Mr. Balke’s
testimony. However, petitioner did not introduce any other evidence to support
Mr. Balke’s testimony, and the Court is not required to accept self-serving
testimony as true. The Court concludes that petitioner did not meet its burden in
proving that, at the time it entered into the Petromaxx SPA, it reasonably believed
the contract would be completed within two years from its commencement date.
Accordingly, petitioner was not eligible to report income from the Petromaxx SPA
using the completed contract method of accounting.
C. Amber Contract
1. Contract Commencement Date
Petitioner and Amber executed the Amber SPA on July 17, 2008. The first
date on which petitioner incurred costs allocable to the Amber SPA (other than
bidding expenses or expenses incurred in connection with negotiating the
contract) was July 24, 2008, when petitioner purchased the Ataº refinery from
Toplam for use in the Amber SPA. Thus, for purposes of section 460, the contract
commencement date of the Amber SPA was July 24, 2008. See sec. 460(g); sec.
1.460-1(b)(7) and (8), Income Tax Regs.
- 52 -
[*52] 2. Two-Year Estimate
a. Parties’ Arguments
As was the case with the Petromaxx SPA, the parties disagree whether
petitioner reasonably estimated that the Amber SPA could have been completed
within two years from the contract commencement date of July 24, 2008.
Respondent argues that the terms of the Amber SPA itself show that petitioner did
not reasonably expect the SPA to be completed within two years. Respondent also
relies on Mr. Harris’ expert testimony that 4-1'2 years is an optimistic estimate of
the time required to complete a project similar to the Amber refinery project.
Petitioner again argues that its 3-D laser scanning and parallel processing system
allowed it to reasonably estimate that the Amber SPA would be completed within
two years and that Mr. Harris did not consider petitioner’s parallel processing
system when determining how long it would take the parties to complete the
Amber refinery project.
b. Terms of the Amber SPA
While the dates specified in a contract are not dispositive, the Court will
first look to the terms of the Amber SPA to help determine petitioner’s
expectations at the time it entered into the agreement. The Amber SPA is
governed by Texas law, including Article 2 of the Uniform Commercial Code
- 53 -
[*53] (UCC). Under Texas law, interpreting a written contract is primarily a
matter of “ascertain[ing] the * * * intentions of the parties as expressed in the
instrument.” Coker v. Coker, 650 S.W.2d 391, 393 (Tex. 1983). A threshold
issue in contract interpretation is whether the contract is ambiguous. A contract is
ambiguous if the terms used are reasonably susceptible of more than one meaning.
See id.
Where an unambiguous writing has been entered into between parties, the
courts will give effect to the parties’ intention as expressed or apparent in the
writing. City of Pinehurst v. Spooner Addition Water Co., 432 S.W.2d 515, 518
(Tex. 1968). In the usual case the instrument alone will be deemed to express the
intention of the parties for it is objective, not subjective, intent that controls. Id.
Generally, the parties to a contract intend every clause to have some effect and in
some measure to evidence their agreement. Id. All parts of a contract are to be
taken together, and such meaning shall be given to them as will carry out and
effect to the fullest extent the intention of the parties. Id. at 519.
The terms of the Amber SPA are not ambiguous. While the Amber SPA is
silent with respect to many anticipated performance dates, there is a significant
legal difference between ambiguous contracts and silent contracts. See Thompson
v. CPN Partners, LP, 23 S.W.3d 64, 71 (Tex. App. 2000). The only term in the
- 54 -
[*54] Amber SPA that references a specific date is with respect to petitioner’s
delivery obligations; the Amber SPA clearly states that petitioner was required to
deliver the last unit to a specified site in Turkey29 by November 15, 2010,
approximately 28 months after the July 24, 2008, contract commencement date. If
petitioner failed to deliver by November 15, 2010, petitioner was subject to
penalties; if petitioner delivered the last unit before November 15, 2010, it was
entitled to bonus payments.
Taken together, the delivery date and the potential penalties and bonus
payments indicate that the parties intended November 15, 2010, to be the
approximate date by which petitioner would deliver the last unit. This delivery
date occurred more than two years after the contract commencement date--July 24,
2008--and Amber still had to transport the refurbished parts from Turkey to
Pakistan, construct the refinery, and commission and performance test the newly
assembled refinery before petitioner would have satisfied its contractual
obligations.
29
The Amber SPA reserved the right to determine the final location of the
refinery, but at the time of executing the SPA, a location in Pakistan was the
target.
- 55 -
[*55] Because the dates specified in the Amber SPA are not dispositive with
respect to the two-year rule, see sec. 1.460-1(f)(4)(i), Income Tax Regs., the Court
will next consider Mr. Balke’s testimony.
c. Mr. Balke’s Testimony
Although the terms of the Amber SPA do not reference parallel processing
or specific dates by which the refinery had to be assembled, commissioned, and
performance tested, petitioner argues that the November 15, 2010, delivery date
was an arbitrary date selected by the parties and that the parties intended to
implement petitioner’s parallel processing system, which would have allowed the
Amber SPA to be completed within “about 18 to 24 months.”
