In the United States Court of Federal Claims
No. 19-1795C
(Filed: June 29, 2020)
___________________________________
) Suit for recovery of “charges” in
SHELL OIL COMPANY, et al., ) the form of environmental
) remediation costs incurred as a
Plaintiffs, ) result of avgas contracts entered in
) the 1940s; res judicata; partial
v. ) breach; Restatement (Second) of
) Contracts § 243; application of the
UNITED STATES, ) Contract Settlements Act and the
) savings clause of Pub. L. No. 111-
Defendant. ) 350
___________________________________ )
Michael W. Kirk, Cooper & Kirk, PLLC, Washington, D.C., for plaintiffs. Of counsel
were Vincent J. Colatriano and J. Joel Alicea, Cooper & Kirk, PLLC, Washington, D.C.
Stephen C. Tosini, Senior Trial Counsel, Commercial Litigation Branch, Civil Division,
United States Department of Justice, Washington, D.C., for defendant. With him on the briefs
were Joseph H. Hunt, Assistant Attorney General, Civil Division, and Robert E. Kirschman, Jr.,
Director, and Franklin E. White, Jr., Assistant Director, Commercial Litigation Branch, Civil
Division, United States Department of Justice, Washington, D.C.
OPINION AND ORDER
LETTOW, Senior Judge.
Plaintiffs Shell Oil Company, Atlantic Richfield Company, Texaco Inc., and Union Oil
Company of California (the “oil companies”) have brought suit against the United States (the
“government”) to obtain indemnification of costs incurred and related interest for environmental
remediation stemming from their performance of war production contracts in World War II. The
factual and procedural posture of this case is closely connected to prior litigation in this court and
the Federal Circuit. In 2018, the Federal Circuit affirmed a decision of this court awarding the
oil companies nearly $100 million for remediation costs incurred by the oil companies through
November 30, 2015. See Shell Oil Co. v. United States, 896 F.3d 1299, 1316 (Fed. Cir. 2018)
(“Fed. Cir. Damages Opinion”). That award also included simple interest running up to
November 30, 2015, even though payment of the judgment was not made until April 1, 2019.
Compl. ¶ 27. Remediation remains ongoing, see Compl. ¶ 23, and plaintiffs now seek damages
for additional remediation costs incurred after November 30, 2015 through November 15, 2019,
and interest on those amounts through the date of payment, Compl. ¶¶ 24-26. They also seek
interest related to costs incurred before November 2015 for the period between November 30,
2015 and the date of final payment on April 1, 2019. Compl. ¶ 27.
The court concludes that plaintiffs are entitled to indemnification and associated interest
through the date of payment for remediation costs incurred after November 30, 2015 through
November 15, 2019, but they are not entitled to any further interest on remediation costs incurred
before November 30, 2015.
BACKGROUND1
A. The Avgas Contracts and Associated Waste
The events underlying this dispute date back nearly eight decades to a world at war.
High-octane aviation gasoline (“avgas”), a technological development of the late 1930s,
“enabled aircraft to fly faster and higher, with improved rates of climb and higher payload
carrying capacity.” Shell Oil Co. v. United States, 751 F.3d 1282, 1285 (Fed. Cir. 2014) (“Fed.
Cir. Liability Opinion”). When the December 1941 attack on the naval base at Pearl Harbor
plunged the United States into World War II, avgas soon became the “most critically needed
refinery product” of the American war effort. Id. But despite its sudden status as an essential
military resource, avgas “production was nowhere near sufficient for the massive quantities the
United States and its allies would require to” wage war on a global scale. Id. Recognizing the
critical nature of its need within days after Pearl Harbor, the government concluded that “[i]t is
essential, in the national interest that the supplies of all grades of aviation gasoline for military,
defense and essential civilian uses be increased immediately to the maximum.” Id. at 1286
(emphasis and citations omitted). Accordingly, the government turned to the American
petroleum industry, and in 1942 and 1943 the United States entered into contracts to purchase
large quantities of avgas from the oil companies. See id.
The agreements required the oil companies to rapidly “expand avgas production
facilities,” Fed. Cir. Liability Opinion, 751 F.3d at 1286 n.3, and “sell vast quantities of avgas”
to the government with an artificially low profit margin between six and seven percent, id. at
1286-87. “The [o]il [c]ompanies agreed to the avgas contracts’ low profits in return for the
[g]overnment’s assumption of certain risks outside of the [o]il [c]ompanies’ control,” id. at 1296,
producing a “cooperative endeavor in which the [o]il [c]ompanies worked to achieve the
[g]overnment’s goal of maximizing avgas production and the [g]overnment assumed the risks of
such increased production,” id. at 1287. Among the concessions made, the government agreed in
each of the contracts to pay “any new or additional taxes, fees, or charges, . . . which [the oil
companies] may be required by any municipal, state, or federal law in the United States or any
foreign country to collect or pay by reason of the production, manufacture, sale or delivery of
[avgas].” Pls.’ App. at 19 (emphasis added).2
1
The following recitations do not constitute findings of fact by the court. Instead, the
recited factual elements are taken from the complaint, the parties’ briefs and attached
appendices, and previous opinions in related litigation.
Both plaintiffs and defendant attached appendices to their opening briefs. Plaintiffs’
2
appendix was consecutively paginated and will be cited as “Pls.’ App. at [page number].”
Defendant’s appendix was filed in seven separate attachments and will be cited as “Def.’s App.
at [appendix number]-[page number].”
2
These cooperative arrangements would prove “crucial to Allied success in the war,”
generating a twelve-fold increase in avgas production “from approximately 40,000 barrels per
day in December 1941 to 514,000 barrels per day in 1945.” Fed. Cir. Liability Opinion, 751
F.3d at 1287 (footnote omitted). But sudden production of avgas on such scale created
deleterious environmental side effects. Avgas blends a base of ordinary gasoline with petroleum
distillates and other hydrocarbons, the most prevalent of which is alkylate. See id. at 1288.
Alkylate is produced by the process of alkylation, which employs sulfuric acid as a catalyst and
results in a waste product called spent alkylation acid—which, even when further processed to
generate a waste product called acid sludge, has severely limited uses. See id. Predictably,
avgas production on the prodigious scale demanded by the war effort generated vast quantities of
acid waste, but the government twice denied applications to construct acid processing facilities,
and wartime scarcities in railroad tank cars inhibited transporting it elsewhere for reprocessing or
other potential uses including especially as raw material for fertilizer production. See id.
