IN THE COMMONWEALTH COURT OF PENNSYLVANIA
TOA Green Pond Advisors, LLC :
t/a TOA Green Pond, L.P., :
Appellant :
:
v. : No. 261 C.D. 2020
: ARGUED: December 8, 2020
Bethlehem Township and The :
Pidcock Company :
BEFORE: HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE ELLEN CEISLER, Judge
OPINION NOT REPORTED
MEMORANDUM OPINION
BY JUDGE CEISLER FILED: January 5, 2021
TOA Green Pond Advisors, LLC, t/a TOA Green Pond, L.P. (TOA), appeals
from the February 25, 2020 Order of the Court of Common Pleas of Northampton
County (Trial Court), which sustained the Preliminary Objections filed by
Bethlehem Township (Township) and The Pidcock Company (Pidcock)1 to TOA’s
Amended Complaint in Mandamus (Amended Complaint) and dismissed the
Amended Complaint. In its Amended Complaint, TOA sought a writ of mandamus
to compel the Township to replace Pidcock with the Township’s back-up engineer,
Arro Consulting, Inc. (Arro), to oversee TOA’s construction of a residential
development in the Township. Because we conclude that TOA has not established
a clear legal right to mandamus relief, we affirm the Trial Court’s Order.
1
On January 7, 2020, the Trial Court permitted Pidcock to intervene in this action over
TOA’s objection.
Background
TOA owns a 236-acre parcel of land in the Township, which includes a public
golf course (Property). TOA received approval from the Township to develop a
planned residential golf course community on the Property consisting of 229 age-
restricted units (Project). Due to the Project’s size, the Township required TOA to
post a $13,039,928 bond to secure the construction of improvements on the Property.
On January 2, 2018, the Township’s Board of Commissioners enacted
Resolution R0005-18, appointing Pidcock to serve as the Township’s engineer for a
two-year term. On the same date, the Board of Commissioners also enacted
Resolution R0006-18, appointing Arro to serve as the Township’s back-up engineer.
As the back-up engineer, Arro would provide professional consulting services if the
Township determined that the use of Pidcock’s services would create a conflict of
interest, since Pidcock performed consulting services for both municipal and private
clients. At a public meeting on January 7, 2019, the Board of Commissioners
approved both Pidcock’s and Arro’s fee schedules.
Section 503(1) of the Pennsylvania Municipalities Planning Code (MPC), Act
of July 31, 1968, P.L. 805, as amended, 53 P.S. § 10503(1), permits the Township
to charge developers “reasonable and necessary” fees for its professional
consultants, including the Township engineer, to review proposed land development
plans. Section 503(1) of the MPC states in relevant part:
Review fees may include reasonable and necessary charges by the
municipality’s professional consultants for review and report[ing]
thereon to the municipality. Such review fees shall be based upon a
schedule established by ordinance or resolution. Such review fees shall
be reasonable and in accordance with the ordinary and customary
charges for similar service in the community, but in no event shall the
fees exceed the rate or cost charged by the professional consultant for
2
comparable services to the municipality for services which are not
reimbursed or otherwise imposed on applicants.
53 P.S. § 10503(1) (emphasis added). Section 503(1)(i)-(ii) of the MPC also
addresses the procedure to be followed when a developer wishes to challenge a
professional consultant’s fees:
(i) . . . In the event the applicant disputes the amount of any such review
fees, the applicant shall, no later than 100 days after the date of
transmittal of the bill to the applicant, notify the municipality and the
municipality’s professional consultant that such fees are disputed and
shall explain the basis of their objections to the fees charged, in which
case the municipality shall not delay or disapprove a subdivision or
land development application due to the applicant’s dispute over fees.
Failure of the applicant to dispute a bill within 100 days shall be a
waiver of the applicant’s right to arbitration of that bill under [S]ection
510(g) [of the MPC, 53 P.S. § 10510(g)].
(ii) In the event that the municipality’s professional consultant and the
applicant cannot agree on the amount of review fees which are
reasonable and necessary, then the applicant and the municipality shall
follow the procedure for dispute resolution set forth in [S]ection 510(g)
[of the MPC], provided that the arbitrator resolving such dispute shall
be of the same profession or discipline as the professional consultant
whose fees are being disputed.
