In the United States Court of Federal Claims
No. 19-469C
(E-Filed: June 24, 2019) 1
)
iACCESS TECHNOLOGIES, INC., )
)
Plaintiff, )
)
v. ) Pre-Award Bid Protest;
) Exclusion from Competitive
THE UNITED STATES, ) Range; Unsuccessful Challenge
) to Technical Ratings;
Defendant, ) Discussions Held with Offerors
) Were Meaningful and Not
and ) Misleading; No Improper
) Responsibility Determination.
L-3 COMMUNICATIONS )
INTEGRATED SYSTEMS L.P., )
)
Intervenor-defendant. )
)
Richard J.R. Raleigh, Jr., Huntsville, AL, for plaintiff. Jerome S. Gabig and Christopher
L. Lockwood, of counsel.
Margaret J. Jantzen, Trial Attorney, with whom were Joseph H. Hunt, Assistant Attorney
General, Robert E. Kirschman, Jr., Director, Lisa L. Donahue, Assistant Director,
Commercial Litigation Branch, Civil Division, United States Department of Justice,
Washington, DC, for defendant.
1
This opinion was issued under seal on May 31, 2019. Pursuant to ¶ 5 of the
ordering language, the parties were invited to identify source selection, proprietary or
confidential material subject to deletion on the basis that the material was
protected/privileged. The redactions jointly proposed by plaintiff and the government
were acceptable to the court—with some minor modifications intended to preserve the
structure, but not all of the content—of the sentences that were redacted. All redactions
are indicated by brackets ([ ]).
Craig A. Holman, Washington, DC, for intervenor-defendant. Mark D. Colley, Dana E.
Koffman, Emma K. Dinan, and Nathaniel E. Castellano, of counsel.
OPINION AND ORDER
CAMPBELL-SMITH, Judge.
This pre-award bid protest is before the court on the parties’ briefing of dispositive
motions brought under Rules 12(b) and 52.1(c) of the Rules of the United States Court of
Federal Claims (RCFC). 2 These briefs were filed pursuant to an expedited schedule
largely determined by the government’s voluntary stay of contract award through May
31, 2019. The briefs before the court, in chronological order, are as follows: plaintiff’s
memorandum in support of its motion for judgment on the administrative record (AR),
ECF No. 55-1; intervenor-defendant’s memorandum in support of its motion to dismiss
and cross-motion for judgment on the AR, ECF No. 58-1; defendant’s cross-motion for
judgment on the AR, ECF No. 59; plaintiff’s response/reply brief, ECF No. 62;
intervenor-defendant’s reply brief, ECF No. 65; and, defendant’s reply brief, ECF No. 66.
In addition, the court has reviewed the amended complaint. See ECF No. 45. The
AR has also been considered by the court. See ECF Nos. 21-25, 52. Oral argument was
deemed to be unnecessary. For the reasons set forth below, plaintiff’s motion for
judgment on the AR is DENIED; intervenor-defendant’s motion to dismiss or, in the
alternative, cross-motion for judgment on the AR is DENIED in part, as to the motion to
dismiss, and GRANTED in part, as to the cross-motion for judgment on the AR; and,
defendant’s cross-motion for judgment on the AR is GRANTED.
I. Background
A. Overview
The procurement that underlies this protest is for avionics modernization of 176
C-130H aircraft. ECF No. 23-2 at 58. The United States Air Force issued Solicitation
No. FA8625-17-R-6608 (solicitation or RFP) on September 1, 2017. ECF No. 21-3 at
915-19. Six offerors responded to the solicitation, including iAccess Technologies, Inc.
(iAccess), plaintiff, and L-3 Communications Integrated Systems L.P. (L3),
intervenor-defendant in this matter. ECF No. 25-2 at 2. One of the offerors, a small
business, was eliminated from the competitive range of proposals on or about August 9,
2018. Id. at 19-20, 27; see also ECF No. 25-1 at 858 (noting that iAccess and the offeror
eliminated in the first competitive range determination were small businesses).
2
Although intervenor-defendant does not cite RCFC 12(b), its arguments for
dismissal of plaintiff’s bid protest are typically considered under this rule.
2
The remaining five offerors entered into discussions with the Air Force to address
the agency’s concerns about their proposals. ECF No. 25-2 at 901. These Round 1
discussions included the following components: (1) the Air Force provided each offeror
with numbered Evaluation Notices (ENs) asking the offeror to address the agency’s
concerns; (2) each offeror was permitted to ask questions about the ENs, to which the
agency provided responses; (3) a conference call was held with each offeror; and (4) the
offeror submitted its written responses to each of the ENs. Id.
The agency also conducted Round 2 discussions with offerors to address concerns
that had not been resolved in Round 1. Id. The procedure was similar, where the Air
Force provided numbered ENs to the offerors, conference call questions and written
questions provided the offerors with an opportunity to obtain feedback about the Round 2
ENs, and, finally, the offerors provided the agency with their written responses to the
Round 2 ENs. Id.
Once Round 2 discussions had been completed, iAccess was eliminated from the
competitive range on December 14, 2018, and was notified of the agency’s decision on
December 18, 2018. ECF No. 25-3 at 11-15. One of the three principal bid protest
grounds before the court is iAccess’s contention that the discussions held by the agency
were not meaningful and were misleading. ECF No. 55-1 at 30-31. The other two
principal bid protest grounds here are that the technical ratings justifying the agency’s
second competitive range decision (SCRD) were flawed, and that the agency improperly
rejected iAccess’s proposal for responsibility reasons, rather than for technical
acceptability reasons. Id. at 20-43.
Once iAccess, the only small business remaining in the first competitive range,
had been eliminated by the SCRD, the four remaining offerors were permitted to submit
final proposal revisions. ECF No. 25-3 at 348. L3 was selected for award. Id. at 350,
473-82. However, before the Air Force could execute a contract with L3, this pre-award
bid protest was filed on March 29, 2019. The agency agreed to voluntarily stay contract
award through May 31, 2019. ECF No. 46 at 2 (joint notice).
B. Proposal Evaluation Scheme
“This is a best value source selection conducted in accordance with . . . Federal
Acquisition Regulation (FAR) 15.3.” 3 ECF No. 23-2 at 87. The solicitation
contemplated an integrated assessment of Technical Rating, Technical Risk Assessment,
and Price. Id. Two evaluation factors, Technical Risk and Price, had approximately
3
All citations to the FAR in this opinion are to the 2018 version of Title 48 of the
Code of Federal Regulations.
3
equal weight. Id. However, only Technically Acceptable proposals would be considered
for the tradeoff analysis. Id.
There were two technical subfactors: Schedule and Systems Engineering. Id. at
89. Each of these subfactors would be separately rated for both acceptability and risk.
Id. “A Technical Rating of Unacceptable or a Technical Risk Rating of High or
Unacceptable will render a proposal ineligible for award.” Id. Each of the technical
subfactors was further divided into Measures of Merit (MoMs). Id. at 90.
The primary focus here is on the MoMs applicable to the second technical
subfactor, Systems Engineering. These are MoMs M4 through M12. Id. at 92-94. M12,
however, did not contribute to the Technical Risk rating for Systems Engineering,
because this MoM measured the offeror’s agreement to comply with small business
contracting requirements. Id. at 89, 92, 94.
An Unacceptable technical rating reflects the agency’s judgment that the proposal
“does not meet the requirements of the solicitation.” Id. at 90. A High Technical Risk
rating indicates, first, that the proposal “contains a significant weakness or combination
of weaknesses which is likely to cause significant disruption of schedule, increased cost
or degradation of performance,” and, second, that the proposed approach is “unlikely to
overcome any difficulties, even with special contractor emphasis and close Government
monitoring.” Id. at 91.