Petitioner relies only on Mr. Balke’s unsupported testimony; petitioner did
not produce any other witnesses, provide the Court or respondent with
documentary evidence that would reflect the parties’ intent to use a parallel
processing system,30 produce any evidence to show that the parties’ conduct
reflected an intent to conduct operations using a parallel processing system, or
even explain exactly how much time parallel processing would save. Even if the
30
Unlike the Petromaxx SPA, which did not reference 3-D laser scanning
and modeling, the Amber SPA specifically refers to 3-D laser scanning and
modeling. However, like the Petromaxx SPA, the Amber SPA does not mention
parallel processing or address the purchaser’s obligations under such a system.
- 56 -
[*56] Court assumes that the parties would be completing their tasks
simultaneously, petitioner did not prove that parallel processing would allow the
parties to complete the contract within two years.
Although Mr. Balke has over 30 years of experience in working with oil
refineries and refinery equipment, including international dealings, he did not
provide a single concrete example of a project similar to the Amber refinery
project where the parties conducted operations using a parallel processing system
and completed it within two years from its commencement date. And there is no
indication that Mr. Balke’s projections took into account any unanticipated delays.
See id. Petitioner simply has not introduced sufficient evidence to show that its
expectations with respect to the Amber refinery project’s timeframe differed from
those objectively manifested in the Amber SPA.31
d. Conclusion
As with the Petromaxx refinery project, petitioner has not met its burden to
prove that respondent’s determination regarding the Amber refinery project was
arbitrary. Respondent’s position that petitioner could not have reasonably
estimated that the Amber refinery project would be completed within two years is
supported by the terms of the Amber SPA; on its face, the Amber SPA called for a
31
The parties canceled the Amber SPA on January 18, 2010.
- 57 -
[*57] delivery date more than two years after the Amber SPA commencement
date. Even if the Court considers Mr. Balke’s self-serving testimony, petitioner
did not provide any evidence to support his testimony. The Court concludes that
petitioner did not meet its burden in proving that, at the time it entered into the
Amber SPA, it reasonably expected the contract to be complete within two years
from its commencement date. Accordingly, petitioner was not eligible to report
income from the Amber project using the completed contract method of
accounting.
IV. Section 6662(a) Accuracy-Related Penalties
Section 6662(a) and (b)(1) and (2) imposes a 20% accuracy-related penalty
with respect “to any portion of an underpayment of tax required to be shown on a
return” if that underpayment is due to, among other things, negligence or a
substantial understatement of income tax. An accuracy-related penalty does not
apply to any portion of an underpayment of tax for which the taxpayer had
reasonable cause and acted in good faith. See sec. 6664(c)(1).
Section 6662(b)(2) imposes a 20% penalty on any underpayment
attributable to any “substantial understatement of income tax.” An
“understatement” generally is the excess of the amount of tax required to be shown
on the return over the amount of tax that is actually shown on the return. Sec.
- 58 -
[*58] 6662(d)(2)(A). For a C corporation, an understatement is “substantial” if it
exceeds the lesser of 10% of the tax required to be shown on the tax return (or, if
greater, $10,000) or $10 million. Sec. 6662(d)(1)(B). Under section 7491(c), the
Commissioner bears the burden of production with regard to penalties for
individual taxpayers, Higbee v. Commissioner, 116 T.C. 438, 446 (2001), but
section 7491(c) does not apply where, as here, the taxpayer is a corporation, NT,
Inc. v. Commissioner, 126 T.C. 191, 194 (2006).
Petitioner substantially understated its income tax for both 2009 and 2010,
reporting zero tax liability for each of those years. And there is no disagreement
that under either of respondent’s alternative positions, the amount of tax required
to be shown exceeds $10,000 for each year. Therefore, the Court will look next to
whether petitioner has shown that it is not liable for the penalty because of
reasonable cause. Rule 142(a); see Higbee v. Commissioner, 116 T.C. at 447.
Petitioner argues that it is not liable for the 20% accuracy-related penalty
because, in view of the complexity of section 460 and the accompanying
regulations, it made a good-faith effort to comply.
In general the accuracy-related penalty does not apply to any portion of an
underpayment of tax if it is shown that there was reasonable cause for such portion
and that the taxpayer acted in good faith. Sec. 6664(c)(1). The determination of
- 59 -
[*59] whether a taxpayer acted with reasonable cause and in good faith is made on
a case-by-case basis, taking into account all of the pertinent facts and
circumstances. Sec. 1.6664-4(b)(1), Income Tax Regs. Generally, the most
important factor is the extent of the taxpayer’s effort to assess his or her proper tax
liability. Id.