Consistent with its concentration on the military situation, the government prioritized
“production over reprocessing,” ultimately requiring the oil companies to dump “spent alkylation
acid, along with acid sludge, on property in California owned by Eli McColl.” Fed. Cir.
Damages Opinion, 896 F.3d at 1304 (footnote and citation omitted).3 The oil companies
disposed of acid waste on that property (“the McColl site”) from 1942 until shortly after the war
ended in 1945, when the need for avgas plummeted and the government terminated the contracts.
See Fed. Cir. Liability Opinion, 751 F.3d at 1288. “The McColl site closed on September 6,
1946.” Fed. Cir. Damages Opinion, 896 F.3d at 1304 (citation omitted).
B. Prior Litigation
Forty-five years later, in the early 1990s, the United States and California sued the oil
companies under the Comprehensive Environmental Response, Compensation, and Liability Act
of 1980 (“CERCLA”), 42 U.S.C. §§ 9601 et seq., seeking to recover costs from cleaning up the
McColl site. The district court first found both the oil companies and the United States jointly
and severally liable, see United States v. Shell Oil Co., 841 F. Supp. 962, 975-76 (C.D. Cal.
1993), but later allocated all the cleanup costs to the government as an “arranger” of the disposal,
see United States v. Shell Oil Co., 13 F. Supp. 2d 1018, 1030 (C.D. Cal. 1998). The Ninth
Circuit reversed that allocation, holding that the United States was not an arranger for most of
the waste at the site. See United States v. Shell Oil Co., 294 F.3d 1045, 1062 (9th Cir. 2002).4
Consequently, the oil companies have borne nearly all the clean-up costs incurred since 1994.
Compl. ¶ 16.
On remand from the Ninth Circuit, the district court transferred the oil companies’ breach
of contract counterclaim to this court. Fed. Cir. Liability Opinion, 751 F.3d at 1289. The oil
3
As relevant here, the avgas contracts pertained to the oil companies’ refineries in the Los
Angeles area: Shell’s Wilmington and Dominquez refineries, Atlantic Richfield’s Watson
refinery, Texaco’s Wilmington refinery, and Union’s Wilmington refinery. See Pls.’ Mot. for
Summary Judgment at 3, ECF No. 25.
4
The Ninth Circuit affirmed the district court’s ruling that the United States was
responsible for the “benzol” waste at the McColl site, which was about 5.5 percent of the total
waste. See Shell Oil, 294 F.3d at 1049.
3
companies voluntarily dismissed the transferred counterclaim without prejudice in order to
exhaust their administrative remedies. Id. Having done so, they filed a new complaint in this
court in 2006. See Shell Oil Co. v. United States, 80 Fed. Cl. 411 (2008). The court found the
government liable for all cleanup costs at the McColl site under the avgas contracts and granted
summary judgment to the oil companies, see id. at 420, but the Federal Circuit vacated that
judgment when it came to light that the judge to whom the case had been assigned had an
inadvertent conflict of interest stemming from his wife’s investments, see Shell Oil Co. v. United
States, 672 F.3d 1283, 1290-91 (Fed. Cir. 2012).
On remand from the Federal Circuit, the case was reassigned to a different judge, and the
court again granted summary judgment in 2013, but this time to the government. See Shell Oil
Co. v. United States, 108 Fed. Cl. 422, 448 (2013). The Federal Circuit reversed, determining
that “[t]he plain language of the new or additional charges provision [] requires the [g]overnment
to indemnify the [o]il [c]ompanies for CERCLA costs incurred ‘by reason of’ the avgas
contracts,” Fed Cir. Liability Opinion, 751 F.3d at 1293, and remanded the case back to this
court “to determine how much acid waste at the McColl site was ‘by reason of’ the avgas
contracts,” id. at 1303. Yet a different judge of this court held a trial on damages in early 2016,
finding that “all of the acid waste disposed of at the McColl site was ‘by reason of’ the avgas
contracts,” Shell Oil Co. v. United States, 130 Fed. Cl. 8, 34 (2017) (heading) (capitalization
omitted), and awarding the oil companies $99,509,847.32 in damages, id. at 40. That amount
“represented 100 percent of the costs that the [o]il [c]ompanies had incurred at the McColl [s]ite
through November 30, 2015, plus the statutory interest on those costs that had accrued up to that
point in time.” Pls.’ Mot. for Summary Judgment (“Pls.’ Mot.”) at 8, ECF No. 25.5 The Federal
Circuit unanimously affirmed the judgment on July 18, 2018, see Fed. Cir. Damages Opinion,
896 F.3d at 1316, and the United States paid the oil companies accordingly on April 1, 2019, see
Pls.’ App. at 3 (Decl. of Michael W. Kirk).
C. Present Litigation
Remediation of the McColl site remains ongoing at the present time. The instant dispute
centers on (1) cleanup costs the oil companies have continued to incur since November 30, 2015;
(2) interest related to those costs; and (3) interest in addition to that already paid on costs
previously reimbursed by the government pursuant to the prior judgment.
The oil companies submitted a formal demand for these costs and interest to the General
Services Administration on July 29, 2019, see Pls.’ App. at 195-203, but they received no
response, see Pls.’ Mot. at 10.6 Accordingly, they filed their complaint in this court pursuant to
5
The Contact Settlement Act allowed recovery of 2.5 percent simple interest that can
continue to run until the date of payment. See 41 U.S.C. § 106(f) (2010) (repealed 2011). This
statutory provision for interest is quoted infra, at 5.
6
The General Services Administration is the successor-in-interest to the Defense Supplies
Corporation, a subsidiary of the Reconstruction Finance Corporation, a government-owned
corporation. See Fed. Cir. Liability Opinion, 751 F.3d at 1286.
4
the Contract Settlement Act (“CSA”), Pub. L. No. 78-395, 58 Stat. 694 (1944) (repealed 2011),
and the Tucker Act, 28 U.S.C. § 1491, on November 22, 2019. See generally Compl.
