Digitally signed by
Reporter of
Decisions
Reason: I attest to
Illinois Official Reports the accuracy and
integrity of this
document
Appellate Court Date: 2020.06.01
12:01:39 -05'00'
BNSF Ry. Co. v. Grohne, 2019 IL App (3d) 180063
Appellate Court BNSF RAILWAY COMPANY, a Delaware Corporation, Plaintiff-
Caption Appellee and Cross-Appellant, v. DAVID F. GROHNE, as Trustee
Under the David F. Grohne Revocable Trust, Dated February 14,
1996; NONRECORD CLAIMANTS; UNKNOWN OWNERS; and
CHICAGO TITLE AND TRUST COMPANY, as Trustee Under Trust
No. 8002346417, Dated April 25, 2006, Defendants (David F. Grohne
and Chicago Title and Trust Company, Defendants-Appellants and
Cross-Appellees).
District & No. Third District
Docket No. 3-18-0063
Filed July 3, 2019
Decision Under Appeal from the Circuit Court of Will County, Nos. 14-ED-65, 14-
Review ED-66, 14-ED-67; the Hon. Roger D. Rickmon, Judge, presiding.
Judgment Affirmed.
Counsel on James A. Murphy, of Mahoney, Silverman & Cross, Ltd., of Joliet,
Appeal and Ken D. Rechtoris, of Sheppard, Mullin, Richter & Hampton LLP,
of Chicago, for appellants.
Thomas F. Geselbracht and Eric M. Roberts, of DLA Piper LLP (US),
of Chicago, for appellee.
Panel PRESIDING JUSTICE SCHMIDT delivered the judgment of the
court, with opinion.
Justice McDade concurred in the judgment and opinion.
Justice Wright concurred in part and dissented in part, with opinion.
OPINION
¶1 Plaintiff-appellee and cross-appellant, BNSF Railway Company (BNSF), filed three
eminent domain lawsuits for the condemnation of tracts of land owned in trust by defendants-
appellants and cross-appellees, David F. Grohne and Chicago Title and Trust Company
(collectively, Grohne). Plaintiff sought to build an intermodal railway facility along BNSF’s
main rail line in Will County, Illinois, using the condemned land. After the trial court’s ruling
on the pending traverse actions, the court held a jury trial for the valuation of Grohne’s tracts
of land for purposes of exercising eminent domain. The jury awarded Grohne compensation
for all three takings.
¶2 Grohne appeals, claiming the trial court erred by (1) limiting his cross-examination of
experts on a comparable land sale contract at the valuation hearing pertaining to Will County
case No. 14-ED-65, (2) denying his traverse and motions to dismiss in Will County case Nos.
14-ED-66 and 14-ED-67, and (3) misinterpreting section 10-5-110 of the Eminent Domain Act
(Act) (735 ILCS 30/10-5-110 (West 2014)) pertaining to Will County case No. 14-ED-67.
¶3 BNSF cross-appeals, raising the following issues regarding the compensation awards:
(1) whether, absent a substantial and material change, the trial court erred in granting a new
valuation date for the properties pertaining to Will County case Nos. 14-ED-66 and 14-ED-67
and (2) whether the final judgment orders should have been entered based upon the parties’
stipulations of value as of October 20, 2014, rather than the jury’s verdicts as of July 21, 2017.
¶4 I. BACKGROUND
¶5 On October 20, 2014, BNSF filed three eminent domain lawsuits to condemn three
separate, but closely located tracts of land in Will County case Nos. 14-ED-65, 14-ED-66, and
14-ED-67. The complaints in the first two cases named David F. Grohne, as trustee of the
David F. Grohne Revocable Trust, as defendant. The third lawsuit, Will County case No. 14-
ED-67, named David F. Grohne, as well as Chicago Title and Trust Company, as holder of a
land trust with David F. Grohne named as the beneficiary, as defendants.
¶6 BNSF intended to build an intermodal facility along its main line near Interstate 55 and
Lorenzo Road in Will County, Illinois. 1 The northernmost tract (Grohne North), the subject of
case No. 14-ED-65, consists of 81.251 acres. BNSF sought 51.872 acres. The two tracts to the
south, the subjects of case Nos. 14-ED-66 (Grohne South) and 14-ED-67 (CTT), consist of
73.118 and 72.717 acres, respectively. BNSF sought 11.733 and 59.316 acres of these tracts,
respectively. The BNSF main line splits the Grohne tracts subject to taking in all three cases.
1
An intermodal facility is a BNSF location where goods are brought in and consolidated for
distribution by trains or trucks into the surrounding areas. The facilities are comprised of a system of
tracks, support facilities, parking areas, roads, and trailers and containers awaiting shipment, unloading,
and distribution.
-2-
¶7 On September 25, 2014, the BNSF Board of Directors (Board), with unanimous consent,
signed a resolution outlining the details and necessity of an intermodal facility. Specifically,
the resolution stated the following:
“[I]n order to alleviate congestion on the [BNSF main line], prevent blocking of the
main line and facilitate the Company’s ability to meet the current demands of its
existing customers and the future demands of additional development in the area, the
Company proposes to construct and operate a multimodal facility adjacent to the
[BNSF main line]. The facility will operate as a freight terminal and intermodal facility
and will start from a connection to the Chillicothe Subdivision just east of Lorenzo
Road and extend that facility west to a second connection to the Chillicothe Subdivision
at Murphy Road. The second connection at Murphy Road is required to provide access
to the facility from both ends to facilitate safe and expeditious operation of the main
line. The facility will consist of multiple tracks and related connections, paved parking
for holding containers and trailers waiting for local delivery or for loading onto rail
cars, cranes for handling the containers and trailers and support facilities. There will
also be truck gate structures to facilitate entrance and exit of containers and trucks to
and from the facility. Full build out of the facility will require between 300 and 450
acres ***.”
The resolution also outlined in detail the property to be acquired, including 122.921 total acres
from Grohne.
¶8 BNSF, in the complaints filed in these consolidated cases, restated the purpose it laid out
in the Board’s resolution. Further, the complaints stated, “[t]he multimodal facility, once
constructed and open for operations, will be used for the benefit of all users of BNSF’s railroad
without discrimination.”
¶9 On November 24, 2014, Grohne filed a traverse and motion to dismiss in each of BNSF’s
lawsuits. On April 6, 2015, the trial court consolidated the cases. Grohne subsequently
withdrew the traverse with respect to Grohne North. Thus, the traverse hearing covered only
the 71.049 acres comprising Grohne South and CTT.
¶ 10 With respect to Grohne South and CTT, Grohne argued BNSF sought to acquire his private
property, in part, for the purpose of providing direct rail service to a private, neighboring
industrial park, RidgePort Logistics Park (RidgePort). Specifically, Grohne maintained
BNSF’s conceptual plan for the intermodal facility included a private track, or spur track,
designed to provide RidgePort and its attracted customers or tenants with direct access to the
newly constructed southern switch on BNSF’s main line.
