NOT FOR PUBLICATION WITHOUT THE
APPROVAL OF THE APPELLATE DIVISION
This opinion shall not "constitute precedent or be binding upon any court ." Although it is posted on the
internet, this opinion is binding only on the parties in the case and its use in other cases is limited. R. 1:36-3.
SUPERIOR COURT OF NEW JERSEY
APPELLATE DIVISION
DOCKET NO. A-2322-18T2
DECUS, INC.,
Plaintiff-Appellant,
v.
GLOUCESTER DATA
CENTER, LLC,
Defendant-Respondent.
_________________________
Submitted June 17, 2020 – Decided July 30, 2020
Before Judges Koblitz and Gilson.
On appeal from the Superior Court of New Jersey, Law
Division, Camden County, Docket No. L-0542-17.
Freundlich & Littman LLC, attorneys for appellant
(Austin Ross Freundlich, of counsel and on the brief).
Alissa Raines Schurr and Jennifer L. Zuch, of the New
York Bar, admitted pro hac vice, attorneys for
respondent (Alissa Raines Schurr and Jennifer L. Zuch,
on the brief).
PER CURIAM
This appeal arises out of a contractual dispute. Plaintiff Decus, Inc. filed
an action to enforce a construction lien seeking to recover more than $128,000
from defendant Gloucester Data Center, LLC. Plaintiff appeals from orders
denying its motion to enter judgment on an arbitration award under Rule 4:21A-
1, vacating that award, denying plaintiff summary judgment, and compelling the
parties to arbitrate in accordance with their contract. We affirm.
I.
In December 2015, plaintiff and defendant entered into a contract under
which plaintiff agreed to act as defendant's representative during the pre-
construction phase of a project to build a solar farm (the Contract). 1 The
Contract states that plaintiff would be paid a lump sum of $72,920 plus
additional fees and costs as authorized by written and signed change orders. The
Contract also contained an arbitration provision that states:
ARBITRATION. Unless the parties mutually agree
otherwise in writing, all claims, disputes and matters in
question arising out of, or relating to, this Agreement
shall be decided by arbitration in accordance with the
Construction Industry Arbitration Rules of the AAA
then in effect. This agreement to arbitrate shall be
specifically enforced under the prevailing arbitration
law. An award entered in an arbitration proceeding
shall be final, and judgment may be entered upon it in
1
The Contract does not define the "Project" but both parties state that the project
involved pre-construction for a solar farm.
A-2322-18T2
2
accordance with the applicable law in any court having
jurisdiction.
Plaintiff asserts it performed all the lump sum work under the Contract
and additional work. Accordingly, plaintiff seeks to recover from defendant
$128,137, consisting of the lump sum of $72,920, plus $76,650 in additional
fees and costs, less $21,433 paid by defendant. Defendant disputes those claims ,
contending that plaintiff never completed the work entitling it to the full lump
sum and there were no additional fees and costs authorized by signed change
orders.
In November 2016, plaintiff filed a construction lien for $128,137.
Defendant asserts that the lien was filed on land it does not own.
In February 2017, plaintiff filed a complaint in the Law Division seeking
to enforce its lien. Defendant responded with an answer disputing plaintiff's
claim. Thereafter, the parties filed cross-motions for summary judgment. While
those motions were pending, the parties were directed to arbitrate under Rule
4:21A-1 (the Court Arbitration). The Court Arbitration was scheduled to take
place on Monday, June 4, 2018. The Friday before that date, plaintiff's then
counsel filed a motion to withdraw and sent a letter to the court administrator
requesting to adjourn the Court Arbitration. Defense counsel called plaintiff's
counsel and left a voicemail requesting that he let her know if he was still going
A-2322-18T2
3
to appear at the Court Arbitration. Plaintiff's counsel did not respond, but did
appear at the Court Arbitration. Defendant's counsel did not appear. The Court
Arbitration proceeded without defendant or its counsel and an award of
$128,137 was granted.
Shortly thereafter, defendant's answer was stricken. Defendant and its
counsel claimed that they did not learn of the Court Arbitration award until
plaintiff moved to enter judgment based on that award. Defendant opposed that
motion and cross-moved to vacate the Court Arbitration and compel arbitration
under the Contract.
On December 21, 2018, the trial court heard oral arguments on those
motions, as well as the cross-motions for summary judgment. The court then
made its rulings on the record and entered three orders: (1) denying the motions
for summary judgment; (2) denying plaintiff's motion to enter a judgment on the
Court Arbitration award and vacating that award; and (3) compelling the parties
to arbitrate their dispute in accordance with the arbitration provision in the
Contract.
In making those rulings, the trial court found that there was good cause
for defense counsel's failure to appear at the Court Arbitration and defendant
A-2322-18T2
4
had a meritorious defense because the lien was defective. The court also found
that the arbitration provision in the Contract was valid and enforceable.
II.
On appeal, plaintiff argues that the trial court erred in finding good cause
and vacating the Court Arbitration. We disagree. We discern no abuse of
discretion by the trial court and affirm.
