ARMED SERVICES BOARD OF CONTRACT APPEALS
Appeal of - )
)
U.S. Coating Specialties & Supplies, LLC ) ASBCA No. 58245
)
Under Contract No. W912EE-10-C-0019 )
APPEARANCE FOR THE APPELLANT: Louis H. Watson Jr., Esq.
Watson & Norris, PLLC
Jackson, MS
APPEARANCES FOR THE GOVERNMENT: Michael P. Goodman, Esq.
Engineer Chief Trial Attorney
Steven H. Finch, Esq.
John M. Breland, Esq.
Engineer Trial Attorneys
U.S. Army Engineer District, Vicksburg
OPINION BY ADMINISTRATIVE JUDGE WOODROW
This appeal arises from the termination for default of a contract to construct a
building to house a large unclassified supercomputer at the Army’s Engineering Research
and Design Center (ERDC). On April 9, 2015, the Board issued a decision denying the
government’s amended motion to dismiss or, in the alternative, for summary judgment.
U.S. Coating Specialties & Supplies, LLC, ASBCA No. 58245, 15-1 BCA ¶ 35,957 (U.S.
Coating I). On January 21, 2016, the government filed a renewed motion for summary
judgment, contending that the parol evidence rule barred evidence of an alleged prior oral
agreement between appellant and the Assistant U.S. Attorney (AUSA) during appellant’s
Chapter 11 bankruptcy proceedings, and alternatively, that the AUSA lacked actual
authority to enter into the alleged agreement. On April 6, 2017, the Board issued a
decision denying the government’s motion. U.S. Coating Specialties & Supplies, LLC,
ASBCA No. 58245, 17-1 BCA ¶ 36,710 (U.S. Coating II).
In U.S. Coating II, we held that the record was insufficient to determine whether
the April 25, 2012 bankruptcy agreement was a fully integrated agreement and that
genuine issues of material fact existed regarding whether there was a separate oral
agreement with the government to terminate the contract for convenience. 17-1 BCA
¶ 36,710 at 178,760. We further held the AUSA possessed the necessary authority to
bind the government when the parties entered into the April 25, 2012 bankruptcy
settlement agreement. Id. at 178,761.
Subsequently, the parties agreed to the submission of the appeal on the record
without a hearing pursuant to Board Rule 11. Based on the briefs and evidence
submitted, we conclude that appellant has not met its burden of demonstrating that the
parties entered into a separate oral agreement to terminate the contract for convenience.
We further conclude that the contracting officer (CO) reasonably exercised her discretion
when she terminated the contract for default. Accordingly, we deny the appeal.
FINDINGS OF FACT
I. The Contract
1. On June 21, 2010, the U.S. Army Corps of Engineers (Corps) awarded Contract
No. W912EE-10-C-0019 (contract) to appellant, U.S. Coating Specialties & Supplies, LLC
(U.S. Coating) in the amount of $11,383,000 for the construction of a U.S. Army Engineer
Research and Development Center Information Technology Laboratory office building and
computer facility in Vicksburg, Mississippi (ERDC Project) (R4, tab 3 at 5-6 1).
2. The contract included the standard Federal Acquisition Regulation (FAR) default
clause, 52.249-10, DEFAULT (FIXED-PRICE CONSTRUCTION) (APR 1984), which
provided, in pertinent part:
(a) If the Contractor refuses or fails to prosecute the work or
any separable part, with the diligence that will insure its
completion within the time specified in this contract including
any extension, or fails to complete the work within this time,
the Government may, by written notice to the Contractor,
terminate the right to proceed with the work (or the separable
part of the work) that has been delayed. . . .
....
(c) If, after termination of the Contractor’s right to proceed, it
is determined that the Contractor was not in default, or that
the delay was excusable, the rights and obligations of the
parties will be the same as if the termination had been issued
for the convenience of the Government.
(Id. at 132-34)
3. U.S. Coating’s principal subcontractor was Mid-State Construction Company,
Inc. (Mid-State) (gov’t br., ex. A at 2).
1
Citations to the Rule 4 file are to the consecutively-numbered pages unless otherwise
indicated.
2
4. Because U.S. Coating lacked the requisite bonding capacity for the project,
Mid-State agreed to serve as a major subcontractor for the Project and to indemnify the
bonds of U.S. Coating and Earl Washington, U.S. Coating’s President and CEO.
Mid-State Construction Company, Inc. provided the bonding for U.S. Coating’s bid and
contract on the ERDC Project. (Gov’t br., ex. A at 2)
5. On November 19, 2010, U.S. Coating entered into a subcontract agreement with
Mid-State to perform the work on the ERDC Project. Pursuant to the terms of an escrow
agreement between U.S. Coating and Mid-State, U.S. Coating was to deposit all of the
project payments it received from the government into an escrow account. (Id. at 3)
6. Mid-State performed work on the ERDC Project pursuant to the terms of the
subcontract agreement with U.S. Coating (id. at 3). U.S. Coating paid Mid-State up until
March 2011, but did not pay Mid-State for the April, May, and June 2011 subcontract
billings, despite having been paid by the government for the work Mid-State performed
(id. at 4).
7. On June 7, 2011, Mid-State provided notice to U.S. Coating that it would exercise
its rights pursuant to the subcontract agreement within seven days unless the defaults were
cured. U.S. Coating did not cure the default, and on June 14, 2011, Mid-State terminated
the subcontract agreement and stopped work on the Project. (Id. at 5)
8. In a letter to U.S. Coating, dated August 17, 2011, the CO, Jeri H. McGuffie
(CO McGuffie), described a host of performance problems, including: a 90-day delay in
schedule, including multiple critical path items; the failure to maintain the site following
rain events; the failure timely to provide the structural steel erection plan; the failure to
reach firm agreements with various subcontractors; changing management personnel
without notice; the failure to ensure adequate materials and equipment are onsite; and
multiple failures to promptly pay subcontractors. (Gov’t reply br., ex. E)
9. On November 22, 2011, Mid-State won a $1.2 million arbitration award against
U.S. Coating determining that U.S. Coating failed to tender payments to Mid-State (gov’t
br., ex. A at 11). The arbitrator found that U.S. Coating had materially breached the
contract for failure to pay Mid-State, stating U.S. Coating had “offered no valid explanation
as to why [Mid-State]” was not paid (id. at 7).
