PUBLISHED
UNITED STATES COURT OF APPEALS
FOR THE FOURTH CIRCUIT
No. 17-2226
NCO FINANCIAL SYSTEMS, INCORPORATED, now known as EGS Financial
Care, Inc.,
Plaintiff - Appellee,
v.
MONTGOMERY PARK, LLC,
Defendant - Appellant.
Appeal from the United States District Court for the District of Maryland, at Baltimore.
George L. Russell, III, District Judge. (1:11-cv-01020-GLR)
Argued: November 1, 2018 Decided: March 15, 2019
Amended: March 15, 2019
Before GREGORY, Chief Judge, and NIEMEYER and HARRIS, Circuit Judges.
Vacated and remanded by published opinion. Judge Niemeyer wrote the opinion, in
which Chief Judge Gregory and Judge Harris joined.
ARGUED: Howard G. Goldberg, GOLDBERG & BANKS, PC, Baltimore, Maryland,
for Appellant. Andrew D. Levy, BROWN, GOLDSTEIN & LEVY, LLP, Baltimore,
Maryland, for Appellee. ON BRIEF: Joshua R. Treem, Kevin D. Docherty, Anthony J.
May, BROWN, GOLDSTEIN & LEVY, LLP, Baltimore, Maryland, for Appellee.
NIEMEYER, Circuit Judge:
This case, which involves disputes between parties to a 12-year commercial lease
of office space in Baltimore, Maryland, comes to us for a second time. In the prior
appeal, we held that NCO Financial Systems, Inc. (the lessee) had failed to properly
exercise its right of early termination of the lease agreement between it and Montgomery
Park, LLC (the lessor) and had, by failing to pay rent thereafter, breached the agreement.
NCO Fin. Sys., Inc. v. Montgomery Park, LLC, 842 F.3d 816, 821–23 (4th Cir. 2016).
Accordingly, we remanded the case for further proceedings on Montgomery Park’s claim
for damages.
On remand, the district court conducted a bench trial at which it received evidence
regarding Montgomery Park’s damages and whether Montgomery Park had, as required
by the lease agreement, used “reasonable commercial efforts” to mitigate its damages.
The court concluded that Montgomery Park failed to use reasonable commercial efforts
to mitigate its damages and that this failure was a condition precedent to any damage
recovery. It therefore denied Montgomery Park any damages for NCO’s breach.
On appeal, Montgomery Park contends that the district court erred (1) by
concluding that the obligation to mitigate damages was a condition precedent to the
recovery of any damages and therefore that the failure to satisfy that condition completely
barred recovery, rather than merely reduced the amount of recoverable damages, and
(2) by concluding that Montgomery Park’s obligation to mitigate damages meant that it
“was under a contractual duty to give special care and attention” to the space previously
2
leased by NCO and therefore that marketing efforts directed at leasing all vacant spaces
in the building were largely irrelevant.
We agree with Montgomery Park on both points and therefore vacate the district
court’s judgment and remand for further proceedings consistent with this opinion. First,
we conclude that the district court misconstrued the lease agreement and misapplied
Maryland law in concluding that Montgomery Park had a duty to “endeavor to re-let the
premises and minimize [its] damages as a condition precedent to recovering” against
NCO. (Emphasis added). Because the lease agreement’s language incorporated the
common law mitigation-of-damages doctrine, which holds that a plaintiff cannot recover
damages which it could have reasonably avoided, Montgomery Park’s recovery should
only have been reduced by the amount of rent that NCO could demonstrate would have
been recovered by reasonable efforts to re-let the space. Second, we conclude that the
district court, in evaluating the commercial reasonableness of Montgomery Park’s
mitigation efforts, applied the wrong standard. Reasonable commercial efforts to
mitigate damages did not require Montgomery Park to favor NCO’s space over other
vacant space in the building. Rather, commercial reasonableness only required
Montgomery Park to reasonably market NCO’s space on an equal footing with the other
spaces that it was seeking to rent.
I
Beginning on March 15, 2003, Montgomery Park leased over 100,000 square feet
of office space to NCO in a building located on Washington Park Boulevard in
3
Baltimore, Maryland. The initial term of the lease was 12 years, but NCO had a limited
right to terminate the lease after 8 years, provided that it gave timely notice and made
timely payment of a termination fee equal to 10 months’ rent.