Between November 30, 2015 and November 15, 2019, the oil companies paid an
additional $1,543,840.68 to the contractor overseeing remediation at the McColl site and
$69,300.00 to the contractor providing security at the site—a total of $1,613,140.68. Pls.’ App.
at 207 (Decl. of Edmond F. Bourke). Plaintiffs seek reimbursement of those costs. They also
seek interest on these amounts, Compl. ¶ 26—accruing though the date of payment pursuant to
the CSA, which provided that federal agencies shall “pay interest on the amount due and unpaid
from time to time on any termination claim under a prime contract at the rate of 2½ per centum
per annum for the period beginning thirty days after the date fixed for termination and ending
with the date of final payment,” 41 U.S.C. § 106(f) (2010) (repealed 2011).7
Finally, the oil companies note that 41 U.S.C. § 106(f) (2010) (repealed 2011) requires
that interest accrue until “the date of final payment.” Because the government’s April 1, 2019
payment of costs incurred through November 30, 2015, plus interest, only included interest
accrued until that time—and did not account for interest accrued up to the date of final
payment—they accordingly seek interest accrued on those costs during the period between
November 30, 2015 and April 1, 2019, an amount totaling $5,709,993.05. See Pls.’ Mot. at 10.
In sum, plaintiffs seek a total of $7,399,297.46 plus interest accrued on the new remediation
costs until such date as payment is made. Id.
The oil companies filed a motion for summary judgment on November 25, 2019, see Pls.’
Mot., and the government filed a response and motion to dismiss on February 4, 2020, see Def.’s
Mot. to Dismiss and Response to Pls.’ Mot. (“Def.’s Cross-Mot.”), ECF No. 12. Briefing was
completed on May 15, 2020, see Pls.’ Reply and Response to Def.’s Mot. (“Pls.’ Resp.”), ECF
No. 15; Def.’s Reply to Pl.’s Resp. (“Def.’s Reply”), ECF No. 16; Pls.’ Notice of Additional
Authority (“Pls.’ Notice”), ECF No. 17; Def.’s Response to Pls.’ Notice (“Def.’s Resp.”), ECF
No. 19, and a hearing was held on June 3, 2020. The case is ready for disposition.
7
As this court previously noted:
In 2011, the CSA was repealed and replaced by An Act To Enact Certain Laws
Relating To Public Contracts, Pub. L. 111-350, 124 Stat. 3677. The 2011 Act
contained a savings clause providing that, “[t]he laws ... are repealed except for
rights and duties that matured, penalties that were incurred, and proceedings that
were begun before the date of enactment of this Act.” Pub. L. No. 111-350, §
7(b), 124 Stat. 3677, 3855 (2011) (emphasis added). Consequently, the Oil
Companies may still recover for interest on the environmental remediation costs
they have incurred, as the Oil Companies’ right to be reimbursed for
environmental remediation costs under the Avgas Contracts matured prior to
2011.
Shell Oil Co., 130 Fed. Cl. at 39 n.42, aff’d, Fed. Cir. Damages Opinion, 896 F.3d at 1306, 1316.
5
STANDARDS FOR DECISION
A. Motion to Dismiss
1. Rule 12(b)(1): Lack of Jurisdiction.
Plaintiff must establish jurisdiction by a preponderance of the evidence. Trusted
Integration, Inc. v. United States, 659 F.3d 1159, 1163 (Fed. Cir. 2011) (citing Reynolds v. Army
& Air Force Exch. Serv., 846 F.2d 746, 748 (Fed. Cir. 1988)). The court must, when ruling on a
motion to dismiss for lack of jurisdiction, “accept as true all undisputed facts asserted in the
plaintiff’s complaint and draw all reasonable inferences in favor of the plaintiff.” Id. (citing
Henke v. United States, 60 F.3d 795, 797 (Fed. Cir. 1995)). “If a court lacks jurisdiction to
decide the merits of a case, dismissal is required as a matter of law.” Gray v. United States, 69
Fed. Cl. 95, 98 (2005) (citing Ex parte McCardle, 74 U.S. (7 Wall.) 506, 514 (1868); Thoen v.
United States, 765 F.2d 1110, 1116 (Fed. Cir. 1985)); see also Rule 12(h)(3) of the Rules of the
Court of Federal Claims (“RCFC”) (“If the court determines at any time that it lacks subject-
matter jurisdiction, the court must dismiss the action.”).
2. Rule 12(b)(6): Failure to State a Claim.
Under RCFC 12(b)(6), a complaint will survive a motion to dismiss if it “contain[s]
sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’”
Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544,
570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows
the court to draw the reasonable inference that the defendant is liable for the misconduct
alleged.” Id. The factual matters alleged “must be enough to raise a right to relief above the
speculative level on the assumption that all the allegations in the complaint are true (even if
doubtful in fact).” Twombly, 550 U.S. at 555-56 (citations omitted).
When reviewing the complaint, “the court must accept as true the complaint’s undisputed
factual allegations and should construe them in a light most favorable to the plaintiff.”
Cambridge v. United States, 558 F.3d 1331, 1335 (Fed. Cir. 2009) (citing Papasan v. Allain, 478
U.S. 265, 283 (1986)) (additional citation omitted). But conclusory statements of law and fact
“are not entitled to the assumption of truth” and “must be supported by factual allegations.”
Iqbal, 556 U.S. at 679. “‘[N]aked assertion[s]’ devoid of ‘further factual enhancement”’ are
insufficient to state a claim. Id. at 678 (quoting Twombly, 550 U.S. at 557); accord Bradley v.
Chiron Corp., 136 F.3d 1317, 1322 (Fed. Cir. 1998) (“Conclusory allegations of law and
unwarranted inferences of fact do not suffice to support a claim.”).
B. Summary Judgment.
“The court shall grant summary judgment if the movant shows that there is no genuine
dispute as to any material fact and the movant is entitled to judgment as a matter of law.” RCFC
Rule 56(a). A fact is material when it “might affect the outcome of the suit.” Anderson v.
6
Liberty Lobby, Inc., 477 U.S. 242, 248 (1986) (interpreting Fed. R. Civ. P. 56).8 A genuine
dispute exists when the finder of fact may reasonably resolve the dispute in favor of either party.
Id. at 250.