II. Bankruptcy Proceedings
10. On January 13, 2012, during performance of the contract, U.S. Coating sought
bankruptcy protection, filing a Chapter 11 voluntary petition in the United States
Bankruptcy Court for the Southern District of Mississippi (Bankruptcy Court) (R4, tab 4).
3
11. On February 24, 2012, Travelers Casualty and Surety Company of America
(Travelers), U.S. Coating’s surety for the contract, filed a motion (“Dkt. #38”) in the
Bankruptcy Court, seeking relief from the automatic stay imposed by U.S. Coating’s
bankruptcy filing to enforce its rights under a General Agreement of Indemnity between
Travelers and U.S. Coating (R4, tab 5). Travelers also filed another motion (“Dkt. #39”) on
the same date to compel rejection of the contract, or alternatively, to compel U.S. Coating to
assume or reject the contract pursuant to 11 U.S.C. § 365 (gov’t supp. R4, tab 1).2
12. On March 13, 2012, Mid-State, U.S. Coating’s subcontractor, filed a response
and limited objection to Travelers’ motion for relief from the automatic stay (“Dkt. #52”)
(R4, tab 7). Mid-State also filed a response and limited objection to Travelers’ motion to
compel on the same date (“Dkt. #53”) (gov’t supp. R4, tab 3).
13. On March 13, 2012, the AUSA for the Southern District of Mississippi,
David N. Usry (AUSA Usry), on behalf of the U.S. Attorney, filed responses to Travelers’
February 24 motions for the United States and the agency. In its response and limited
joinder in Travelers’ motion for relief from the automatic stay (“Dkt. #51”), the United
States moved to lift the automatic stay to pursue termination proceedings pursuant to
FAR Part 49 and allow the Corps to complete the construction (R4, tab 6 at 7). The United
States pled that the CO “was proscribed from . . . determin[ing] whether [U.S. Coating] was
defaulted or is likely to default on the Contract for failure to make progress . . . ” (id. at 6
¶ 26). The United States also supported Travelers’ motion to compel rejection of the
contract, or alternatively, to compel U.S. Coating to assume or reject the contract (gov’t
supp. R4, tab 2).
14. The Bankruptcy Court issued an order on March 30, 2012, directing U.S.
Coating, the debtor, to file a motion to assume or reject the contract by April 13, 2012 and
setting a trial on any such motion for April 26, 2012 (gov’t supp. R4, tab 4).
15. In April 2, 2012, correspondence with the Corps, U.S. Coating stated that it had
arranged for a new subcontractor, MTNT, to take over the contract after Mid-State
Construction walked off the job. Mr. Washington requested a meeting with the government
to discuss a reorganization of the contract such that MTNT would become the prime
contractor, but CO McGuffie refused to meet. (Gov’t br., ex. D)
16. On April 4, 2012, CO McGuffie responded and explained why she refused to
meet. She said that, despite her numerous requests, U.S. Coating had not provided her with
sufficient information about the exact contractual relationship it intended. She explained
that FAR 49.402-4, Procedures in lieu of Termination for Default, allows a contractor to
“continue performance of the contract by means of a subcontract or other business
2
See U.S. Coating I, 15-1 BCA ¶ 35,957 at 175,706 for a discussion of the terms
“assumption” and “rejection” of contracts under bankruptcy law.
4
arrangement with an acceptable third party, provided the rights of the Government are
adequately preserved.” FAR 49.402-4(b). According to CO McGuffie, U.S. Coating
provided her no assurances that its current bonding company consented to the assignment of
the contract to MTNT and that, without such assurances, the government’s rights would not
be adequately protected. (Gov’t br., ex. D)
17. After obtaining leave from the Bankruptcy Court to file its motion, U.S. Coating
moved to assume the contract on April 17, 2012 (R4, tab 9). The United States filed a
response to the motion on April 20, 2012, demanding proof of U.S. Coating’s ability to
assume the contract at the April 26, 2012 trial. The response was filed by AUSA Usry.
(R4, tab 12)
A. The April 24, 2012 Teleconference
18. On April 24, 2012, prior to the scheduled April 26, 2012 hearing, U.S.
Coating, Travelers, the United States, and Mid-State participated in a telephone call to
discuss a potential settlement of Traveler’s motion for relief from the automatic stay.
The participants in the call included AUSA Usry, Earl Washington, President and CEO
of U.S. Coating, Herbert J. Irvin, counsel for U.S. Coating in the bankruptcy action,
Mark Herbert, counsel for Travelers, Ms. Velma Day, an employee of U.S. Coating, and
Mr. Alden Brooks, an employee of U.S. Coating. (R4, tab 15 ¶ 20).
19. With respect to the April 24, 2012 teleconference, Mr. Washington’s affidavit
stated, in pertinent part:
With respect to my main concern, the nature of the
termination that could be entered by the Corps, there was
difficulty hearing everything due to speaker phone breakup
on both ends of the call, but I understood David Usry to say
that the Corps would have no issue with a termination for
reasons other than default, but that the Corps could not take
any action until the Automatic Stay was lifted.
(App. supp. R4, tab 1 at 7, ¶ 37 (Washington aff., dated Oct. 31, 2018))
20. Ms. Day’s affidavit stated that telephone discussions between U.S. Coating’s
counsel, Herb Irvin, and AUSA Usry took place on April 24, 2012, and there were
discussions about the automatic stay being lifted to allow discussions about a termination
for convenience (app. supp. R4, tab 4 (Day aff., dated Jan. 7, 2014)).