In the prior appeal in this case, we concluded that while NCO manifested its intent
to exercise the early termination option, it failed to satisfy the lease agreement’s
conditions precedent for doing so. We therefore held that NCO had a continuing
obligation to pay rent, even though it had vacated the premises. Thus, we remanded the
case to the district court for further proceedings on Montgomery Park’s claim for
damages. See NCO Fin. Sys., 842 F.3d at 822–25.
On remand, the district court conducted a bench trial on damages, at which it
considered whether Montgomery Park had used “reasonable commercial efforts” to
mitigate its damages, as required in § 14.03 of the lease agreement. That section, entitled
“Remedies,” authorized Montgomery Park to re-let the NCO premises once NCO
breached the lease and vacated the building. It provided further:
Landlord shall not be liable for, nor shall Tenant’s obligations hereunder be
diminished by reason of, any failure by Landlord to relet the Premises or
any failure by Landlord to collect any rent due upon such reletting, but
Landlord does agree to use reasonable commercial efforts to mitigate
damages caused by any Event of Default or if Tenant shall surrender the
Premises back to Landlord for such purpose. No action taken by the
Landlord under the provisions of this section shall operate as a waiver of
any right which the Landlord would otherwise have against the Tenant for
the Rent hereby reserved or otherwise, and the Tenant shall at all times
remain responsible to the Landlord for any loss and/or damage suffered by
the Landlord by reason of any Event of Default, provided that in no event
shall Tenant be liable for consequential damages . . . .
4
(Emphasis added). After concluding that this provision required Montgomery Park to
take commercially reasonable steps to re-let the NCO space “from the date that NCO
vacated the property,” the court found that Montgomery Park had not used reasonable
commercial efforts to find a replacement tenant for the NCO space. In articulating the
standard that it applied, the court stated that “if you had the real estate space that you
need to lease, reasonable efforts require that you advertise it and promote it specifically
and not generally as part of an overall scheme to fill a larger vacant space.” (Emphasis
added). The court concluded that Montgomery Park had failed to target its efforts,
emphasizing that although Montgomery Park had taken substantial steps to market the
building as a whole — which included NCO’s space — it had done much less to market
the NCO space specifically:
Montgomery Park . . . engaged in significant effort, including the creation
of brochures; hanging banners; engaging with prospective tenants;
conducting tours of the premises, including several tours of the NCO space;
and holding meetings regarding leasing the Montgomery space in general.
But these efforts were designed only to market Montgomery Park space as
a whole, with no serious effort to target or re-lease NCO space, as they
were obligated to do.
(Emphasis added). The court added that Montgomery Park’s monthly marketing
meetings “were never geared . . . to treat the NCO premises any different than any other
premises within the Montgomery Park property” and that Montgomery Park’s marketing
reports, which had been admitted into evidence, “shed little, if any, light on a plan to
specifically market the NCO premises.” The court also dismissed the instances where
Montgomery Park offered the NCO space to prospective tenants, citing the fact that
5
Montgomery Park had, among other things, also offered those prospects alternative
spaces:
The prospects identified by Montgomery Park as being interested in the
NCO premises . . . were offered space either while NCO still occupied the
premises; were offered premises other than the NCO premises; when
offered the NCO premises, the NCO premises was listed as an alternative
space, a last alternative space for leasing, or almost last alternative space
for leasing, or the offer failed to provide any benefit or provided little
benefit to NCO regarding its rental obligations because the offer included
free rent. As a result, such efforts did not meet the commercial reasonable
efforts required under the lease or by industry standard.
In short, under the standard that the district court applied, “Montgomery Park was under a
contractual duty to give special care and attention to NCO,” and thus generalized efforts
directed at leasing the building as a whole were insufficient.
The district court also took issue with Montgomery Park’s lack of a formalized
marketing plan, noting that “[n]o written marketing plan was ever created related to the
NCO space or to Montgomery Park, the property, in general.” The court reasoned that:
[A]s part of its obligation to exercise reasonable commercial efforts,
[Montgomery Park] was required by contract or by industry standards to
put a written marketing plan in place given the challenges of the particular
property. This marketing plan would include an evaluation of the NCO
space, a list of prospects for the NCO space, specific timetables and goals
for re-listing the NCO space, and methods of advertising the NCO space.
The court accordingly concluded that “the failure to create a marketing plan for the NCO
premises was commercially unreasonable at the outset of the vacancy.”