The movant bears the burden of demonstrating the absence of any genuine disputes of
material fact, see Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986), which requires the movant
to “cite[] to particular parts of materials in the record, including depositions, documents,
electronically stored information, affidavits or declarations, stipulations . . . , admissions,
interrogatory answers, or other materials,” RCFC 56(c)(1)(A). The court may consider other
materials in the record even if not cited by the parties. RCFC 56(c)(3). “[T]he inferences to be
drawn . . . must be viewed in the light most favorable to the party opposing the motion.”
Matsushita Elec. Indus. Co. v. Zenith Radio Corp., 475 U.S. 574, 587-88 (1986) (quoting United
States v. Diebold, Inc., 369 U.S. 654, 655 (1962)). If the record taken as a whole “could not lead
a rational trier of fact to find for the non-moving party, there is no ‘genuine issue for trial’” and
summary judgment is appropriate. Matsushita, 475 U.S. at 587 (quoting First Nat’l Bank of
Ariz. v. Cities Serv. Co., 391 U.S. 253, 289 (1968)).
ANALYSIS
A. Res Judicata and Partial Breach Doctrine
The legal issues presented by this case require reference to its pedigree in this court and
the Federal Circuit. In that respect, the oil companies and the government find common ground,
both conceding that “(1) the parties to this litigation and the previous litigation are identical; (2)
the [c]ourt’s [prior] judgment became final; and (3) this litigation is based on the same set of
transactional facts as the first round of litigation.” Pls.’ Resp. at 2 (quoting Def.’s Mot. at 8).
The parties part ways on the implications of that common ground.
The doctrine of res judicata establishes that “a final judgment on the merits of an action
precludes the parties or their privies from relitigating issues that were or could have been raised
in that action,” Allen v. McCurry, 449 U.S. 90, 94 (1980) (citation omitted), and is central to “the
conclusive resolution of disputes,” Montana v. United States, 440 U.S. 147, 153 (1979) (citations
omitted). It protects litigants “from the expense and vexation attending multiple lawsuits,
conserves judicial resources, and fosters reliance on judicial action by minimizing the possibility
of inconsistent decisions.” Id. at 153-54 (footnote omitted).
The bar of res judicata generally applies if three prerequisites appertain: “(1) there is
identity of parties (or their privies); (2) there has been an earlier final judgment on the merits of a
claim; and (3) the second claim is based on the same set of transactional facts as the first.” Jet,
Inc. v. Sewage Aeration Sys., 223 F.3d 1360, 1362 (Fed. Cir. 2000) (citation omitted). “The
doctrine of res judicata rests at bottom upon the ground that the party to be affected . . . has
litigated or had an opportunity to litigate the same matter in a former action in a court of
competent jurisdiction.” Richards v. Jefferson Cty., Ala., 517 U.S. 793, 797 n.4 (1996). Thus, a
judgment is generally res judicata “not only as to all matters litigated and decided by it, but as to
8
Because RCFC 56 mirrors Fed. R. Civ. P. 56, the two rules should be interpreted in pari
materia.
7
all relevant issues which could have been but were not raised and litigated in the suit.” Heiser v.
Woodruff, 327 U.S. 726, 735 (1946) (citations omitted); see also Brown v. Felsen, 442 U.S. 127,
131 (1979) (“Res judicata prevents litigation of all grounds for, or defenses to, recovery that
were previously available to the parties, regardless of whether they were asserted or determined
in the prior proceeding.”).
The oil companies contend that their claims are not barred by res judicata because they
fall within a partial breach exception to general claim preclusion principles. See Pls.’ Resp. at 2-
7. The court agrees insofar as it relates to the claims for new costs and related interest, but it is
not persuaded that such an exception applies to the oil companies’ claim for additional interest
on the costs already recovered on April 1, 2019 pursuant to the prior judgment.
The partial breach doctrine is implicated when the non-breaching party to a contract has
performed its duties under the contract, but the breaching party’s obligations under the contract
remain unsatisfied or ongoing. Under such circumstances, the non-breaching party is not
automatically entitled to immediately recover the full value of the bargain as a result of any
breach; instead, “a party to a contract who has no longer any obligation of performance on his
side, but is in the position of an annuitant or a creditor exacting payment from a debtor, may be
compelled to wait for the installments as they severally mature, just as a landlord may not
accelerate the rent for the residue of the term because the rent is in default for a month or for a
year.” New York Life Ins. Co. v. Viglas, 297 U.S. 672, 680 (1936); see also City of Hampton, Va.
v. United States, 218 F.2d 401, 405 (4th Cir. 1955) (“[I]t is clear . . . that for breach of a contract
for the payment of money in instalments, where the contract is unilateral or has become
unilateral as the result of performance by the complaining party, the right of recovery is limited
to the instalments due at the time of institution of suit.”). In sum, “[i]f the injured party elects to
or is required to await the balance of the other party’s performance under the contract, [its] claim
is said instead to be one for damages for partial breach.” RESTATEMENT (SECOND) OF
CONTRACTS § 236 cmt. b (1981). Underlying this precept is the premise that “contract law
precludes recovery for speculative damages.” San Carlos Irrigation and Drainage Dist. v.
United States, 111 F.3d 1557, 1563 (Fed. Cir. 1997). The law permits “a series of recoveries for
partial breach, as opposed to a single recovery for total breach, [] to avoid speculation about the
quantum of future damages.” Boston Edison Co. v. United States, 658 F.3d 1361, 1367 (Fed. Cir.
2011) (citation omitted).