21. Mr. Brooks’ affidavit stated that he received a telephone call on April 24,
2012, to attend a meeting to discuss a resolution that would allow for a termination of the
contract for convenience. Mr. Brooks stated that U.S. Coating’s counsel and AUSA Usry
5
exchanged messages and it was his understanding that all parties agreed to terminate the
contract for convenience. (App. supp. R4, tab 3 (Brooks aff., dated Oct. 31, 2018))
22. U.S. Coating’s counsel, Mr. Irvin, stated “that either everyone on our end of the
conference call . . . must have misunderstood what David Usry said, or the Corps was not
acting in good faith during the negotiations” (app. supp. R4, tab 2 at 6-7, ¶ 35 (Irvin aff.,
dated Oct. 31, 2018)). Mr. Irvin does not explicitly claim that an agreement with the
government was reached during the phone call. Instead, he avers that:
[W]e understood [AUSA] David Usry to stay that the Corps
would have no issue with a termination for reasons other than
default, but that the Corps could not take any action until the
Automatic Stay was lifted.
(App. supp. R4, tab 2 at 5, ¶ 29 (Irvin aff., dated Oct. 31, 2018))
23. Prior to the phone call, the only explicit discussion of a termination for other
than default was between counsel for U.S. Coating and counsel for the surety, Travelers
(app. supp. R4, tab 1 at 4, ¶¶ 19-20 (Washington aff., dated Oct. 31, 2018); R4, tab 15
at 1-2, ¶¶ 7-8).
B. The Bankruptcy Settlement
24. On April 25, 2012, the parties advised the Bankruptcy Court that they reached
a settlement on pending issues set for trial and submitted a proposed order for the
Bankruptcy Court’s approval (R4, tab 20 at 45 3).
25. Based on the parties’ communicated settlement and proposed order, the
Bankruptcy Court judge issued an order on April 25, 2012 (Agreed Order), stating in
pertinent part:
The Court, being fully advised in the premises and
having considered the settlement of the foregoing pleadings as
reflected below, finds that cause exists pursuant to 11 U.S.C.
§ 362(d)(1) to grant Travelers and the Corps relief from the
automatic stay and finds that the Motion to Assume should be
denied and that the contract (“Contract”) between the Debtor
and the Corps . . . should be deemed rejected.
IT IS, THEREFORE, ORDERED that the Contract is
hereby rejected as a matter of law.
3
Citation is to the original pagination.
6
IT IS FURTHER ORDERED that the automatic stay is
hereby terminated in favor of the Corps and Travelers with
respect to the Contract and General Agreement of Indemnity
(“GAI”).
IT IS FURTHER ORDERED that this Order does not
adjudicate or waive any respective rights and/or defenses of
Travelers, the Corps, or Mid State with respect to the
Contract, the Bonded Project, the GAI, or the performance
and payment bonds issued by Travelers on the project.
IT IS FURTHER ORDERED that, because the
Automatic Stay Motion was sufficient to afford reasonable
notice of the material provisions of the agreement between
the parties and opportunity for hearing, the provisions of Fed.
R. Bankr. P. 4001(d)(1)-(3) do not apply and the agreement is
approved without further notice.
ORDERED that the Stay of execution of Fed. R.
Bankr. P. 4001(a)(3) is hereby waived. SO ORDERED.
(R4, tab 13 at 2-3) The order was “AGREED TO AND APPROVED AS TO FORM” by
AUSA Usry, U.S. Coating’s bankruptcy counsel, and representatives for Travelers, and
Mid-State (id. at 3-4).
III. Termination for Default and Bankruptcy Hearing
26. Following the issuance of the Bankruptcy Court’s April 25, 2012 order,
CO McGuffie terminated the contract for default on the same date, asserting that U.S.
Coating’s consent to rejection of the contract constituted an anticipatory repudiation of
the contract (R4, tab 2).
27. On April 30, 2012, U.S. Coating formally filed a motion in the Bankruptcy
Court to vacate the April 25, 2012 order. In its motion, U.S. Coating asserted that its
consent to the settlement was based on representations made by AUSA Usry that the
Corps would terminate the contract for “reasons other than default” (R4, tab 15 at 4 ¶ 32).
The United States, Travelers, and Mid-State filed responses to U.S. Coating’s motion to
vacate the April 25, 2012 order (R4, tabs 16-18).
28. The CO’s Memorandum for the Record, dated May 7, 2012, provides support
for the termination for default based upon U.S. Coating’s failure to make reasonable
progress on critical path items. In particular, CO McGuffie noted that U.S. Coating’s
7
schedule updates from December 2011 through April 2012 showed little or no progress on
critical path items. During that time frame, U.S. Coating reported negative float that
increased from 69 days to 185 days. Although CO McGuffie sought an explanation for
the delay, U.S. Coating did not respond to her multiple letters. Moreover, U.S. Coating
admitted that it would not complete performance by the June 30, 2012 completion date.
Finally, U.S. Coating provided CO McGuffie with no indication that it had a viable plan to
halt slippage and regain the lost time. (Gov’t br., ex. B)
29. On May 17, 2012, the Bankruptcy Court held a hearing on U.S. Coating’s
motion to vacate. Ruling from the bench, the Bankruptcy Court denied U.S. Coating’s
motion, holding that U.S. Coating’s contentions were insufficient to set aside the April 25
order. The Bankruptcy Court did not address the propriety of the Corps’ termination of
the contract for default. (R4, tab 20) The Bankruptcy Court subsequently issued a written
Final Judgment based on the reasons articulated at the hearing (R4, tab 19).
IV. Proceedings before the Board
30. On July 20, 2012, U.S. Coating timely appealed from the CO’s April 25, 2012
final decision, terminating the contract for default.
