Case: 19-1692 Document: 41 Page: 1 Filed: 05/29/2020
United States Court of Appeals
for the Federal Circuit
______________________
COOPER/PORTS AMERICA, LLC,
Appellant
v.
SECRETARY OF DEFENSE,
Appellee
______________________
2019-1692
______________________
Appeal from the Armed Services Board of Contract Ap-
peals in Nos. 61348, 61351, 61536, 61537, Administrative
Judge James R. Sweet, Administrative Judge Owen C. Wil-
son, Administrative Judge Richard Shackleford.
______________________
Decided: May 29, 2020
______________________
ANDREW M. GROSSMAN, Baker & Hostetler LLP, Wash-
ington, DC, argued for appellant. Also represented by
WILLIAM BARRON ARBUTHNOT AVERY.
KELLY A. KRYSTYNIAK, Commercial Litigation Branch,
Civil Division, United States Department of Justice, Wash-
ington, DC, argued for appellee. Also represented by
ANTHONY F. SCHIAVETTI, JOSEPH H. HUNT, ROBERT
EDWARD KIRSCHMAN, JR., PATRICIA M. MCCARTHY; JEFFREY
P. HILDEBRANT, CARYL A. POTTER, III, DANIELLE RUNYAN,
Case: 19-1692 Document: 41 Page: 2 Filed: 05/29/2020
2 COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE
Air Force Legal Operations Agency, Joint Base Andrews,
MD.
______________________
Before DYK, TARANTO, and CHEN, Circuit Judges.
DYK, Circuit Judge.
Cooper/Ports America LLC (“CPA”) provided stevedor-
ing and related terminal services to the government under
a contract dated January 28, 2015. CPA submitted a claim
that the government failed to provide a timely preliminary
written notice of intent to exercise the government’s option
to extend the parties’ contract, and that the subsequent op-
tion exercise was ineffective. The claim was denied by a
contracting officer, and CPA appealed before the Armed
Services Board of Contracts Appeals (“Board”). The Board
held that the government satisfied the preliminary written
notice requirement. We affirm.
BACKGROUND
In January 2015, CPA’s predecessor-in-interest, Ship-
pers Stevedoring Co. (“SSC”), was awarded a contract from
the United States Transportation Command, a component
of the Department of Defense. The United States Trans-
portation Command supports military transportation to
other commands and government organizations. The con-
tract required SSC to provide stevedoring and related ter-
minal services along the Eastern Seaboard of the United
States, including Charleston, South Carolina (“the
Charleston contract,” HTC711-15-D-R036). SSC was sep-
arately awarded a contract covering the Gulf region (“the
Beaumont contract,” HTC711-15-D-R037). Only the
Charleston contract is at issue in this appeal.
The original Charleston contract executed by SSC in-
corporated a Federal Acquisition Regulation (“FAR”) provi-
sion (section 52.217-9) that gave the government options to
extend the term of the agreement for up to four one-year
Case: 19-1692 Document: 41 Page: 3 Filed: 05/29/2020
COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE 3
periods. That provision required that the government give
CPA “a preliminary written notice of its intent to extend at
least 60 days before the contract expire[d].” J.A. 65; see
also 48 C.F.R. § 52.217-9 (“Option to Extend the Term of
the Contract”). Providing such notice did not obligate the
government to actually exercise the option. After the pre-
liminary notice, the government was required to exercise
the option itself within 15 days of the contract expiration
date. Section 52.217-9 contained no language permitting
adjustment of the contract price.
The original contract term expired on June 30, 2016.
On April 28, 2016, the government provided a preliminary
written notice of its intent to exercise the first-year option
to extend the term of the Charleston contract to June 30,
2017. This communication was in a formal letter titled
“Contract HTC711-15-D-R036, Preliminary Notice of In-
tent to Exercise Option” and stated that “[i]n accordance
with FAR [§] 52.217-9, Option to Extend the Term of the
Contract, [SSC is] hereby given preliminary notice of the
Government’s intent to extend the term of the contract
through 30 June 2017.” J.A. 107. Thereafter, on June 15,
2016, the government exercised the first-year option, ex-
tending the contract period to June 30, 2017. If the gov-
ernment wished to exercise its option for a second-year
extension, it had to provide CPA a preliminary written no-
tice of its intent by May 1, 2017, pursuant to the 60-day
notice requirement of section 52.217-9.