53 P.S. § 10503(1)(i)-(ii) (emphasis added).
Section 510(g)(2)-(4) of the MPC outlines the procedure for resolution of a
fee dispute as follows:
(2) If the professional consultant and the applicant cannot agree on
the amount of expenses which are reasonable and necessary, then the
applicant shall have the right, within 100 days of the transmittal of the
final bill or supplement to the final bill to the applicant, to request the
appointment of another professional consultant to serve as an
arbitrator. The applicant and professional consultant whose fees are
being challenged shall, by mutual agreement, appoint another
professional consultant to review any bills the applicant has disputed
3
and which remain unresolved and make a determination as to the
amount thereof which is reasonable and necessary. The arbitrator
shall be of the same profession as the professional consultant whose
fees are being challenged.
(3) The arbitrator so appointed shall hear such evidence and review
such documentation as the arbitrator in his or her sole opinion deems
necessary and shall render a decision no later than 50 days after the date
of appointment. Based on the decision of the arbitrator, the applicant
or the professional consultant whose fees were challenged shall be
required to pay any amounts necessary to implement the decision
within 60 days. In the event the municipality has paid the professional
consultant an amount in excess of the amount determined to be
reasonable and necessary, the professional consultant shall within 60
days reimburse the excess payment.
(4) In the event that the municipality’s professional consultant and
applicant cannot agree upon the arbitrator to be appointed within 20
days of the request for appointment of an arbitrator, then, upon
application of either party, the President Judge of the Court of Common
Pleas of the judicial district in which the municipality is located (or if
at the time there [is] no President Judge, then the senior active judge
then sitting) shall appoint such arbitrator, who, in that case, shall be
neither the municipality’s professional consultant nor any professional
consultant who has been retained by, or performed services for, the
municipality or the applicant within the preceding five years.
53 P.S. § 10510(g)(2)-(4) (emphasis added).
On August 21, 2019, TOA submitted a formal challenge (First Challenge) to
Pidcock’s fees for services performed between March 24, 2019 and June 25, 2019.
On August 27, 2019, TOA submitted a formal challenge (Second Challenge) to
Pidcock’s fees for services performed between June 23, 2019 and July 20, 2019. The
First and Second Challenges questioned the reasonableness of the amounts charged
for Pidcock’s services, as well as Pidcock’s billing practices and the manner in which
4
Pidcock performed its engineering services in connection with the Project.
Specifically, TOA raised the following objections to Pidcock’s fees and practices:
(a) charges for professional(s) preparing for meeting(s) that were not
attended;
(b) bills for more than 200 hours of services provided in connection
with a single[-]page email containing eight comments;
(c) bills for more than 35 hours of service to prepare that single[-]page
email containing 8 comments;
(d) failure to comply with the MPC regarding security estimates for the
public improvements of the [Project];
(e) bills for more than 70 hours of services to review and modify the
security estimates for the public improvements of the [Project];
(f) bills for more than 30 hours of services to review stormwater plans
notwithstanding that [TOA] had already obtained an NPDES permit
from DEP in connection therewith;
(g) bills for over 30 hours of services for the review of the handicap
accessibility of the [Project] and the handicap ramps, which review
resulted in a comment letter consisting of 2 sentences;
(h) having 19 different professionals involved in the review of the
design documents;
(i) bills for 100 hours in connection with internal meetings;
(j) bills for more than 14 hours of services to review an “assignment
letter”;
(k) using multiple professionals to perform the same tasks;
(l) inconsistencies in the billing records for Pidcock and the Township
solicitor for calls between them;
5
(m) the reasonableness of Pidcock’s billing increments;
(n) the reasonableness and necessity of the number of professionals
involved in the review of the design document for the [Project];
(o) the reasonableness and necessity of the amount of time spent on
many tasks; and
(p) the manner in which billing was completed.
Am. Compl. ¶ 25(a)-(p).
By letter dated September 4, 2019, TOA requested that the Township remove
Pidcock from the Project and appoint the back-up engineer, Arro, to oversee the
Project. The Township declined to do so.