31. The Corps filed a motion to dismiss or, in the alternative, for summary
judgment in this appeal, which was later amended, that was the subject of our April 9,
2015 decision in U.S. Coating I. 15-1 BCA ¶ 35,957 at 175,705, ¶¶ 14-16. In its decision,
the Board struck U.S. Coating’s affirmative claims in its amended complaint and denied
the remainder of the Corps’ motion. Id. at 175,707-08.
32. On January 21, 2016, the Corps filed a renewed motion for summary judgment
in this appeal. In its renewed motion for summary judgment, the Corps advanced two new
theories to bar U.S. Coating’s introduction of an alleged prior oral agreement to terminate
the contract for convenience for the purposes of contesting the propriety of the default
termination. First, it contended that U.S. Coating’s allegation of a prior agreement is
barred by the parol evidence rule. Second, it contended that, even if the allegation is
assumed true, AUSA Usry, whose representations U.S. Coating relies upon, lacked the
requisite actual authority to bind the government to such an agreement.
33. In support of its renewed motion, the Corps submitted the affidavits of
CO McGuffie and AUSA Usry. CO McGuffie’s affidavit stated in pertinent part:
2. I was the Government Procuring Contracting Officer who
awarded and administered the contract (number W912EE-10-
C-0019) that is the subject of this appeal.
8
3. My authority as the duly authorized Contracting Officer
under the subject Contract was never delegated to or usurped
by the Assistant United States Attorney who represented the
Corps in the bankruptcy proceeding that involved U.S.
Coating and implicated contract number W912EE-10-C-0019.
4. Because of the Contractor’s actions endangering
performance on the contract, I had clear justification for
termination for default. Due to the significant financial and
contractual ramifications a termination for convenience
would have presented to the Corps and our customer, I never
would have agreed to terminate the contract for convenience.
The Assistant United State[s] Attorney had no authority
granted to him on the subject contract. Had the Assistant
United State[s] Attorney advised or recommended a
termination for convenience, which he did not, I would not
have entertained such a recommendation.
(U.S Coating II, gov’t reply, ex. L (McGuffie aff., dated May 10, 2016))
34. AUSA Usry’s affidavit stated in pertinent part:
2. I represented the United States Army Corps of Engineers
(“the Corps”) in the Chapter 11 bankruptcy proceedings that
involved the Corps’ contract, number W912EE-10-B-0011,
with U.S. Coating Specialties & Supplies, LLC (“U.S.
Coating”), the debtor . . . .
3. I had conversations with U.S. Coatings’ counsel in the
bankruptcy proceedings, Herb Irvin, and representatives of
the debtor on multiple occasions during the course of the
bankruptcy proceedings.
4. During my discussions and negotiations in the bankruptcy
proceedings with debtor’s counsel and debtor’s
representatives, I never promised anyone that the Corps
would terminate the contract for convenience if U.S. Coating
rejected the contract in bankruptcy.
5. During my discussions and negotiations in the bankruptcy
proceedings with debtor’s counsel and debtor’s
representatives, I never did state or otherwise imply that I had
9
any authority whatsoever to bind the Corps to terminate the
contract for convenience.
(U.S Coating II, gov’t reply, ex. M (Usry aff., dated May 9, 2016))
35. In its opposition to the Corps’ renewed motion for summary judgment, U.S.
Coating relied on three affidavits of its employees - President and CEO, Mr. Earl J. Washington;
Ms. Velma Day; and Mr. Alden Brooks - originally submitted in the earlier U.S. Coating I
proceedings. Mr. Washington’s affidavit stated in pertinent part:
3. I never consented to a termination by default. I agreed to
lift the automatic stay on the condition that U.S. Coating
would be terminated only by convenience. I held this
discussion with Travelers’ legal counsel, the Respondent’s
legal counsel, and U.S. Coating’s legal counsel, Herb Irvin,
on April 24, 2012.
(U.S Coating I, app. opp’n, ex. A (Washington aff., dated Jan. 13, 2013))
36. On April 6, 2017, we denied the government’s renewed motion for summary
judgment. We held that the record was insufficient to determine whether the April 25,
2012 bankruptcy agreement was a fully integrated agreement, and that genuine issues of
material fact existed regarding whether there was a separate oral agreement with the
government to terminate the contract for convenience. U.S. Coating II, 17-1 BCA
¶ 36,710 at 178,760. We further held the AUSA possessed the necessary authority to
bind the government when the parties entered into the April 25, 2012 bankruptcy
settlement agreement. Id. at 178,761. We concluded that the Corps was not entitled to
judgment as a matter of law on the factual record and that U.S. Coating should have an
opportunity to fully develop the facts surrounding the parties’ negotiations prior to the
Bankruptcy Court settlement. Id.
37. On October 26, 2018, the parties agreed to the submission of the appeal on the
record without a hearing pursuant to Board Rule 11 (Br. corr. ltr. dtd. November 6, 2018).
On October 31, 2018, we issued a scheduling order for the submission of Rule 11 briefs
and permitting appellant to take additional discovery.
38. Appellant submitted in support of its Rule 11 brief the depositions of
CO McGuffie and David Townsend, a Quality Assurance Technician with the Corps, the
three affidavits of its employees that it previously had submitted, and an affidavit from its
counsel in the bankruptcy matter, Herbert J. Irvin (app. supp. R4, tabs 1-7).
39. The Corps submitted in support of its Rule 11 brief a variety of exhibits,
including correspondence between appellant and the CO, a decision in the arbitration
10
between U.S. Coating and its principal subcontractor, Mid State Construction Company,
Inc., and CO McGuffie’s Memorandum for the Record in support of the termination for
default (gov’t br., exs. A-K).
40. On February 11, 2019, the parties completed briefing pursuant to Board Rule 11.
DECISION
The threshold issue is whether appellant has demonstrated that a separate oral
agreement existed requiring the government to terminate the contract for convenience. If
we conclude that a separate agreement existed, then we must decide whether the CO
violated that agreement when she terminated the contract for default. Alternatively, if
appellant cannot demonstrate that a separate agreement existed, we must determine
whether the CO’s default termination was justified.
