NOT RECOMMENDED FOR FULL-TEXT PUBLICATION
File Name: 19a0061n.06
No. 18-3399
UNITED STATES COURT OF APPEALS FILED
FOR THE SIXTH CIRCUIT Feb 06, 2019
DEBORAH S. HUNT, Clerk
G.G. MARCK AND ASSOCIATES, INC., )
)
Plaintiff-Appellant, )
ON APPEAL FROM THE
)
UNITED STATES DISTRICT
v. )
COURT FOR THE
)
NORTHERN DISTRICT OF
JAMES PENG, et al., )
OHIO
)
Defendants-Appellees. )
)
BEFORE: GIBBONS, ROGERS and STRANCH, Circuit Judges.
JULIA SMITH GIBBONS, Circuit Judge. On October 19, 2005, G.G. Marck and
Associates, Inc. (“Marck”) reached an oral settlement agreement with James Peng and his
companies (“Peng”). For the next eight years, however, the parties argued over the terms of the
agreement: the district court twice vacated the settlement and reopened the case, and the Sixth
Circuit twice vacated the district court’s reopening and instructed the district court to put the
settlement back in place. On January 2, 2013, the district court finally entered a written agreement
to enforce the settlement. Four years later, on October 10, 2017, Marck filed a new complaint. It
alleged that Peng breached the 2005 oral agreement as early as November 2005 and that the breach
continued until the parties stopped litigating the case in 2013. Marck therefore requested
$1,073,172.97 in compensatory damages for breach of the 2005 settlement agreement—damages
equal to the attorneys’ fees Marck incurred in litigating the case between December 15, 2005 and
December 2, 2013.
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
Peng moved to dismiss the case, arguing that the complaint (1) was barred by Ohio’s six-
year statute of limitations for oral contracts, (2) was barred by res judicata, and (3) failed to state
a claim. The district court granted Peng’s motion, and dismissed the case under Ohio’s statute of
limitations for breach of oral contracts without considering Peng’s alternative arguments for
dismissal. We agree that the case is time-barred and affirm the district court’s dismissal of Marck’s
complaint.
I.
Marck is an Ohio corporation that makes and imports sublimation mugs—blank mugs onto
which images can be placed. Peng, a California resident, owns three companies that compete in
the sublimation mug market. In September 2005, Marck filed a complaint against Peng in the
Lucas County Common Pleas Court in Toledo, Ohio. Marck alleged various unfair competition
and trademark violations. Peng removed to the United States District Court for the Northern
District of Ohio on the basis of diversity of citizenship and federal question jurisdiction.
On October 19, 2005, during a hearing, the parties stated that they had reached an oral
settlement agreement. They read the key terms of the agreement into the record. The agreement
included mutual releases of claims and a provision that Peng would be monitored for compliance
with federal customs, importation, and transportation laws for three years. The next day, the
district court entered an order marking the case as “[s]ettled and dismissed without prejudice.”
DE4, Amended Compl., Page ID 35. The district court retained jurisdiction to vacate the order
and reopen the case “upon cause shown that the settlement has not been completed and further
litigation is necessary.” Id.
After a month of negotiations in which Marck alleged that the Peng companies refused to
sign the settlement, attempted to add new material terms, and told Marck that they were “breaching
2
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
and otherwise had repudiated and rejected the settlement,” the district court held a settlement
enforcement hearing on December 7, 2005. Id. at 36. The next day, the district court entered a
stipulated permanent injunction, signed by the parties, to effectuate the settlement.
In the weeks that followed, however, the parties were unable to reach a final, written
agreement. In large part, their dispute centered around whether Anna Peng, an officer of the Peng
companies, would be a party to the agreement. On January 23, 2006, the Peng companies emailed
Marck. They contended that they would not follow through with the agreement unless Anna Peng
was not required to sign a release. As a result of their disagreement, Marck moved to reopen the
case and the district court granted its motion on January 24, 2006.
