RENDERED: OCTOBER 30, 2020; 10:00 A.M.
TO BE PUBLISHED
Commonwealth of Kentucky
Court of Appeals
NO. 2019-CA-0928-MR
ALL THAT N MORE, LLC;
MARTY NILEST; AND
MATT NILEST APPELLANTS
APPEAL FROM JEFFERSON CIRCUIT COURT
v. HONORABLE JUDITH MCDONALD-BURKMAN, JUDGE
ACTION NO. 17-CI-002319
ROMAN KUSYO AND
NATALIE KUSYO APPELLEES
OPINION
AFFIRMING IN PART, REVERSING IN PART,
AND REMANDING
** ** ** ** **
BEFORE: CLAYTON, CHIEF JUDGE; DIXON AND JONES, JUDGES.
JONES, JUDGE: All That N More, LLC (“All That”), a construction company,
and its owners, Marty and Matt Nilest, appeal orders of the Jefferson Circuit Court
which granted default judgment against the company and awarded damages to
Roman and Natalie Kusyo based on a home construction contract. After thorough
review, we affirm in part, reverse in part, and remand.
I. BACKGROUND
This case has a somewhat lengthy and complex background and
procedural history. In August 2016, the Kusyos signed a contract drafted by
Appellants to construct a new home on a plot of land owned by the Kusyos in
Louisville, Kentucky. Pursuant to the contract, All That agreed to construct the
home for $228,500.00, payable in a series of installments or “draws” based on
specific milestones achieved during the course of construction. Further, the
contract required any changes or overages to be in writing and approved by both
parties in what are referred to as “change orders.” There were only two authorized
change orders during the construction: an added room for $5,000.00 and a window
for $320.00. This resulted in a new total owed on the contract of $233,820.00.
Unfortunately, All That encountered rock on the third day of
excavating the foundation for the house. A “rock clause” in paragraph 6.5 of the
contract, entitled “Concealed Conditions,” applied to such an event:
The Contractor is not responsible for subsurface or latent
physical conditions at the site or in an existing structure
that differ from those (a) indicated or referred to in the
contract documents or (b) ordinarily encountered and
generally recognized as inherent in the work of the
character provided for in this contract.
-2-
After receiving notice of the conditions, the Owner shall
investigate the condition within five (5) working days. If
the parties agree that the condition will increase (a) the
Contractor’s cost of performance of any part of the work
under this contract or (b) the time required for that work,
the parties may sign a change order agreement
incorporating the necessary revisions, or the Owner may
terminate the contract. If the Owner terminates the
contract, the Contractor will be entitled to recover from
the Owner payment for all work performed, including
normal overhead, and a reasonable profit.
Matt Nilest informed the Kusyos’ agent, their daughter Oksana, that All That had
encountered rock. However, Oksana testified that she was informed there would
be no added cost as a result; it would simply change how the house would be built,
i.e., “up” from the rock, rather than digging down through it. Matt Nilest denied
telling Oksana there would be no added cost. Nonetheless, it is undisputed that no
change order was prepared and signed at the time All That discovered rock on the
property. It is likewise undisputed that the construction project continued after
discovery and notice of the rock.
From September 2016 through January 2017, the Kusyos paid All
That a total of $203,500.00, approximately eighty-seven percent of the contracted
price. Oksana’s fiancé noticed the house did not appear to be progressing, and it
did not appear that drawn funds were being spent on intended purchases. Then, in
February 2017, Oksana began to receive text messages and emails from Matt
Nilest requesting more money, even though All That had drawn nearly all the
-3-
money allocated to it under the contract. The only remaining draw was the final
ten percent of the contract price, which under the terms of the contract was due on
the completion of construction. Oksana and her fiancé agreed to meet with the
Nilests at the construction site on March 1, 2017, to discuss the project. During the
meeting, the Nilests handed Oksana an invoice, dated that day, demanding a price
addendum to the contract of $81,340.00 and claiming the new balance owed was
$107,840.00, over and above the $203,500.00 which the Kusyos had already paid.
Oksana declined to pay this new invoice. At the conclusion of this meeting,
Appellants walked away from the job.