The government would also “consider, throughout the evaluation, the ‘correction
potential’ of any deficiency” in a proposal. Id. at 87. In this regard, the solicitation states
that “[i]f an aspect of an Offeror’s proposal not meeting the Government’s requirements
is not considered correctable, or if the amount and/or complexity of the corrections
needed to meet the Government requirement requires a major proposal revision, the
Offeror may be eliminated from the competitive range.” Id. The court reserves further
discussion of the solicitation for the analysis section of this opinion.
II. Standards of Review
A. Dismissal under RCFC 12(b)(1)
When reviewing a complaint to determine its jurisdiction over a plaintiff’s claims,
this court must presume all undisputed factual allegations to be true and construe all
reasonable inferences in favor of the plaintiff. Scheuer v. Rhodes, 416 U.S. 232, 236
(1974), abrogated on other grounds by Harlow v. Fitzgerald, 457 U.S. 800 (1982);
Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 747 (Fed. Cir. 1988) (citations
omitted). Plaintiff bears the burden of establishing subject matter jurisdiction by a
preponderance of the evidence. Reynolds, 846 F.2d at 748 (citations omitted). If
jurisdiction is found to be lacking, this court must dismiss the action. RCFC 12(h)(3).
4
B. Dismissal under RCFC 12(b)(6)
It is well-settled that a complaint should be dismissed under RCFC 12(b)(6) “when
the facts asserted by the claimant do not entitle him to a legal remedy.” Lindsay v.
United States, 295 F.3d 1252, 1257 (Fed. Cir. 2002). When considering a motion to
dismiss brought under RCFC 12(b)(6), “the allegations of the complaint should be
construed favorably to the pleader.” Scheuer, 416 U.S. at 236. “To survive a motion to
dismiss, a complaint must contain sufficient factual matter, accepted as true, to ‘state a
claim to relief that is plausible on its face.’” Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009)
(quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544, 570 (2007)).
C. Bid Protest Standard of Review
1. Judgment on the Administrative Record
RCFC 52.1(c) provides for judgment on the administrative record. To review a
motion, or cross-motions, under RCFC 52.1(c), the court asks whether, given all the
disputed and undisputed facts, a party has met its burden of proof based on the evidence
in the record. Bannum, Inc. v. United States, 404 F.3d 1346, 1356-57 (Fed. Cir. 2005).
The court must make factual findings where necessary. Id. The resolution of RCFC
52.1(c) cross motions is akin to an expedited trial on the paper record. Id.
2. Arbitrary and Capricious Standard
As the United States Court of Appeals for the Federal Circuit has stated, “the
proper standard to be applied in bid protest cases is provided by 5 U.S.C. § 706(2)(A)
[(2012)]: a reviewing court shall set aside the agency action if it is ‘arbitrary, capricious,
an abuse of discretion, or otherwise not in accordance with law.’” Banknote Corp. of
Am. v. United States, 365 F.3d 1345, 1350-51 (Fed. Cir. 2004) (citing Advanced Data
Concepts, Inc. v. United States, 216 F.3d 1054, 1057-58 (Fed. Cir. 2000)). Under this
standard, a procurement decision may be set aside if it lacked a rational basis or if the
agency’s decision-making involved a clear and prejudicial violation of statute, regulation
or procedure. Emery Worldwide Airlines, Inc. v. United States, 264 F.3d 1071, 1085-86
(Fed. Cir. 2001) (citing Impresa Construzioni Geom. Domenico Garufi v. United States,
238 F.3d 1324, 1332-33 (Fed. Cir. 2001)). “The arbitrary and capricious standard
applicable [in bid protests] is highly deferential.” Advanced Data Concepts, 216 F.3d at
1058.
The level of deference depends on the circumstances of the procurement and the
errors alleged by the protestor. In negotiated procurements, “the protestor’s burden of
proving that the award was arbitrary, capricious, an abuse of discretion, or otherwise not
in accordance with law is greater than in other types of bid protests.” Galen Med.
Assocs., Inc. v. United States, 369 F.3d 1324, 1330 (Fed. Cir. 2004) (citation omitted).
When technical evaluation errors are alleged, those technical ratings fall within a
5
category of “discretionary determinations of procurement officials that a court will not
second guess.” E.W. Bliss Co. v. United States, 77 F.3d 445, 449 (Fed. Cir. 1996).
Finally, in best value procurements “the contracting officer ha[s] even greater discretion
than if the contract were to have been awarded on the basis of cost alone.” Galen, 369
F.3d at 1330 (citing E.W. Bliss, 77 F.3d at 449).
De minimis errors in the procurement process do not justify relief. Grumman Data
Sys. Corp. v. Dalton, 88 F.3d 990, 1000 (Fed. Cir. 1996) (citing Andersen Consulting v.
United States, 959 F.2d 929, 932-33, 935 (Fed. Cir. 1992)). The bid protest plaintiff
bears the burden of proving that a significant error marred the procurement in question.
Id. (citing CACI Field Servs., Inc. v. United States, 854 F.2d 464, 466 (Fed. Cir. 1988)).
Examples of arbitrary and capricious agency action include “when the agency ‘entirely
failed to consider an important aspect of the problem, offered an explanation for its
decision that runs counter to the evidence before the agency, or [the decision] is so
implausible that it could not be ascribed to a difference in view or the product of agency
expertise.’” Ala. Aircraft Indus., Inc.-Birmingham v. United States, 586 F.3d 1372, 1375
(Fed. Cir. 2009) (quoting Motor Vehicle Mfrs. Ass’n v. State Farm Mut. Auto. Ins. Co.,
463 U.S. 29, 43 (1983)) (alteration in original). The court will, however, “uphold a
decision of less than ideal clarity if the agency’s path may reasonably be discerned.”
Bowman Transp., Inc. v. Arkansas-Best Freight Sys., Inc., 419 U.S. 281, 286 (1974)
(citation omitted).
“‘If the court finds a reasonable basis for the agency’s action, the court should stay
its hand even though it might, as an original proposition, have reached a different
conclusion as to the proper administration and application of the procurement
regulations.’” Honeywell, Inc. v. United States, 870 F.2d 644, 648 (Fed. Cir. 1989)
(quoting M. Steinthal & Co. v. Seamans, 455 F.2d 1289, 1301 (D.C. Cir. 1971)).
3. Prejudice
To establish a plaintiff’s standing to bring a bid protest, the protestor generally
must show that it had a substantial chance of contract award. See Orion Tech., Inc. v.
United States, 704 F.3d 1344, 1349 (Fed. Cir. 2013) (holding that where “an adequate
factual predicate” exists, even in a pre-award scenario, prejudice is established if the
protestor can show that it had a substantial chance of award but for the procurement
errors alleged). This initial inquiry into prejudice has been described as the establishment
of “potential prejudice[] [i]f the various challenges to the [procurement process] were
well-founded.” Beta Analytics Int’l, Inc. v. United States, 67 Fed. Cl. 384, 396 (2005).
If, on the merits, the court finds that procurement errors have indeed occurred, a second
prejudice inquiry is required. See, e.g., Glob. Comput. Enters., Inc. v. United States, 88
Fed. Cl. 350, 401 (“Confusion over the standard of prejudice necessary for establishing
standing exists ‘because, in addition to being an element of standing, a showing of
prejudice is required before injunctive relief is granted.’”) (citations omitted), modified
on reconsideration, 88 Fed. Cl. 466 (2009). The second prejudice inquiry asks, again,
6
whether “there was a ‘substantial chance’ [the protestor] would have received the
contract award but for the errors” made by the agency. Bannum, 404 F.3d at 1353
(citations omitted).