On October 29, 2019, TOA submitted another challenge (Third Challenge)
contesting the reasonableness of Pidcock’s fees for services performed between July
21, 2019 and August 24, 2019.
On November 13, 2019, TOA filed in the Trial Court a “Petition to Appoint
Mediator Pursuant to 53 P.S. § 10510(g)(4)” (Petition to Appoint), requesting that
the President Judge of the Trial Court appoint an independent arbitrator to adjudicate
the fee disputes between TOA and Pidcock in accordance with Section 510(g) of the
MPC. In its Petition to Appoint, TOA averred that the parties were unable to agree
on an independent arbitrator to resolve their disputes. See Am. Compl., Ex. 9.2
2
On September 16, 2019, TOA proposed two engineers as potential arbitrators, but
Pidcock rejected both of them. Pidcock’s Pet. to Intervene, Ex. H. On October 10, 2019, Pidcock
proposed an engineer as a potential arbitrator, but TOA rejected him because Pidcock was a current
client of that engineer’s firm. Id., Exs. I, J. On November 4, 2019, Pidcock proposed another
engineer to arbitrate the fee disputes. Id., Ex. K. TOA did not respond to this proposal, instead
filing the Petition to Appoint in the Trial Court on November 13, 2019. Id., Ex. L.
6
TOA’s Petition to Appoint is still being litigated in the Trial Court under a separate
docket number. See Trial Ct. Order, 2/25/20, at 3 n.3.3
On November 26, 2019, TOA filed its Amended Complaint, seeking to
compel the Township to exercise its ministerial duty to replace Pidcock with its
back-up engineer to oversee the Project. TOA averred that Pidcock breached its
obligations under the MPC by engaging in retaliatory conduct that has created an
adversarial relationship between the parties and a conflict of interest that precludes
Pidcock from reviewing the Project in a fair and unbiased manner. TOA alleged in
pertinent part:
95. [TOA] has submitted the [First, Second, and Third] Challenges
asserting legitimate claims disputing Pidcock’s fees and billing
practices.
96. In light of the dispute, [TOA] and Pidcock are now engaged in an
adversarial proceeding, creating a conflict of interest between them.
97. Pidcock has exacerbated the situation by refusing to proceed
through the arbitration process with an independent arbitrator, thereby
requiring [TOA] to commence a lawsuit against Pidcock, which is now
pending in [the Trial] Court.
98. The existence of that adversarial relationship alone creates an
appearance of impropriety in Pidcock’s ability to perform a fair and
unbiased review of [TOA’s] work.
Am. Compl. ¶¶ 95-98. TOA further alleged that “Pidcock has engaged in a series of
conduct designed solely to impede the construction of the [Project] in retaliation for
[TOA’s] exercise of its statutory rights to contest Pidcock’s . . . [f]ees,” which “not
3
In its Preliminary Objections, Pidcock avers that “[TOA] and [Pidcock] are involved in a
separate proceeding concerning the [Petition to Appoint] that [TOA] filed on November 13, 2019.
See TOA Green Pond Advisors, LLC t/a TOA Green Pond, L.P. v. The Pidcock Company, Docket
No. C-48-CV-2019-10772.” Pidcock’s Prelim. Objs., ¶ 15.
7
only violates the Code of Ethics governing engineers, but violates Pennsylvania
law.” Id. ¶¶ 101-02.
In support of its request for mandamus relief, TOA averred as follows:
117. Since the Township has already retained [Arro], the appointment
of [Arro] to replace Pidcock for the [Project] is a ministerial act.
118. The Township has a clear duty to perform that ministerial act to
avoid a violation of Pennsylvania law and/or to avoid compelling
Pidcock to violate the regulations and rules governing engineers.
119. [TOA] has no other adequate remedy at law by which to get the
Township to appoint [Arro] to replace Pidcock for review of the
[Project].
Id. ¶¶ 117-19.
On December 17, 2019, Pidcock filed Preliminary Objections to the Amended
Complaint, asserting a demurrer on the grounds that: (1) TOA has no legal right to
have Pidcock removed as the Township engineer on the Project; (2) the Township
has no duty to remove Pidcock as the Township engineer on the Project; and (3)
TOA has an adequate remedy at law under Section 510(g) of the MPC, 53 P.S. §
10510(g). On the same date, the Township also filed Preliminary Objections
asserting the same grounds for dismissal of the Amended Complaint.