The Kusyos eventually hired a second contractor, Jeremy Murphy, to
finish the house. Murphy would later testify the house was approximately fifty
percent complete when he first inspected the site, and it contained incorrect or poor
quality construction. As a result, the second contractor estimated it would take
over $76,000.00 to repair the previous, subpar construction completed by
Appellants and another approximately $200,000.00 to complete the remaining
construction. At the time of the damages hearing in December 2019, the home was
not yet complete.
Meanwhile, on May 11, 2017, the Kusyos filed a complaint against
Appellants in Jefferson Circuit Court alleging breach of express contract, breach of
express and implied warranty, negligent or reckless misrepresentation, and
-4-
violating KRS1 Chapter 367 et seq., the Kentucky Consumer Protection Act. The
Kusyos alleged Appellants breached the contract by walking off the job site after
receiving $203,500.00, when it appeared less than $80,000.00 had been expended
on the project. The Kusyos also alleged the project was less than fifty percent
complete when Appellants walked away from the contract and that it would require
in excess of $150,000.00 to complete the construction of the home Appellants
contracted to construct for them.
Appellants did not file an answer to the complaint within twenty days.
The summonses for Matt Nilest and Marty Nilest were returned as undeliverable.
However, on May 15, 2017, the summons for All That was successfully served
upon its registered agent. All That had been dissolved as a corporate entity, but
nonetheless remained subject to suit. See KRS 275.300(4)(a) (“Dissolution of a
limited liability company shall not . . . [p]revent commencement of a proceeding
by or against the limited liability company in its name[.]”). On June 21, 2017, the
Kusyos moved the circuit court for default judgment against All That, and the
circuit court granted this motion on June 23, 2017.
Several days later, attorney J. Clark Baird entered his appearance on
behalf of Appellants. He subsequently filed a “motion to alter, amend, or vacate
1
Kentucky Revised Statutes.
-5-
default judgment” citing CR2 59.05 or CR 60.02. The stated basis for this motion
was that Appellants had previously “required time to acquire funds to retain
counsel upon receipt of the complaint.” (Record (“R.”) at 33.) The circuit court
granted Baird’s motion to set aside the default judgment to allow Appellants to file
answers to the complaint. “Marty Nilest, of All That N More, LLC” and “Matt
Nilest, of All That N More, LLC” filed answers to the complaint, but All That did
not. (R. at 47, 60.)
On July 31, 2017, the circuit court set aside its earlier order setting
aside the June 23 order—effectively reinstating the default judgment. (R. at 74.)
The court’s July 31 order stated Appellants’ CR 59.05 motion was untimely as its
justification for setting aside the prior order. However, in a hearing on the motion
that same day, the circuit court also stated that the CR 59.05 motion was not proper
in any event, because the judgment was not final. It reasoned that instead
Appellants should have moved to set aside the default judgment under CR 55.02.
Less than two weeks later, Appellants moved the circuit court to set
aside the default judgment pursuant to the correct rule, CR 55.02. In a hearing on
the motion, Baird blamed his secretary for mislabeling his previous motion as one
to alter, amend, or vacate. He also repeated his earlier argument that the Nilests
2
Kentucky Rules of Civil Procedure.
-6-
did not have funds to retain him in order to file an answer within the twenty days
noted in the summons. After hearing the arguments of counsel, the circuit court
ruled that the failure to raise a fee to pay an attorney does not amount to excusable
neglect which would be sufficient to set aside a default judgment. The circuit court
thereafter entered a written order on October 20, 2017, which summarily denied
Appellants’ motion to set aside the default judgment. (R. at 98.)
After retaining new counsel, Appellants again moved to set aside or,
in the alternative, modify the default judgment. The circuit court heard arguments
on the renewed motion on January 2, 2018. The circuit court noted it had already
denied Appellants’ motion to set aside and would not revisit that decision.
However, the circuit court was willing to consider modifying the default judgment
based on counsel’s arguments that the Kentucky Consumer Protection Act was
inapplicable in this context. The circuit court then ruled that these issues could be
discussed at a hearing on the Kusyos’ damages, which had yet to take place. Over
the next several months, the circuit court continued the damages hearing while the
parties argued over discovery. In a status hearing on June 25, 2018, Appellants
argued the Kusyos were not supplying enough discovery materials regarding their
asserted damages. In response, the Kusyos contended they had given documents to
Appellants, but the damages were ongoing due to the continued construction on the
-7-
house. The circuit court ruled the discovery period would continue until the end of
August.