SSC’s business experienced difficulties, and this led to
CPA’s acquisition of SSC’s assets on September 30, 2016. 1
CPA replaced SSC as a party to the Charleston contract
through novation and modification agreements that were
signed on November 15, 2016, and December 19, 2016,
1 CPA was named “Integrated Marine Services,
LLC” when it acquired SSC’s assets. CPA changed to its
current name in October 2016.
Case: 19-1692 Document: 41 Page: 4 Filed: 05/29/2020
4 COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE
respectively. Similar agreements were reached with re-
spect to the Beaumont contract.
After CPA purchased SSC’s assets on September 30,
2016, it began urging the government to revise the pricings
of the Charleston and Beaumont contracts. CPA then as-
serted that it might default on the contracts because the
contracts’ pricings were not profitable. On January 31,
2017, the government’s contracting officer, William Sea-
mon, sent an email (“the January 31 email”) to CPA’s Vice
President of Operations, Chris Lewis, stating:
The Government intends to exercise options at
awarded rates on contracts HTC711-15-D-R036
[(i.e., the Charleston contract)] and HTC711-15-D-
R037 [(i.e., the Beaumont contract)]. With this, the
Government expects [CPA] to continue performing
per the terms and conditions of the contract.
J.A. 117. The question here is whether this email consti-
tuted a preliminary written notice with respect to the
Charleston contract.
No such issue exists with respect to the Beaumont con-
tract, because on February 1, 2017, Mr. Seamon sent a for-
mal letter, stating that “[CPA was] hereby given
preliminary notice of the Government’s intent to extend the
term of the [Beaumont] contract through 2 April 2018.”
J.A. 111. But it was not until May 3, 2017, that Mr. Sea-
mon sent a formal letter to CPA concerning the Charleston
contract, stating that “[CPA was] hereby given preliminary
notice of the Government’s intent to extend the term of the
[Charleston] contract through 30 June 2018.” J.A. 109.
The May 3 letter would not have been a timely preliminary
notice under the contract.
On June 9, 2017, CPA responded to the May 3 letter
and stated that the government’s preliminary written no-
tice under section 52.217-9 was untimely because the
May 3 letter was received after May 1, 2017. On June 13,
Case: 19-1692 Document: 41 Page: 5 Filed: 05/29/2020
COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE 5
2017, the government pointed to the January 31 email as
the preliminary written notice of its intent to exercise the
second-year option, and sent a letter exercising that option.
On June 15, 2017, CPA responded that it would “be per-
forming the Modification [of the Charleston contract] un-
der protest” because that contract “w[ould] expire by its
own terms with the conclusion of the period of performance
on June 30, 2017.” J.A. 134.
Beginning in July 2017, CPA filed several claims with
the government, seeking a declaration that the Charleston
contract had expired and requesting compensation for ad-
ditional money for its performance under protest. A con-
tracting officer denied the claims, and CPA appealed to the
Board. The Board granted summary judgment in favor of
the government, holding that “the January [31] email was
a preliminary notice of intent,” J.A. 9, and that the “email
unambiguously, absolutely, and positively provided pre-
liminary written notice of the government’s intent to ex-
tend at least 60 days before the contract expired on May 1,
2017,” J.A. 6.
CPA appeals, and we have jurisdiction under 41 U.S.C.
§ 7107(a)(1) and 28 U.S.C. § 1295(a)(10). We review de
novo the “the Board’s conclusions of law, including grants
of summary judgment,” Rex Sys., Inc. v. Cohen, 224 F.3d
1367, 1371 (Fed. Cir. 2000), and the “interpretation of a
government contract,” Lear Siegler Servs., Inc. v.
Rumsfeld, 457 F.3d 1262, 1266 (Fed. Cir. 2006). After oral
argument, at our request, the parties supplemented the
record on appeal to include additional record documents re-
lating to communications between the parties before and
after their January 31 email exchange.
DISCUSSION
The issue in this case is whether the government’s Jan-
uary 31 email was a “preliminary written notice” required
by section 52.217-9. CPA argues that the January 31 email
was ineffective for various reasons. Some of these are
Case: 19-1692 Document: 41 Page: 6 Filed: 05/29/2020
6 COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE
without substance, such as CPA’s contentions that the no-
tice was unclear as to whether it referred to the Charleston
contract (it did so specifically); that the notice was ambig-
uous as to whether it was directed to the second option year
or a later year (there was no ambiguity); or whether it was
ambiguous because in contrast to the earlier notice for the
first-year option it was informal (the contract did not re-
quire formality). We discuss below CPA’s other arguments.