¶ 11 In further support of the traverse, Grohne argued BNSF desired to acquire Grohne South
for unstated or speculative future uses. BNSF did not specifically identify these uses in its
conceptual plan. As such, Grohne claimed BNSF attempted to acquire “significantly more”
than the amount of acreage necessary for the planned intermodal facility project.
¶ 12 On July 27, 2015, the trial court held a hearing on the traverse. James Ball, senior manager
of real estate for BNSF, testified about the Board’s plan for the construction of an intermodal
facility. Ball was in charge of acquiring property for the benefit of BNSF. Ball discussed the
purpose and nature of the operations of intermodal facilities in general. Ball also stated that in
October 2014, BNSF made three separate offers for the acquisition of Grohne’s 124 acres.
Grohne rejected each offer.
-3-
¶ 13 John Hovland, director of marketing and facility development for BNSF, testified before
the court. Hovland explained that his responsibilities included siting, developing, and
maintaining intermodal and automotive facilities. Hovland was responsible for determining the
specific land necessary to construct an intermodal facility. In this case, Hovland anticipated
the ultimate size of the proposed intermodal facility would be within the standard size for
constructing intermodal facilities, approximately 460 acres.
¶ 14 Hovland also described the operations and demand for the proposed intermodal facility. In
particular, Hovland discussed how BNSF’s four other intermodal facilities in the area were too
small and had minimal expansion capabilities. The newly proposed intermodal facility would
take three years to construct. BNSF needed the additional intermodal facility due to forecasted
growth in the Chicago area over the next five years. Further, the proposed intermodal facility
could include and/or require support tracks for trains entering and leaving the facility, support
facilities, an administration building, repair facilities for instrumentalities and equipment,
parking areas, an overpass, water retention/detention facilities, grade separations, emergency
facilities, and relocated power lines.
¶ 15 Hovland clarified that the plans were conceptual and would be implemented in phases,
rather than all at once. Since BNSF had not acquired the necessary tracts of land, final planning
and permitting could not be completed. Completion of the plans required additional
engineering, surveying, and geotechnical exploration. The Grohne South and CTT tracts would
potentially become the site of lead outs for the intermodal tracks, parking areas, water
retention/detention facilities, and a grade separation for nearby roads. BNSF would be unable
to construct the proposed intermodal facility without Grohne South and CTT. In Hovland’s
view, the proposed intermodal facility would serve many customers, without discrimination.
¶ 16 Opposing counsel cross-examined Hovland about the proposed spur track directly linking
RidgePort to the main line. Hovland averred that the spur track was necessary to provide rail
service to the industries attracted by RidgePort and to distribute the products of RidgePort’s
customers or tenants. Hovland admitted the spur track was not necessary to the intermodal
facility itself but was essential for the industrial track to be fully functional.
¶ 17 David Irving, a civil engineer and vice president for Trans Systems Corporation, directed
the design of the proposed intermodal facility. Irving testified that the intermodal facility and
spur track were separate projects. He also approximated the spur track would traverse four
acres of Grohne South and CTT. BNSF intended the spur track to serve RidgePort’s customers
with direct access to ship their goods via railway.
¶ 18 Irving agreed that the plans for the intermodal facility were conceptual. However, plans for
the intermodal facility were difficult to conceive without Grohne South, as the project required
8000 feet of clear track. Further, additional tracks, water retention/detention areas, and parking,
among other things, could encumber both tracts. The proposed intermodal facility did not yet
include concrete plans for about 50% to 70% of Grohne South.
¶ 19 James Gordon, director of economic development for BNSF’s northern lines, testified that
BNSF entered a separate letter agreement with RidgePort outlining the parties’ roles in
constructing and paying for a spur track. Gordon explained that BNSF was to take on the task
of using commercially reasonable efforts to acquire the land necessary for the construction of
the spur track to link RidgePort’s customers directly to the main line. RidgePort had begun
advertising the spur track to potential private customers or tenants.
-4-
¶ 20 BNSF planned to construct the spur track in phases. One phase would include going south
and west across CTT and Grohne South to BNSF’s southern switch. Gordon stated BNSF was
constructing the first phase of the spur track, but nothing else was contemplated until the
Grohne tracts were available. He agreed BNSF desired the spur track for the purpose of
providing RidgePort with direct access to the main line. If private customers or tenants were
attracted, as planned, RidgePort, 1200 to 1500 acres in total size, would comprise 300 acres of
rail-serviced property. BNSF had devoted approximately $20 million to the spur track project
at the time of the traverse hearing.
¶ 21 Gordon clarified that as RidgePort attracted more rail-serviced customers across 300 acres,
the spur track would be necessary for BNSF to manage increased traffic from RidgePort on
what is already one of the busiest rail lines in North America. In particular, the spur track
would provide a way for trains to enter and exit the main line from both directions without
causing impediments to or congestion of the main line. The proposed design was the most
effective way for BNSF to ensure this purpose, while also expanding its local operations,
utilizing the acquired property, and serving customers located across RidgePort.
¶ 22 In closing arguments, Grohne argued the takings, namely for the spur track, were for a
private purpose and excessive. Grohne also pointed out that BNSF’s current plan did not
include stated current uses for significant portions of the takings but, rather, mere speculative
future uses. BNSF responded that it would not be serving merely one customer, RidgePort,
with the side or spur track but potentially 300 acres of future rail-serviced customers. As such,
BNSF maintained its takings were for the public, necessary, and not excessive.
¶ 23 On July 31, 2015, the trial court denied Grohne’s traverse and motions to dismiss. The trial
court stated that after reviewing the pleadings, suggestions, and arguments of the parties, it
found that BNSF’s takings were for a necessary, not excessive, public purpose.
¶ 24 The court set the trial for August 22, 2016, less than two years from the date BNSF filed
its complaint for condemnation. In July 2016, Grohne filed a motion to reset the valuation date
for the parcels. The court denied his first motion; it reset the jury trial for May 12, 2017. In
April 2017, Grohne filed a motion to reconsider the court’s denial of his motion for a new
valuation date. The court, again, denied Grohne’s motion. Instead of proceeding to trial in May,
the parties entered into various stipulations regarding, inter alia, the 2014 value of the parcels.
On May 30, 2017, Grohne once again filed a motion for a new valuation date. This time, the
trial court granted Grohne’s motion to reset the valuation date. It set the new values as of July
21, 2017. The court indicated it set a new valuation date to minimize error. It did not reach the
issue of a substantial and material change but did state, “I would probably have found *** that
there would be a substantial, material change.” The court set the date for trial.
¶ 25 On September 27, 2017, Grohne offered to settle with BNSF on CTT. Grohne’s proposed
settlement included a joint stipulation that CTT was worth $3.9 million as of July 21, 2017,
provided BNSF agreed to use the July date as the date of valuation. Additionally, Grohne’s
offer was only good so long as he retained the ability to appeal the trial court’s denial of his
traverse motion. BNSF rejected the offer.
¶ 26 The parties filed a variety of motions in limine. For the purpose of this appeal, our focus is
on BNSF’s motion to bar the use of comparable sales from before October 2014. The court
denied BNSF’s motion.
