[Cite as Hannibal Dev., L.L.C. v. Monroe Water Sys., 2019-Ohio-3697.]
IN THE COURT OF APPEALS OF OHIO
SEVENTH APPELLATE DISTRICT
MONROE COUNTY
HANNIBAL DEVELOPMENT, LLC,
Plaintiff-Appellant,
v.
MONROE WATER SYSTEMS, et al.,
Defendants-Appellees.
OPINION AND JUDGMENT ENTRY
Case No. 18 MO 0023
Civil Appeal from the
Court of Common Pleas of Monroe County, Ohio
Case No. 2018-224.
BEFORE:
Cheryl L. Waite, Gene Donofrio, David A. D’Apolito, Judges.
JUDGMENT:
Affirmed in part. Reversed and Remanded in part.
Atty. Randolph L. Snow, Atty. James M. Wherley, Jr., Atty. Robert B. Preston III, Black,
McCuskey, Souers & Arbaugh, 220 Market Ave. S., Suite 1000, Canton, Ohio 44702,
for Plaintiff-Appellant Hannibal Development, LLC.
Atty. Thomas D. White, Atty. Matthew A. Kearney, The White Law Office, Co., 209 N.
Washington Street, Millersburg, Ohio 44654, for Defendant-Appellee Monroe Water
Systems.
Atty. James L. Peters, Monroe County Prosecutor, 101 North Main Street, Room 15,
P.O. Box 430, Woodsfield, Ohio 43793-0430, for Defendants-Appellees Monroe
County Auditor and Treasurer.
–2–
Dated: September 11, 2019
WAITE, P.J.
{¶1} Appellant Hannibal Development, L.L.C. (“Hannibal”) appeals a September
27, 2018 Monroe County Court of Common Pleas decision to grant Appellee Monroe
Water Systems’ (“Monroe Water”) Civ.R. 12(B)(6) motion to dismiss. Hannibal argues
that the trial court improperly failed to consider its alternative causes of action before
granting the motion to dismiss the complaint in its entirety. Hannibal also argues that the
court should have granted Hannibal permission to amend the complaint in lieu of
dismissal. For the reasons provided, Hannibal’s arguments have merit in part.
Accordingly, the trial court’s dismissal of the contract claims found in counts one, two,
and three of the complaint is reversed and this case is remanded for further proceedings
on these issues. However, the court’s judgment is affirmed as to the dismissal of the Title
7 claim in count one of the complaint.
Factual and Procedural History
{¶2} In July of 2014, Hannibal purchased the former Ormet manufacturing facility
(“Ormet”) which is located in Monroe County. Ormet was not in use at the time of the
purchase nor at anytime during Hannibal’s ownership. At the time of purchase, Hannibal
informed Monroe Water that it had purchased Ormet and that any bills should be sent to
Hannibal. Apparently, Monroe Water suggested that Hannibal pay $5,000 per month until
a usage history could be determined.
{¶3} Monroe Water did not send Hannibal a bill until nearly a year later, and
Hannibal did not make any payments during that time. This bill sent on May 29, 2015 by
Case No. 18 MO 0023
–3–
Monroe Water was in the amount of $87,302.24. This bill stated that late fees of
$8,730.22 would be added if payment was not timely received. The late fee would raise
the total amount to $96,032.46. According to Hannibal, Monroe Water failed to return
phone calls regarding this bill. At some point, Hannibal was informed that the amount
was due in full and that partial payments would not be accepted. Sometime thereafter,
Hannibal discovered and repaired an underground leak that was apparently responsible
for the high usage.
{¶4} Initially, Hannibal did not pay the bill and disputed the amount. Monroe
Water transferred the balance to the county auditor, who transferred it to the county
treasurer. The treasurer placed a lien on the Ormet property in the amount of
$228,436.60. It is unclear which portion of this amount derived from usage and which is
the result of late fees. Hannibal paid the amount in full to satisfy the lien, but continued
to dispute the amount owed. Hannibal subsequently sold the Ormet property after the
lien was removed.
{¶5} On June 13, 2018, Hannibal filed a complaint against Monroe Water,
Monroe County Auditor, Monroe County Treasurer, and John Does 1-5. The first count
of the complaint raised a claim to recover funds paid. This claim is based on an argument
that Monroe Water failed to determine the actual amount of usage through reading the
meter and failed to provide a quarterly bill to Hannibal, in violation of R.C. 743.04. The
complaint also raises alternate theories of breach of implied contract to monitor usage
and issue bills in the event that Title 7 of the Revised Code does not apply. The second
count of the complaint raises unjust enrichment. The third count requests declaratory
Case No. 18 MO 0023
–4–
judgment to establish that Hannibal did not owe the amount paid. This claim, presumably
focusing on the late fees, requests that these fees be returned to Hannibal.