As this court has explained:
Th[e] first showing of prejudice to the protestor, in order to prove
standing, must occur before reaching the merits of the bid protest review.
See Info. Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319
(Fed. Cir. 2003) (stating that “because the question of prejudice goes directly
to the question of standing, the prejudice issue must be reached before
addressing the merits”). The Federal Circuit has also stated that the two-step
review of contract awards begins with an “arbitrary and capricious” review
of an award and then proceeds to the issue of prejudice to the protestor.
Bannum, Inc. v. United States, 404 F.3d 1346, 1351 (Fed. Cir. 2005). This
court thus looks twice at prejudice, first weighing prejudice as it pertains to
standing, and then more thoroughly weighing prejudice to determine whether
plaintiff shall be afforded relief. See Night Vision Corp. v. United States, 68
Fed. Cl. 368, 392 & n.23 (2005) (characterizing the prejudice determination
for standing purposes as a “limited review for prejudice,” seeking “minimum
requisite evidence necessary for plaintiff to demonstrate prejudice and
therefore standing”).
A & D Fire Prot., Inc. v. United States, 72 Fed. Cl. 126, 131 n.4 (2006).
For the second inquiry into prejudice, plaintiff again bears the burden of proof
and must “show that there was a ‘substantial chance’ [plaintiff] would have received the
contract award but for the [government’s] errors in the [procurement] process.” Bannum,
404 F.3d at 1358 (citations omitted). In other words, if a protestor can show that there
was a substantial chance that it would have won the contract award but for the
procurement errors of the agency, relief may be granted because prejudicial error has
been established. Id. at 1353 (citations omitted). “Prejudice is a question of fact.” Id. at
1353 (citing Advanced Data Concepts, 216 F.3d at 1057).
4. Permanent Injunctive Relief
As the Federal Circuit has held:
In deciding whether a permanent injunction should issue, a court considers:
(1) whether, as it must, the plaintiff has succeeded on the merits of the case;
(2) whether the plaintiff will suffer irreparable harm if the court withholds
injunctive relief; (3) whether the balance of hardships to the respective
parties favors the grant of injunctive relief; and (4) whether it is in the public
interest to grant injunctive relief.
7
PGBA, LLC v. United States, 389 F.3d 1219, 1228-29 (Fed. Cir. 2004) (citing Amoco
Prod. Co. v. Vill. of Gambell, Alaska, 480 U.S. 531, 546 n.12 (1987)).
III. Analysis
iAccess’s arguments for judgment on the administrative record can be divided into
three principal inquiries. 4 ECF No. 55-1 at 7-9. First, did the agency err when it
assigned iAccess an Unacceptable rating and a High Technical Risk rating for the
Systems Engineering technical subfactor, and also concluded that iAccess’s proposal
flaws lacked correction potential? Second, were the discussions held with iAccess
meaningful and not misleading? Third, was the agency obliged to consult with the Small
Business Administration before eliminating iAccess from the competitive range? Before
addressing these questions, however, the court considers whether L3’s motion to dismiss
has merit.
A. L3’s Arguments for Dismissal
1. Standing
According to L3, “iAccess has not and cannot establish that it has a substantial
chance for award.” ECF No. 58-1 at 18. The court disagrees. If all of the alleged
procurement errors asserted by iAccess have merit, but for those errors iAccess would
have remained in the competitive range and would have been afforded an opportunity to
submit a final proposal revision with a revised price. ECF No. 62 at 26-27. Under the
circumstances of this procurement, iAccess has established standing under the substantial
chance test.
L3 also appears to argue that iAccess must prevail on the merits of its protest to
establish standing. In this regard, L3 asserts that “unless iAccess can demonstrate that it
has both an Acceptable Technical rating and at least a Marginal Risk rating under
[Systems Engineering], iAccess is ineligible for award.” ECF No. 58-1 at 20 (citing
COMINT Sys. Corp. v. United States, 700 F.3d 1377, 1383-84 (Fed. Cir. 2012)). L3’s
standing argument contravenes established precedent and, in the court’s view, misreads
COMINT.
4
The court has considered all of plaintiff’s challenges to its elimination from the
second competitive range, and all of the government’s and L3’s counter-arguments.
Although only the most prominent arguments advanced by the parties are discussed in
this opinion, the court’s resolution of this bid protest is founded on a comprehensive
review of the record and all of the parties’ arguments. Any of plaintiff’s arguments not
discussed here were deemed unpersuasive.
8
As discussed supra, there are two distinct types of prejudice inquiries in bid
protests before this court, and the decision in COMINT acknowledges this fact. See 700
F.3d at 1383 (“Here, the propriety of the marginal Quality/Capability rating assigned to
Comint by the agency is determinative of both Comint’s standing and the merits” of its
protest.”) (emphasis added). Generally, “substantial chance” prejudice is determined at
the outset, to establish standing. See, e.g., Info. Tech. & Applications Corp. v. United
States, 316 F.3d 1312, 1319 (Fed. Cir. 2003) (ITAC) (stating that “because the question
of prejudice goes directly to the question of standing, the prejudice issue must be reached
before addressing the merits”). Standing is an element of this court’s jurisdiction over
bid protest cases. See Rex Serv. Corp. v. United States, 448 F.3d 1305, 1307-08 (Fed.
Cir. 2006) (upholding a dismissal for lack of jurisdiction because the protestor was not an
actual bidder in the competition and could not show prejudice, i.e., that it had a
substantial chance of receiving the contract but for the alleged procurement errors).
Here, the threshold inquiry into standing does not require that iAccess first prevail on the
merits of its protest. See, e.g., ITAC, 316 F.3d at 1319 (“ITAC has established prejudice
(and therefore standing), because it had greater than an insubstantial chance of securing
the contract if successful on the merits of the bid protest.”) (emphasis added).
To read COMINT as requiring success on the merits of the protest to establish
standing would conflict with the standing analysis in ITAC, which is itself cited by the
COMINT panel. 700 F.3d at 1384 (citing ITAC, 316 F.3d at 1319). In its opening brief,
ECF No. 58-1 at 20, L3 relies on the following passage in COMINT for the draconian
test for standing intervenor-defendant proposes here:
Because Comint has not shown that its marginal Quality/Capability
rating was arbitrary or capricious, Comint cannot show that it had a
substantial chance of receiving the award. Comint thus cannot demonstrate
standing to object to the agency’s failure to award it a contract. See Info.
Tech. & Applications Corp. v. United States, 316 F.3d 1312, 1319 (Fed. Cir.
2003).
700 F.3d at 1384. This is not a radical revision of the binding precedent regarding
standing set forth in ITAC.
The conclusion regarding standing in the COMINT decision merely indicates that
the second inquiry as to actual prejudice, under the circumstances of that protest, was also
determinative of the threshold inquiry into prejudice for the purposes of determining
standing. Id. In other words, the “potential prejudice” necessary for standing purposes
had been extinguished by the lack of actual prejudice. Beta Analytics, 67 Fed. Cl. at 396;
see also Orion, 704 F.3d at 1349 n.1 (distinguishing COMINT on the basis that “no such
determination on the merits” had been made in Orion). Once the proper test for standing
is applied, iAccess has standing to bring this bid protest.
2. Waiver
9
L3 also argues that iAccess waived its protest under the authority of the waiver
doctrine announced in Blue & Gold Fleet, L.P. v. United States, 492 F.3d 1308 (Fed. Cir.