-5-
¶ 27 On October 16, 2017, the trial commenced. At trial, each party called two appraisers. For
BNSF, Joseph Thouvenell opined that the values of the tracts of land were as follows:
(1) $3,371,680 for Grohne North, (2) $645,315 for Grohne South, and (3) $2,965,800 for CTT.
¶ 28 Prior to Thouvenell’s cross-examination, BNSF argued that the trial court should limit
Grohne’s questioning on an unexercised option to buy additional land, contained within a
comparable land sale contract for a property adjacent to the Grohne tracts and relied upon in
valuing the Grohne tracts. Elion Partners, RidgePort’s predecessor, owned the adjacent
property. Elion sold it to Batory Foods. Grohne argued that the option showed how downward
adjustments in value were calculated for tax increment finance benefits on the adjacent
property.
¶ 29 The trial court barred discussion of the unexercised option provision, acknowledging that
there were two parts to the comparable land sale contract for the adjacent property—an actual
sale and an unexercised option. The court reasoned that questioning on the unexercised option
was far more prejudicial than probative. The trial court found that Grohne could cross-examine
BNSF’s experts on their calculations for the actual sale but did not believe the jury could
consider the value of an option that was, and might remain, unexercised.
¶ 30 Susan Enright, also for BNSF, opined that the values of the tracts of land were as follows:
(1) $3.5 million for Grohne North and (2) $2.5 million for CTT. Enright did not give an opinion
as to the value of Grohne South.
¶ 31 For Grohne, Michael MaRous opined that the values of the tracts of land were as follows:
(1) $6,095,000, plus $225,000 in damages to the remainder for Grohne North, (2) $880,000 for
Grohne South, and (3) $4,210,000 for CTT.
¶ 32 John Mundie, also for Grohne, opined that the values of the tracts of land were as follows:
(1) $6,485,000, plus $100,000 in damages to the remainder for Grohne North, (2) $1,020,000
for Grohne South, and (3) $4.5 million for CTT. Grohne requested the jury award amounts
consistent with the appraisals of MaRous.
¶ 33 On October 20, 2017, the jury awarded the following amounts for the Grohne takings:
(1) $4,927,840, plus $100,000 in damages to the remainder for Grohne North, (2) $862,375.50
for Grohne South, and (3) $4,063,146 for CTT. On October 24, 2017, the trial court entered
judgment orders consistent with the jury’s awards.
¶ 34 Both BNSF and Grohne filed posttrial motions. The trial court denied all posttrial motions.
Grohne filed a notice of appeal. BNSF cross-appealed.
¶ 35 II. ANALYSIS
¶ 36 Grohne raised the following three issues on appeal: (1) whether prohibiting cross-
examination about a comparable land sale contract constituted an abuse of discretion with
respect to Grohne North, (2) whether denying the traverse and motions to dismiss pertaining
to Grohne South and CTT was against the manifest weight of the evidence, and (3) whether
the trial court’s interpretation of section 10-5-110 of the Act (735 ILCS 30/10-5-110 (West
2014)) was erroneous as a matter of law, pertaining to CTT.
¶ 37 BNSF’s cross-appeal raised the following three issues: (1) whether, absent a substantial
and material change, the trial court erred in granting a new valuation date for Grohne South
and CTT and (2) whether the final judgment orders should have been entered based upon the
-6-
parties’ stipulations of value for Grohne South and CTT as of October 20, 2014.
¶ 38 A. Grohne’s Appeal
¶ 39 1. Will County Case No. 14-ED-65 (Grohne North)
¶ 40 On appeal, the only issue Grohne raised with respect to Grohne North was whether the trial
court abused its discretion by limiting the cross-examination of BNSF’s expert witnesses
during the valuation hearing. Grohne argued that the trial court’s decision to limit questioning
about an unexercised option in a comparable land sale contract prejudiced Grohne’s right to
just compensation for Grohne North.
¶ 41 Elion Partners, RidgePort’s predecessor, owned property that was the subject of the
comparable land sale contract. It planned to sell to Batory Foods. Pursuant to the land sale
contract, the parties agreed that Batory Foods could execute an option to purchase additional
land in the future as part of the agreement. Grohne maintained that prohibiting cross-
examination about this unexercised option, and thereby on downward value adjustments used
by the experts, prevented him from painting an accurate picture of the value for the adjacent
tract. Namely, Grohne argued he was not allowed to produce evidence showing how BNSF’s
appraisal expert had adjusted the adjacent tract’s $141,000-per-acre starting value to $62,880.
In Grohne’s view, this questioning would have necessarily caused the jury to consider
downward adjustments, applicable to the adjacent property and award a higher amount per acre
for Grohne North. Barring cross-examination, according to Grohne, misled the jury on how
downward adjustments impacted the expert valuations submitted to the jury for consideration.
¶ 42 The scope of cross-examination rests within the sound discretion of the trial court and will
not be disturbed absent an abuse of that discretion. Leonardi v. Loyola University of Chicago,
168 Ill. 2d 83, 102 (1995). The same is true for the admissibility of evidence showing
comparable land sales. Department of Public Works & Buildings v. First National Bank of
Joliet, 9 Ill. App. 3d 633, 636 (1973). The trial court abuses its discretion when its decision is
arbitrary, fanciful, unreasonable, or where no reasonable person would take the adopted view.
Seymour v. Collins, 2015 IL 118432, ¶ 41.
¶ 43 Purchase options are admissible in some condemnation cases where no recent sales of
similar lands occurred in the vicinity. City of Chicago v. Blanton, 15 Ill. 2d 198, 201-02 (1958).
However, the trial court may properly refuse to admit evidence of an option agreement if there
is evidence of an actual real estate sale. Id. at 202.
¶ 44 Here, we acknowledge the land sale contract between Elion Partners and Batory Foods
included an actual sale, as well as an option to purchase additional land in the future. In other
words, the sale involved two parts to one sales agreement. This distinguishes the transaction
from other cases where an option contract is the only evidence of a comparable land sale.
¶ 45 The trial court’s decision to limit the scope of Grohne’s cross-examination was not without
a sound basis in existing case law. We cannot ignore existing precedent averring that option
agreements, here an unexercised option, are generally inadmissible where there is evidence of
an actual, comparable land sale. See id. at 201-02. We agree with the trial court that such
evidence had the potential to confuse the jurors and was overwhelmingly more prejudicial than
probative. The trial court’s ruling was within its discretion.
-7-
¶ 46 2. Will County Case Nos. 14-ED-66 (Grohne South) and 14-ED-67 (CTT)
¶ 47 Grohne raised two issues with respect to Grohne South and CTT: (a) whether denying the
traverse and motions to dismiss was against the manifest weight of the evidence and (b)
whether the trial court’s interpretation of section 10-5-110 of the Act was erroneous as a matter
of law. 735 ILCS 30/10-5-110 (West 2014).
¶ 48 a. Traverse and Motions to Dismiss
¶ 49 Grohne argued the trial court’s denials of its traverse and motions to dismiss pertaining to
Grohne South and CTT were against the manifest weight of the evidence. See Department of
Transportation ex rel. People v. Hunziker, 342 Ill. App. 3d 588, 593-94 (2003). More
particularly, Grohne maintained the takings of Grohne South and CTT, in part, were for private
and unstated or speculative purposes that were not necessary to fulfill the needs of the public.