On February 5, 2009, the Sixth Circuit vacated the district court’s reopening of the case.
G.G. Marck & Assocs., Inc. v. Peng (Marck I), 309 F. App’x 928, 935 (6th Cir. 2009). The Sixth
Circuit remanded, reasoning that the district court did not sufficiently explain the basis for granting
this exceptional relief under Fed. R. Civ. P. 60(b)(6). Id. On remand, the district court again
vacated the settlement and reopened the case on October 21, 2009. The case then “[made] a return
visit” to the Sixth Circuit. G.G. Marck & Assocs., Inc. v. North Am. Invs., Corp. (Mark II), 465 F.
App’x 515, 516 (6th Cir. 2012) (per curiam). On March 6, 2012, the Sixth Circuit again vacated
the district court’s decision to reopen the case and remanded with instructions to enforce the
settlement. Id. at 518–19. Accordingly, on January 2, 2013, the district court entered a “Settlement
Agreement and Mutual Release of All Claims,” effective October 19, 2005, and a “Final Order for
Permanent Injunction.” DE 4, Amended Compl., Page ID 42. The agreement included a clause
stating that it “constitutes the entire agreement between the parties hereto.” DE 8-5, Settlement
Agreement, Page ID 108. It also contained a section stating that any claim for attorneys’ fees or
expenses incurred after October 19, 2005 “is not released, acquitted or discharged.” Id. at 107.
3
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
The Peng companies appealed the district court’s agreement. They argued, inter alia, that
the agreement included terms that were not part of the original 2005 oral agreement. The Sixth
Circuit agreed but affirmed the agreement anyway. It explained:
[W]hen the parties originally entered their settlement into the record in 2005, they
discussed only the agreement’s basic framework. . . . The district court was thus on
solid ground in concluding that the record contained only “the agreement’s bare
essential terms,” with “additional terms” remaining to be specified. The parties,
however, never got around to writing down those additional terms. Nor could the
parties agree about what they had agreed to, even though the district court urged
them to work these differences out themselves. The parties thus saddled the district
court with the unsought responsibility of figuring out just what the unrecorded
terms of the parties’ settlement were. We can discern no clear error in the district
court’s execution of this factual task—and Peng’s appellate briefs offer no basis for
finding one.
G.G. Marck & Assocs. Inc. v. Peng (Marck III), No. 13-3015, 2013 U.S. App. LEXIS 26529, at
*5–6 (6th Cir. Sept. 3, 2013). On December 2, 2013, the Peng companies provided a signed release
from Anna Peng.
The case stayed quiet for four years. Then, in August 2017, Marck filed a motion for
sanctions, contending that the Peng companies acted in bad faith by failing “to timely comply with
the essential terms of the settlement agreement.” DE 15, Order, Page ID 478. Marck requested
that the Peng companies pay its attorneys’ fees and costs incurred between December 15, 2005
and December 2, 2013.
On October 10, 2017, while the sanctions motion was pending, Marck filed a new
complaint—from which the current appeal stems—alleging the Peng companies breached the
October 19, 2005 settlement agreement. Marck requested $1,073,173 in compensatory damages—
equal to the amount Marck incurred in attorneys’ fees between December 15, 2005 and December
2, 2013. Marck alleged that the Peng companies:
4
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
[1] breach[ed], reject[ed], and repudiate[ed] the Settlement Framework terms of
October 19, 2005 that were read into the record of the District Court in the
Initial Lawsuit;
[2] refus[ed] to timely cooperate in the reduction of the Settlement Framework
terms into writing;
[3] fail[ed] to timely provide signed Mutual Releases for each of the Peng
Defendants;
[4] fail[ed] to timely provide a Mutual Release signed by Anna Peng;
[5] fail[ed] to timely seek Anna Peng’s cooperation in the execution of a Mutual
Release signed by Anna Peng; [and]
[6] continu[ed] to litigate without completing the required settlement including, but
not limited to, executing a Settlement and Mutual Releases, and producing a
Release executed by Anna Peng.