2007). ECF No. 58-1 at 21. In Blue & Gold Fleet, the court stated:
We also hold that a party who has the opportunity to object to the
terms of a government solicitation containing a patent error and fails to do so
prior to the close of the bidding process waives its ability to raise the same
objection subsequently in a bid protest action in the Court of Federal Claims.
492 F.3d at 1313. According to L3, the waiver doctrine has been further extended to
other procurement events that are evident before award, not just the occurrence of patent
errors in a solicitation, so that these events also trigger a duty to protest before the
contract is awarded. ECF No. 58-1 at 21-23. In short, L3 argues that once iAccess was
notified that it was eliminated from the competitive range on December 18, 2018, it could
not wait until March 29, 2019, to file its pre-award bid protest without waiving its right to
protest its elimination from the competitive range. Id.
At the heart of this dispute is the Federal Circuit’s COMINT decision, which
extended the Blue & Gold Fleet waiver rule to bar a challenge to a solicitation
amendment that took effect after bidding had closed, and that was alleged to have been
improper in a post-award bid protest. See 700 F.3d at 1382 (“[W]e think the reasoning of
Blue & Gold applies to all situations in which the protesting party had the opportunity to
challenge a solicitation before the award and failed to do so.”). A reasonable reading of
COMINT limits its extension of the waiver rule to patent errors in a solicitation occurring
after bidding has closed but before the contract has been awarded. Id. (“[A]ssuming that
there is adequate time in which to do so, a disappointed bidder must bring a challenge to
a solicitation containing a patent error or ambiguity prior to the award of the contract.”).
Indeed, this court recently issued a decision that interpreted COMINT in that manner.
See ATSC Aviation, LLC v. United States, 141 Fed. Cl. 670, 694 (2019) (“The Federal
Circuit extended this waiver rule to post-award challenges of a solicitation when the error
arose in the interval between the close of bidding and the award of the contract.” (citing
COMINT, 700 F.3d at 1382)).
ATSC is analogous to this case, because that decision, too, addressed a claim that
the protestor had been improperly removed from a competitive range of offerors. Id. at
673, 692, 694. There could also be significant factual distinctions between ATSC and
this case, including, perhaps, the extent of the protestor’s knowledge of the reasons the
agency eliminated its proposal from the competitive range. See id. at 694 (noting that the
protestor in ATSC alleged that the “evaluative error was not evident before the final
award”). The court does not disagree, however, with ATSC as to its application of
COMINT to the circumstances of that case; nor does the court disagree with the
determination in ATSC that the protestor’s claims were not waived under those
circumstances. See id. at 696 (“The waiver doctrine explicated in COMINT and Blue &
Gold does not bar ATSC’s protest given the somewhat unusual setting of this case.”).
10
L3 argues that a broader reading of COMINT should be applied in this case,
relying primarily on Synergy Solutions, Inc. v. United States, 133 Fed. Cl. 716 (2017).
ECF No. 58-1 at 21; ECF No. 65 at 11-12. The court focuses on key aspects of Synergy
without reproducing here the entirety of the lengthy discussion of waiver and COMINT
contained in Synergy. Of note, the Synergy decision explains that the Blue & Gold Fleet
waiver rule is analogous to timeliness restrictions on bid protests brought before the
Government Accountability Office (GAO). Synergy, 133 Fed. Cl. at 738 (citing Blue &
Gold Fleet, 492 F.3d at 1313-15). The Federal Circuit in COMINT also drew parallels
between the timeliness rules governing GAO protests and that court’s application of
waiver to one of the protest grounds in the appeal before it. 700 F.3d at 1383 (citing 4
C.F.R. § 21.2). Certainly the fact that iAccess’s protest might have been untimely at the
GAO, because this protest was filed more than ten days after iAccess knew that it had
been eliminated from the competitive range, weighs, to some degree, in favor of the
application of waiver here. 5 See 4 C.F.R. § 21.2(a)(2) (2018) (stating that protests are
untimely if filed more than ten days after the alleged procurement improprieties were
“known or should have been known,” although debriefing rights may affect this
deadline).
According to Synergy, the waiver rule in COMINT is not limited to challenges to
solicitation terms, but may be applied more broadly to challenges to the agency’s actions
taken after the close of bidding but before contract award:
Thus, the court respectfully declines to follow the reasoning in [Vanguard
Recovery Assistance v. United States, 99 Fed. Cl. 81 (2011)]. As noted
above, in that case—which is not binding authority—the court drew a
distinction between perceived defects in the solicitation versus perceived
defects in the evaluation process. The undersigned does not view the
reasoning of the Federal Circuit in Comint Systems as being so limited.
Rather, the language in Comint Systems expresses a clear, practical intent to
expand the reach of the Blue & Gold Fleet waiver rule to include any defects
that could potentially be raised and resolved prior to the contract award,
despite the fact that in Comint Systems, the defect at issue related to an
amended solicitation and not a defect arising during the evaluation process.
5
According to L3, iAccess did not receive the debriefing that the agency prepared
because “iAccess apparently failed to timely request and thus never received the
debriefing that the Agency had prepared.” ECF No. 58-1 at 15. The record is not clear
on this point. See ECF No. 25-3 at 419-20 (showing that iAccess requested a debriefing
that was scheduled by the agency for February 20, 2019); see also ECF No. 25-2 at
855-97 (prepared debriefing slides). Whether or not iAccess took advantage of its right
to a debriefing would have been a factor in the timeliness of any protest brought by
iAccess at the GAO. See 4 C.F.R. § 21.2(a)(2) (2018).
11
See also Jacobs Tech., Inc. v. United States, 100 Fed. Cl. 179, 182 n.4 (2011)
(“Although [Blue & Gold Fleet] deals with a protester’s objections to terms
of the solicitation, this Court suggests that it raises legitimate concerns for
prudent protesters challenging the solicitation process or the evaluation of
offerors’ proposals.”).
Synergy, 133 Fed. Cl. at 740. The court notes that the procurement challenge discussed
in Synergy had already been rejected by the GAO, on waiver grounds, and that the
protest before the court focused on an alleged failure of the agency to hold discussions,
not the exclusion of an offeror from the competitive range of proposals. Id. at 739. The
underlying facts in Synergy also included two GAO protests and corrective action
undertaken by the agency, circumstances that are not present in iAccess’s protest before
this court. Id. at 729-33.
The court considers both decisions of this court, ATSC and Synergy, to be
reasonable interpretations of the holding in COMINT, as applied to the facts of each of
those protests. The facts of iAccess’s protest align more closely with those in ATSC.
The court observes, too, that the general rule stated in Synergy does not compel a finding
that iAccess’s protest was necessarily waived here: “the prejudiced offeror was obliged
to raise its objection to the amended solicitation as early as possible and at a minimum,
prior to the agency’s award of the contract.” 133 Fed. Cl. at 740 (citing COMINT, 700
F.3d at 1383). Here, iAccess brought its protest before the award to L3 occurred. Under
the facts of this case, the court does not find that the waiver rule stated in COMINT bars
plaintiff’s claims in this suit.
3. Laches
The last doctrine relied upon by L3 in its motion to dismiss is laches. ECF No.
58-1 at 23-26; ECF No. 65 at 12-14. According to L3, the doctrine of laches bars
plaintiff’s bid protest because iAccess delayed too long to file its bid protest. L3 relies, to
a great extent, on the discussion of laches in Global Dynamics, LLC v. United States, 137
Fed. Cl. 105, 114-17 (2018). 6 ECF No. 58-1 at 23-25; ECF No. 65 at 12, 14.