BNSF contended that the trial court’s denial of each traverse and motion to dismiss was
supported by the evidence of record.
¶ 50 i. General Legal Principles
¶ 51 A traverse is a method for a landowner, such as Grohne, to challenge an entity’s authority
to take property through the extraordinary power of eminent domain against the landowner’s
wishes. Lake County Forest Preserve District v. First National Bank of Waukegan, 154 Ill.
App. 3d 45, 51 (1987). The appellate court reviews the denial of a traverse against the manifest
weight of the evidence. Enbridge Pipeline (Illinois), LLC v. Temple, 2017 IL App (4th)
150346, ¶ 89. A finding of fact is against the manifest weight of the evidence where an opposite
conclusion is clearly evident. University of Illinois v. Industrial Comm’n, 365 Ill. App. 3d 906,
910 (2006). If the record contains sufficient factual evidence to support the determination, we
will not set it aside on appeal. Beattie v. Industrial Comm’n, 276 Ill. App. 3d 446, 450 (1995).
¶ 52 Section 18c-7501 of the Illinois Vehicle Code (Code) provides railroads with the statutory
authority to exercise the extraordinary power of eminent domain under certain circumstances.
625 ILCS 5/18c-7501 (West 2014). The Code provides the power of eminent domain to any
rail carrier that has been “unable to agree with the owner for the purchase of any real estate
required for the purposes of [the rail carrier’s] incorporation, or the transaction of [the rail
carrier’s] business, *** or any other lawful purpose connected with or necessary to the
building, operating or running of such rail carrier.” Id.
¶ 53 The Code works in conjunction with the Act. See 735 ILCS 30/5-5-5(c)(9) (West 2014).
Specifically, pursuant to the statutory authority conferred by section 18c-7501 of the Code,
section 5-5-5(c)(9) of the Act creates a rebuttable presumption that the acquisition of private
property by a rail carrier’s exercise of the eminent domain authority is (i) primarily for the
benefit, use, or enjoyment of the public and (ii) necessary for a public purpose. Id.
¶ 54 In this case, both parties agree that the interface between the Code and the Act entitled
BNSF to the rebuttable presumption that its decision to act, as embodied in the Board’s 2014
resolution of necessity, was (i) primarily for the benefit, use, or enjoyment of the public and
(ii) necessary for a public purpose. See id.; 625 ILCS 5/18c-7501 (West 2014).
¶ 55 However, the parties disagreed on Grohne’s burden of proof to overcome the statutory
presumption in favor of the railroad. Grohne argued a landowner may overcome the statutory
presumption by showing merely “some evidence.” BNSF claimed a landowner must introduce
-8-
not “some evidence” but “clear and convincing evidence” to overcome this statutory
presumption.
¶ 56 In a similar case of condemnation, the reviewing court held that “a party challenging a
strong presumption must present clear and convincing evidence to rebut the presumption.”
Enbridge Energy (Illinois), L.L.C. v. Kuerth, 2016 IL App (4th) 150519, ¶ 134. This standard
requires proof greater than a preponderance of the evidence but less than proof beyond a
reasonable doubt. Altenheim German Home v. Bank of America, N.A., 376 Ill. App. 3d 26, 37
(2007).
¶ 57 Thus, at the traverse hearing, Grohne was required to show by clear and convincing
evidence that BNSF’s exercise of eminent domain authority was not (i) primarily for the
benefit, use, or enjoyment of the public, or (ii) necessary for a public purpose. Id.
¶ 58 ii. Primary Public Benefit, Use, or Enjoyment.
¶ 59 We first turn to Enbridge Energy (Illinois), L.L.C. v. Kuerth, 2018 IL App (4th) 150519-
B, ¶ 53, which was decided in the context of section 5-5-5(c) of the Act. In that case, the Fourth
District Appellate Court recognized there is no bright-line test for whether the public is the
primary beneficiary of a taking. Id. ¶ 54. Instead, the court observed there are two
considerations relevant to that question. Id. These considerations include (1) the actual motives
behind the taking and (2) whether the taking was an independent and legitimate decision to
further a planned public use. Id. This position, adopted in the context of section 5-5-5(c), is
consistent with past decisions recognizing that the main criterion of a public use is a benefit to
the general public, even when the condemnation would simultaneously be highly beneficial to
other private interests. See Department of Public Works & Buildings v. Farina, 29 Ill. 2d 474,
480 (1963); Limits Industrial R.R. Co. v. American Spiral Pipe Works, 321 Ill. 101, 107-08
(1926).
¶ 60 BNSF executives testified that the proposed intermodal facility was necessary to service
an ever-growing market of customers shipping goods across North America. Hovland averred
the spur track was necessary to provide rail service to the industries attracted by RidgePort
while managing the increased traffic. The facility would serve many customers without
discrimination. Irving estimated that if private customers or tenants were attracted as planned,
RidgePort would comprise 300 acres of rail-serviced property. Gordon explained the spur track
would provide a way for trains to enter and exit the main line from both directions without
causing impediments to or congestion of the main line. He averred this plan was the most
effective way for BNSF to ensure the intermodal facility served its purpose to expand local
operations, fully utilize the acquired property, and efficiently serve RidgePort customers
looking to ship consumer goods across the nation.
¶ 61 Grohne elicited competing testimony from these same executives. Hovland admitted the
side or spur track was not necessary to the intermodal facility itself but was essential for the
industrial track to be fully functional. He said the plans were mostly conceptual as of the date
of the traverse hearing. BNSF could only take so many steps before acquiring the necessary
Grohne tracks. Irving considered the spur track to be its own project. BNSF did not have
specific plans for some of the land.
¶ 62 By enacting section 5-5-5(c), the legislature included language recognizing the acquisition
of private property by eminent domain should be “primarily” for the public benefit, use, or
enjoyment. See 735 ILCS 30/5-5-5(c) (West 2014). In this respect, the Act is consistent with
-9-
prior case law on the nature of a public benefit, use, or enjoyment. Consequently, we hold there
is no express legislative requirement that the property acquired by eminent domain be
exclusively for the benefit, use, or enjoyment of the public. Thus, despite 4 of 71.049 acres
being taken from Grohne for the spur track, we conclude Grohne could not overcome BNSF’s
evidence that the takings of Grohne South and CTT were “primarily” for the public benefit,
use, or enjoyment of an intermodal facility. Common sense dictates that the spur track would
benefit not only the industries in the industrial park but also their many customers throughout
the country. The trial court’s finding in this regard was not against the manifest weight of the
evidence.
¶ 63 iii. Necessary for a Public Purpose
¶ 64 Next, we turn to whether Grohne provided clear and convincing evidence that the taking
of Grohne South and CTT was not necessary for a public purpose or excessive.
¶ 65 Initially, we address Grohne’s argument pursuant to People ex rel. Director of Finance v.