DE 4, Amended Compl., Page ID 43–44.
The Peng companies filed a motion to dismiss Marck’s complaint. They argued that the
complaint (1) was barred by Ohio’s six-year statute of limitations for oral contracts, (2) was barred
by res judicata, and (3) failed to state a claim.
The district court consolidated Marck’s motion for sanctions and new amended complaint.
It denied sanctions and dismissed the complaint. The court found that Ohio’s six-year statute of
limitations for oral agreements applied and that the statute was not tolled at any point. The district
court therefore concluded that since the statute of limitations began running when the alleged
breach occurred, at the latest, in January 2006, Marck’s 2017 complaint was barred by the six-year
statute of limitations. The district court did not address the Peng companies’ alternative theories
for dismissal. Marck timely appealed, contending that Ohio’s six-year statute of limitations for
oral contracts did not bar its suit.
II.
This court reviews de novo a district court’s grant of a motion to dismiss on statute of
limitation grounds. Am. Premier Underwriters, Inc. v. Nat’l R.R. Passenger Corp., 839 F.3d 458,
461 (6th Cir. 2016). Although the statute of limitations is an affirmative defense and “a plaintiff
5
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
generally need not plead the lack of affirmative defenses to state a valid claim,” the court can
dismiss the claim if “the allegations in the complaint affirmatively show that the claim is time-
barred.” Cataldo v. U.S. Steel Corp, 676 F.3d 542, 547 (6th Cir. 2012). When the allegations
show that relief is barred by the applicable statute of limitations, dismissal is proper under Fed. R.
Civ. P. 12(b)(6) for failure to state a claim. Id.
In assessing a motion to dismiss under Rule 12(b)(6), this court “construes the complaint
in the light most favorable to the plaintiff, accepts the plaintiff’s factual allegations as true, and
determines whether the complaint ‘contain[s] sufficient factual matter, accepted as true, to state a
claim to relief that is plausible on its face.’” Heinrich v. Waiting Angels Adoption Servs., Inc., 668
F.3d 393, 403 (6th Cir. 2012) (alteration in original) (quoting Ashcroft v. Iqbal, 556 U.S. 662, 678
(2009)). A claim has facial plausibility when the plaintiff “pleads factual content that allows the
court to draw the reasonable inference that the defendant is liable for the misconduct alleged.”
Iqbal, 556 U.S. at 678 (citing Bell Atl. Corp. v. Twombly, 550 U.S. 544, 556 (2007)). The
plausibility standard “asks for more than a sheer possibility that a defendant has acted unlawfully”
but is not akin to a probability requirement. Id. In conducting this analysis, a court “primarily
considers the allegations in the complaint, although matters of public record, orders, items
appearing in the record of the case, and exhibits attached to the complaint also may be taken into
account.” Amini v. Oberlin Coll., 259 F.3d 493, 502 (6th Cir. 2001) (quoting Neiman v. NLO, Inc.,
108 F.3d 1546, 1554 (6th Cir. 1997)).
III.
On appeal, Marck argues that the district court erred in finding that its complaint for breach
of contract was time-barred. We disagree. First, the statute of limitations began running when the
cause of action began accruing—at the earliest in November 2005, and at the latest, in January
6
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
2006. Second, the 2013 written agreement does not alter when the statute of limitations for breach
of the 2005 agreement began running. Third, even if the statute was tolled when the district court
reopened the case between January 24, 2006 and March 6, 2012, Marck’s complaint still is
untimely. We therefore affirm the district court’s dismissal of Marck’s complaint.
A.