For the reasons set forth below, we conclude that appellant has not met its burden
of demonstrating that the parties had entered into a separate oral agreement to terminate
the contract for convenience. We further conclude that the CO reasonably exercised her
discretion when she terminated the contract for default. Accordingly, we deny the appeal.
I. Standard of Review
Board Rule 11 permits parties “to waive a hearing and to submit [their] case upon
the record.” The standards of review and burdens of proof of a motion for summary
judgment and a decision on the merits under Board Rule 11 vary substantially. DG21,
LLC, ASBCA No. 57980, 15-1 BCA ¶ 36,016 at 175,909 n.1. Unlike a motion for
summary judgment, which must be adjudicated on the basis of a set of undisputed facts,
pursuant to Board Rule 11, the Board “may make findings of fact on disputed facts.”
Grumman Aerospace Corp., ASBCA No. 35185, 92-3 BCA ¶ 25,059 at 124,886 n.13.
The legal standards for a default termination are well established. Under the
default clause, in this appeal FAR 52.249-10, DEFAULT (FIXED-PRICE
CONSTRUCTION) (APR 1984), the government may terminate a contract for default
when the contractor, without excuse, fails diligently to prosecute the work or fails to
complete the work within the time prescribed by the contract. The government bears the
burden to prove that its termination was justified. Lisbon Contractors, Inc. v. United
States, 828 F.2d 759, 765 (Fed. Cir. 1987); New Era Contract Sales, Inc., ASBCA
No. 56661 et al., 11-1 BCA ¶ 34,738 at 171,022. If the government establishes a prima
facie case justifying the termination, the burden shifts to the contractor to prove the
default was excusable. ADT Constr. Grp., Inc., ASBCA No. 55358, 13 BCA ¶ 35,307
at 173,312 (citing Empire Energy Management Systems, Inc., ASBCA No. 46741, 03-1
BCA ¶ 32,079 at 158,553).
11
II. Whether the Parties Had a Separate Oral Agreement that the Corps Would
Terminate the Contract for Convenience
In U.S. Coating II, we held that the parol evidence rule did not prevent U.S.
Coating from introducing evidence that a separate oral agreement existed apart from the
Bankruptcy Court’s April 25, 2012 Agreed Order. 17-1 BCA ¶ 36,710 at 178,760. We
subsequently allowed U.S. Coating to take additional discovery to support its allegation
of a separate agreement (Docket No. 115).
The parties agree that there is no written agreement that the Corps would terminate
the contract for convenience. Therefore, U.S. Coating must establish the existence of an
implied-in-fact contract. “An implied-in-fact contract has all the requirements of an
express contract except that the evidence of the meeting of the minds differs.” Safeco
Ins. Co. of Am., 17-1 BCA ¶ 36,819 at 179,450 (citing Hanlin v. United States, 316 F.3d
1325, 1328 (Fed. Cir. 2003)). In order to establish an implied-in-fact contract, U.S.
Coating must satisfy the following elements: (1) mutuality of intent; (2) consideration;
(3) lack of ambiguity in offer and acceptance; and (4) the existence of a government
representative whose conduct is relied upon who had actual authority to bind the
government in a contract. Safeco, 17-1 BCA ¶ 36,819 at 179,450 (quoting Todd Pacific
Shipyards Corp., ASBCA No. 55126, 08-2 BCA ¶ 33,891 at 167,755).
U.S. Coating offers sworn testimony of four individuals, as well as deposition
testimony from CO McGuffie, to support the existence of a separate agreement to
terminate the contract for convenience (finding 39). U.S. Coating contends that it
reached an agreement during an oral teleconference that took place on April 24, 2012,
two days before the scheduled hearing (finding 19). The participants in the call included
AUSA Usry, Herbert J. Irvin, counsel for U.S. Coating in the bankruptcy action, and
Mark Herbert, counsel for Travelers (finding 18). The government, in turn, relies on the
sworn statement and deposition testimony of CO McGuffie and the sworn statement of
AUSA Usry to support its contention that no separate agreement existed (finding 39).
A. No Evidence of Mutuality of Intent
The first element of an implied-in-fact contract is mutuality of intent. Walsh
Constr. Co. of Ill., ASBCA No. 52952, 02-2 BCA ¶ 32,024 at 158,279, aff’d, 80 F. App’x
679 (Fed. Cir. 2003). To show mutuality of intent, appellant must demonstrate, by
objective evidence, the existence of an offer and reciprocal acceptance. Guardian Safety
& Supply LLC, ASBCA No. 61932, 19-1 BCA ¶ 37,333 at 181,561 (citing Anderson v.
United States, 344 F.3d 1343, 1353 (Fed. Cir. 2003)). Once an offer is made,
“acceptance of the offer must be manifested by conduct that indicates assent to the
proposed bargain.” Guardian Safety, 19-1 BCA ¶ 37,333 at 181,561 (quoting Russell
Corp. v. United States, 537 F.2d 474, 482 (Ct. Cl. 1976)).
12
Prior to the phone call, the only explicit discussion of a termination for other than
default was between counsel for U.S. Coating and counsel for the surety, Travelers
(finding 23) (app. br. at 22-23). Travelers was not a party to the contract between the
United States and U.S. Coating and, therefore, had no authority to enter into an
agreement concerning the termination of the contract. See Guardian Safety, 19-1 BCA
¶ 37,333 at 181,561 (citing Federal Crop Ins. Corp. v. Merrill, 332 U.S. 380, 384 (1947)
(holding contractor assumes risk of ascertaining authority of agents who purport to act for
the government)). Therefore, discussions between counsel for Travelers and U.S.
Coating do not establish mutual intent.
U.S. Coating’s counsel, Herb Irvin, does not explicitly claim that an agreement
with the government was reached during the phone call. Instead, he avers that:
[W]e understood [AUSA] David Usry to say that the Corps
would have no issue with a termination for reasons other than
default, but that the Corps could not take any action until the
Automatic Stay was lifted.