The court finds that Global does not provide sufficient support for L3’s defense of
laches. First, Global was an unusual case, with “unique circumstances.” 137 Fed. Cl. at
117. Second, the delay in filing the protest in Global was approximately one year, not a
little more than three months. 7 Id. at 116. Finally, there was evidence that the delay in
6
To the extent that L3 also relies on COMINT, ECF No. 65 at 13, the court notes
that the term laches does not appear in that Federal Circuit decision.
7
Although in some contexts three or four months may be an excessive time to wait
before filing a protest, the court notes that the solicitation issued on September 1, 2017
and an award has not yet occurred. The offerors were on notice, as of August 13, 2018,
12
Global was a strategic move by the plaintiff, i.e., inaction with an expectation that
abstaining from protest would allow sufficient time for a procurement outcome favorable
to the protestor to occur. Id. at 116-17. These facts in Global are not analogous to the
facts of this case.
The court notes, too, that there is authority questioning whether the defense of
laches should apply where statutes of limitation provide a measure of timeliness. E.g.,
SCA Hygiene Prods. Aktiebolag v. First Quality Baby Prods., LLC, 137 S. Ct. 954
(2017); Petrella v. Metro-Goldwyn-Mayer, Inc., 572 U.S. 663 (2014); Advanced
Cardiovascular Sys., Inc. v. Scimed Life Sys., Inc., 988 F.2d 1157, 1161-64 (Fed. Cir.
1993); ATSC, 141 Fed. Cl. at 696 (citing SCA Hygiene, 137 S. Ct. at 960-61). In light of
these authorities and the differences between this case and the facts in Global, the court
does not find that laches applies here. Under the circumstances of this case, although it is
a close question, iAccess’s protest is not barred by the doctrine of laches.
For the above reasons, the court is unpersuaded by L3’s arguments on standing,
waiver, and laches. Accordingly, L3’s motion to dismiss is denied.
B. Challenge to Technical Ratings
The court now turns to the merits of plaintiff’s bid protest, beginning with
plaintiff’s challenge to the ratings it received for the Systems Engineering subfactor. In
the interest of brevity, the court restricts its focus here to the final evaluation results for
iAccess stated in the second competitive range determination, or SCRD. ECF No. 25-3
at 4-11. iAccess’s final proposal, after Round 1 and Round 2 discussions, received both
an Unacceptable rating for the Systems Engineering subfactor, and a High Technical Risk
rating, for this subfactor. Id. at 4. Pursuant to the evaluation scheme set forth in the
solicitation, each of these ratings independently rendered iAccess’s proposal ineligible
for award. ECF No. 23-2 at 89. Because the agency did not believe iAccess’s proposal
had correction potential, iAccess was eliminated from the competition. ECF No. 25-3 at
11.
1. Evaluation Results for iAccess
a. Technically Unacceptable
The Unacceptable rating was based on iAccess’s approach to achieving [ ]. Id. at
5-6. “[ ].” Id. at 5. The critical portion of iAccess’s proposal discussed in this section of
the SCRD was iAccess’s “[ ].” Id.
that a “more realistic” award date was contemplated for April 2019. ECF No. 22-5 at 44.
iAccess thus filed its protest before the expected contract award date and in the context of
an ongoing procurement that at twenty-one months has yet to produce a contract award.
13
Overall, the agency found deficiencies in iAccess’s [ ]. Id. The Measure of Merit,
or MoM, in question was [ ], which measured [ ]. Id.; see also ECF No. 23-1 at 47; ECF
No. 23-2 at 93. The problem areas in iAccess’s [ ]. 8 ECF No. 25-3 at 5-6. The agency’s
conclusion as to the significance of these flaws was that iAccess [ ]. Id. at 6.
b. High Technical Risk
Plaintiff’s High Technical Risk rating for the Systems Engineering subfactor was
based on three MoMs: [ ]. ECF No. 25-3 at 6-11. The court will not discuss every
weakness or significant weakness described in the SCRD for MoMs [ ]. Instead, the
court will focus on a single flaw related to each MoM to give context for the High
Technical Risk rating iAccess received for the Systems Engineering subfactor.
MoM [ ] addresses “[ ].” ECF No. 23-2 at 93. One problem area noted by the
agency was iAccess’s “[ ].” ECF No. 25-3 at 7. According to the agency, “[ ].” Id. The
SCRD stated that iAccess “[ ].” Id.
As noted supra, MoM [ ] addresses the offeror’s [ ]. ECF No. 23-2 at 93. The
flaws in iAccess’s [ ]. ECF No. 25-3 at 10. After discussions were concluded, the
agency stated that iAccess’s “proposed approach continued to pose a performance risk for
MoM [ ].” Id. at 9.
Finally, MoM [ ] requires an offeror to “[ ].” ECF No. 23-2 at 93. The [ ]. Id.
According to the agency, iAccess “[ ].” ECF No. 25-3 at 10. The concerns that the
agency had expressed regarding iAccess’s [ ]. Id. at 11. The Air Force concluded that
iAccess’s [ ] “approach continues to constitute a weakness.” Id.
2. Evaluation Errors Alleged by Plaintiff
a. Correction Potential
The court notes at the outset of its analysis that plaintiff’s challenges to the
technical ratings that iAccess received in the SCRD are interwoven with plaintiff’s
challenges to the discussions that preceded those ratings, or which did not extend into a
third round of discussions. For example, plaintiff argues that when the agency decided
that iAccess’s proposal lacked correction potential, that decision violated both the
solicitation’s evaluation procedures and the arbitrary and capricious standard of review
applicable here. ECF No. 55-1 at 40-41. With regard to the issue of correction potential,
however, plaintiff primarily focuses on the discussions that were either held, or not held,
with iAccess. Id. at 41. Here, the court considers the technical ratings themselves, and
whether these ratings survive the arbitrary and capricious standard of review.
8
According to L3, these section numbers originate in [ ]. ECF No. 58-1 at 29 n.8.
14
Plaintiff contends that the agency “failed to set forth a rational basis for
concluding there was little correction potential” in the section of iAccess’s proposal
devoted to Systems Engineering. Id. The court disagrees. The agency’s SCRD
articulates a rational basis for the Air Force’s position that correcting iAccess’s proposal
was not feasible under the circumstances of this procurement. ECF No. 25-3 at 4-11.
Further, the position of the agency conforms with the evaluation scheme set forth in the
solicitation. ECF No. 23-2 at 87.
Finally, in its reply brief, plaintiff contends that it was illogical for the agency to
conclude that iAccess’s final proposal could not easily be corrected, when an earlier
version of iAccess’s [ ] had been rated as acceptable. ECF No. 62 at 12. It appears to be
undisputed that an earlier version of iAccess’s [ ] was technically acceptable. ECF No.
59 at 23; ECF No. 65 at 17. Here, however, the court must defer to the agency’s
technical expertise. On this record, the agency could reasonably conclude that iAccess’s
final proposal had sufficient correction potential, just as it could reasonably conclude that
iAccess’s final proposal did not have sufficient correction potential. Under the arbitrary
and capricious standard applicable here, the agency’s assessment of the correction
potential of iAccess’s proposal is rational and unassailable.
b. Second Competitive Range Determination Validity
In its reply brief, plaintiff suggests that the SCRD which eliminated iAccess’s
proposal from the competition for its technical flaws was an abuse of discretion under the
analytical framework set forth in Harris Data Communications, Inc. v. United States, 2
Cl. Ct. 229, 241, aff’d, 723 F.2d 69 (Fed. Cir. 1983) (table). ECF No. 62 at 13-14.