First, CPA asserts that the notice was ambiguous be-
cause there was no way to know whether the January 31
email referred to the one-year option under section 52.217-
9 or the six-month option under section 52.217-8, which
was also provided in the contract. We have recognized that
a required notice must be unambiguous. See McCall Stock
Farms, Inc. v. United States, 14 F.3d 1562, 1569–70 (Fed.
Cir. 1993); see also First Commerce Corp. v. United States,
335 F.3d 1373, 1379–80 (Fed. Cir. 2003) (holding that a
binding agreement requires an unambiguous acceptance);
Holly Corp., ASBCA No. 24975, 83-1 BCA ¶ 16,327, 1983
ASBCA LEXIS 272, at *21 (“The acceptance of an option,
to be effectual, must be unqualified, absolute, uncondi-
tional, unequivocal, unambiguous, positive, without reser-
vation, and according to the terms or conditions of the
option.”). We think that a similar standard applies to the
sufficiency of a preliminary notice of intent to exercise an
option in that it must provide clear notice to a reasonable
recipient.
The sufficiency of a notice is generally considered in the
context of the communication between the parties. Empire
Energy Mgmt. Sys., Inc. v. Roche, 362 F.3d 1343, 1356 (Fed.
Cir. 2004) (considering circumstances outside the notice);
Halifax Engineering, Inc. v. United States, 915 F.2d 689,
691 (Fed. Cir. 1990) (same); Black’s Law Dictionary (11th
ed. 2019) (explaining that due notice is “notice that is le-
gally adequate given the particular circumstance”).
Case: 19-1692 Document: 41 Page: 7 Filed: 05/29/2020
COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE 7
Here, CPA claims that the notice was unclear because
there was another option provision in the contract. In ad-
dition to the “Option to Extend the Term of the Contract”
by one-year extensions (section 52.217-9), the Charleston
contract included a separate “Option to Extend Services”
provision (section 52.217-8). This latter provision stated
that “[t]he Government may require continued perfor-
mance of any services . . . . The option provision may be ex-
ercised more than once, but the total extension of
performance hereunder shall not exceed 6 months.”
J.A. 65; see also 48 C.F.R. § 52.217-8. In support of its
claim, CPA asserts that Mr. Seamon (the contracting of-
ficer) testified that the January 31 email “could be inter-
preted as [referring to] either -9 or -8.” J.A. 257.
Mr. Seamon, however, was discussing the email’s language
on its face, and stated that he believed the January 31
email constituted a notice:
Q: . . . [Do] you think [the January] E-mail consti-
tutes preliminary notice of an intent to exercise an
option on the contract?
A: Yes.
Q: Okay. Why is that?
A: Because it specifically states that the govern-
ment intends to exercise options at award rates on
both contracts . . . .
J.A. 4 (alterations in original). In any event, as we discuss
below, the subjective and uncommunicated view of the par-
ties as to the notice is of no relevance. Unlike sec-
tion 52.217-9, the “Option to Extend Services” provision did
not require a preliminary written notice. That fact alone
makes it unlikely that a reasonable recipient of the notice
would think that the January 31 email was related to the
“Option to Extend Services” provision. Significantly, the
record shows that in late 2016 and early 2017 the parties
were discussing pricing for the Charleston contract,
Case: 19-1692 Document: 41 Page: 8 Filed: 05/29/2020
8 COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE
including the next one-year option extension period, and
that the subject of the January 31 email was understood to
be the option for a one-year extension period under section
52.217-9.
It appears that as early as October 2016 CPA asked for
a rate increase under the contract. It is apparent that CPA
was concerned about performing the contract at the exist-
ing pricing during additional option periods. Only a few
months remained in the Charleston contract that was set
to expire on June 30, 2017. On January 21, 2017,
Mr. Lewis of CPA emailed Mr. Seamon, stating that “I’d
like to discuss next steps for processing the contact [sic]
modifications for the labor increase we talked about from
Oct. 1st.” S.A. 2. On January 24, 2017, Mr. Seamon
emailed Mr. Lewis with a subject line “SSC-Charleston,”
stating that he was “attach[ing] . . . the final schedule of
rates from SSC for [the Charleston contract]” in light of
their “rate adjustment conversation.” S.A. 4–5. In re-
sponse, on January 24 and 25, 2017, Mr. Lewis communi-
cated that he would “try to back into the numbers so [they
could] have an agreed starting point,” S.A. 4, and would
“start working on the adjustment and w[ould] forward for
[Mr. Seamon’s] review,” S.A. 3.