Further, the court pointed out that Montgomery Park failed to update its “CoStar”
listing to reflect the vacancy of the NCO premises. CoStar is an online database used by
real estate brokers and owners to list available commercial properties and is considered to
6
be “the leading provider of commercial real estate information and data” in the United
States. Montgomery Park maintained an active CoStar listing but, after NCO vacated the
property, it did not update the listing to reflect the change, meaning that the listing
continued to show the NCO premises as occupied. The district court concluded that “the
failure to advertise the NCO premises as available on CoStar was intentional” and that
such failure was motivated by Montgomery Park’s “concern[] that listing an additional
100,000 square feet as being available on CoStar . . . would lead to a bad impression of
the building, thus stagnating leasing opportunities.” The court noted that to address this
concern “Montgomery Park . . . could have [instead] listed the NCO premises as
available and simply made space that had been deemed available for leasing
unavailable.”
Finally, the court found that Montgomery Park made no significant efforts to
subdivide the NCO space, concluding that “Montgomery Park failed to conduct a cost-
benefit analysis of subdividing the space to determine whether such mitigation was even
practical” and that “the failure to create such an analysis was . . . commercially
unreasonable.”
Having concluded that Montgomery Park failed to use commercially reasonable
efforts to re-let the NCO space, the district court then held that such failure precluded
Montgomery Park from recovering any damages whatsoever. The court reasoned that “if
a tenant has abandoned the leased premises and there is a breach of contract action for
damages, like in this case, the landlord must endeavor to re-let and minimize his damages
as a condition precedent to recovering against the original tenant.” (Emphasis added)
7
(citing Circuit City Stores, Inc. v. Rockville Pike Joint Venture Ltd. P’ship, 829 A.2d 976
(Md. 2003)). Thus, the court reasoned, “from and after the time that the landlord
breached its contractual obligations to mitigate damages, the landlord is entitled to no
further payment from the tenant.” It concluded that “[b]ecause . . . Montgomery Park
breached the lease from the date that NCO vacated the property due to [its] failure to use
reasonable commercial efforts to [re-let] the NCO premises, . . . Montgomery Park is not
entitled to any damages.”
From the district court’s judgment dated October 11, 2017, Montgomery Park
filed this appeal.
II
Montgomery Park contends that the requirement in the lease agreement that it use
reasonable commercial efforts to mitigate damages is not, as the district court held, “a
condition precedent to [its right] to recover its lost rent due to [NCO’s] default” and that
the district court accordingly erred in treating it as such. In support of its position,
Montgomery Park contrasts the language at issue here with the language we addressed in
the prior appeal, noting that the “language employed with regard to [its] obligation to use
reasonable commercial efforts contains no language similar to the conditional language
employed with regard to the early termination provision.” Rather than imposing a
condition precedent to any recovery, Montgomery Park argues that the lease agreement
incorporated the mitigation-of-damages doctrine, as that doctrine has been applied under
Maryland contract law. And proper application of that doctrine here would require NCO
8
to “prove the net loss resulting from Montgomery Park’s failure to [mitigate damages]”
and the district court then to reduce recovery by that amount. In short, Montgomery Park
argues that the district court erred by foreclosing recovery altogether.
NCO amplifies the district court’s position, contending that when both parties to a
contract breach their obligations, courts should decline to award any contract damages. It
argues that:
[U]nder both Maryland law and general contract law, courts have held that
in some instances where both parties are at fault (or in default) neither may
recover. . . . Whether this doctrine is described as failure of consideration,
failure to satisfy a condition precedent, or mutual breach of contract, it is
clear that in proper circumstances a court may refuse to allow recovery by
either party to an agreement because of their mutual fault, which in contract
terms might be more properly described as mutual default.
(quoting Westinghouse Elec. Corp. v. Garrett Corp., 601 F.2d 155, 158 (4th Cir. 1979)
(citations omitted) (emphasis added)). NCO maintains that Montgomery Park’s failure to
mitigate damages — whether labeled a mutual breach, a failure to satisfy a condition
precedent, or a failure of consideration — bars Montgomery Park from recovering any
damages whatsoever.
We agree with Montgomery Park’s reading of the lease agreement and its
application of Maryland law. First, the lease agreement itself clearly does not make the
obligation to mitigate damages a condition precedent to recovery for breach of the
agreement. To the contrary, the relevant portion of the lease provides:
Landlord shall not be liable for, nor shall Tenant’s obligations hereunder
be diminished by reason of, any failure by Landlord to relet the Premises or
any failure by Landlord to collect any rent due upon such reletting, but
Landlord does agree to use reasonable commercial efforts to mitigate
damages caused by any Event of Default or if Tenant shall surrender the
9
Premises back to Landlord for such purpose. No action taken by the
Landlord under the provisions of this section shall operate as a waiver of
any right which the Landlord would otherwise have against the Tenant for
the Rent hereby reserved or otherwise, and the Tenant shall at all times
remain responsible to the Landlord for any loss and/or damage suffered by
the Landlord by reason of any Event of Default, provided that in no event
shall Tenant be liable for consequential damages . . . .