The circuit court held the damages hearing over two days, on
December 14 and 19, 2018. At the hearing, the circuit court heard testimony from
Oksana and her fiancé which conformed to the above narrative. The circuit court
also heard from Jeremy Murphy, the general contractor employed by the Kusyos to
complete construction on the house. As noted previously, Murphy testified that the
house was in poor repair when he first arrived on the site, containing
approximately fifty percent usable work. He also testified about the amounts
required to repair and complete the structure. Finally, the circuit court also heard
from Matt and Marty Nilest. The essence of Matt Nilest’s testimony was that
hitting rock changed the scope of the construction project in such a way that it
could not help being a much more expensive undertaking. He also stated the
invoice he handed Oksana during the March 1, 2017, meeting amounted to the
change order required under paragraph 6.5 of the contract. Finally, Matt Nilest
denied walking off the job. Instead, he argued that the Kusyos had not allowed All
That to finish construction, and that—if anything—the Kusyos owed money to
Appellants.
Following post-hearing briefs by the parties, the circuit court entered
its findings of fact, conclusions of law, and judgment on March 5, 2019. The court
-8-
found there were only two valid change orders on the contract, one for $5,000.00
and one for $320.00. The circuit court also found that Appellants had walked off
the job and thereby breached the contract. The Kusyos had conceded the Kentucky
Consumer Protection Act was not applicable to real estate, and thus the circuit
court disallowed recovery for punitive damages under that statutory scheme.
Ultimately, the circuit court awarded damages to the Kusyos as follows:
$76,045.40 for repairs; $101,500.00 in overpaid draws; $200,000.00 for the cost to
complete the house; and $5,605.47 in expenses relating to the release of a brick
subcontractor’s lien. All told, the circuit court granted damages to the Kusyos
amounting to $383,150.87, then added costs and attorney’s fees in the amount of
$24,601.18.
Appellants subsequently moved the court to alter, amend, or vacate
the judgment, arguing against certain categories of damages and alleging the
damage award gave the Kusyos a larger and more valuable home than Appellants
originally contracted to construct. The circuit court denied this motion in an
opinion and order entered on May 15, 2019. Regarding the damages awarded, the
circuit court ruled the overpaid draws should be refunded because Appellants only
completed approximately fifty percent of the work for which they were paid, and
the award of attorney’s fees was based on a provision in the contract granting such
fees to the non-prevailing party. Regarding the size and value of the home, the
-9-
circuit court agreed the house was larger than originally contracted, but noted the
Kusyos paid $5,000.00 for the five-hundred-square-foot addition. The circuit court
ruled, “In sum, the house was not significantly different than the one [Appellants]
contracted to build.” (R. at 584-85.) This appeal followed.
II. ANALYSIS
We begin with the general standard of review in cases where a circuit
court acts as the factfinder. “In all actions tried upon the facts without a jury or
with an advisory jury, the court shall find the facts specifically and state separately
its conclusions of law thereon and render an appropriate judgment . . . . Findings
of fact, shall not be set aside unless clearly erroneous, and due regard shall be
given to the opportunity of the trial court to judge the credibility of the witnesses.”
CR 52.01; see also Moore v. Asente, 110 S.W.3d 336, 353-54 (Ky. 2003). Factual
findings are not clearly erroneous if supported by substantial evidence. Owens-
Corning Fiberglas Corp. v. Golightly, 976 S.W.2d 409, 414 (Ky. 1998).
“Substantial evidence has been conclusively defined by Kentucky courts as that
which, when taken alone or in light of all the evidence, has sufficient probative
value to induce conviction in the mind of a reasonable person.” Bowling v.
Natural Res. and Envtl. Prot. Cabinet, 891 S.W.2d 406, 409 (Ky. App. 1994)
(citations omitted).