A few days later, Mr. Seamon sent the January 31
email, stating that “[t]he Government intends to exercise
options at awarded rates on [the Charleston and Beaumont
contracts].” J.A. 117. At the same time, Mr. Seamon re-
jected any price adjustments, stating that “the Govern-
ment expects [CPA] to continue performing per the terms
and conditions of the contract.” Id. After the January 31
email, on February 23, 2017, Mr. Lewis emailed Mr. Sea-
mon, urging an “increase [to be] reflected in option year two
of the final SSC-Charleston schedule.” S.A. 36 (emphasis
added). The parties continued to discuss the
“O[ption]Y[ear]2 rates.” S.A. 57 (March 21, 2017 email);
S.A. 60 (showing future adjusted rates for the next one-
year period). Under these circumstances, there was no
Case: 19-1692 Document: 41 Page: 9 Filed: 05/29/2020
COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE 9
ambiguity and CPA “had sufficient notice” that the Janu-
ary 31 email was directed to the second-year option of the
Charleston contract. Empire, 362 F.3d at 1356 (quoting
Halifax, 915 F.2d at 691).
Second, CPA claims that the January 31 email was not
effective because the government did not intend it to be a
“preliminary written notice” under section 52.217-9, and
that CPA did not understand it to be such a notice. This
argument lacks merit because the January 31 email ex-
pressly stated that “[t]he Government intends to exercise
options at awarded rates [of the Charleston and Beaumont
contracts].” J.A. 117. It is well established that a notice is
judged by objective standards. See NEC Sols. (Am.), Inc. v.
United States, 411 F.3d 1340, 1346 (Fed. Cir. 2005) (hold-
ing that the sender’s intent and the recipient’s knowledge
of that intent were irrelevant to whether an email consti-
tuted notice required by a Customs statute and “the rele-
vant inquiry [wa]s whether [the recipient] would or could
have reasonably comprehended the e-mail as being unam-
biguous”); see also United States v. Locke, 471 U.S. 84, 88–
89, 102 (1985) (holding that the plaintiffs’ actual intent was
irrelevant to whether they satisfied a federal mining stat-
ute’s requirement to file a notice of intent to hold a mining
claim by a certain date); Rodash v. AIB Mortg. Co., 16 F.3d
1142, 1145–46 (11th Cir. 1994) (holding that the sender’s
subjective intent and recipient’s misunderstanding of the
notice required under the Truth in Lending Act (“TILA”)
was irrelevant to compliance with that requirement), abro-
gated on other ground by Veale v. Citibank, F.S.B., 85 F.3d
577 (11th Cir. 1996); Hauk v. JP Morgan Chase Bank USA,
552 F.3d 1114, 1122 (9th Cir. 2009) (holding that a sender’s
“undisclosed intent to act inconsistent with its disclosures”
required under the TILA was “irrelevant in determining
the sufficiency of those disclosures”). The government’s
purported undisclosed intent and CPA’s subjective under-
standing here did not make an otherwise valid notice inef-
fective.
Case: 19-1692 Document: 41 Page: 10 Filed: 05/29/2020
10 COOPER/PORTS AMERICA, LLC v. SECRETARY OF DEFENSE
Finally, CPA contends that the January 31 email failed
to give notice because it “d[id] not comply with FAR
§ 17.207(g)’s requirement that any ‘written document
which notifies the contractor of the exercise of the option
shall cite the option clause as authority.’” Appellant’s
Br. 24 (quoting 48 C.F.R. § 17.207(g)). CPA claims that the
January 31 email should have explicitly identified sec-
tion 52.217-9 in order for it to be an effective notice. We
agree with the Board that “by its plain terms, FAR
[§] 17.207(g) only applies to ‘[t]he contract modification or
other written document which notifies the contractor of the
exercise of the option,’ and not to the preliminary notice of
the intent.” J.A. 8–9 (second alteration in original).
CONCLUSION
For the foregoing reasons, we uphold the Board’s deci-
sion.
AFFIRMED
COSTS
No costs.