Young Women’s Christian Ass’n of Springfield, 86 Ill. 2d 219, 239 (1981) (YWCA of
Springfield), that the takings here are “grossly excessive” due to significant portions having no
stated, present public purpose. In our view, YWCA of Springfield is unpersuasive, as this is not
a case where “over half of the total area sought [is] being taken without any showing of need,
present or future.” (Emphases added.) Id. Rather, BNSF was able to account for needs that
could be “fairly anticipated in the future.” (Internal quotation marks omitted.) Id.
¶ 66 In this case, the testimony at the traverse hearing indicated BNSF sought to acquire an
amount of land that was within the standard size for intermodal facilities and the specific uses
and encumbrances of Grohne South and CTT that would make the intermodal facility
operational. In particular, the testimony of Hovland and Irving indicated BNSF could fairly
anticipate using Grohne South and CTT for, among other things, support tracks, parking areas,
water retention/detention facilities, and a grade separation of the intermodal facility from
nearby Murphy and Lorenzo Roads. As a result, Grohne’s argument under YWCA of
Springfield is unavailing.
¶ 67 In the past, our supreme court stated, “ ‘where the legislature has delegated to a corporation
the authority to exercise the power of eminent domain, the corporation has also the authority
to decide on the necessity for exercising the right, and its decision will be conclusive in the
absence of a clear abuse of the power granted.’ ” City of Chicago v. Midland Smelting Co., 385
Ill. App. 3d 945, 965 (2008) (quoting City of Chicago v. Vaccarro, 408 Ill. 587, 597 (1951));
see also Goldman v. Moore, 35 Ill. 2d 450, 453 (1966).
¶ 68 Grohne contends BNSF’s decision to acquire and then use a portion of his land for private
profit constitutes such a “clear abuse” of power. In order to resolve this issue, we turn to the
language of the resolution passed by the Board in September 2014. The Board’s resolution
states the proposed takings are necessary in order “to provide access to the facility from both
ends to facilitate safe and expeditious operation of the main line.” (Emphasis added.) Similarly,
the complaints filed by BNSF one month later consistently allege that the land to be taken by
the railroad was “needed for the construction of a multimodal facility” that would consist of
“multiple tracks and related connections, to allow trains to be taken off the main line, and
broken down, for further handling by Plaintiff.”
¶ 69 Necessary, as used in a statute, should mean “expedient, reasonably convenient or useful
to the public, and cannot be limited to an absolute physical necessity.” (Internal quotation
- 10 -
marks omitted.) Department of Public Works & Buildings v. Lewis, 411 Ill. 242, 245-46 (1952).
The proper judicial inquiry into necessity is whether “the purpose for which the land is sought
is one of public convenience, and the acquisition, reasonable in scope, is an expedient means
of accomplishing the purpose.” Department of Transportation v. Keller, 127 Ill. App. 3d 976,
980 (1984).
¶ 70 As discussed above, great deference is afforded to the legislature’s grant of the eminent
domain authority. In this case, the spur track allows RidgePort’s many customers access to a
rail line without interfering with the normal flow of BNSF’s traffic. The big picture
consequence of the spur track is that more businesses will be able to ship more goods across
North America with limited stops and congestion at this location. The spur track is “expedient,
reasonably convenient, [and] useful to the public” in that it serves a purpose of “public
convenience, and the acquisition, reasonable in scope, is an expedient means of accomplishing
the purpose.” (Internal quotation marks omitted.) Id. More businesses shipping more goods is
a net benefit to the flow of commerce and those engaged in its practices. Grohne did not present
clear and convincing evidence to rebut the presumption that BNSF’s takings were necessary
for a public purpose or not excessive. Thus the trial court’s denial of Grohne’s traverse and
motions to dismiss was not against the manifest weight of the evidence.
¶ 71 b. Attorney Fees
¶ 72 Grohne argued the trial court erred in its interpretation of section 10-5-110(b) of the Act
(735 ILCS 30/10-5-110(b) (West 2014)). This misinterpretation prevented Grohne from
recovering his attorney fees with regard to CTT. The statute, titled “[o]ffers of settlement by
defendant; attorney’s fees and litigation expenses” states:
“At any time between (i) the close of discovery in accordance with Supreme Court Rule
218(c), as now or hereafter amended, or another date set by the court or agreed to by
the parties, and (ii) 14 days before the commencement of trial to determine final just
compensation, any defendant may serve upon the plaintiff a written offer setting forth
the amount of compensation that the defendant will accept for the taking of that
defendant’s interest in the property. If the defendant does not make such an offer, the
defendant shall not be entitled to the attorney’s fees ***.” Id.
Grohne made an offer to BNSF for the CTT property. He argues he thereby qualified under
the statute; the trial court should have awarded him the properly attributed attorney fees.
¶ 73 Our interpretation of a fee-shifting statute is an exercise of statutory construction. Forest
Preserve District v. Continental Community Bank & Trust Co., 2017 IL App (1st) 170680,
¶ 31. We give the language of the statute its plain and ordinary meaning. Southern Illinoisan
v. Department of Public Health, 218 Ill. 2d 390, 415 (2006). We strive to give each word a
meaning; words should not be rendered superfluous. Williams v. Staples, 208 Ill. 2d 480, 487
(2004). The court may consider the purpose of the law in construing a statute. Id. Whether the
court has the authority to grant attorney fees under a particular statute is a question of law we
review de novo. Continental Community Bank & Trust Co., 2017 IL App (1st) 170680, ¶ 32.
We review the ultimate decision of whether to award attorney fees for an abuse of discretion.
Id.
¶ 74 The statute on which Grohne relied required him to make an offer of compensation that he
would accept for “the taking of [his] interest in the property.” (Emphasis added.) 735 ILCS
30/10-5-110(b) (West 2014). Grohne, as the owner, had an ownership interest in CTT. The
- 11 -
Property Tax Code defines ownership interest as “any title or other interest in property.” 35
ILCS 200/21-285(1) (West 2014). Grohne, in his proposed settlement to BNSF, refused to
settle if he could not appeal the trial court’s denial of his traverse. In order to have standing to
challenge the trial court’s denial, Grohne would have to retain an interest in CTT. He cannot
be said to have offered to relinquish his interest in property if he simultaneously wanted to
maintain the right to proceed with further legal action.
¶ 75 Grohne stated in his brief that he “wanted to preserve his ability to contest [BNSF’s] right
to take the property.” A plain reading of the statute indicates a defendant can recoup his
attorney fees only if he (1) made an offer and (2) was willing to relinquish his interest in the
property. Grohne was not willing to cede his interest in CTT to BNSF. Grohne did not qualify
under this statute. The trial court did not err in its interpretation of the statute. The court did
not abuse its discretion by failing to award Grohne his attorney fees attributable to CTT.