(Finding 22) Even if we accept Mr. Irvin’s assertion that AUSA Usry stated that he
“would have no issue with a termination for reasons other than default,” this is well short
of an agreement.
The statements of U.S. Coating’s employee, Mr. Brooks, also fail to establish the
existence of mutual intent. His statements indicate his subjective understanding that the
government would agree to a termination for convenience:
I believed that that there would be good-faith steps taken by
Mr. Usry and the Corps to satisfactorily resolve the contract
in the best manner possible.
(App. supp. R4, tab 3 at 2, ¶ 9 (Brooks aff., dated Oct 31, 2018))
Moreover, Mr. Washington’s statements fail to establish mutual intent. He states
in his affidavit that he “understood David Usry to say that the Corps would have no issue
with a termination for reasons other than default, but that the Corps could not take any
action until the Automatic Stay was lifted.” (Finding 19) This understanding, assuming
it is entirely factual, falls short of establishing mutual intent.
From the government’s perspective, AUSA Usry’s sworn statement indicates that
he did not believe that he possessed the authority to agree to a termination for
convenience and that a decision on termination would need to occur after the bankruptcy
stay was lifted (finding 34). Even if AUSA Usry was mistaken about whether he
possessed authority to enter into an agreement to terminate the contract, his subjective
13
belief at the time would have made it impossible for him to possess the requisite intent to
reach a binding agreement. Therefore, it was not possible for him to have a meeting of
the minds with counsel for U.S. Coating. See Man & Machine, Inc., ASBCA No. 61608,
19-1 BCA ¶ 37,401 at 181,812 (mutual intent cannot be inferred when government
official does not hold himself out as possessing authority to bind government).
Taken together, these statements fall well short of mutual intent. A contractor’s
subjective understanding that the government would agree is not sufficient to establish a
meeting of the minds. See Engineering Solutions & Products, LLC, ASBCA No. 58633,
17-1 BCA ¶ 36,822 at 179,466 (holding that contractor’s unilateral “understanding” is
not sufficient to establish a mutuality of intent).
B. Existence of Offer and Acceptance is Ambiguous
Moreover, the record is ambiguous – at best – concerning the existence of an offer
and acceptance. To satisfy its burden, U.S. Coating must show, by objective evidence,
the existence of an offer and reciprocal acceptance. Anderson, 344 F.3d at 1353; Yonir
Technologies Inc., ASBCA No. 56736, 10-1 BCA ¶ 34,417 at 169,897. In this situation,
the precatory statements of U.S. Coating’s representatives are not sufficient to
demonstrate the existence of an agreement to terminate the contract for convenience.
The sworn statements of the individuals representing U.S. Coating are consistent
in stating that U.S. Coating wanted a termination for convenience. As we previously
observed, it is hard to imagine why U.S. Coating would agree to settle the bankruptcy
litigation in exchange for a termination for default. U.S. Coating II, 17-1 BCA ¶ 36,710
at 178,760. Indeed, U.S. Coating’s president, Earl Washington, stated in his affidavit that
his agreement to the bankruptcy order was based on his understanding that such an order
was necessary to proceed with negotiations with the Corps to allow the addition of the
subcontractor to assist U.S. Coating in completing the contract. U.S. Coating I, 15-1
BCA ¶ 35,957 at 175,705 (citing R4, tab 20 at 23-30).
However, the subjective beliefs of U.S. Coating’s representatives are not sufficient
to establish the existence of an offer and acceptance. The subjective unexpressed intent
of one of the parties is irrelevant to contract interpretation. Altanmia Commercial
Marketing Co., ASBCA No. 55393, 09-1 BCA ¶ 34,095 at 168,585 (citing Andersen
Consulting v. United States, 959 F.2d 929, 934 (Fed. Cir. 1992)). It will not bind the
other party, especially when the latter reasonably believes otherwise. See Firestone Tire
& Rubber Co. v. United States, 444 F.2d 547, 551 (Ct. Cl. 1971).
Finally, AUSA Usry unequivocally states in his sworn statement that he did not
agree to a termination for convenience and that a decision on termination would need to
occur after the bankruptcy stay was lifted. Specifically, Mr. Usry averred that he “never
promised anyone that the Corps would terminate the contract for convenience if U.S.
14
Coating rejected the contract in bankruptcy.” (Finding 34) We find Mr. Usry’s statement
to be credible and consistent with the other evidence.
In summary, U.S. Coating has failed to demonstrate the existence of an
implied-in-fact contract to terminate the contract for convenience.
III. Whether the CO Abused her Discretion by Terminating the Contract for Default
In the absence of an agreement between the parties that the contract would be
terminated for convenience, the remaining issue is whether the contracting officer abused
her discretion by terminating the contract for default.
In U.S. Coating I, we held that rejection in bankruptcy is not, by itself, tantamount
to anticipatory repudiation. 15-1 BCA ¶ 35,957 at 175,707 (citations omitted) (holding
that rejection and termination are distinct concepts). We further held that U.S. Coating
consented to the bankruptcy order rejecting the contract and thus communicated to the
Corps that it was freeing itself from the obligation to perform under the contract. Id. We
held open the possibility that if appellant could prove the existence of an agreement to
terminate the contract for convenience, it may be able to demonstrate that the CO
improperly exercised her discretion when terminating the contract for default. Id.
at 175,708; see The Ryan Co., ASBCA No. 48151, 00-2 BCA ¶ 31,094 at 153,543, recon.
denied, 01-1 BCA ¶ 31,151 (holding that “the default clause does not require the
Government to terminate on a finding of a bare default but merely gives the agency the
discretion to do so.”). However, as we discussed above, we conclude that U.S. Coating
has not demonstrated the existence of an agreement to terminate the contract for
convenience.