The Trial Court heard argument on the Preliminary Objections on February
18, 2020, after which it sustained both defendants’ Preliminary Objections and
dismissed TOA’s Amended Complaint. The Trial Court concluded that TOA’s
request for mandamus was improper because TOA failed to identify a clear legal
mandate that Pidcock must be removed from the Project due to the alleged conflict
of interest implicated by the underlying fee disputes. The Trial court explained its
reasoning as follows:
8
7. Upon review of the Amended Complaint, we agree with
Pidcock that [TOA] has not identified a clear legal mandate that
Pidcock must be removed as the reviewing engineer as a result of the
alleged conflict of interest implicated by the underlying fee dispute.
Even accepting all of the allegations of the Amended Complaint as true,
[TOA] has not identified a statute, rule or any case[]law that would
require the Township to replace Pidcock with [Arro.] [TOA] cites only
to general professional licensure and ethical standards, but does not
identify any specific provision that precludes further work on a project
following a fee dispute. Assuming that [TOA] could establish that
Pidcock’s conduct violated professional standards, no professional
organization has made such a finding against Pidcock. [TOA] has
provided no basis for the removal of Pidcock prior to or in the absence
of such a finding.
8. Further, the [MPC] delineates the process for a developer to
challenge the fees assessed by a reviewing engineer. See 53 [P.S.] §
10510(g). This statute prescribes several mandatory actions on the
Township and [Pidcock], but specifically does not require that the
disputed engineer be precluded from further review of the project, and
does not require that the governing body delegate or reassign further
review to an alternative engineer. [TOA] is certainly not the first
developer to challenge a reviewing engineer’s fees, yet has failed to
identify any other case in which a mandamus action was successfully
pursued to compel a municipality to utilize a substitute engineer. As
noted above, a mandamus action is only appropriate where the legal
right is “clearly established.” The fact that there is no other case where
[TOA’s] alleged right to relief has been upheld leads to the necessary
conclusion that the purported right to relief is not clearly established.
Consequently, [TOA] has failed to identify both a clear legal right to
relief, and failed to identify a well-defined, clear, and specific duty on
the part of the Township to undertake the requested action. [TOA] has
not established the necessary elements to maintain the instant
mandamus complaint.
9
Trial Ct. Order, 2/25/20, ¶¶ 7-8 (footnote omitted) (emphasis added). TOA now
appeals from that decision.4
Analysis
“Mandamus is an extraordinary remedy designed to compel the performance
of a ministerial act or a mandatory duty.” Orange Stones Co. v. City of Reading,
Zoning Hearing Bd., 32 A.3d 287, 290 (Pa. Cmwlth. 2011). The party seeking this
extraordinary remedy has the burden of proving its legal right to such relief. Baron
v. Com. Dep’t of Hum. Servs., 169 A.3d 1268, 1272 (Pa. Cmwlth. 2017) (en banc),
aff’d, 194 A.3d 563 (Pa. 2018). To state a claim for mandamus relief, the petitioner
must establish: (1) a clear legal right to relief; (2) a corresponding duty in the
respondent; and (3) the lack of any other adequate and appropriate remedy. Id.
1. Clear Right to Relief
First, TOA argues that it has a clear statutory right to have the Project
inspected and approved by an independent Township engineer. According to TOA,
the MPC requires both the Township and its professional consultant to remain
unbiased when a dispute arises over the consultant’s fees. In essence, TOA contends
that its challenges to Pidcock’s fees have created an adversarial relationship between
the parties such that the Township is required to remove Pidcock from the Project.
In support of its contention, TOA relies on Section 503(1)(i) of the MPC,
which states:
In the event the applicant disputes the amount of any such review fees,
the applicant shall, no later than 100 days after the date of transmittal
of the bill to the applicant, notify the municipality and the
municipality’s professional consultant that such fees are disputed and
4
“Our scope of review of a trial court order granting preliminary objections is limited to
determining whether the trial court committed legal error or abused its discretion.” Bell v. Twp. of
Spring Brook, 30 A.3d 554, 557 n.7 (Pa. Cmwlth. 2011).