¶ 76 B. BNSF Cross-Appeal
¶ 77 1. Whether the Trial Court Erred in Granting a New Valuation Date
¶ 78 BNSF cross-appeals, contending the land’s value did not substantially and materially
change. Absent such a change, the trial court erred in granting a new valuation date. We review
a lower court’s decision to grant a new valuation date for an abuse of discretion. In re D.T.,
212 Ill. 2d 347, 356 (2004) (holding the abuse of discretion standard applies to a trial judge’s
decision regarding the progress of a trial). The question here is not whether the reviewing court
agrees with the trial court’s action but whether the trial court “acted unreasonably and ignored
recognized principles of law, which resulted in substantial prejudice.” Petryshyn v. Slotky, 387
Ill. App. 3d 1112, 1116 (2008). We can affirm for any reason apparent in the record. City of
Champaign v. Torres, 214 Ill. 2d 234, 241 (2005).
¶ 79 Forest Preserve District v. First National Bank of Franklin Park, 2011 IL 110759 (Forest
Preserve II), is instructive here. In Forest Preserve II, the Illinois Supreme Court adopted
Kirby Forest Industries, Inc. v. United States, 467 U.S. 1 (1984), holding that “a taking in
Illinois for the purposes of applying Kirby occurs on the date that the government (1) deposits
the amount of compensation that has been ascertained and awarded, and (2) acquires title and
the right to possess the property.” (Emphasis in original.) Forest Preserve II, 2011 IL 110759,
¶ 40.
¶ 80 In 1999, the preserve filed a condemnation action to acquire a public golf course. Id. ¶ 5.
The landowners filed a traverse and motion to dismiss the condemnation action. Id. ¶ 8. The
case did not proceed to trial until 2007. Id. ¶ 12. The Act, on which BNSF relies in the case
sub judice, provided the valuation of the condemned property is to be “determined as of the
date of filing the complaint to condemn.” 735 ILCS 30/10-5-60 (West 2014). However, the
legislature had recently amended the Act to allow a circuit judge to revise a valuation date in
the interests of equity and justice. See id. (“[I]f the trial commences more than 2 years after
the date of filing the complaint to condemn, the court may, in the interest of justice and equity,
declare a valuation date no sooner than the date of filing the complaint to condemn and no later
than the date of commencement of the trial ***.”).
¶ 81 The jury valued the property based on the 1999 valuation. Forest Preserve II, 2011 IL
110759, ¶ 13. The landowners complained that an increase in value had occurred by 2007. Id.
The landowners obtained no relief in the trial court and appealed. Id. ¶¶ 13-14. The Illinois
Supreme Court applied Kirby to the facts of the case. Id. ¶ 39. It agreed with the appellate court
- 12 -
that the jury’s verdict should be vacated and the cause should be remanded to the circuit court
for a determination as to whether the jury awards provided substantially less than the market
value of the property at the time of the taking. Id. ¶ 70. Our supreme court did not make a
finding that the value of the land had substantially and materially increased because, as the
appellate court noted, “the plaintiff has not had the opportunity to proffer contrary evidence of
the [p]roperty’s value as of the time of trial, and the trial court has not weighed any such
evidence.” Forest Preserve District v. First National Bank of Franklin Park, 401 Ill. App. 3d
966, 991 (2010) (Forest Preserve I). The appellate court noted, “defendants [are] entitled to
receive just compensation for the [p]roperty, i.e., its fair market value at the time of the taking.”
Id. at 990.
¶ 82 The court, in the case sub judice, reset the valuation date for the takings. The procedural
history here is distinct from Forest Preserve I and II, where the trial court did not hear
arguments from both sides as to a change in value. Here, the court had the opportunity to hear
from both sides and consider the arguments and evidence before deciding whether the change
in value warranted a new valuation date. This difference is important as it is the exact reason
that the reviewing courts in Forest Preserve I and II could not conclude whether the defendants
received just compensation.
¶ 83 BNSF argues the trial court was inconsistent in its findings and therefore abused its
discretion. BNSF cites no case law to support this position. The court denied BNSF’s motion
in limine to bar the introduction of four sales that occurred prior to October 2014. Grohne, as
the proponent of the sale, was required to show that no substantial change in conditions or
fluctuations in value occurred between the comparable sale and the court’s valuation date.
Department of Transportation v. Prombo, 63 Ill. App. 3d 407, 412-13 (1978). BNSF contends
implicit in the court’s denial of its motion is a finding that there no was no substantial change
between the comparable sales and the valuation date. This is at odds with the court’s earlier
ruling granting a new valuation date. However, BNSF does not appeal the trial court’s denial
of its motion in limine.
¶ 84 We afford considerable deference to the trial court’s decision to set a new valuation date.
We may also affirm for any reason apparent on the record. The value of Grohne North
increased by 39% and the values of Grohne South and CTT increased by 25% each. Grohne
was entitled to just compensation valued on the day of the taking. The properties’ values
increased markedly between the date BNSF filed its action for condemnation and the date of
the taking. The court did not abuse its discretion in granting a new valuation date.
¶ 85 2. Jury Verdicts
¶ 86 Finally, BNSF asks this court to vacate and reverse the final judgment orders with
instructions for the trial court to substitute the jury awards for the stipulated October 2014
values. We will not vacate a jury verdict unless the verdict is contrary to the manifest weight
of the evidence. Stanford v. City of Flora, 2018 IL App (5th) 160115, ¶ 32. A verdict is against
the manifest weight of the evidence when, after viewing the evidence in the light most
favorable to the determination, we conclude that no rational trier of fact could have made the
same finding. Briggs v. State, 323 Ill. App. 3d 612, 618 (2001).
¶ 87 At trial, each party called two appraisers to testify. The jury rendered verdicts at a value
higher than to what BNSF appraisers testified and lower than Grohne’s appraisers’ estimates.
The verdicts bear a reasonable relationship to the evidence presented at trial. See City of Flora,
- 13 -
2018 IL App (5th) 160115, ¶ 32. The jury verdicts were not against the manifest weight of the
evidence.
¶ 88 III. CONCLUSION
¶ 89 For the foregoing reasons, we affirm the judgment of the circuit court of Will County.
¶ 90 Affirmed.
¶ 91 JUSTICE WRIGHT, concurring in part and dissenting in part:
¶ 92 I write separately because I believe the majority’s holding creates a dangerous precedent
and relegates Grohne’s property rights to an inferior position in relation to BNSF and
RidgePort’s private economic interests. In particular, the majority’s holding is contrary to the
legislative intent of the Act. This decision creates a template for other private industries to
surreptitiously acquire land, against a landowner’s wishes, for private purposes. For this
reason, I dissent from a decision that ignores BNSF’s subterfuge and fails to employ a strict
construction of the Act.
¶ 93 As will be discussed in detail below, I agree Grohne failed to show the takings of Grohne
South and CTT were not primarily for the public benefit. However, unlike the majority, I am
convinced that Grohne rebutted the presumption of necessity and revealed BNSF’s taking was
excessive.
¶ 94 For the sake of simplicity, I will address each issue in the same order and with the same
headings as the majority opinion.
¶ 95 II. ANALYSIS
¶ 96 A. Grohne’s Appeal
¶ 97 1. Will County Case No. 14-ED-65 (Grohne North)
¶ 98 I concur with my esteemed colleagues in the majority that the trial court’s decision to limit
the scope of Grohne’s cross-examination was not an abuse of discretion.