-10-
Appellants present four main arguments on appeal. First, they argue
the circuit court erroneously set aside its July 17, 2017 order which set aside the
default judgment. Second, Appellants argue the circuit court erroneously awarded
repayment damages. Third, Appellants argue the circuit court’s damages award
was not supported by the evidence. Fourth, and finally, Appellants argue the
circuit court erroneously awarded attorney’s fees. We will consider each argument
in turn.
A. July 17, 2017 Order
For their first argument, Appellants contend the circuit court
erroneously set aside the July 17, 2017 order which set aside the default judgment.
As noted previously, the circuit court’s stated rationale for setting aside the
July 17 order was that Appellants’ CR 59.05 motion was untimely filed. In a
somewhat convoluted argument, Appellants argue the original motion was not a
valid CR 59.05 motion because there was no final judgment at that time, and thus
the court’s stated reason citing the untimeliness of the CR 59.05 motion as a reason
to set aside the July 17 order was also erroneous.
Although Appellants correctly note the improper application of CR
59.05 early on in this case, we consider this to be of no significance to the
underlying issue. Appellants themselves created this procedural muddle by
incorrectly using CR 59.05 in an attempt to set aside the default judgment. The
-11-
record reflects how, in the midst of these proceedings, the circuit court correctly
noted that CR 59.05 was not applicable and steered the parties toward the correct
rule. Thus, we give no credence to the issue of whether CR 59.05 timing was
appropriate to set aside the order because everyone acknowledges that using CR
59.05 here was incorrect from the beginning. The appropriate issue is whether the
circuit court correctly ruled on the underlying question of whether there was
sufficient reason to set aside the default judgment. This question is resolved by an
examination of the correct rule, CR 55.02.
CR 55.02 allows a court to set aside a default judgment “[f]or good
cause shown[.]” “The moving party must show: (1) a valid excuse for default, (2)
a meritorious defense to the claim, and (3) absence of prejudice to the non-
defaulting party. All three elements must be present to set aside a default
judgment.” S.R. Blanton Development, Inc. v. Inv’rs Realty and Management Co.,
Inc., 819 S.W.2d 727, 729 (Ky. App. 1991) (citation and internal quotation marks
omitted). We review a decision by the circuit court regarding whether to set aside
a default judgment for an abuse of discretion. VerraLab Ja LLC v. Cemerlic, 584
S.W.3d 284, 287 (Ky. 2019). To find an abuse of discretion, we must find the
“trial judge’s decision was arbitrary, unreasonable, unfair, or unsupported by sound
legal principles.” Commonwealth v. English, 993 S.W.2d 941, 945 (Ky. 1999)
(citations omitted).
-12-
The circuit court considered the default judgment under CR 55.02 in a
hearing held on October 20, 2017. The record reflects Appellants and their
eventual counsel had notice of the suit. “[M]ere inattention on the part of the
defendant or his attorney” is not good cause to set aside default. Howard v.
Fountain, 749 S.W.2d 690, 692 (Ky. App. 1988). The record also reflects
Appellants consulted with attorney Baird about the complaint during the twenty-
day time period provided for in the summons. Attorney Baird requested and
received a copy of the complaint from the Kusyos’ attorneys. Yet Appellants’ only
rationale for their failure to respond was that they had to raise money to retain
Attorney Baird to assist them. During the hearing, the circuit court held the failure
to raise an attorney’s fee was not a valid excuse for All That’s failure to file an
answer. We agree. See, e.g., Richardson v. Brunner, 327 S.W.2d 572, 574 (Ky.
1959) (purported inability to hire an attorney is not sufficient excuse for a failure to
defend).
Appellants also argued that the answers submitted by the Nilests
should be extended to cover All That as well, based on principles allowing
multiple defendants to respond “in a joint or separate answer[.]” Ellington v.
Becraft, 534 S.W.3d 785, 791 n.1 (Ky. 2017) (citation omitted). This argument
ignores the fact that All That did not reply in a joint or separate answer; the two
answers submitted were clearly on behalf of the individuals Matt and Marty Nilest
-13-
and not for the company itself. Appellants’ motion to the circuit court conceded
the pleadings submitted by previous counsel were “inartfully drawn.” (R. at 111.)
However, “[c]arelessness by a party or his attorney is not reason enough to set an
entry aside.” Perry v. Central Bank & Tr. Co., 812 S.W.2d 166, 170 (Ky. App.