Although the term “abuse of discretion” is mentioned in plaintiff’s opening brief, the
brief contains no substantive analysis of the term. See generally ECF No. 55-1. The
opposing briefs filed by the government and L3 also did not explore the term “abuse of
discretion.” See generally ECF No. 58-1; ECF No. 59. The court views plaintiff’s abuse
of discretion argument, as buttressed by the five-factor test set forth in Harris Data, as a
new argument that is untimely raised in a reply brief and thus is waived. See, e.g.,
Arakaki v. United States, 62 Fed. Cl. 244, 246 n.9 (2004) (“The court will not consider
arguments that were presented for the first time in a reply brief or after briefing was
complete.” (citing Novosteel SA v. United States, 284 F.3d 1261, 1274 (Fed. Cir. 2002);
Cubic Def. Sys., Inc. v. United States, 45 Fed. Cl. 450, 467 (1999))).
Even if this argument were not waived, it is not persuasive. The five-factor test
set forth in Harris Data, 2 Cl. Ct. at 241, is not founded on the regulation governing
competitive range determinations in the current version of the FAR. See FAR
15.306(c)(2). Further, this court must apply the arbitrary and capricious standard of
review to competitive range determinations, not the Harris Data factors. See, e.g., Orion,
704 F.3d at 1351 (reviewing the protestor’s exclusion from the competition by applying
the arbitrary and capricious standard). Finally, to the extent that the Harris Data factors
are more stringent than the arbitrary and capricious standard, the Federal Circuit has
15
counseled against the use of more stringent tests in place of the arbitrary and capricious
standard. See Dell Fed. Sys., L.P. v. United States, 906 F.3d 982, 993 (Fed. Cir. 2018)
(rejecting an “overly stringent test for corrective action,” because the correct standard to
be applied in bid protests is the arbitrary and capricious standard) (citation omitted). For
all of the above reasons, plaintiff’s abuse of discretion argument founded on the Harris
Data factors is unconvincing.
c. Unacceptable Rating
The court turns now to the Unacceptable rating assigned to iAccess’s Systems
Engineering technical subfactor. The parties hotly debate whether the flaws the agency
perceived in sections [ ] of iAccess’s [ ] justify a rating of Unacceptable. One principal
flaw in the [ ] was related to iAccess’s marking of certain sections as [ ]; the other
principal flaw concerned the [ ].
Plaintiff argues that iAccess appropriately used the designation [ ] in its [ ], and
that its use of the [ ] designations did not merit the deficiency rating assigned in the
SCRD. ECF No. 55-1 at 24-25, 29; ECF No. 62 at 11-12. L3 and the government
disagree, and counter that criticism in the SCRD of iAccess’s [ ] designations, or of the
[ ], was proper. ECF No. 58-1 at 29-31, 49 & n.16; ECF No. 59 at 23-24; ECF No. 65 at
17-18; ECF No. 66 at 6-9. After due consideration of all of the parties’ arguments and
the record before the court, the court finds that the agency’s deficiency rating regarding
[ ] was rational. ECF No. 25-3 at 5-6.
The term [ ], as that term is applied to an offeror’s [ ], is referenced in Section L of
the solicitation, as follows:
[]
ECF No. 23-2 at 71. The same term is used again in Section M of the solicitation, which
states, in relevant part: “[ ].” Id. at 93. The SCRD states that iAccess’s [ ]. ECF No.
25-3 at 5. [ ]. 9 Id. at 6.
Plaintiff asserts that its final proposal contained [ ] for [ ] of iAccess’s [ ], and that
the record “provides no rationale for” the agency’s determination that these [ ]. ECF No.
55-1 at 27. There is a rationale stated in the SCRD, however. According to the agency,
in [ ] of iAccess’s [ ]
[ ].
9
According to L3, [ ]. ECF No. 58-1 at 30 & n.9. Because the rationale posited by
L3 is not stated in the SCRD, the court does not rely on L3’s assertion for its analysis
here.
16
ECF No. 25-3 at 6.
Plaintiff has not explained why the Air Force’s criticism of section [ ] in iAccess’s
[ ] is arbitrary or capricious. On this record, the court finds that all of the deficiencies
noted in the SCRD in support of iAccess’s Unacceptable rating on the Systems
Engineering technical subfactor are rational. Plaintiff’s challenge to its Unacceptable
rating provides no reason to overturn the agency’s decision to eliminate iAccess from this
competition.
d. High Technical Risk Rating
Plaintiff raises three principal challenges to the High Technical Risk rating
assigned to iAccess’s proposal, which were based on flaws in MoMs [ ]. ECF No. 55-1
at 31-40. First and foremost is plaintiff’s assertion that the High Technical Risk rating
was arbitrary and capricious because the flaws noted in the SCRD had been entirely, or
almost entirely, resolved through discussions. Id. at 31-33, 35-38. Second, plaintiff
contends that positive technical ratings on other aspects of iAccess’s proposal show that
the flaws noted in the SCRD were inconsistent with the record and irrational. Id. at
34-35, 39-40. Third, plaintiff argues that there was, at most, only one unresolved EN
remaining after discussions, and that a single weakness could not merit a High Technical
Risk rating under the evaluation scheme in the solicitation. Id. at 40.
The parties vigorously debate the meaning of the notation “resolved” that appears
in the AR where agency evaluators documented the ENs that were issued in Round 1 and
Round 2 discussions. Plaintiff notes that some of this debate references information not
in the AR. ECF No. 62 at 31-32 (citing ECF No. 59 at 28). The court need not expand
the record of this case beyond the AR. Plaintiff’s position is that a “resolved” notation
for an EN indicates that no weaknesses were found in iAccess’s final proposal as to the
topic of that EN. See id. at 8 (stating that the “Contracting Officer erroneously relied
upon ENs that had been ‘resolved,’ in which case the competitive range decision was
arbitrary and capricious”).
It is important to distinguish the parties’ arguments in this regard from those that
might be brought in a protest on significantly different facts. A Source Selection
Authority’s rationale for award may be overturned if that decision relies on a number of
weaknesses from an initial technical evaluation of proposals, when all of those
weaknesses in the protestor’s proposal were subsequently eliminated after discussions
and final proposal revisions had been submitted by the offerors. Indeed, that is the
situation, broadly speaking, in the GAO decision cited by plaintiff, Celta Services, Inc.,
B-411835, B-411835.2, 2015 CPD ¶ 362, 2015 WL 7731719 (Comp. Gen. Nov. 2, 2015).
See ECF No. 55-1 at 31, 36; ECF No. 62 at 7-9 & n.3. The record in that protest was
“clear that the inclusion of Celta’s weaknesses in the [Source Selection Authority’s]
memorandum was in error.” Celta, 2015 WL 7731719, at *7 & nn.8-9.
17
Here, however, the notation “resolved” is attached not to a specific weakness in an
evaluation team’s list of identified weaknesses, but to an EN. The record simply does not
support plaintiff’s contention that a “resolved” EN necessarily signifies that a weakness
in the offeror’s proposal has been eliminated. Indeed, the government cites one example
from the AR where a weakness persisted even after an EN issued to another offeror had
been marked “resolved.” ECF No. 59 at 28 (citing ECF No. 25-4 at 201).
L3 argues that both a “resolved” EN notation and a weakness or significant
weakness could co-exist in the evaluation record for iAccess’s final proposal. ECF No.
58-1 at 41 (citing ECF No. 25-3 at 1619-20). L3 cites the Technical Evaluation Report as
proof that a “resolved” EN did not eliminate proposal weaknesses and/or significant
weaknesses. Id. at 41 (citing ECF No. 25-3 at 1454-62). The record citations provided
by the government and L3 are sufficient to show that the “resolved” annotation for ENs
does not carry the meaning that plaintiff proposes in this protest. Therefore, the court
finds that the “resolved” ENs cited by plaintiff do not invalidate the High Technical Risk
rating assigned to iAccess’s proposal.