¶ 99 2. Will County Case Nos. 14-ED-66 (Grohne South) and 14-ED-67 (CTT)
¶ 100 a. Traverse and Motions to Dismiss
¶ 101 i. General Legal Principles
¶ 102 Certainly, I agree that BNSF is entitled to the rebuttable presumption contained in section
5-5-5(c)(9). See 735 ILCS 30/5-5-5(c)(9) (West 2014). Thus, under the Act, it is presumed that
BNSF has the limited, statutory authority to condemn private property if the taking is primarily
for the public benefit, use, or enjoyment and necessary to the primarily public purpose. Id.
However, unlike the majority, I am unconvinced Grohne’s burden of proof, needed to rebut
the statutory presumption, is the clear and convincing standard, rather than something less.
Regardless, this disagreement regarding the correct burden of proof is inconsequential to my
dissent. By either standard, I am convinced Grohne rebutted the presumption’s necessity prong.
- 14 -
¶ 103 ii. Primary Public Benefit, Use, or Enjoyment
¶ 104 I agree with the majority’s analysis and conclusion that Grohne failed to show the takings
of Grohne South and CTT were not primarily for the public benefit, use, or enjoyment of
constructing and operating an intermodal facility.
¶ 105 iii. Necessary for a Public Purpose
¶ 106 Contrary to the majority’s position, I would hold that Grohne successfully rebutted the
presumption of necessity contained in section 5-5-5(c)(9). Grohne’s evidence establishes that
4 out of the 71.049 acres taken from Grohne South and CTT were not presently necessary for
the intermodal facility at the time of this taking. I observe that the four-acre strip taken from
Grohne would be immediately put to use by BNSF to complete the spur track. However, it
might take much more time before the remaining acreage is used for the intermodal facility.
BNSF had a present need to acquire these four acres as promised in the letter agreement. The
record makes it clear to me that BNSF’s only present need was to fulfill a promise to finish the
spur track.
¶ 107 For purposes of this appeal, using a backwards analysis, BNSF urges our court to recognize
that the completed spur track was currently necessary to relieve some hypothetical future
congestion on the main line. Yet, at the time of this taking, the industrial park had only a
handful of tenants and there was no congestion on the main line. A taking is not “necessary”
as required by the Act, when the purported need is based solely on speculation. I conclude that
this taking of four acres was needed to finish the spur track but was not necessary to complete
the intermodal facility.
¶ 108 In support of my view, I point to the testimony presented at the traverse hearing. During
the hearing, Hovland, Irving, and Gordon testified that the private spur track project was
presently unnecessary for, separate from, and/or unrelated to the plans for the intermodal
facility project. Further, Gordon made it clear that the private letter agreement, which outlined
BNSF and RidgePort’s roles in acquiring the land and paying for the private spur track, was in
place before the traverse hearing was held. 2 Most tellingly, before BNSF knew whether it
could condemn Grohne’s property, RidgePort began advertising the existence of a private spur
track that would link RidgePort’s prospective customers or tenants to BNSF’s main line.
¶ 109 Gordon carefully explained to the trial court that the private spur track was to be
constructed in phases, and the construction of certain phases of the private spur track would
not be finalized until Grohne South and CTT were titled to BNSF. I cannot ignore that before
the traverse hearing took place for the intermodal facility project, BNSF had already devoted
$20 million to the private spur track project. It makes little sense for BNSF to claim the private
spur track project was necessary to the intermodal facility project, when the private spur track
project was leaps and bounds ahead of the intermodal facility project. To me, these facts
indicate the private spur track was moving full steam ahead and was the driving force behind
this taking rather than the intermodal facility. I suggest that even if BNSF abandoned the plan
for the intermodal facility, the spur track project would not be cast aside by BNSF for any
reason.
2
The record does not include a copy of the letter agreement. However, the testimony of Gordon
seems to indicate the letter agreement had a date of December 11, 2014, which was after the resolution
of necessity was approved and before the traverse hearing was held.
- 15 -
¶ 110 Unlike the majority, I conclude Grohne presented credible, compelling, and unrefuted
evidence from the BNSF executives that BNSF always had two separate plans for Grohne’s
land. I agree one plan would primarily benefit the public. However, the public benefit from an
intermodal facility was not the primary reason BNSF chose this location for the new facility. I
contend that the second plan, completing the spur track, was the reason BNSF selected this
location for the intermodal facility. This second plan to complete the private spur track linking
RidgePort to BNSF’s main line was the primary reason BNSF picked this location. At the time
the resolution was enacted, the second plan would solely advance the mutual, private economic
interests of BNSF and RidgePort.
¶ 111 Having concluded Grohne rebutted the present necessity prong of the presumption
contained in section 5-5-5(c)(9), I now consider an additional step under the Act that was not
necessary for my friends in the majority to address. See id. In particular, I consider what steps
remain available to BNSF with respect to this four-acre strip, within the lawful parameters of
the Act.
¶ 112 In my view, once Grohne rebutted the statutory presumption, the burden shifted to BNSF
under the Act’s “default provision.” See id. § 5-5-5(c). BNSF was now required to show by
clear and convincing evidence that its acquisition of property would be primarily for the
benefit, use, or enjoyment of the public and necessary to the public purpose of constructing
and operating an intermodal facility. Id. In other words, BNSF was required to start anew under
the Act and make a showing of what is required when a party is not initially entitled to the
same rebuttable presumption afforded to BNSF. Id.
¶ 113 Before embarking on this analysis, I will briefly discuss the history of the Act. In response
to Kelo v. City of New London, 545 U.S. 469 (2005), our General Assembly reconsidered the
concept of public takings, “particularly in the context of takings from private landowners to
other private individuals or groups.” 94th Ill. Gen. Assem., House Proceedings, Apr. 19, 2006,
at 12 (statements of Representative Bradley). The result of our legislature’s efforts was the
consolidation of all eminent domain or condemnation proceedings into one statute, the Act,
which goes beyond the context of public takings and instead “deals with all aspects of eminent
domain.” Id. In particular, during the House of Representatives proceeding, it was stated that
the Act intended to deliver two “substantial wins” for private landowners in Illinois. Id. at 13.
¶ 114 First, section 5-5-5(c), the Act’s “default provision,” assigned the clear and convincing
evidentiary standard to a “condemning authority *** want[ing] to condemn property *** when
none of the exceptions applies.” (Emphasis added.) Id.; see 735 ILCS 30/5-5-5(c) (West 2014).
As stated above, I believe this provision applies because Grohne rebutted the statutory
presumption found in section 5-5-5(c)(9). Second, the legislature “shifted the burden of proof
to the condemning authorities.” 94th Ill. Gen. Assem., House Proceedings, Apr. 19, 2006, at
13 (statements of Representative Bradley); see 735 ILCS 30/5-5-5(c) (West 2014). I contend
the majority misreads the Act and misunderstands the protections it was meant to afford
landowners.