Marck’s complaint alleges breach of contract, and the defendants removed to federal court
on the basis of diversity of citizenship. Thus, this court applies the substantive law of the forum
state—Ohio—and federal procedural law. Biegas v. Quickway Carriers, Inc., 573 F.3d 365, 374
(6th Cir. 2009) (“Under the Erie doctrine, federal courts sitting in diversity apply the substantive
law of the forum state and federal procedural law.”) (citing Erie R.R. Co. v. Tompkins, 304 U.S.
64 (1938)). In applying Ohio law, this court “must follow the decisions of the state’s highest court
when that court has addressed the relevant issue.” Savedoff v. Access Grp., Inc., 524 F.3d 754,
762 (6th Cir. 2008) (internal quotation marks omitted). If the highest court has not yet answered
the precise question at hand, this court “must predict how the [state] court would rule by looking
to all the available data, including intermediate appellate decisions.” Lutz v. Chesapeake
Appalachia, L.L.C., 717 F.3d 459, 464 (6th Cir. 2013) (internal citations omitted). Thus, this court
must determine whether Marck’s complaint was time-barred under Ohio contract law.
Under Ohio law, when parties enter into an oral settlement agreement in court, the
agreement constitutes “a binding and enforceable contract.” Tabbaa v. Koglman, 777 N.E.2d 338,
341 (Ohio Ct. App. 2002). Ohio’s general rule is that “a breach of contract action accrues when
the breach occurs or when the complaining party suffers actual damages as a result of the breach.”
Lutz, 717 F.3d at 473 (citing Columbus Green Bldg. Forum v. State, 980 N.E.2d 1, 10 (Ohio Ct.
7
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
App. 2012)). When the “terms of a contract are clearly repudiated by a party,” “a cause of action
for breach of contract accrues only once—at the time of repudiation.” Id. at 468 n.7.
The Ohio Revised Code Chapter 2305 provides the statutes of limitations for breach of
contract claims. If the contract is oral, parties have up to six years after the cause of action accrues
to file suit. Id. § 2305.07. If the contract is written, parties are afforded eight years.1 Id. § 2305.06.
Here, Marck alleges breach of “[t]he settlement agreement reached on October 19, 2005.”
DE 4, Amended Compl., Page ID 43. The October 19 agreement was oral. Marck II, 465 F. App’x
at 516 (“In October 2005, the parties reached an oral settlement agreement.”). That hearing
transcript is the only written document discussed by the parties describing an agreement reached
in October 2005, and a transcript is not a writing sufficient to convert an oral agreement into a
written one. See, e.g., Smith v. ABN AMRO Mortg. Grp., Inc., 434 F. App’x 454, 461–62 (6th Cir.
2011) (concluding that “the parties reached an oral settlement agreement” even though the district
court read the “basic settlement terms” into the record); Selvage v. Emnett, 909 N.E.2d 143, 146–
47 (Ohio Ct. App. 2009) (determining that “the parties reached a valid oral agreement to settle the
case” based on the terms of the agreement read into the record). Thus, the applicable statute of
limitations for breach of the oral contract was six years. Ohio Rev. Code § 2305.07.
Since the clock starts when breach or repudiation occurs, see Lutz, 717 F.3d at 468 n.7,
473, Marck’s action began accruing as early as November 16, 2005 and as late as January 23,
2006. In its complaint, Marck contended that on November 16, 2005, Peng’s attorney “told
Marck’s counsel that the Peng Defendants were breaching and otherwise had repudiated and
1
On appeal, Marck argues that the eight-year statute of limitations for written agreements should apply.
Marck is correct that the current Ohio Revised Code contains an eight-year statute for claims involving breach of
written contracts. Ohio Rev. Code § 2305.06. But because the alleged breach occurred prior to 2012, the applicable
statute of limitations for a written contract would likely be fifteen years. See Browne v. Artex Oil Co., No. 17 CA 20,
--- N.E.3d ---, 2018 WL 4471737, at *4 n.1 (Ohio Ct. App. May 31, 2018) (“The statute was amended from fifteen
years to eight years, effective September 28, 2012.”). This discrepancy is inconsequential, however, because Marck’s
complaint alleges breach of an oral contract.