{¶6} On August 8, 2018, Monroe Water filed a Civ.R. 12(B)(6) motion to dismiss
the complaint in its entirety. Monroe Water argued that Hannibal’s first count is based on
Chapter 7 of the Ohio Revised Code, which does not apply to an independent political
subdivision. Because they contended the second and third counts were predicated on
the first, Monroe Water argued that they must also be dismissed.
{¶7} On September 27, 2018, the trial court granted Monroe Water’s motion.
The trial court reasoned that Chapter 7 of the Ohio Revised Code does not apply to a
political subdivision pursuant to Chapter 6119. The court decided that Hannibal’s second
and third counts could not succeed without establishing the Chapter 7 claim. The court
did not specifically address Hannibal’s implied contract claim. It is from this judgment
entry that Hannibal timely appeals.
ASSIGNMENT OF ERROR
The Trial Court erred in granting Appellee's motion to dismiss under Ohio
Civ.R. 12(B)(6).
{¶8} Hannibal contends that, even if Title 7 does not apply to Monroe Water, it
was error for the trial court to dismiss the entire complaint where alternative contract
claims were asserted within the complaint. Hannibal argues that the first count included
an alternative claim based on contract and that the second and third counts are also
grounded in contract law. Hannibal also argues that the trial court should have allowed
them to amend the complaint instead of dismissing it in its entirety.
Case No. 18 MO 0023
–5–
{¶9} Monroe Water responds by arguing that each of Hannibal’s claims are
rooted in Title 7, which does not apply to them. While conceding that the unjust
enrichment and declaratory judgement claims are not specifically rooted in Title 7, Monroe
Water argues that the underlying complaint is based on Title 7.
{¶10} “A Civ.R. 12(B)(6) motion to dismiss for failure to state a claim upon which
relief can be granted tests only the legal sufficiency of the complaint.” Youngstown Edn.
Assn. v. Kimble, 2016-Ohio-1481, 63 N.E.3d 649, ¶ 11 (7th Dist.), citing State ex rel.
Hanson v. Guernsey Cty. Bd. of Commrs., 65 Ohio St.3d 545, 548, 605 N.E.2d 378
(1992). When reviewing a Civ.R. 12(B)(6) motion, “the court must accept the factual
allegations contained in the complaint as true and draw all reasonable inferences from
these facts in favor of the plaintiff.” Kimble, supra, at ¶ 11, citing Mitchell v. Lawson Milk
Co., 40 Ohio St.3d 190, 192, 532 N.E.2d 753 (1988). In order to grant a Civ.R. 12(B)(6)
motion, “it must appear beyond doubt from the complaint that the plaintiff can prove no
set of facts entitling him to recovery.” O'Brien v. Univ. Community Tenants Union, Inc.,
42 Ohio St.2d 242, 327 N.E.2d 753 (1975), syllabus. However, “[i]f there is a set of facts
consistent with the complaint that would allow for recovery, the court must not grant the
motion to dismiss.” Kimble, supra, at ¶ 11, citing York v. Ohio State Hwy. Patrol, 60 Ohio
St.3d 143, 144, 573 N.E.2d 1063 (1991).
{¶11} A Civ.R. 12(B)(6) claim is reviewed de novo. Ford v. Baska, 2017-Ohio-
4424, 93 N.E.3d 195, ¶ 6 (7th Dist.), citing Perrysburg Twp. v. Rossford, 103 Ohio St.3d
79, 2004-Ohio-4362, 814 N.E.2d 44, ¶ 5.
{¶12} Monroe Water is a regional water district that is organized pursuant to
Chapter 6119 of the Ohio Revised Code. Monroe Water contends that R.C. 6119.06
Case No. 18 MO 0023
–6–
provides that regional water districts “may adopt their own rules and regulations, levy and
collect taxes and special assessments, and set their own rates and terms of service.”
(Emphasis deleted.) (Appellee Brf., p. 9.)
{¶13} In relevant part, R.C. 6119.06 provides:
Upon the declaration of the court of common pleas organizing the regional
water and sewer district pursuant to section 6119.04 of the Revised Code
and upon the qualifying of its board of trustees and the election of a
president and a secretary, said district shall exercise in its own name all the
rights, powers, and duties vested in it by Chapter 6119. of the Revised
Code, and, subject to such reservations, limitations and qualifications as
are set forth in this chapter, such district may:
(A) Adopt bylaws for the regulation of its affairs, the conduct of its business,
and notice of its actions;
***
(W)(1) Charge, alter, and collect rentals and other charges for the use of
services of any water resource project as provided in section 6119.09 of the
Revised Code. Such district may refuse the services of any of its projects
if any of such rentals or other charges, including penalties for late payment,
are not paid by the user thereof, and, if such rentals or other charges are
not paid when due and upon certification of nonpayment to the county
auditor, such rentals or other charges constitute a lien upon the property so
Case No. 18 MO 0023
–7–
served, shall be placed by the auditor upon the real property tax list and
duplicate, and shall be collected in the same manner as other taxes.
***
(BB) Do all acts necessary or proper to carry out the powers granted in
Chapter 6119. of the Revised Code.