The partial breach doctrine, however, is juxtaposed against principles of res judicata,
which ordinarily would bar successive claims between identical parties over the same set of
transactional facts. If both doctrines were applied in a draconian way, they could engender
situations where non-breaching parties might be prevented by the partial breach doctrine from
seeking all their claimed post-trial damages in the initial round of litigation but then barred from
recovering those same damages in the second round by res judicata. The Federal Circuit
addressed this precise circumstance in Indiana Michigan Power Co. v. United States, noting an
exception to the doctrine of res judicata: “[a] judgment in an action for breach of contract does
not normally preclude the plaintiff from thereafter maintaining an action for breaches of the same
contract that consist of failure to render performance due after commencement of the first
action.” 422 F.3d 1369, 1377 (Fed. Cir. 2005) (quoting RESTATEMENT (SECOND) OF JUDGMENTS
§ 26 cmt. g). The court concluded that “[w]hen a party sues for partial breach, it retains its right
to sue for damages for its remaining rights to performance,” id. (citing RESTATEMENT (SECOND)
8
OF CONTRACTS § 236(2) (1981)), because “prospective damages for anticipated future
nonperformance” are not recoverable in a partial breach case, id. at 1376 (citation omitted). In
short, if the partial breach doctrine prevented a claim or part of a claim from being resolved in
the first place—as it would for a claim for prospective, indeterminate damages—then it is not the
kind of claim that would be barred by res judicata in a later suit. And that understanding is
consistent with the principles underlying res judicata, which only bars a claim that “could have
been but w[as] not raised and litigated” in the first suit. Heiser, 327 U.S. at 735 (emphasis
added).
Again, the general rule is that when one party has performed its duties under a contract
and the other party’s obligations are ongoing, a breach by the latter party must be considered
partial. See New York Life, 297 U.S. at 678-80 (noting that damages may not exceed the amount
in default when the suit is commenced); see also RESTATEMENT (SECOND) OF CONTRACTS §
243(3) (“Where at the time of the breach the only remaining duties of performance are those of
the party in breach and are for the payment of money in installments not related to one another,
his breach by nonperformance as to less than the whole, whether or not accompanied or followed
by a repudiation, does not give rise to a claim for damages for total breach.”). In these respects,
the oil companies’ initial lawsuit must be classified as a suit for partial, not total, breach insofar
as it sought indemnification for past cleanup costs at the McColl site. Insurance or indemnity
agreements like the one at hand are a paradigmatic example giving rise to partial breach claims.
See RESTATEMENT (SECOND) OF CONTRACTS § 243 cmt. c, ill. 5. Plaintiffs note that the Federal
Circuit already conclusively determined that they “held up their end of the bargain,” Pls.’ Resp.
at 5 (quoting Fed. Cir. Liability Opinion, 751 F.3d at 1287), but the government’s duty to
indemnify them under the “charges” clause of the contract carried forward indefinitely. As a
result, plaintiffs correctly contend that, when “[t]he [g]overnment breached its contract 60 years
after the [o]il [c]ompanies had finished performing under the [a]vgas [c]ontracts,” id. (emphasis
in original), they stood “in the position of an annuitant or a creditor exacting payment from a
debtor” and as such were “compelled to wait for the instalments as they severally mature,” id. at
6 (quoting New York Life, 297 U.S. at 680). The partial breach doctrine thus applies.
The government’s objections to this conclusion are unavailing. First, the government
insists that “[t]he oil companies cannot cram these facts into a partial breach analysis” because
they “sought a single payment in 2005, with the intent of resolving all of their claims related to
the McColl site” and “elect[ed] to treat the alleged breach as total in seeking past and future
costs” when they brought suit. Def.’s Reply at 8. In the government’s view, the oil companies
cannot now characterize the prior claims as claims for a partial breach when they originally
elected to plead a total breach, thereby merging their demands for future damages into the
judgment awarding past damages. See Hr’g Tr. at 30:20 to 31:22 (June 3, 2020).9 That
contention is unpersuasive to the extent that the government would apply it to costs incurred
after the prior trial. What the government overlooks is that, even if the oil companies in their
complaint in the prior action had sought future costs, plaintiffs could not effectively elect to treat
their claims for future costs as part of a total breach. See RESTATEMENT (SECOND) OF
CONTRACTS § 243(3); New York Life, 297 U.S. at 680. The mere fact that plaintiffs asserted
those claims in their complaint in the first case did not make them viable claims. “[C]ontract law
9
Further citations to the hearing conducted on June 3, 2020 will omit the date.
9
precludes recovery for speculative damages,” San Carlos Irrigation, 111 F.3d at 1563, and it
would be difficult to describe an attempt by the oil companies at the time of the first suit to
project future costs they might (or might not) incur as anything but speculative. And, those
claims for speculative future damages did not merge into the judgment rendered but were simply
put aside and not reflected in, or addressed by, the judgment.10
Second, the government maintains that the oil companies were obligated to claim a total
breach because the government had repudiated any obligation under the contracts. See Def.’s
Reply at 8-10. To support this contention, the government cites a comment in the Restatement
(Second) of Judgments, which states that if a breach is followed by repudiation “and the plaintiff
thereafter commences an action for damages, he is obliged in order to avoid ‘splitting,’ to claim
all his damages with respect to the contract, prospective as well as past, and judgment in the
action precludes any further action by the plaintiff for damages arising from the contract.”
Def.’s Reply at 9 (quoting RESTATEMENT (SECOND) OF JUDGMENTS § 26 cmt. g). That statement
is inconsistent with the more specific statement found in the Restatement (Second) of Contracts,
which expressly specifies that—under circumstances exactly like these, where “the only
remaining duties of performance are those of the party in breach and are for the payment of
money in installments”—non-performance by the breaching party, “whether or not accompanied
or followed by a repudiation, does not give rise to a claim for damages for total breach.”
RESTATEMENT (SECOND) OF CONTRACTS § 243(3); see also id. § 243 cmt. c, ills. 4, 5. The
tension between these two provisions can be reconciled by noting the generality of the former
and the specificity of the latter, and as the facts at hand are precisely described by the more
specific provision, they fit squarely within its purview.
It also is not apparent that the government acted explicitly to repudiate the content in
conjunction with the first claim. The government points to a denial in 2006 by the General
Services Administration (“GSA”) of the oil companies’ claims as an “unequivocal repudiation of
any obligations under the avgas contracts.” Def.’s Reply at 9.11 But the GSA’s denial did not
10
Relatedly, the government contends that to the extent the oil companies did not pursue
their claims for future costs to judgment in the prior litigation or on appeal, they waived those
claims. See Def.’s Cross-Mot. at 13; Def.’s Reply at 11. “Waiver consists of a voluntary and
intentional relinquishment of a known right.” Cherokee Nation v. United States, 355 F.2d 945,
950 (Ct. Cl. 1966). The government’s position fails because it incorrectly assumes that the
future claims were available to plaintiffs in the first suit. The partial breach doctrine precluded
the oil companies from receiving speculative future damages in this context and, accordingly,
they could not have waived a right to claims that they could not assert.