1991) (citation omitted).
Finally, the circuit court pointed out that the Kusyos would be
prejudiced by setting aside default, in that they were only able to obtain a
construction loan to finish their house based on the default judgment against
Appellants. Based on these factors, we cannot say the circuit court abused its
discretion in refusing to set aside the default judgment.
B. Repayment Damages
For their second issue, Appellants contend the circuit court’s award of
repayment damages was erroneous. They allege several different grounds in
support of this argument. First, Appellants contend the Kusyos failed to timely
disclose their alleged damages resulting from overpaid draws when they provided
“Supplemental Discovery Responses” on the day before the damages hearing was
scheduled, contrary to CR 8.01(2). Second, Appellants contend the repayment of
draws is not a proper measure of damages. Third, Appellants contend that an
award providing repayment of draws as well as the cost to complete construction
results in a double recovery to the Kusyos.
-14-
We need not consider the first or second grounds asserted by
Appellants because we agree with the third argument. The circuit court’s award
based on overpaid draws improperly allowed a double recovery for the Kusyos.
In the case of a breach of contract, the goal of
compensation is not the mere restoration to a former
position, as in tort, but the awarding of a sum which is
the equivalent of performance of the bargain—the
attempt to place the plaintiff in the position he would be
in if the contract had been fulfilled.
Batson v. Clark, 980 S.W.2d 566, 577 (Ky. App. 1998) (quoting SEG Employees
Credit Union v. Scott, 554 S.W.2d 402, 406 (Ky. App. 1977)). Here, if the
contract between Appellants and the Kusyos had been fulfilled, the Kusyos would
have paid the contract price, approximately $233,820.00, and in exchange would
have gotten their contracted house. We disagree with Appellants’ claim that the
Kusyos are getting a better house than that promised by the contract, because the
circuit court determined that the Kusyos paid $5,000.00 for the additional square
footage in a valid change order. The circuit court then concluded “the house was
not significantly different than the one [Appellants] contracted to build.” As an
appellate court, we defer to the factual findings of the trial court unless they are
clearly erroneous. Kentucky Properties Holding LLC v. Sproul, 507 S.W.3d 563,
568-69 (Ky. 2016); CR 52.01.
Having established the house actually constructed is consistent with
the parties’ contract, we now turn to the purchase price. As provided by the
-15-
contract and amended by valid change orders, the Kusyos owed $233,820.00 under
the contract for the construction. The Kusyos paid $203,500.00 to Appellants, and
the circuit court ordered $101,500.00 of that amount to be refunded in an award for
overpaid draws. These draws were deemed overpayments because they were
based on construction which was not performed by Appellants. The circuit court
then awarded the Kusyos another $200,000.00 for the completion of the house.
The problem is that this $200,000.00 effectively also compensates the Kusyos for
the unperformed construction. Logically, if Appellants had performed more work
under the draws, this would have reduced the amount of work the second
contractor needed to perform.
Because the completion amount overlaps the amount awarded on the
basis of the overpaid draws, the circuit court inadvertently awarded the Kusyos a
double recovery. Based on these considerations, we reverse that portion of the
award based on overpaid draws as duplicative of amounts already awarded to the
Kusyos based on completing construction of the house. It is also worth noting that
the circuit court’s damage award does not account for the $30,320.00 ($233,820.00
- $203,500.00) which the Kusyos may still owe toward the completion of the house
pursuant to the contract. If this amount is taken into consideration anywhere in the
record by the circuit court, we have been unable to find it. Despite these
considerations, the awards based on repair of Appellants’ construction and the
-16-
brick subcontractor’s lien appear to be grounded in substantial evidence, and we
affirm those portions of the judgment.
C. Damages Not Supported by the Evidence
For their third argument on appeal, which is closely related to the
second, Appellants contend the amounts awarded to the Kusyos were not
supported by the evidence. Appellants argue, “From the evidence at the damages
hearing, it would be impossible to determine the cost to complete the structure
which All That contracted to construct for the Kusyos.” (Appellants’ Brief at 16.)
A review of the record refutes this argument. As previously noted, the circuit court
found the house being built is “not significantly different” than the one contracted.