8
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
rejected the settlement and Settlement Framework terms.” DE 4, Amended Compl., Page ID 36
(emphasis added). Additionally, Marck asserts that on January 23, 2006, Peng’s attorney emailed
Marck and “confirmed there would be no settlement on the terms reached on October 19, 2005.”
Id. at 37. Construing the complaint in the light most favorable to Marck, see Heinrich, 668 F.3d
at 403, we will assume the claim began accruing on January 23, 2006.
Marck filed the complaint for breach and repudiation of the October 2005 agreement on
October 10, 2017—eleven years and eight months after January 23, 2006. Therefore, under Ohio’s
six-year statute of limitations for oral contracts, Marck’s complaint is time-barred. See Ohio Rev.
Code § 2305.07.
B.
The later 2013 written agreement—whether it memorialized or integrated the previous oral
agreement—does not alter our conclusion.
1.
First, Marck argues that “the settlement agreement of January 2, 2013 is a written contract”
and “memorialization of the settlement.” CA6 R. 15, Marck Br., at 30. It therefore contends that
the eight-year statute of limitations for written contracts applies and that it did not begin running
until the agreement was written on January 2, 2013. We disagree.
Despite later memorialization, the six-year statute of limitations for oral contracts governs
this dispute. When an oral contract’s terms are later memorialized in writing, the six-year statute
of limitations applies because the written memorialization “does not convert the oral contract into
a contract in writing” so long as the litigant “does not seek to enforce [the later written agreement]
as a distinct instrument.” First Nat’l Sec. Corp. v. Hott, 122 N.E.2d 777, 778–79 (Ohio 1954); see
9
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
also Joseph W. Diemert, Jr. & Assocs. Co. v. Rubenstein, Novak, Einbund & Pavlik, No. 76575,
2000 WL 1038177, at *2–3 (Ohio Ct. App. July 27, 2000).
Second, when an agreement is memorialized does not affect when the statute of limitations
begins accruing. Under Ohio law, a valid oral agreement has the same binding effect as a valid
written agreement. RE/MAX Int’l, Inc. v. Realty One, Inc., 271 F.3d 633, 646 (6th Cir. 2001)
(applying Ohio contract law). Thus, parties can breach an oral agreement in the same way they
can breach a written agreement, and a cause of action for breach of contract accrues when the
breach occurs. Lutz, 717 F.3d at 473 (citing Columbus Green Bldg. Forum, 980 N.E.2d at 10).
Thus, the relevant starting point for a breach of contract action is when the breach occurs, not when
the terms are memorialized.
Here, Marck alleged that the Peng companies breached the “terms of October 19, 2005.”
DE 4, Amended Comp., Page ID 45. Thus, Marck does not “seek to enforce [the 2013 agreement]
as a distinct instrument.” First Nat’l Sec. Corp., 122 N.E.2d at 778. Rather, Marck’s complaint
explicitly alleges breach of the 2005 agreement, and the later memorialization does not convert the
earlier agreement into a written one for statute of limitations purposes. Thus, even if the 2013
agreement is a “lawful memorialization of the settlement,” the oral six-year statute still applies,
and it began running when the breach first occurred.
2.
Similarly, Marck’s argument about integration is not persuasive. Under Ohio law, when a
written agreement is completely integrated, it is the “single and final memorial of the
understanding of the parties,” and “prior and contemporaneous negotiations, oral or written, are
excluded.” Galmish v. Cicchini, 90 Ohio St.3d 22, 27 (2000). Thus, a fully integrated agreement
“cannot be modified by evidence of earlier or contemporaneous agreements that might add to,
10
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
vary, or contradict the writing.” Bellman v. Am. Int’l Grp., 865 N.E.2d 853, 857 (Ohio 2007)
(citation omitted).