11
The GSA denial read as follows:
I have reviewed your claim and can find no basis for recovery and no basis for the
appointment of a contracting officer. Specifically, your letters assert a termination
claim under § 113(a) of the Contract Settlement Act of 1944 (the “Act”), 41
U.S.C. § 113(a) for terminated World War II contracts, yet no evidence has been
provided demonstrating that these war contracts were actually terminated for the
convenience of or at the option of the former Defense Supplies Corporation,
rather than expiring of their own accord. War contracts that were not terminated
10
constitute a repudiation. “Repudiation occurs when one party refuses to perform and
communicates that refusal distinctly and unqualifiedly to the other party.” Dow Chem. Co. v.
United States, 226 F.3d 1334, 1344 (Fed. Cir. 2000) (citations omitted). GSA’s denial reveals
that it sets forth a conclusion about the GSA’s ability to assert jurisdiction over the claims under
the CSA. The denial did not constitute a distinct and unqualified refusal to perform, but an
insistence that GSA did not possess authority to assert jurisdiction over the claims under the
CSA because of its view that the avgas contracts had not been terminated after the war. That
interpretation of the denial is also consistent with the government’s position throughout the
previous litigation, where it never claimed repudiation but consistently maintained that the
contract simply did not require it to indemnify the oil companies. See Hr’g Tr. at 12:3-9. In
short, the government cannot show that it repudiated the contract or, even if it had done so, that
the partial breach doctrine was inapplicable.
One further, separate, aspect of res judicata deserves attention. The partial breach
doctrine does not preserve the oil companies’ claim for interest accrued through the date of
payment on the charges awarded in the first suit. Unlike plaintiffs’ claims for future damages—
which were speculative and barred by the doctrine of partial breach—the oil companies could
have sought interest on past damages through the date of payment under Section 106(f) of the
CSA in the first suit, and the decision to award such interest was within the discretion of the
court. See, e.g., Modeer v. United States, 68 Fed. Cl. 131, 145 (2005) (awarding “interest
running from the date indicated in the parties’ notice to the date this judgment is paid”).
Accordingly, that claim for interest merged into the prior judgment and is barred from
consideration in this subsequent claim.12
B. The Contract Settlement Act
In 2011, a legislative enactment reorganizing federal public contract law included a
detailed table of statutory provisions repealed thereby. Pub. L. No. 111-350, 124 Stat. 3677,
3855-62 (Jan. 4, 2011). Among those repealed provisions was the CSA and its interest-
mandating section, but preceding the list of repealed provisions Congress included a savings
clause stating that “[t]he laws specified in the following schedule are repealed, except for rights
and duties that matured, penalties that were incurred, and proceedings that were begun before the
date of enactment of this Act.” Id. at 3855. The parties dispute whether any of those exceptions
in the savings clause apply to preserve the oil companies’ claims. The government contends that
because “[n]o proceeding had begun with respect to the 2019 claim as of [the date of repeal],”
in the manner prescribed by the Act are not eligible for compensation or
consideration under the Act. See 41 U.S.C. §§ 103(d) and 103(h).
Def.’s Reply at 9.
12
The government also challenges this court’s jurisdiction to award pre-judgment interest
on similar CERCLA-related litigation currently pending in the District Court for the Central
District of California. See Def.’s Cross-Mot. at 21-22; Hr’g Tr. at 6:5 to 9:1. Nonetheless, the
court need not address that matter because the oil companies aver that they “have not yet
incurred these costs” and thus the “argument is premature.” Pls.’ Resp. at 1 n.1.
11
Def.’s Reply at 14, and because its duties under the avgas contracts had not matured by the time
of repeal in 2011, “the court lacks jurisdiction to entertain this action under the CSA,” Def.’s
Cross-Mot. at 16 (heading) (capitalizations omitted). The court finds the government’s position
unpersuasive because the rights and duties of the parties had matured before the repealing
statute’s enactment.13
The parties do not dispute that the oil companies’ rights under the contracts had matured
by the 1990s at the latest, well before the repeal. See Pls.’ Response at 17-18; Def.’s Reply at
16; Hr’g Tr. at 35:20 to 36:5.14 But the government correctly observes that “both ‘rights’ and
‘duties’ must have ‘matured’ as of January 4, 2011, for a claim to be cognizable under the CSA.”
Def.’s Cross-Mot. at 17 (emphasis in original) (citation omitted). It then notes that “no CSA
contracting officer claim had been filed as of 2011,” and thus “the savings clause of the
[repealing statute] cannot apply” because “the [g]overnment lacked any CSA ‘duty’ at the time
that law was repealed.” Id. The government insists that the court’s assertion of CSA jurisdiction
over the oil companies’ complaint in 2006 does not mean that “any right to payment under the
same contracts must have ‘matured’ before 2011” because “a right to seek reimbursement cannot
lead to a ‘duty’ to reimburse until the contractor actually seeks reimbursement and, thus, there
can be no duty to reimburse absent a plaintiff’s election to invoke its rights.” Id. (emphasis and
citation omitted). In other words, the government contends that the event triggering its duty was
the oil companies’ formal request for reimbursement now before the court, which occurred after
2011.
When the government’s duty to indemnify the oil companies matured is thus the
dispositive question in determining whether this provision in the savings clause applies. The
avgas contracts established corresponding rights and duties—a right to reimbursement and a duty
to indemnify—and likewise defined when those rights and duties would mature. The contracts
did not specify a precise time for performance. Given the unforeseeable nature of the costs
obviously contemplated by the indemnification provisions, they could not have done so. But the
13
The government also seeks to undermine the court’s jurisdiction over claims made by
Atlantic Richfield Company and Texaco by reference to the Anti-Assignment Act, 41 U.S.C. §
6305, which sets out a general bar of unconsented assignments of government contracts. See
Def.’s Cross-Mot. at 20-21. The merits of that position were subsequently rebutted and
conceded as a factual matter after consideration of corporate reorganizations through the
decades. See Hr’g Tr. at 22:4 to 23:1. The Texas Company, an entity that entered a contract for
avgas production, simply changed its name in 1959. See Pls.’ Reply at 23-24. Atlantic
Richfield’s predecessor-in-interest, the Richfield Oil Corporation, entered into avgas contracts in
1942. In 1966, Richfield Oil Corporation merged into the Atlantic Refining Company. That
latter company was the surviving corporation, and it changed its name to the Atlantic Richfield
Company. Id. Transfers by operation of law fall outside the Anti-Assignment Act’s prohibition.