A. Government Has Demonstrated Prima Facie Grounds for Default
Termination
The only remaining question, therefore, is whether the rejection of the contract in
bankruptcy, coupled with non-performance, was a reasonable basis for termination. The
government bears the burden of proof with respect to whether the default termination was
justified. Lisbon, 828 F.2d at 765. The default provision “require[s] reasonable belief on
the part of the contracting officer that there was no reasonable likelihood that the
contractor could perform the entire contract effort within the time remaining for contract
performance.” McDonnell Douglas Corp. v. United States, 323 F.3d 1006, 1016 (quoting
Lisbon, 828 F.2d at 765).
U.S. Coating’s decision to reject the contract in bankruptcy, considered alone, is
sufficient to establish prima facie grounds for default termination. The bankruptcy
15
statute states that the rejection in bankruptcy of a contract is a breach of that contract:
Except as provided in subsections (h)(2) and (i)(2) of this
section, the rejection of an executory contract or unexpired
lease of the debtor constitutes a breach of such contract or
lease
11 U.S.C. § 365(g) (2005).
As we previously explained, rejection of a contract in bankruptcy “frees the estate
from the obligation to perform under the contract.” U.S. Coating I, 15-1 BCA ¶ 35,957
at 175,707 (quoting Lewis Bros. Bakeries Inc. & Chi. Baking Co. v. Interstate Brands
Corp., 751 F.3d 955, 961 (8th Cir. 2014)). Moreover, in Thomas & Sons Building
Contractors, Inc., we concluded that a contractor’s rejection of a contract in bankruptcy
was sufficient to justify the government’s termination for default. ASBCA No. 53395,
05-2 BCA ¶ 33,083 at 163,989-90.
However, as we held in U.S. Coating I, the default clause does not require the CO
to terminate upon a finding of bare default, but gives the CO discretion to do so. Indeed,
the CO’s exercise of that discretion must be fair and reasonable and not arbitrary and
capricious. U.S. Coating I, 15-1 BCA ¶ 35,957 at 175,708 (citations omitted).
We conclude that the CO reasonably exercised her discretion in terminating the
contract for default. The CO’s memorandum for the record, dated May 7, 2012, provides
support for her termination decision based upon U.S. Coating’s failure to make
reasonable progress on critical path items. In particular, CO McGuffie noted that U.S.
Coating’s schedule updates from December 2011 through April 2012 showed little or no
progress on critical path items. During that time frame, U.S. Coating reported negative
float that increased from 69 days to 185 days. Although CO McGuffie sought an
explanation for the delay, U.S. Coating did not respond to her multiple letters. Moreover,
U.S. Coating admitted that it would not complete performance by the June 30, 2012
completion date. Finally, U.S. Coating provided CO McGuffie with no indication that it
had a viable plan to halt slippage and regain the lost time. (Finding 28) In her affidavit,
CO McGuffie reiterated her position regarding default, averring that “[b]ecause of the
Contractor’s actions endangering performance on the contract, I had clear justification for
termination for default.” (Finding 33)
U.S. Coating offers no specific facts to refute the CO’s assertions. The CO’s
memorandum for the record offers a contemporaneous account of the facts that supported
her decision and is consistent with her subsequent sworn statement in her affidavit. As
stated in Board Rule 11, “Submission of a case without hearing does not relieve the
parties from the necessity of proving the facts supporting their allegations or defenses.”
16
We conclude that the government has demonstrated a prima facie basis for the
termination for default.
B. U.S. Coating Has Not Demonstrated That Default Was Excusable
Having concluded that the government has demonstrated a prima facie basis for
the default termination, the burden shifts to the contractor to demonstrate that its default
was excusable. Truckla Services, Inc., ASBCA Nos. 57564, 57752, 17-1 BCA ¶ 36,638
at 178,445 (citing ADT Constr. Grp., 13 BCA ¶ 35,307 at 173,312). Here, U.S. Coating
contends that the default was excusable because it resulted from the non-foreseeable
circumstance of its primary subcontractor, Mid-State Construction, walking off the job
and bringing a dispute against U.S. Coating that subsequently required U.S. Coating to
file bankruptcy protection under Chapter 11 (app. br. at 1, 17-19).
U.S. Coating asserts, without evidence, that “Mid-State Construction walked off
the job and brought a dispute against U.S. Coating in an effort to undermine U.S. Coating
and to take over the contract U.S. Coating had in place with the Corps” (app. br. at 17).
The government, in turn, presents uncontroverted evidence that Mid-State walked off the
job because U.S. Coating had not paid Mid-State for its work on the project. The Corps
points to the November 22, 2011, arbitration award against U.S. Coating, in which the
arbitrator found that U.S. Coating had materially breached the contract between it and
Mid-State for failure to pay Mid-State, stating that U.S. Coating had “offered no valid
explanation as to why [Mid-State]” was not paid (finding 9).
U.S. Coating has offered no new facts to refute these assertions, nor do we see any
reason to disturb the arbitrator’s findings. Further, U.S. Coating has offered no evidence
that Mid-State’s decision to walk off the job was due to an unforeseeable event. Instead,
the evidence demonstrates that it walked off the job because it was not being paid
(finding 9). See Bichler Co., ASBCA No. 30680, 89-1 BCA ¶ 21,320 at 107,511
(upholding termination for default against prime contractor based on subcontractor’s
delay). Appellant’s failure to pay Mid-State was the cause of job disruption and
Mid-State provided notice to U.S. Coating that Mid-State would stop working on the
contract unless it was paid (gov’t br., ex. A at 5).
U.S. Coating further contends that termination for default was not justified,
because the Corps materially breached the contract when the CO repeatedly refused to
meet with Mr. Washington to resolve issues regarding the replacement subcontractor
(app. br. at 19-21). According to U.S. Coating, it arranged for a new subcontractor,
MTNT, to take over the contract after Mid-State Construction walked off the job
(finding 15). U.S. Coating wrote to the CO to arrange a meeting to discuss continuing
the contract using MTNT, but the CO refused to meet (finding 15). U.S. Coating
contends, without evidence, that the CO “did not want U.S. Coating to continue and
complete the contract” (app. br. at 19).