Murphy, the replacement contractor hired by the Kusyos, testified that the total
amount required for him to complete the structure, including the repairs, will be
about $285,000.00. The circuit court’s award, when shorn of the improper refund
of overpaid draws, is consistent with this amount. We defer to the circuit court’s
findings when supported by substantial evidence, giving “due regard . . . to the
opportunity of the trial court to judge the credibility of the witnesses.” CR 52.01.
Appellants also argue the amount of the damage award is speculative,
pointing to the fact that the Kusyos’ house was not yet completed at the time of the
hearing. However, “[i]f it is established with reasonable certainty that damage has
resulted from a breach of duty or a wrongful act of defendant, mere uncertainty as
-17-
to the amount will not preclude recovery.” Roadway Exp., Inc. v. Don Stohlman &
Associates, Inc., 436 S.W.2d 63, 65 (Ky. 1968). Aside from the issues in the
award regarding double recovery and possible underpayment by the Kusyos on the
contract, which we noted in the previous argument, we affirm the circuit court’s
award of damages.
D. Attorney’s Fees
In their fourth and final argument, Appellants contend the circuit court
erroneously awarded attorney’s fees to the Kusyos. Originally, the Kusyos pleaded
a claim for attorney’s fees in Count III of the complaint, alleging a violation of the
Kentucky Consumer Protection Act, which provides a statutory basis for such an
award.3 However, the parties dismissed this count by agreement when they
discovered the Kentucky Consumer Protection act does not apply to real estate
transactions or construction contracts, pursuant to Craig v. Keene, 32 S.W.3d 90
(Ky. App. 2000) and its progeny. With Count III removed, the only specific
reference to attorney’s fees left in the complaint was in the ad damnum clause.
Citing O’Roarke v. Lexington Real Estate Company, L.L.C., 365 S.W.3d 584 (Ky.
App. 2011), Appellants contend the prayer for attorney’s fees in the ad damnum
clause was not sufficient to state a cause of action to recover those fees. The
3
See, e.g., KRS 367.220(3) (“In any action brought by a person under this section, the court may
award, to the prevailing party, in addition to the relief provided in this section, reasonable
attorney’s fees and costs.”).
-18-
circuit court disagreed and awarded the Kusyos attorney’s fees based on a
provision of the construction contract which shifted liability for attorney’s fees to
the non-prevailing party.
After some consideration, we must agree with Appellants. In
Nesselhauf v. Haden, 412 S.W.3d 213 (Ky. App. 2013), we held that placing
“attorney’s fees in the ‘prayer for relief’ sections of two pleadings . . . was
insufficient to create a separate claim for relief.” Id. at 217 (citation omitted).
Commenting on O’Roarke, we said that case stood for the proposition that “a claim
does not arise merely from stating a prayer for relief in the ad damnum section
clause of a pleading; a party must also state why he or she is legally entitled to that
which is being requested.” Id. Although the Kusyos stated their claims for breach
of contract in Count I of the complaint, there is nothing in this count which would
give notice to Appellants that the Kusyos would seek attorney’s fees based on the
contractual provision. “Despite the informality with which pleadings are
nowadays treated, and despite the freedom with which pleadings may be amended,
CR 15.01, the central purpose of pleadings remains notice of claims and defenses.”
Hoke v. Cullinan, 914 S.W.2d 335, 339 (Ky. 1995) (citations omitted).
Accordingly, we reverse the circuit court’s award of attorney’s fees in this case.
-19-
III. CONCLUSION
For the foregoing reasons, we affirm the amounts awarded in the
judgment, excepting that we reverse the circuit court’s award of damages to the
Kusyos which were grounded in overpaid draws and the award of attorney’s fees.
In addition, on remand, we direct the circuit court to conduct further proceedings
which will determine if there are any amounts owed by the Kusyos on their
contract and, if so, to reduce their award to reflect their obligations under the
contract toward construction of the home. The circuit court shall thereafter enter a
new judgment not inconsistent with this Opinion.
ALL CONCUR.
BRIEFS FOR APPELLANTS: BRIEF FOR APPELLEES:
Thomas E. Roma, Jr. Sarah Chervenak
Louisville, Kentucky Britt Stevenson
Louisville, Kentucky
-20-