¶ 115 The “substantial wins” resulting from the Act staunchly protected landowners from
unlawful takings in all eminent domain contexts. The House of Representatives sponsor,
Representative John E. Bradley, specifically asked his colleagues for an “ ‘aye’ vote” to “swing
the pendulum back in favor of the private individual landowner.” 94th Ill. Gen. Assem., House
Proceedings, Apr. 19, 2006, at 13-14 (statements of Representative Bradley). As a clear sign
of this effort, our legislature explicitly directed that “[t]his Act shall be strictly construed as a
- 16 -
limitation on the exercise of eminent domain powers.” 735 ILCS 30/90-5-15 (West 2014).
Moreover, our legislature stated section 5-5-5 was a limitation on eminent domain powers but
“not an independent grant of authority” to exercise those powers. Id. § 5-5-5(g). Thus, public
and private condemning authorities must still satisfy section 5-5-5’s procedural safeguards and
requirements.
¶ 116 As a result of the clear legislative intent and directives, I conclude this court must reverse
the denial of Grohne’s traverse and motions to dismiss because BNSF did not meet the clear
and convincing standard found in the Act’s “default provision.” See id. § 5-5-5(c). Specifically,
I disagree that BNSF demonstrated the acquisition of the entire parcel of 71.049 acres from
Grohne South and CTT was necessary and not excessive for purposes of the intermodal facility.
It should be recognized that this is not a traditional case of excessiveness, where we simply do
the math to assess whether the taking is “grossly in excess” of what would be necessary to
accomplish the condemning authority’s stated public purpose. Vaccarro, 408 Ill. at 597.
Instead, this is a case where it has been made clear that a present and nonspeculative necessity
does not exist for the private spur track project, particularly where the resolution of necessity
does not make a specific reference to the partially completed private spur track.
¶ 117 It is true, as the majority states, “where the legislature has delegated to a corporation the
authority to exercise the power of eminent domain, the corporation has also the authority to
decide on the necessity for exercising the right, and its decision will be conclusive in the
absence of a clear abuse of the power granted.” (Internal quotation marks omitted.) City of
Chicago v. Midland Smelting Co., 385 Ill. App. 3d 945, 965 (2008); see also Goldman, 35 Ill.
2d at 453; Vaccarro, 408 Ill. at 597 (abuses of the eminent domain authority “will not be
tolerated, and if no necessity for its exercise exists, or if it appears that the quantity of the
property sought to be taken is grossly in excess of the amount necessary for the public use, the
court will not permit the land to be taken”).
¶ 118 I would hold, under the Act’s necessity prong, this case documents a “clear abuse of the
power granted” to BNSF. (Internal quotation marks omitted.) Midland Smelting Co., 385 Ill.
App. 3d at 965. Contrary to the clear instructions from our lawmakers that the Act must be
“strictly construed,” the private spur track project has been allowed to leach onto what is
otherwise a primarily public and necessary intermodal facility project to increase BNSF’s
taking while serving two purposes. BNSF has misused the Act by camouflaging the four
excessive acres, now taken from an unwilling landowner, by packaging those acres onto the
same footprint of the intermodal facility that was still being planned on the back of a napkin.
¶ 119 In my opinion, we should not turn a blind judicial eye to BNSF’s “end around” approach
to the Act. In the absence of the four additional acres, I would have no difficulty deferring to
the legislature’s grant of the eminent domain authority to BNSF for its nonspeculative, future
anticipated uses of Grohne South and CTT. See id. However, due to the absence of a clearly
definable present and nonspeculative purpose for the private spur track set out in the resolution
of necessity, I do not believe any deference to BNSF is appropriate pursuant to the Act.
¶ 120 Here, the Board’s resolution of necessity for the intermodal facility project clearly defines
the reason for the proposed taking was “to provide access to the [intermodal] facility from
both ends to facilitate safe and expeditious operation of the main line.” (Emphasis added.)
Similarly, the intermodal facility would “allow trains to be taken off the main line, and broken
down, for further handling by BNSF.” Yet, the private spur track was not expressly referenced
in the resolution of necessity and does not provide access to the intermodal facility at all.
- 17 -
Similarly, the unmentioned private spur track will not be used to allow trains to be taken off
the main line and “broken down for further handling by BNSF.”
¶ 121 Thus, I would hold deference to BNSF is not warranted in this case, where this plan is
primarily for the public but was merged with a plan that selfishly serves private interests alone.
This constitutes misuse of the Act. The majority creates a dangerous precedent that paves the
way for private condemning entities to successfully and creatively evade legislative
limitations. Indeed, deferring to a section 5-5-5(c) entity, such as BNSF, under the
circumstances here, constitutes a relinquishment of a judicial task of ensuring the Act is
“strictly construed” to limit the eminent domain powers of private entities. See 735 ILCS
30/90-5-15 (West 2014). In my opinion, the unnecessary private spur track cannot bootstrap
itself to the necessary intermodal facility project. The two plans are presently unnecessary,
separate from, and unrelated to each other. The temptation of section 5-5-5(c) entities to resort
to similar future tactics must be renounced before momentum is gained in practice.
¶ 122 My position is also not without a sound basis in the case law preceding the Act. In the past,
railroad companies were prohibited from condemning private property to construct a spur track
connecting particular industries to a railroad’s main line, when such action would be solely for
the private but mutual benefit of the industrial customers of the railroad and the railroad
company itself. Limits Industrial R.R. Co., 321 Ill. at 107. In fact, “[i]t has been held a number
of times that the right of eminent domain cannot be exercised for the purpose of acquiring land
for a private switch from an industry to the main line of a railroad.” People ex rel. Tuohy v.
City of Chicago, 394 Ill. 477, 482 (1946).
¶ 123 As an aside, I note that the trial court astutely questioned whether a court may reduce or
change the boundaries of the tracts BNSF hoped to acquire in order to eliminate any misuse of
the eminent domain authority. Logically, decreasing the boundaries of the proposed taking by
four acres might cure the abuse of that power. However, this court, like the trial court,
questioned the parties on this possibility and received the agreed response that the case law
supports an all-or-nothing approach. Since I conclude BNSF should have requested four acres
less, the all-or-nothing approach results in BNSF taking nothing from Grohne.
¶ 124 For the foregoing reasons, I respectfully dissent from the majority’s application of the
rebuttable presumption to the facts in this case. I would hold that Grohne rebutted the
presumption of necessity and BNSF failed to meet theirs.
¶ 125 I would also hold that unlawfully expanded takings, of the sort presented in this case,
should be viewed as both excessive and unnecessary no matter how small in size the expansion
is when compared to the totality of land properly taken. I would reverse the trial court’s order
denying Grohne’s traverse and motions to dismiss due to BNSF’s clear abuse of the authority
granted under section 5-5-5(c).
¶ 126 While my holding would be limited to this case, I am unaware of any scenario where the
separate and unrelated projects of a section 5-5-5(c) entity, one which is legitimately for the
public and the other which is not necessary to any present or nonspeculative public purpose, is
anything other than excessive. My reversal of the court’s ruling on the traverse and motion to
dismiss would render Grohne’s remaining issues, and BNSF’s cross-appeal, moot.
- 18 -