See Seaboard Airline Ry. v. United States, 256 U.S. 655, 657 (1921) (The Act does not apply to
transfers arising from “the orderly merger or consolidation of corporations.”).
14
The court previously held as much when it concluded that “the [o]il [c]ompanies[’]
right to be reimbursed for environmental remediation costs under the [a]vgas [c]ontracts matured
prior to 2011.” Shell Oil Co., 130 Fed. Cl. at 39 n.42.
12
agreements did indicate when the government’s obligation or duty would be triggered, i.e., when
the oil companies’ corresponding liability arose and charges were incurred.
Under the plain language of the agreements, the government’s duty to pay any new or
additional charges the oil companies incurred by reason of the production of avgas was not
contingent on the oil companies’ act of seeking reimbursement, but instead upon their incurrence
of new liabilities dictated by federal law. The agreements thus indicate that the government’s
duty to pay arose at whatever time the oil companies became liable to pay charges required by
CERCLA due to their production of avgas—and both parties agree that that happened, at the
latest, when the oil companies were found liable for remediation at the McColl site in the 1990s,
well before the CSA’s repeal. That no breach could occur until the oil companies demanded
performance is irrelevant to whether the government previously had an existing duty to
eventually perform.
In support of this conclusion, the oil companies rely on Kratz v. United States, 300 F.2d
461 (Ct. Cl. 1962). See Pls.’ Resp. at 19-20. Kratz involved an Army Reserve officer who had
been selected for promotion from lieutenant colonel to colonel, but without issuing his promotion
orders, the Army forced him to retire in 1952 when he was found permanently unfit for duty due
to physical disability. Kratz, 300 F.2d at 482. Kratz was entitled to a colonel’s pension under a
1947 statute, and he sued after receiving a lieutenant colonel’s pension, but the government
argued that he was not entitled to the larger pension because the 1947 statute was repealed in
1956. Id. at 482-83. The repealing statute, however, contained a savings clause like the one at
issue here, leading the court to conclude that “[p]laintiff’s rights ‘matured’ under the Act of 1947
by virtue of his retirement as a lieutenant colonel in 1952, and the subsequent repeal of [the
relevant statute] . . . in 1956 had no effect on his right to recovery under that [statute].” Id. at
484. The oil companies stress that “Kratz forecloses the [g]overnment’s argument that the [o]il
[c]ompanies’ right to indemnification—and the [g]overnment’s corresponding duty to indemnify
them—matured when the [o]il [c]ompanies demanded that the [g]overnment perform its duty.”
Pls.’ Resp. at 20. Rather, they note that in Kratz, the “claim matured when he retired, not when
he demanded his pension” and “[t]he latter was completely irrelevant to the Court of Claims’
decision.” Pls.’ Resp. at 20 (citations and emphasis omitted).
The government unsuccessfully attempts to distinguish Kratz by emphasizing that the
plaintiff there was challenging governmental action—namely, the decision to medically retire
him as a lieutenant colonel rather than colonel—that happened in 1952 before the statute’s repeal
in 1956. See Def.’s Reply at 16. “Here,” the government asserts, “the first action by the
[f]ederal [g]overnment with respect to the contracts was the denial of plaintiffs’ claims,
submitted [in 2019] more than eight years after repeal.” Id. at 17 (emphasis in original). But the
government misstates the governmental action at issue. The action relevant here reaches all the
way back to the 1940s, when the government agreed to reimburse future charges the oil
companies might incur by reason of the avgas contracts. That duty was triggered decades later,
but well before the repeal of the CSA, when the oil companies became liable for remediation
costs at the McColl site.
The government cites Ford Motor Co. v. United States, 378 F.3d 1314, 1317 (Fed. Cir.
2004), for the proposition that plaintiffs must make an administrative demand for written
findings as a “necessary predicate” for bringing a claim under the CSA. See Def.’s Reply at 15.
13
On that basis, the government contends that administrative exhaustion under the CSA was
required before it had any duty to pay. Id. But that postulate misinterprets the implications of
Ford Motor, which says nothing about when a duty matures but simply clarifies that certain
administrative procedures are “a necessary predicate to bringing a claim under the CSA.” Ford
Motor, 378 F.3d at 1317. The CSA does not dictate when the rights and duties defined in a
contract mature for purposes of the savings clause in the repealing statute; rather, it defines a set
of procedural rules that are unrelated to the substantive legal obligations arising under an
independent contractual agreement like the one here. In sum, Ford Motor has no bearing on
whether the savings clause of the repealing statute applies here.
The government’s reliance on Tektel, Inc. v. United States, 121 Fed. Cl. 680 (2015), is
likewise misplaced. The government cites Tektel to support the proposition that its duties could
not mature until the oil companies had exhausted their administrative remedies. See Def.’s
Cross-Mot. at 18. But it dismisses a significant difference between Tektel and this case. The
driving force requiring the exhaustion of administrative remedies before rights matured in Tektel
was a provision to that effect in the contract itself. See Tektel, 121 Fed. Cl. at 686. The avgas
contracts at issue here contained no such requirement. The government would graft such
requirements onto the plain language of the contracts by incorporating the procedural rules of the
CSA, which it asserts are a necessary predicate under Ford Motor to bringing any CSA claim.
As already noted, however, the CSA establishes required procedures for bringing a claim
thereunder; it does not purport to define rights and obligations under the contract itself. And
unlike the contract at issue in Tektel, the avgas contracts do not specify any set of procedures the
oil companies must follow before the government’s duty to indemnify can mature. The plain
terms of the contract indicate that the duty matured in tandem with the oil companies’
corresponding incurrence of liability. Tektel is thus not relevant to when the government’s duty
to indemnify the oil companies matured.