Here, Marck argues that the 2013 agreement entirely replaced the earlier oral agreement
through its integration clause, and therefore the statute of limitations for written contracts applied
and began running in January 2013. Marck is correct that the 2013 agreement states that it
“constitutes the entire agreement between the parties.” DE 8-5, Settlement Agreement, Page ID
108. But the district court’s own explanation of the written agreement indicates that it does not
entirely replace the 2005 agreement. When the district court entered the 2013 agreement, it noted
that it “[did] not alter the effect of the settlement entered by the parties on October 19, 2005.” DE
8-4, Order, Page ID 103. And even if the 2013 agreement was fully integrated, Marck cites no
Ohio caselaw construing a suit under a preexisting oral agreement as brought under a subsequent,
fully integrated agreement. To the contrary, when an Ohio appellate court concluded, based on an
integration clause, that a written Service and License Agreement was “the entire agreement
between the parties” as to the development of a certain software platform, it promptly affirmed the
grant of judgment on the pleadings on all of the plaintiff’s claims “arising out of the alleged oral
development contract.” Fontbank, Inc. v. CompuServe, Inc., 742 N.E.2d 674, 679 (Ohio Ct. App.
2000).
Moreover, Marck alleges breach as early as November 2005—far before the 2013
agreement came into existence. Marck’s complaint “only refers to the 2013 agreement in passing
and does not seek relief for any breach or failure to comply with that agreement.” DE 15, Order,
Page ID 486. Thus, whether or not the 2013 agreement was fully integrated is not dispositive
because Marck does not allege breach of the 2013 agreement. It explicitly requests relief for
breach of the 2005 oral agreement.
11
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
3.
Marck also argues that the 2013 agreement is a separate agreement that allows recovery
for breach of the earlier oral agreement. In Ohio, while “a prevailing party in a civil action may
not recover attorney fees as part of the costs of litigation,” there is an exception for breach of
settlement agreements that “specifically provide[] for the losing party to pay the prevailing party’s
attorney fees or when the prevailing party demonstrates bad faith on the part of the unsuccessful
litigant.” Wilborn v. Bank One Corp., 906 N.E.2d 396, 400 (Ohio 2009). “When a party breaches
a settlement agreement to end litigation and the breach causes a party to incur attorney fees in
continuing litigation, those fees are recoverable as compensatory damages in a breach of settlement
claim.” Tejada-Hercules v. State Auto. Ins. Co., No. 08AP-150, 2008 WL 4416534, at *3 (Ohio
Ct. App. Sept. 30, 2008) (citation omitted).
Here, Marck argues that under the 2013 agreement, it “could seek recovery of its attorneys’
fees and costs incurred from October 19, 2005, forward.” CA6 R. 22, Marck Reply Br., at 2. But
while Marck’s underlying theory—that it could seek compensatory damages for breach in the
amount incurred as attorneys’ fees stemming from Peng’s failure to adhere to the oral settlement
agreement—may be warranted under Wilborn, this theory is unrelated to calculating when the
statute of limitations expired. Wilborn provides a vehicle through which Marck could request
compensatory damages equal to attorneys’ fees—but Marck’s suit is still a breach of contract suit
subject to the applicable statute of limitations.
C.
1.
Lastly, even if the statute of limitations was tolled when the district court reopened the
case, Marck’s suit is still time-barred. Marck contends that “any Statute of Limitations that may
12
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
have applied did not run, or was tolled[,] between January 23, 2006, with the Order ‘destroying’
and ‘superseding’ [the] settlement, and March 6, 2012, when the appellate court found and ordered
that there was a settlement to be enforced, vacating the last judgment for monetary damages.”
CA6 R. 15, Marck Br., at 37.