Rule 4:21A-1(a) mandates arbitration in certain civil cases. In contrast to
an arbitration agreed to by the parties, arbitration under Rule 4:21A-1 is a court-
ordered proceeding. Accordingly, all parties are required to participate, unless
excused, and either party can file a timely notice of rejection of the arbitration
award and the matter will then proceed to a trial de novo. R. 4:21A-6(b)(1), (c).
Missing a Rule 4:21A-1 arbitration has consequences. "An appearance on
behalf of each party is required at the arbitration hearing." R. 4:21A-4(f). If a
party fails to appear, that party's pleadings "shall be dismissed" or "stricken."
Ibid. In addition, if an award is made, relief from the award can only be obtained
by filing a timely motion "showing good cause." Ibid.
For a party defending against a claim for damages, such as defendant here,
Rule 4:21A-4(f) states:
If a party defending against a claim of damages does
not appear, the party's pleading shall be stricken, the
A-2322-18T2
5
arbitration shall proceed and the non-appearing party
shall be deemed to have waived the right to demand a
trial de novo. A party obtaining the arbitration award
against the non-appearing party shall serve a copy of
the arbitration award within [ten] days of the receipt of
the arbitration award from the court pursuant to R.
4:21A-5. Service shall be upon counsel of record or, if
not represented, upon such non-appearing party.
Service shall be made as set forth in R. 4:21A-9(c).
Relief from any order entered pursuant to this rule shall
be granted only on motion showing good cause, which
motion shall be filed within [twenty] days of the date of
service of the non-appearing party by the appearing
party. Relief shall be on such terms the court may deem
appropriate, including litigation expenses and
attorney's fees incurred for services directly related to
the non-appearance.
A party seeking to vacate a civil arbitration award entered under Rule
4:21A-1 must show both "good cause" and a meritorious defense. SWH Funding
Corp. v. Walden Printing Co., Inc., 399 N.J. Super. 1, 17 (App. Div. 2008).
"Good cause" is difficult to define. Del. Valley Wholesale Florist v. Addalia,
349 N.J. Super. 228, 232 (App. Div. 2002). "Its application requires the exercise
of sound discretion in light of the facts and circumstances of the particular case
considered in the context of the purpose of the Court Rule being applied." Ibid.
When the default arises out of counsel's failure to appear, the motion
"should be viewed with great liberality and every reasonable grounds for
indulgences [will be] tolerated to the end that a just result is reached." Ibid.
A-2322-18T2
6
(quoting Davis v. DND/Fidoreo, Inc., 317 N.J. Super. 92, 99 (App. Div. 1998)).
We have repeatedly recognized that "the sins of the attorney" should not be
visited "upon [a] blameless client." Jansson v. Fairleigh Dickinson Univ., 198
N.J. Super. 190, 196 (App. Div. 1985). Consequently, "inadvertence of counsel
may justly be deemed to constitute good cause when the delay does not prejudice
the adverse party and a rational application under the circumstances present
favors a determination that provides justice to the litigant." Burns v. Belafsky,
326 N.J. Super. 462, 471 (App. Div. 1999).
Here, the trial court found that defendant had a meritorious defense to the
construction lien claim and, in that regard, the court noted several deficiencies
in the lien including an overstated damage claim and the lack of a signature by
plaintiff. The court also found that there was good cause to excuse defense
counsel's failure to appear at the arbitration. In making that finding, the court
noted that defense counsel could have been more diligent, but the court also
found that plaintiff suffered no prejudice. We discern no abuse of discretion by
the trial court in making those findings and note that they are consistent with the
judicial goal of adjudicating matters on their merits.
On appeal, plaintiff has presented no arguments concerning the order
denying its motion for summary judgment. Accordingly, we deem that argument
A-2322-18T2
7
abandoned. Pullen v. Galloway, 461 N.J. Super. 587, 595 (App. Div. 2019)
(citing N.J. Dep't of Envtl. Prot. v. Alloway Twp., 438 N.J. Super. 501, 505 n.2
(App. Div. 2015)). We also note that the trial court made express findings
concerning material issues of disputed facts that would preclude the entry of
summary judgment in favor of plaintiff. R. 4:46-2(c); Friedman v. Martinez,
___ N.J. ___, ___ (2020) (slip op. at 13) (quoting Brill v. Guardian Life Ins. Co.
of Am., 142 N.J. 520, 528-29 (1995)).
Finally, plaintiff has presented no arguments as to why the order
compelling arbitration under the Contract should be reversed. Consequently,
we also deem this argument to have been abandoned. Pullen, 461 N.J. Super. at
595. We note, moreover, that the arbitration provision in the Contract was the
product of mutual assent and made it clear that the parties were giving up the
right to pursue claims in court and, instead, were agreeing to arbitrate those
claims. See Atalese v. U.S. Legal Servs. Grp., L.P., 219 N.J. 430, 442 (2014).
In summary, we affirm the three orders entered by the trial court on
December 21, 2018, which vacated the award in the Court Arbitration, denied
summary judgment to plaintiff, and compelled the parties to arbitrate their
dispute in accordance with the arbitration provision in the Contract.
Affirmed.
A-2322-18T2
8