10
shall explain the basis of their objections to the fees charged, in which
case the municipality shall not delay or disapprove a subdivision or
land development application due to the applicant’s dispute over fees.
53 P.S. § 10503(1)(i) (emphasis added). TOA also relies on Section 510(g)(1) of
the MPC, which states that if an applicant disputes a fee, “the municipality shall not
delay or disapprove a request for release of financial security, a subdivision or land
development application or any approval or permit related to development due to
the applicant’s dispute of inspection expenses.” 53 P.S. §10510(g)(1) (emphasis
added).
We conclude that neither of these statutory provisions establishes a clear legal
right to the relief TOA seeks. Section 503(1)(i) of the MPC addresses the
Township’s responsibility to “not delay or disapprove a subdivision or land
development application due to the applicant’s dispute over fees.” 53 P.S. §
10503(1)(i). Likewise, Section 510(g)(1) addresses the Township’s responsibility to
“not delay or disapprove a request for release of financial security, a subdivision or
land development application or any approval or permit related to development due
to the applicant’s dispute of inspection expenses.” 53 P.S. § 10510(g)(1). TOA,
however, does not allege that the Township delayed its land development application
or approval as a result of the instant fee disputes. In fact, TOA specifically avers
that at the time it filed its First Challenge, TOA “had already received its final land
development approvals [from the Township] and obtained permits relating to the
construction of the [Project].” Am. Compl. ¶ 18. More importantly, contrary to
TOA’s assertion on appeal, nothing in Section 503(1)(i) or Section 510(g)(1) of the
MPC mandates that a municipality remove a professional consultant from a project
when a fee dispute (however contentious it may be) arises between the consultant
and the developer.
11
Furthermore, the authority to appoint or remove a municipal engineer lies
exclusively with the Township. Under Section 1301 of The First Class Township
Code (Code), Act of June 24, 1931, P.L. 1206, as amended, 53 P.S. § 56301,5 the
Township’s Board of Commissioners, in its sole discretion, appoints the township
engineer:
The [township’s] board of commissioners at the commencement of the
fiscal year in any even-numbered year, or as soon thereafter as may be
practicable, may elect, by a vote of a majority of the members, one
person as township engineer, who shall be a registered civil engineer.
He shall serve for a term of two years, and until his successor qualifies.
The board of commissioners shall fix the compensation of the engineer.
Vacancies in the office of township engineer shall be filled by the board
of commissioners for the unexpired term.
53 P.S. § 56301 (emphasis added). Section 1303 of the Code further provides that
the appointed “engineer shall have the superintendence, direction and control of the
engineering matters of the township.” 53 P.S. § 56303.
While the Township acknowledges that it has the discretion to remove an
appointed engineer from a project, see Twp.’s Br. at 16, TOA has cited no legal
authority for its position that the Township must do so simply because the developer
claims that the engineer is biased against it. See Seeton v. Adams, 50 A.3d 268, 275
(Pa. Cmwlth. 2012) (en banc) (recognizing “the fundamental principle that
mandamus is not available to compel an official to exercise his discretion in a
particular way”); see also Pa. Dental Ass’n v. Ins. Dep’t, 516 A.2d 647, 652 (Pa.
1986) (“[Mandamus] is not used to direct the exercise of judgment or discretion in a
particular way, nor to direct the retraction or reversal of an action already taken.”).
5
The General Assembly amended several provisions of the Code on October 29, 2020.
Those amendments did not alter the language in either Section 1301 or Section 1303 of the Code,
which are discussed above.
12
Therefore, we conclude that TOA has failed to establish that it has a clear
legal right to have Pidcock removed from the Project due to the ongoing fee disputes.
2. Ministerial Act or Mandatory Duty
Next, TOA argues that the Township’s obligation to direct the back-up
engineer to replace Pidcock is ministerial in nature and, thus, may be compelled by
mandamus. TOA contends that because Pidcock has demonstrated a conflict of
interest, and because the Township has already appointed Arro as its back-up
engineer, the Township has a duty to direct Arro to perform engineering services for
the Project. We disagree.