But even if we assume that the statute was tolled when the district court reopened the case,
Marck’s complaint is still time-barred because the case was not open for the entire time that Marck
contends it was. Rather, the settlement was alive again between February 5, 2009, when the Sixth
Circuit vacated the district court’s reopening, and October 21, 2009, when the district court again
reopened the case. Thus, if the statute of limitations was tolled when the case was reopened, the
proper calculation would be between January 23, 2006 and February 5, 2009, and then again
between October 21, 2009 and March 6, 2012. Accounting for 1976 days of potential tolling,
Marck still filed its complaint six years, three months, and 21 days after the claim began accruing.
Its complaint is therefore time-barred under Ohio’s six-year statute of limitations for oral contracts.
2.
Finally, this case does not present extraordinary circumstances in which to apply the
equitable tolling doctrine. Ohio state law governs the analysis. See Weikle v. Skorepa, 69 F. App’x
684, 687 (6th Cir. 2003) (“We have generally held that . . . tolling principles are governed by state
law, except when dealing with federal claims or in unusual cases where doing so would produce
an outcome substantially different from the outcome that would have been obtained in state
court.”) (internal citations and quotation marks omitted). Under Ohio law, “[a] litigant seeking
equitable tolling must demonstrate that he or she diligently pursued his or her rights, but some
extraordinary circumstance stood in his or her way and prevented timely action.” Lottridge v.
Gahanna-Creekside Invs., L.L.C., 36 N.E.3d 744, 753 (Ohio Ct. App. 2015). Equitable tolling is
13
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
“to be applied sparingly and only in exceptional circumstances.” Id. With regard to breach of
contract claims, the Ohio Court of Appeals has noted that the statute of limitations is not tolled
when “a party chooses to seek redress by filing a motion to enforce the terms of a settlement
agreement rather than an independent action sounding in breach of contract.” Castle King L.L.C.
v. Attorney Gen. of Ohio, No. 10AP-735, 2011 WL 1137299, at *3 (Ohio Ct. App. Mar. 29, 2011).
Here, Marck does not present a compelling case for equitable tolling. Marck argues that
this court should apply the equitable tolling doctrine because “[i]t would have been inequitable to
require Marck to file a lawsuit flowing from the breach of a settlement that simply did not exist
and could not be enforced as a matter of law between January 23, 2006 and March 6, 2012—a
period of more than 6 years itself.” CA6 R. 15, Marck Br., at 40. But Marck has not demonstrated
that it “diligently pursued [its] rights” and that “some extraordinary circumstance” stood in its way.
Lottridge, 36 N.E.3d at 753. Rather, Marck argues that it could not bring a breach of contract
claim earlier because the district court had reopened the case between January 2006 and March
2012. Marck, however, is the party who moved to have the settlement enforced in 2005 and the
case reopened in January 2006. At Marck’s request, the district court reopened it. Instead of
requesting that the district court reopen the case, Marck could have immediately sued for breach
of contract. Marck chose not to. Where a party could bring an independent action sounding in
breach of contract but chooses to take another route—as Marck did—there are not “extraordinary
circumstances” that compel equitable tolling. See Castle King L.L.C., 2011 WL 1137299, at *3;
Lottridge, 36 N.E.3d at 753.
Second, the heart of Marck’s argument is that it was unfair to expect it to bring its claim
while the case was reopened. But even if we agree with this reasoning, there is no support for
otherwise tolling the statute of limitations past when the district court reopened the case. Marck
14
No. 18-3399
G.G. Marck and Associates v. James Peng, et al.
alleged breach of contract almost twelve years after becoming aware of the breach. With no
tolling, Marck’s statute of limitations expired on January 23, 2012. If we credit Marck’s argument
and assume the statute was paused when the district court reopened the case, its clock ran out on
June 14, 2017. But Marck did not file its complaint until October 10, 2017. Marck does not
provide any support for why we should not only toll the statute during the time when the case was
reopened but also for an additional three months.
IV.
For the reasons stated, we affirm the district court’s grant of Peng’s motion to dismiss the
case under Ohio’s six-year statute of limitations for breach of contract.
15