This finding also disposes of plaintiff’s argument that its sole unresolved EN
constituted just one weakness, and that one weakness cannot justify a High Technical
Risk rating. Because “resolved” ENs did not necessarily eliminate weaknesses or
significant weaknesses, the record does not show that iAccess, after discussions, had only
one weakness. Because none of iAccess’s weaknesses or significant weaknesses
associated with MoMs [ ] have been shown to be irrational, the High Technical Risk
rating, under the evaluation scheme set forth in the solicitation, has not been shown to be
improper.
The court turns now to plaintiff’s argument that its High Technical Risk rating was
contradicted by other technical ratings that appear to address the same or similar aspects
of iAccess’s proposal. In essence, plaintiff relies on its ratings for MoM [ ], to contradict
its weaknesses in MoM [ ], and its technical subfactor Schedule ratings to contradict its
weaknesses in MoM [ ]. ECF No. 55-1 at 34-35, 39-40. The court cannot agree that the
agency’s ratings for MoM [ ] and MoM [ ] are invalid because they do not match ratings
on different and distinct measures in the evaluation scheme.
Both the government and L3 argue that the MoMs must be individually satisfied,
and that MoM [ ] is not the same as MoM [ ]. ECF No. 59 at 26-27; ECF No. 65 at 18
n.4; ECF No. 66 at 9. L3 contends, further, that each of the technical subfactors,
Schedule and Systems Engineering, addresses distinct aspects of the offeror’s approach.
ECF No. 58-1 at 32. The government’s and L3’s arguments are more persuasive than
plaintiff’s attempt to convert MoM [ ] ratings into MoM [ ] ratings, or Schedule subfactor
ratings into MoM [ ] ratings. In sum, all of plaintiff’s challenges to the High Technical
Risk rating it received for the Systems Engineering subfactor fail to meet its burden under
the arbitrary and capricious standard applicable here.
18
C. Challenge to Discussions
The parties are in apparent agreement that discussions held with offerors under
FAR 15.306(d) must be meaningful and not misleading. ECF No. 55-1 at 16-17, 30; ECF
No. 58-1 at 46-49 & n.16; ECF No. 59 at 26. There also appears to be no real dispute
that an agency has considerable discretion in deciding whether to reopen or continue
discussions. See ECF No. 58-1 at 47-48 (citing cases); see also FAR 15.306(d)(3) (“The
scope and extent of discussions are a matter of contracting officer judgment.”). The
parties dispute, however, whether the Round 1 and Round 2 discussions held with
iAccess were meaningful and not misleading, and whether further discussions should
have been held with iAccess. It is to these two topics that the court now turns.
1. Round 1 and Round 2 Discussions
The court notes at the outset that for each of the flaws under the Systems
Engineering subfactor noted in iAccess’s proposal, the SCRD identified the ENs that had
addressed the pertinent MoM in Round 1 and Round 2 discussions with iAccess. ECF
No. 25-3 at 5-7, 9-10. The cited ENs in the SCRD that were delivered to iAccess are EN
Nos. [ ]. Id. Plaintiff also cites a number of ENs that were issued by the agency to
iAccess, in support of its arguments regarding discussions, including EN Nos. [ ]. ECF
No. 55-1 at 19, 21, 32-33, 37-38; ECF No. 62 at 7.
The court has reviewed the content of all of the ENs issued by the agency that are
cited in plaintiff’s briefs and compared these ENs to the proposal flaws noted in the
SCRD. See ECF No. 25-3 at 5-11, 1542-47, 1563-65, 1572-76, 1580-82, 1589-1612,
1615-20, 1624-33. The court has also reviewed the relevant portions of the Technical
Evaluation Report, which provides a comprehensive recitation of the Systems
Engineering ENs issued to iAccess, the responses to those ENs received by the agency,
and the agency’s evaluation of iAccess’s final proposal. ECF No. 25-3 at 1129-1638.
Based on this record, the court concludes that the agency met the standard for meaningful
discussions, because the ENs cited by plaintiff led iAccess into the areas of its proposal
that, if changed, could have improved iAccess’s chances for award. See, e.g., Carahsoft
Tech. Corp. v. United States, 86 Fed. Cl. 325, 342 (2009) (“Meaningful discussions are
discussions that lead offerors into the areas of their proposals requiring amplification or
correction.”) (citations omitted).
The parties focus much of their attention on EN Nos. [ ] and [ ], and these ENs are
representative of the ENs in the evaluation record of discussions. ECF No. 55-1 at 35-36;
ECF No. 58-1 at 39-41; ECF No. 59 at 16-18; ECF No. 62 at 10-11; ECF No. 65 at
15-17; ECF No. 66 at 3-4. As discussed earlier in this opinion, the Air Force was
concerned that iAccess’s plan to [ ] was a weakness; this concern was reflected in
negative risk ratings received by iAccess’s final proposal in both the [ ] and [ ] MoMs.
See supra. This concern was clearly communicated to iAccess in EN No. [ ], and
iAccess’s response to EN No. [ ] did not alleviate the agency’s concern. ECF No. 25-3 at
19
1615, 1617. The agency therefore issued EN No. [ ], a “Follow-on EN” for the Round 2
discussions. Id. at 1617.
EN No. [ ] reiterated the agency’s concern with iAccess’s [ ]. Id. at 1618. This
EN was marked as “resolved.” Id. at 1620. The Technical Evaluation Report shows,
however, that iAccess’s response to EN No. [ ] did not remove the agency’s doubt about
the solution proposed by iAccess. Id. at 1454-62. The SCRD also contains a rational
assessment of the remaining flaws in iAccess’s [ ]. Id. at 7-9, 11. Based on the record
before the court, the SCRD and other documents in the record show that the agency
conducted meaningful discussions with iAccess.
Plaintiff also characterizes the ENs as misleading. Plaintiff contends, for example,
that the agency, in EN No. [ ], did not specify whether it wanted specific artifacts or
better justifications, for MoM [ ] where iAccess had marked sections of its [ ], and that
this lack of clarity prevented iAccess from improving its proposal. ECF No. 55-1 at 8,
26-27, 30. The court finds, however, that EN No. [ ], ECF No. 25-2 at 808-09, was
meaningful under the discretionary standard applicable here: “While meaningful
discussions should be as specific as practical considerations permit, they do not require
the agency to identify each and every item that could be raised as to improve its
proposal.” Carahsoft, 86 Fed. Cl. at 343 (internal quotations and citations omitted). Nor
has the court found any record evidence that EN No. [ ] was misleading. See DMS
All-Star Joint Venture v. United States, 90 Fed. Cl. 653, 670 (2010) (“[D]iscussions
become misleading when communications from the government misdirect the protestor
as it revises its proposal.”) (citations omitted). For all of the above reasons, the Round 1
and Round 2 discussions have not been shown to be improper.
2. Round 3 Discussions Not Held
Plaintiff notes that the agency’s technical evaluators produced additional
follow-on ENs that were never issued, EN Nos. [ ] and [ ], and argues that additional
discussions would have permitted iAccess to resolve weaknesses in the Systems
Engineering subfactor. ECF No. 55-1 at 31, 39, 41. According to plaintiff, the agency’s
decision to not open Round 3 discussions with iAccess “was irrational, arbitrary,
capricious, and an abuse of discretion.” 10 ECF No. 62 at 20. There are two principles
that support the agency’s decision to not open a third round of discussions with iAccess.