C. Statute of Limitations
The government also asserts that the oil companies’ claims are time-barred under the
CSA and the Tucker Act, both of which have their own applicable statutes of limitations. See
Def.’s Cross-Mot. at 15-16. Because the court determines that it possesses jurisdiction under the
CSA, it need not address whether it would similarly have jurisdiction, at least over non-interest
claims, pursuant to the Tucker Act.
The CSA requires plaintiffs to submit a claim to the relevant contracting agency, but
“[t]he claim is subsequently time-barred if the contractor fails to initiate civil proceedings within
ninety days after delivery of the [agency’s] findings or, if no findings are provided, within one
year after the demand for findings.” Ford Motor, 378 F.3d at 1316-17 (referring to 41 U.S.C. §
113(a)-(c)). The government asserts that “the oil companies’ 2019 administrative claim and
complaint seek a subset of the exact relief that they demanded in their 2005 administrative claim
and 2006 complaint,” and because “GSA denied that claim in 2006 . . . all of plaintiffs’ claims in
this case accrued no later than 2006.” Def.’s Cross-Mot. at 15 (emphasis omitted). Therefore,
the government considers the complaint time-barred under the CSA. Id.
The government’s position is premised on the same faulty assumptions as its assertion of
res judicata. Insisting that “[f]iling a second administrative claim cannot restart the clock,”
14
Def.’s Reply at 12, the government assumes that the oil companies cannot now bring these
claims because they brought the same claims in 2006. But as already noted, under the partial
breach doctrine—regardless of their aspirational but unavailing inclusion of such costs in the
2006 claims—the oil companies could not previously bring these claims and the court could not
previously consider them. See New York Life, 297 U.S. at 680. Thus, the oil companies
correctly observe that “nothing in the CSA forbids [them] from obtaining jurisdiction under the
CSA in a second, follow-on lawsuit that is otherwise permitted by principles of preclusion.”
Pls.’ Resp. at 12 (emphasis removed).
D. The Government’s Insurance-Offset Defense
In the aftermath of CERCLA’s enactment, thousands of claims made against the oil
companies led them in turn “to make claims on hundreds of general liability insurance policies
that were in effect over different periods for over half a century,” and “the [o]il [c]ompanies
entered a series of omnibus settlement agreements with their insurers” in the 1990s. Hr’g Tr. at
23:3-12. The government now seeks “to assert insurance recovery defenses based upon the
massive amounts that plaintiffs obtained from their insurers.” Def.’s Cross-Mot. at 22. Such
defenses, however, are barred in this suit by principles of preclusion. And in any event,
recoveries from independent insurance agreements cannot offset the government’s obligation to
indemnify the oil companies because remote insurance transactions do not appertain to
calculating damages.
Principles of res judicata generally apply to both claims and defenses. See Brown, 442
U.S. at 127. “When a valid and final personal judgment is rendered in favor of the plaintiff . . .
the defendant cannot avail himself of defenses he might have interposed, or did interpose, in the
first action.” RESTATEMENT (SECOND) OF JUDGMENTS § 18 (1982); see also Hallco Mfg. Co. v.
Foster, 256 F.3d 1290, 1297 (Fed. Cir. 2001) (holding as precluded “a defense that was or could
have been raised in the prior litigation”). Here, as already noted, the oil companies’ claims fit
within the partial breach exception to res judicata, but no such exception applies to the
government’s insurance-offset defense. The Federal Circuit previously affirmed this court’s
conclusion that attempting to offset liability by reference to third party payments “is an
affirmative defense and hence waivable.” Fed. Cir. Damages Opinion, 896 F.3d at 1315. It then
held that the government waived the defense and concluded that permitting the government to
amend its answer to include it would prejudice the oil companies because “nearly a decade had
passed since the [o]il [c]ompanies filed their [c]omplaint . . . and more than seven decades had
passed since the operative events that gave rise to the insurance policies.” Id. at 1316 (citation
omitted). Accordingly, the government may not now—absent some showing, which it has not
made, that it is exempt from preclusion—raise a defense in this suit that it could have timely
raised in the prior suit.
Moreover, the government’s defense fails on the merits. Because of the “the endlessness
and futility of the effort to follow every transaction to its ultimate result,” the law does not
generally “go beyond the first step” in calculating damages. Southern Pac. Co. v. Darnell-
Taenzer Lumber Co., 245 U.S 531, 533-34 (1918). Paradigmatic of remote transactions that do
go beyond the first step, and are thus irrelevant for calculating damages, are those involving
insurance recoveries. See id. at 534 (noting that the recovery of insurance is not something with
which defendants are concerned). “An injured party’s recovery from third parties does not
15
decrease the amount of the wrongdoer’s liability.” Wisconsin Elec. Power Co. v. United States,
90 Fed. Cl. 714, 794 (2009). And, despite the government’s protestations to the contrary, see
Def.’s Cross-Mot. at 24-25, the rule makes no distinction as to whether the recovery precedes or
succeeds the breach. Such an arbitrary classification would further complicate determinations
about when and what transactions could or could not be considered, undermining the very
rationale for cutting off the inquiry at the first step. That the oil companies later recovered some
amount of the remediation costs they incurred due to the production of avgas is thus irrelevant to
the government’s independent obligation to indemnify them for such costs.
CONCLUSION
For the reasons stated, plaintiffs’ motion for summary judgment is GRANTED IN PART
and DENIED IN PART, and defendant’s motion to dismiss is GRANTED IN PART and
DENIED IN PART. Plaintiffs are entitled to indemnification for remediation costs incurred at
the McColl site since November 30, 2015 through September 30, 2019, amounting to
$1,613,140.68. Plaintiffs are also entitled to interest on such costs, accruing through the date of
final payment, at the rate and terms specified in 41 U.S.C. § 106(f) (2010). All costs and interest
shall be allocated between plaintiffs in accord with the percentages specified in plaintiffs’
complaint. See Compl. ¶ 23.15 Plaintiffs’ claim for interest on remediation costs incurred before
November 30, 2015 is DISMISSED. The clerk is directed to enter judgment accordingly.
Plaintiffs are awarded their costs of suit.
It is so ORDERED.
s/ Charles F. Lettow
Charles F. Lettow
Senior Judge
15
That allocation is as follows: Shell, 58.58%; Union Oil, 18.94%; Atlantic Richfield,
18.94%; Texaco, 3.54%. See Pls.’ Mot. at 37.
16