17
In her April 4, 2012 letter, CO McGuffie explained why she refused to meet. She
said that, despite her numerous requests, U.S. Coating had not provided her with
sufficient information about the exact contractual relationship it intended. She explained
that FAR 49.402-4, Procedures in lieu of Termination for Default, allows a contractor to
“continue performance of the contract by means of a subcontract or other business
arrangement with an acceptable third party, provided the rights of the Government are
adequately preserved.” FAR 49.402-4(b). According to CO McGuffie, U.S. Coating
provided her no assurances that its current bonding company consented to the assignment
of the contract to MTNT and that, without such assurances, the government’s rights
would not be adequately protected. (Finding 16)
We conclude that the CO was justified in her reluctance to meet with U.S. Coating
without first receiving adequate assurances that U.S. Coating’s bonding company
supported MTNT’s assumption of the contract. We further conclude that U.S. Coating
has not carried its burden of proving that the default was excusable.
C. U.S. Coating Has Not Demonstrated That Corps Acted in Bad Faith
U.S. Coating contends that the Corps acted in bad faith when it terminated the
contract for default the day after the Agreed Order was filed. U.S. Coating presents its
bad faith argument as an exception to the parol evidence rule to persuade us to allow
consideration of the parties’ April 24, 2012 phone conversation during which the parties
allegedly agreed that the contract would be terminated for convenience (app. br. at 16-17).
Because we previously held that the parol evidence rule did not prevent U.S. Coating from
introducing evidence regarding a separate oral agreement, there is no need for us to decide
whether the government acted in bad faith in order to consider the April 24, 2012 phone
conversation. U.S. Coating II, 17-1 BCA ¶ 36,710 at 178,760.
U.S. Coating additionally argues that the CO, Ms. McGuffie, acted in bad faith
when she “completely ignored the agreement reached between Earl Washington and the
AUSA” (app. reply. br. at 2).
Government officials are presumed to act in good faith. Puget Sound
Environmental Corp., ASBCA No. 58828, 16-1 BCA ¶ 36,435 at 177,597 (citing Road
and Highway Builders, LLC v. United States, 702 F.3d 1365, 1368 (Fed. Cir. 2012)). To
prove that a government official acted in bad faith, a contractor “must show a ‘specific
intent to injure”’ by clear and convincing evidence. Road and Highway Builders, 702
F.3d at 1369 (quoting Am-Pro Protective Agency, Inc. v. United States, 281 F.3d 1234,
1240 (Fed. Cir. 2002)).
Here, U.S. Coating has offered no specific evidence to overcome the presumption
that government officials acted in good faith. Other than Mr. Washington’s sworn
18
statement expressing his surprise that the Corps terminated the contract for default the
day after the Agreed Order was signed (finding 27), U.S. Coating offers no testimony,
correspondence, or other evidence that any government official intended to deceive U.S.
Coating or otherwise negotiated in bad faith.
In his sworn statement, U.S. Coating’s counsel, Mr. Irvin, stated “that either
everyone on our end of the conference call . . . must have misunderstood what David
Usry said, or the Corps was not acting in good faith during the negotiations” (finding 23).
Although Mr. Irvin implies that the Corps was not acting in good faith, this statement is a
conclusory allegation and offers no evidence of specific intent. Sia Construction, Inc.,
ASBCA No. 57693, 14-1 BCA ¶ 35,762 at 174,987 (appellant “must do more than
merely allude to bad faith by contracting officials” to overcome the presumption).
Moreover, as we previously discussed, U.S. Coating’s own affidavits fall short of
stating that the Corps specifically agreed to terminate the contract for convenience. In
the absence of an agreement, we cannot conclude that the CO acted in bad faith when she
terminated the contract for default.
IV. Whether the Doctrine of Res Judicata Precludes Appellant from Re-Litigating
Issues Decided by the Bankruptcy Court
The government contends that the doctrine of res judicata bars consideration of
whether the government induced appellant to reject the contract before the Bankruptcy
Court. According to the government, the Bankruptcy Court previously considered this
issue in its May 17, 2012 hearing and appellant is barred from raising it again before the
Board (gov’t br. at 22).
The government did not raise this argument in its January 21, 2016 renewed
motion for summary judgment. There, the government argued that the April 25, 2012
Agreed Order was an integrated agreement and that the parole evidence rule barred the
Board from considering whether a separate contrary agreement existed. We held that the
parol evidence rule did not prevent U.S. Coating from introducing evidence that a
separate oral agreement existed apart from the Bankruptcy Court’s Agreed Order. U.S.
Coating II, 17-1 BCA ¶ 36,710 at 178,760.
In light of our conclusion that the parties did not have an implied-in-fact contract
to terminate the contract for convenience, we need not consider whether res judicata bars
U.S. Coating from re-litigating whether the government induced U.S. Coating to reject
the contract before the Bankruptcy Court.
19
CONCLUSION
For these reasons, we deny the appeal.
Dated: September 28, 2020
KENNETH D. WOODROW
Administrative Judge
Armed Services Board
of Contract Appeals
I concur I concur
RICHARD SHACKLEFORD J. REID PROUTY
Administrative Judge Administrative Judge
Acting Chairman Vice Chairman
Armed Services Board Armed Services Board
of Contract Appeals of Contract Appeals
I certify that the foregoing is a true copy of the Order of Dismissal of the Armed
Services Board of Contract Appeals in ASBCA No. 58245, Appeal of U.S. Coating
Specialties & Supplies, LLC, rendered in conformance with the Board’s Charter.
Dated: September 29, 2020
PAULLA K. GATES-LEWIS
Recorder, Armed Services
Board of Contract Appeals
20