Reasonable cause requires that the taxpayer exercised ordinary business
care and prudence as to the disputed item. United States v. Boyle, 469 U.S. 241,
246 (1985). It can be shown through reasonable reliance on professional advice
on matters beyond a layperson’s understanding:
When an accountant or attorney advises a taxpayer on a matter of tax
law, such as whether a liability exists, it is reasonable for the taxpayer
to rely on that advice. Most taxpayers are not competent to discern
error in the substantive advice of an accountant or attorney. To
require the taxpayer to challenge the attorney, to seek a “second
opinion,” or to try to monitor counsel on the provisions of the Code
himself would nullify the very purpose of seeking the advice of a
presumed expert in the first place. * * *
Id. at 251; Graev v. Commissioner, 147 T.C. __, __ (slip op. at 39-40) (Nov. 30,
2016); Neonatology Assocs., P.A. v. Commissioner, 115 T.C. 43, 99 (2000), aff’d,
299 F.3d 221 (3d Cir. 2002); Freytag v. Commissioner, 89 T.C. 849, 888 (1987),
aff’d on another issue, 904 F.2d 1011 (5th Cir. 1990), aff’d, 501 U.S. 868 (1991).
- 60 -
[*60] Petitioner used the services of the same CPA from at least 2005 through
2010. However, the only evidence of petitioner’s reliance upon professional
advice rendered by its CPA is the fact that its Federal income tax returns were
filed. Nothing in the record indicates that petitioner either requested of or
received from its CPA advice regarding the application of the long-term contract
exception under section 460(e) to the Petromaxx or Amber SPAs. Based on the
absence of evidence indicating that petitioner even addressed this issue with its
CPA, the Court cannot find that it exercised ordinary business care and prudence
here.
Circumstances that may also indicate reasonable cause and good faith
include an honest misunderstanding of fact or law that is reasonable in the light of
all the facts and circumstances, including the experience, knowledge, and
education of the taxpayer. Higbee v. Commissioner, 116 T.C. at 449; sec.
1.6664-4(b)(1), Income Tax Regs.
As discussed at length supra, the Court has found unreasonable petitioner’s
alleged belief, at the time it entered into the Petromaxx and Amber SPAs, that
either contract could be completed within two years. Despite his extensive
experience in working with both domestic and international oil refinery projects,
Mr. Balke did not provide any concrete examples of previous projects that he had
- 61 -
[*61] worked on to support his claim that he thought the Petromaxx and Amber
SPAs could be completed within two years, and he agreed with Mr. Harris’
estimates with respect to each project’s duration to the extent they were based on
traditional industry practices.
Although the regulations state that dates identified in a contract are not
dispositive to the Court’s analysis, sec. 1.460-1(f)(4)(1), Income Tax Regs.,
petitioner could have controlled--at least to some extent--the various performance
dates that were specified in the SPAs. If petitioner believed that it would deliver
the last refurbished unit before the delivery dates specified, it could have provided
so in the SPAs themselves. Petitioner could have required Amber and Petromaxx
to ship the refurbished units by a certain date, complete the refinery site by a
specific date, complete assembly by a specific date, and complete commissioning
and performance testing by a certain date. However, neither SPA specified those
anticipated performance dates. The only performance dates specified in the
Amber and Petromaxx SPAs were with respect to petitioner’s delivery obligations,
and those respective dates reflect an expectation of completing each contract
within a period exceeding two years.
Although the contracts lacked specific performance dates, petitioner had
another opportunity to control completion dates by creating a project schedule.
- 62 -
[*62] Both SPAs referenced project schedules to be provided by petitioner; but the
project schedules were not included in the SPAs, and petitioner did not provide the
Court or respondent with any separate project schedule. A reasonably prudent
taxpayer would have some documentation to support its position; outside of Mr.
Balke’s testimony, petitioner did not provide the Court or respondent with any
evidence that would support its decision to account for the Petromaxx and Amber
SPAs using the completed contract method.
For the aforementioned reasons, the Court concludes that petitioner did not
act with reasonable cause and in good faith when it accounted for the Petromaxx
and Amber SPAs using the completed contract method of accounting.
Accordingly, the Court will sustain respondent's determinations with respect to the
accuracy-related penalties for 2009 and 2010.32
The Court has considered all of the arguments made by the parties, and to
the extent they are not addressed herein, they are considered unnecessary, moot,
irrelevant, or without merit.
32
Because the Court sustains the sec. 6662(a) accuracy-related penalty on
the ground of substantial understatement under sec. 6662(b)(2), the Court does not
need to decide whether the penalty should also be sustained on the ground of
negligence under sec. 6662(b)(1). Sec. 1.6662-2(c), Income Tax Regs.
- 63 -
[*63] To reflect the foregoing and the concessions of the parties,
Decision will be entered
under Rule 155.