{¶14} In relevant part, R.C 6119.09 states:
A regional water and sewer district may charge, alter, and collect rentals or
other charges, including penalties for late payment, for the use or services
of any water resource project or any benefit conferred thereby and contract
in the manner provided by this section with one or more persons, one or
more political subdivisions, or any combination thereof, desiring the use or
services thereof, and fix the terms, conditions, rentals, or other charges,
including penalties for late payment, for such use or services. Such rentals
or other charges shall not be subject to supervision or regulation by any
authority, commission, board, bureau, or agency of the state or any political
subdivision[.]
{¶15} Hannibal admits that count one is, in part, rooted in Title 7 of the Revised
Code. Thus, the trial court properly dismissed that claim. However, because Hannibal
raised alternative claims grounded in contract law, dismissal of the entire complaint was
improper.
Case No. 18 MO 0023
–8–
{¶16} Although count one did raise a Title 7 claim, it also provided: “[a]lternatively,
if such water charges are not considered to be taxes or assessments under R.C. 743.04,
then Monroe Water breached an implied contract to issue bills to Hannibal within a
reasonable time period and to monitor the water usage at the Ormet Facility.” (6/13/18
Complaint, p. 6.)
{¶17} In relevant part, count two of the complaint, titled “Unjust Enrichment,”
states:
32. By making the payment referenced above, a benefit was conferred by
Hannibal with knowledge by Defendants of the payment and retention of the
payment by Defendants under circumstances where it would be unjust to
do so.
33. The payment was made due to illegal water bills issued by Monroe
Water, which were then used to place an improper lien upon the Ormet
Facility.
(6/13/18 Complaint, p. 6.)
{¶18} In relevant part, count three of the complaint, titled “Declaratory Judgment”
states: “Hannibal did not owe the fees charged by Monroe Water and only paid them,
under protest, because a lien was placed upon the Ormet Facility.” (6/13/18 Complaint,
p. 7.)
{¶19} Monroe Water insists that they are entitled to create their own billing
procedure as they are not bound by those contained in Title 7. However, the question is
not whether Monroe Water violated Title 7. The question is whether Monroe Water
Case No. 18 MO 0023
–9–
violated its own billing procedures, procedures it created and adopted by Monroe Water
presumably pursuant to R.C. 6119. Monroe Water conceded at oral argument that
because this matter was dismissed at this early stage in the proceedings, its billing
procedures were not made part of the trial court record. As such, the issue of whether
Monroe Water breached its own procedures created pursuant to R.C. 6119 cannot be
resolved by simply looking to the complaint. Instead, discovery is required to develop
Hannibal’s claim.
{¶20} As the law requires denial of a Civ.R. 12(B)(6) motion where there exists
any set of facts consistent with the complaint that may allow for recovery, the trial court
erroneously granted Monroe Water’s motion to dismiss the complaint in its entirety.
Although the trial court properly dismissed the Title 7 claim, the remaining contract claims
cannot be resolved by reviewing the complaint, alone. Accepting all facts alleged by
Hannibal as true, there are allegations within the complaint that could allow Hannibal to
recover pursuant to law.
{¶21} We note that Hannibal also argues that the trial court should have allowed
them to amend the complaint for a more definitive statement of facts in lieu of granting
the motion to dismiss the complaint in its entirety. Due to our resolution of Hannibal’s
other arguments, this issue is moot. Accordingly, Hannibal’s sole assignment of error has
merit and is sustained.
Conclusion
{¶22} Hannibal argues that the trial court erroneously failed to consider the
alternative contractual causes of action before it granted a Civ.R. 12(B)(6) motion to
dismiss the complaint in its entirety. For the reasons provided, their argument regarding
Case No. 18 MO 0023
– 10 –
the contractual claims raised in the complaint has merit. Accordingly, the trial court’s
judgment as to these claims is reversed and remanded for further proceedings concerning
these issues according to law and consistent with this Court’s Opinion. However, the trial
court’s dismissal of the direct Title 7 claim is affirmed.
Donofrio, J., concurs.
D’Apolito, J., concurs.
Case No. 18 MO 0023
[Cite as Hannibal Dev., L.L.C. v. Monroe Water Sys., 2019-Ohio-3697.]
For the reasons stated in the Opinion rendered herein, the assignment of error
is sustained in part and overruled in part. It is the final judgment and order of this Court
that the judgment of the Court of Common Pleas of Monroe County, Ohio, is affirmed
in part as to the Title 7 claim and reversed in part as to the contract claims. We hereby
remand this matter to the trial court for further proceedings according to law and
consistent with this Court’s Opinion. Costs to be taxed against the Appellees.
A certified copy of this opinion and judgment entry shall constitute the mandate
in this case pursuant to Rule 27 of the Rules of Appellate Procedure. It is ordered that
a certified copy be sent by the clerk to the trial court to carry this judgment into
execution.
NOTICE TO COUNSEL
This document constitutes a final judgment entry.