10
In its reply brief, plaintiff argues for the first time that mere clarifications under
FAR 15.306(a)(2), not Round 3 discussions, could have resolved the proposal
weaknesses that led to iAccess being eliminated from the second competitive range. ECF
No. 62 at 18-19. This argument is both untimely raised, in the court’s view, and
unpersuasive. As L3 points out, the revisions required to remove the bases for iAccess’s
20
First, the number of rounds of discussions to be held with offerors is largely a
matter of the procuring agency’s discretion. See FAR 15.306(d)(3) (noting both that “the
contracting officer must . . . indicate to, or discuss with, each offeror still being
considered for award, deficiencies [and] significant weaknesses,” but also that “[t]he
scope and extent of discussions are a matter of contracting officer judgment”); see also
FAR 15.306(d)(5) (“If, after discussions have begun, an offeror originally in the
competitive range is no longer considered to be among the most highly rated offerors
being considered for award, that offeror may be eliminated from the competitive range
whether or not all material aspects of the proposal have been discussed, or whether or not
the offeror has been afforded an opportunity to submit a proposal revision . . . .”). The
parties cite numerous authorities, but no binding precedent on this court, for guidance on
the topic of the contracting officer’s discretion to cut off discussions, or to extend
discussions, with a particular offeror. ECF No. 58-1 at 46-49; ECF No. 59 at 24, 29; ECF
No. 62 at 20; ECF No. 65 at 21-22. Having considered all of the parties’ arguments and
the extensive record of this case, the agency’s decision to not open a third round of
discussions with iAccess was in accordance with the FAR and these authorities. See,
e.g., Lyon Shipyard, Inc. v. United States, 113 Fed. Cl. 347, 357 (2013) (“An agency
need not reopen discussions simply because it perceives some weakness in an offeror’s
best and final proposal.”) (citations omitted).
The second principle concerns the role of new weaknesses or deficiencies that
appear in an offeror’s revised proposal after discussions have begun. This principle
addresses the scenario where an offeror, when responding to other agency concerns,
creates a new flaw in a proposal section that was previously adequate. In this protest,
iAccess altered section [ ] of its [ ] to its detriment in response to Round 2 discussions, by
marking this [ ] and [ ]. ECF No. 52-6 at 219.
Deficiencies or weaknesses that appear for the first time in a revised proposal
during discussions do not oblige the agency to extend discussions further with that
offeror. See Tele-Consultants, Inc. v. United States, No. 19-203C, 2019 WL 1615801, at
*10 (Fed. Cl. Apr. 12, 2019) (rejecting the protestor’s “contention that the Army was
required to reopen discussions after [the protestor’s] revised proposal introduced a new
issue of noncompliance with the Solicitation’s requirements”); Iron Bow Techs., LLC v.
United States, 133 Fed. Cl. 764, 779 & n.11 (2017) (stating that the government is not
obliged to reopen discussions with an offeror that makes unprompted negative changes to
its revised proposal after discussions) (citations omitted). The Air Force, therefore, was
not obliged to reopen discussions with iAccess to allow iAccess an opportunity to further
revise [ ]. For these reasons, plaintiff’s challenge to the discussions held with iAccess,
Unacceptable and High Technical Risk ratings for Systems Engineering exceed the scope
of mere clarifications under FAR 15.306(a)(2). ECF No. 65 at 21-22.
21
contending that these discussions were not meaningful, were misleading, or were
otherwise improper, must be rejected.
D. De Facto Responsibility Determination or Technical Evaluation
Plaintiff’s final protest ground is that its elimination from the second competitive
range, allegedly for technical flaws in its proposal, was, in effect, an improper de facto
responsibility determination. ECF No. 45 at 11-12. The primary authorities cited for
plaintiff’s argument are KWR Construction, Inc., v. United States, 124 Fed. Cl. 345
(2015), Competitive Range Solutions, LLC, B-413104.10, 2017 CPD ¶ 124, 2017 WL
1511203 (Comp. Gen. Apr. 18, 2017), and Joanell Laboratories, Inc., B-242415,
B-242415.8, B-242415.9, B-242415.10, 92-1 CPD ¶ 369, 1992 WL 88096 (Comp. Gen.
Apr. 15, 1992). ECF No. 55-1 at 43; ECF No. 62 at 21-23. Plaintiff also relies on FAR
9.104-1. ECF No. 62 at 23, 25.
In essence, plaintiff’s argument contains three propositions. First, a small business
may not be eliminated from a competition for responsibility reasons unless a Certificate
of Competency has been sought from the Small Business Administration (SBA). ECF
No. 55-1 at 42-43. Second, iAccess is alleged to have been eliminated by the Air Force
from the second competitive range for responsibility reasons. Id. at 43; ECF No. 62 at
24-25. Third, plaintiff concludes that the agency’s de facto responsibility determination
was “irrational and impermissible.” ECF No. 55-1 at 43.
Although the government and L3 do not disagree with plaintiff’s first proposition,
they argue that the elimination of iAccess from the second competitive range was not a
de facto responsibility determination. As L3 states:
The Air Force found iAccess’s proposal Unacceptable and High Risk
under a Technical Subfactor. The Air Force properly then excluded iAccess
from the competitive range and did not make any responsibility
determination for iAccess, de facto or otherwise. Accordingly, the Air Force
decision falls squarely within the Air Force’s purview, and the SBA has no
role here.
ECF No. 58-1 at 51-52. In the court’s view, this is an accurate representation of the facts
established by the administrative record in this case.
The government compares the responsibility determination elements set forth in
FAR 9.104-1 with the technical evaluation results for iAccess for the Systems
Engineering subfactor. ECF No. 66 at 12. Defendant notes that “none of the language
iAccess cites from the [SCRD] reflects a concern with iAccess’s financial resources
(FAR § 9.104-1(a)), its existing business commitments (FAR § 9.104-1(b)), its
performance record (FAR § 9.104-1(c)-(d)) or its organizational, operational or capital
resources (FAR § 9.104-1(e)-(f)).” Id. (citing ECF No. 62 at 24-25). The court must
22
agree with L3 and the government that iAccess’s elimination from the second
competitive range was for “specific technical concerns with the proposed approach” for
Systems Engineering. Id. Because the record does not support plaintiff’s contention that
a de facto responsibility determination occurred here, this protest ground, too, must be
rejected.
E. Prejudice Inquiry Not Required, and Permanent Injunctive Relief Not
Warranted
Because plaintiff has not met its burden to show significant error in the agency’s
decision to eliminate iAccess from the second competitive range in this procurement, an
inquiry into the prejudicial nature of demonstrated procurement errors is not required.
Further, because plaintiff has not succeeded on the merits of its protest, the court need not
examine the factors required to support an award of injunctive relief. See Dell Federal,
906 F.3d at 999 & n.13 (stating that “proving success on the merits is a necessary element
for a permanent injunction”). This protest must be dismissed on the merits.
IV. Conclusion
Accordingly,
(1) Plaintiff’s motion for judgment on the AR, ECF No. 55, is DENIED;
(2) Intervenor-defendant’s motion to dismiss or, in the alternative,
cross-motion for judgment on the AR, ECF No. 58, is DENIED in
part, as to the motion to dismiss, and GRANTED in part, as to the
cross-motion for judgment on the AR;
(3) Defendant’s cross-motion for judgment on the AR, ECF No. 59, is
GRANTED;
(4) The clerk’s office is directed to ENTER final judgment for defendant
and intervenor-defendant, DISMISSING plaintiff’s complaint, with
prejudice; and,
(5) On or before June 21, 2019, the parties shall CONFER and FILE a
proposed redacted version of this opinion, with any competition-
sensitive or otherwise protectable information blacked out.
IT IS SO ORDERED.
s/Patricia E. Campbell-Smith
PATRICIA E. CAMPBELL-SMITH
Judge
23