(Emphasis added). Far from imposing a condition precedent to Montgomery Park’s
recovery of damages, this provision makes clear that NCO “shall at all times remain
responsible” for any loss suffered due to its breach of the agreement and states further
that “[n]o action taken by [Montgomery Park] under the provisions of this section shall
operate as a waiver of any right [Montgomery Park] would otherwise have against
[NCO].” Moreover, the language of this provision is totally unlike that of the provision
construed in the first appeal, where we concluded that the language imposed a condition
precedent to early termination. The provision in the first appeal imposed conditions to
early termination that were subject to “strict compliance” such that early termination
would be effective “if and only if” the conditions were met. NCO Fin. Sys., 842 F.3d at
822.
We also agree with Montgomery Park that its lease obligation to “use reasonable
commercial efforts to mitigate damages caused by any Event of Default” must be read as
incorporating the mitigation-of-damages doctrine. This doctrine, which is rooted in the
“avoidable consequences” rule of contract damages, applies only after a breach has
already occurred and functions to decrease a plaintiff’s recovery for that breach. In this
respect, the “duty” to mitigate damages is not one of the mutual duties going to the
10
essence and nature of the contract. As the Maryland Court of Special Appeals has
explained:
The doctrine of minimization of damages is not a defense to a plaintiff’s
cause of action, whether that cause of action be one based in negligence or
contract; rather, it is a “disability on (or a ‘no right’ to) recovery of
reasonably avoidable damages.” The doctrine serves to reduce the amount
of damages to which a plaintiff might otherwise have been entitled had he
or she used all reasonable efforts to minimize the loss he or she sustained as
a result of a breach of duty by the defendant. . . . Thus, it is clear that the
doctrine does not place any duty on a plaintiff or create an affirmative right
in anyone. . . . [I]n order for the doctrine of minimization of damages to
apply, there must first have been a breach of duty on the part of the
defendant, who then raises an issue as to the propriety of the losses or
damages claimed by the plaintiff.
Schlossberg v. Epstein, 534 A.2d 1003, 1006–07 (Md. Ct. Spec. App. 1988) (emphasis
added) (citations omitted).
NCO’s argument that a mitigation obligation implicates the doctrine of “mutual
breach” is simply off the mark. The central, bargained-for mutual rights and duties of the
lease agreement arose from (1) Montgomery Park’s agreement to provide NCO with
functional commercial office space and (2) NCO’s agreement to timely pay rent for the
space. Accordingly, once NCO failed to pay rent, it was in breach of the contract and
Montgomery Park was entitled to contract damages against it. To the extent Montgomery
Park owed NCO a “duty” to mitigate damages, therefore, the duty arose only after and
because of NCO’s breach and became relevant only when Montgomery Park sought
contract damages from NCO. As such, treating Montgomery Park’s alleged failure to
mitigate damages as a typical breach of contract — and thus as a potential ground for
11
“mutual breach” — fundamentally misconstrues contract law and a landlord’s duty to
mitigate damages resulting from a tenant’s breach.
The principal case relied on by NCO and the district court, Circuit City, does not
hold to the contrary. Circuit City concerned a landlord that, in order to attract a new
tenant following a prior tenant’s breach of its lease agreement, permitted a commercial
property to be demolished. 829 A.2d at 977. The Maryland Court of Appeals remanded
the case to the trial court for a determination of whether that arrangement was
“reasonable,” instructing that if the lower court were to determine that it was not
reasonable, the court could, “on that basis, conclude that [the landlord] breached its
contractual obligation to mitigate damages and that, from and after the time of that
breach” — i.e., from and after the time the property was demolished and thus could no
longer be re-let — the landlord “was entitled to no further payments.” Id. at 991. In so
holding, the Court of Appeals noted:
[W]hether seeking to recover rent under property covenants on the theory
that a surrender has not occurred or to recover contract damages under
contract law, the landlord has its own obligation to mitigate damages. We
have recognized generally that, when one party breaches a contract, the
other party is required by the “avoidable consequences” rule of damages to
make all reasonable efforts to minimize the loss sustained from the breach
and can charge the defaulting party only with such damages as, with
reasonable endeavors and expense and without risk of additional substantial
loss or injury, he could not prevent.
Id. at 990 (internal quotation marks and citation omitted). Thus, contrary to NCO’s and
the district court’s reading, Circuit City stands for the well-established proposition that a
failure to mitigate damages may decrease the amount of recoverable damages but does
not necessarily preclude recovery of damages altogether. Of course, if the evidence
12
shows that the lessor, with reasonable efforts, could have recovered all of the rent owed
by the lessee, there would be no recovery of unpaid rent. But that conclusion can be
reached only by determining the amount that the lessor could have obtained with
reasonable efforts and then setting off that amount against the rent owed.
Thus, to apply the mitigation-of-damages doctrine correctly, the district court
should have required NCO to prove how much, if any, additional rent Montgomery Park
could have collected by exercising reasonable commercial efforts to re-let the NCO space
and then decreased Montgomery Park’s contract damages by that amount. Because the
district court did not engage in this analysis, we remand for further proceedings.
III
Montgomery Park also contends that the district court applied the wrong standard
when evaluating the commercial reasonableness of the efforts to re-let the NCO space,
asserting that the court wrongly “believed the NCO [p]remises must be given preferred
treatment over all other vacant space” in the same building. (Emphasis added). It argues
that, as a result of this error, the district court “ignored” relevant evidence of commercial
reasonableness regarding marketing efforts directed at the building as a whole.
At trial, the district court applied a reasonableness standard that required
Montgomery Park to show that it favored the NCO space in its marketing efforts, stating
that “Montgomery Park was under a contractual duty to give special care and attention to
NCO” and that although “Montgomery Park . . . engaged in significant effort[s],” “these
efforts were designed only to market Montgomery Park space as a whole, with no serious
13
effort to target or [re-let] NCO space, as they were obligated to do.” Indeed, at times the
court seemed to view the relevant inquiry as what a hypothetical landlord of solely the
NCO premises should have done. Under this standard, Montgomery Park became
obligated to develop a unique, preferred plan for leasing the NCO space and then to
market that space at the expense of its other vacant spaces, despite the fact that it was
NCO who breached the lease. In the same vein, the court seemed to adopt a standard that
would require the victim of the breach to sacrifice other opportunities to favor the
breaching party — suggesting that Montgomery Park “could have listed the NCO
premises as available and simply made space that had been deemed available for leasing
unavailable.”
As Montgomery Park rightly points out, however, a landlord’s obligation to
mitigate damages does not require that it favor the vacated space or otherwise drastically
alter its business plan. See Circuit City, 829 A.2d at 990. Rather, Montgomery Park’s
duty to mitigate damages merely required that it act reasonably to re-let the NCO space
under the circumstances, with “the circumstances” including the fact that the NCO space
was but one of a number of vacant spaces that Montgomery Park had available in the
building. As such, the duty to mitigate damages mandated only that Montgomery Park
act reasonably to market the NCO space on an equal footing with its other vacant spaces.
Of course, Montgomery Park was not entitled to sit on its hands and take advantage of
the fact that NCO had a continuing obligation to pay rent, but neither was it required to
single out the NCO space for special treatment to the detriment of its other business
opportunities.
14
We offer no view on whether Montgomery Park satisfied this standard.
Montgomery Park’s generalized marketing efforts — which the district court recognized
as “significant” — suggest that it may have. But other of Montgomery Park’s actions,
particularly its failure to update its CoStar listing, might suggest otherwise. On remand,
the district court should consider all the relevant evidence, including evidence concerning
Montgomery Park’s generalized marketing efforts, to determine whether Montgomery
Park’s efforts were reasonable and impose on NCO the burden to quantify the
consequence of any failure to mitigate that it is able to prove.
IV
Finally, Montgomery Park challenges the district court’s admission of certain
expert testimony. Such rulings, however, are entitled to great deference and are subject
to review only for abuse of discretion. See United States v. Fuertes, 805 F.3d 485, 495–
96 (4th Cir. 2015); Noel v. Artson, 641 F.3d 580, 591 (4th Cir. 2011) (“[W]e will only
overturn an evidentiary ruling that is arbitrary and irrational” (internal quotation marks
and citation omitted)). We conclude that the district court did not abuse its discretion.
* * *
For the reasons given, we vacate the district court’s judgment and remand for
further proceedings consistent with this opinion.
VACATED AND REMANDED
15