A ministerial act is an act that “a public officer is required to perform upon a
given state of facts, in a prescribed manner, in obedience to the mandate of legal
authority, and without regard to his own judgment or opinion concerning the
propriety or impropriety of the act to be performed.” Council of City of Phila. v.
Street, 856 A.2d 893, 896 (Pa. Cmwlth. 2004) (emphasis added). Moreover, “[t]he
petitioner’s right to performance of a [ministerial act or] mandatory duty must be
well-defined, clear, and specific; where any doubt exists, mandamus relief will not
lie.” Kegerise v. Delgrande, 183 A.3d 997, 1004 (Pa. 2018) (emphasis added).
We conclude that TOA has failed to allege a ministerial act or mandatory duty
that is well-defined, clear, and specific. The record shows that the Township
appointed Arro as its back-up engineer in the event that a conflict existed between
Pidcock and a developer at the onset of a project, since Pidcock performs consulting
services for both municipal and private clients. See Am. Compl. ¶¶ 8, 9; Pidcock’s
Reply Br. in Support of Prelim. Objs. at 4. However, there is no indication in the
record that the Township is required to replace Pidcock with its back-up engineer if
an alleged conflict arises after a land development project is well underway and
13
approvals and permits have been granted, as in this case.6 In any event, as discussed
above, the Township’s decision to appoint or remove a professional consultant is
neither a ministerial act nor a mandatory duty; it is entirely within the Township’s
discretion.
In rejecting TOA’s claim for mandamus relief, the Trial Court observed:
[TOA] has not identified a statute, rule[,] or any case[]law that would
require the Township to replace Pidcock with the [back-up e]ngineer.
[TOA] cites only to general professional licensure and ethical
standards, but [it] does not identify any specific provision that precludes
further work on a project following a fee dispute.
Trial Ct. Order, 2/25/20, ¶ 7. We agree with the Trial Court that TOA has failed to
establish a ministerial act or mandatory duty enforceable by mandamus.7
Conclusion
TOA’s factual allegations in support of its request for mandamus relief derive
from ongoing fee disputes between TOA and Pidcock. The procedure for resolving
such disputes is clearly set forth in the MPC. As the Trial Court correctly observed,
“[The MPC] prescribes several mandatory actions on the Township and [its
e]ngineer, but specifically does not require that the disputed engineer be precluded
from further review of the [P]roject, and does not require that the governing body
6
Pidcock avers that it has been reviewing land development plans for the Project and has
inspected the public improvements constructed on the Property since July 2014. Pidcock’s Prelim.
Objs., ¶¶ 7, 8.
7
In its appellate brief, TOA also argues, for the first time, that Pidcock has a legal
obligation to remove itself from the Project due to its perceived conflict of interest. See TOA’s
Br. at 24-25. This argument contradicts TOA’s position in its Amended Complaint and before the
Trial Court that the Township has a mandatory duty to remove Pidcock from the Project.
Therefore, because TOA did not raise this claim before the Trial Court, we conclude that it has
waived this argument on appeal. See Pa. R.A.P. 302(a) (“Issues not raised in the trial court are
waived and cannot be raised for the first time on appeal.”).
14
delegate or reassign further review to an alternative engineer.” Trial Ct. Order,
2/25/20, ¶ 8. Furthermore, litigation is still pending in the Trial Court regarding the
appointment of an independent arbitrator to resolve the parties’ fee disputes. TOA
has cited no authority establishing its legal right to demand Pidcock’s removal from
the Project in the midst of these disputes, nor has it cited any legal authority
establishing the Township’s duty to remove Pidcock from the Project based solely
on TOA’s allegations of bias and unethical conduct.8
Accordingly, because we conclude that TOA has not established a clear legal
right to mandamus relief, we affirm the Trial Court’s Order.
__________________________________
ELLEN CEISLER, Judge
8
Because we conclude that TOA has failed to meet the first two requirements for
mandamus relief, we need not address whether TOA has an adequate alternative remedy.
We further note that TOA has filed with this Court a “Reproduced Record,” which contains
documents post-dating the Trial Court’s February 25, 2020 Order. However, it is well-settled that
this Court cannot consider evidence on appeal that was not presented to the Trial Court. See Pa.
Tpk. Comm’n v. Unemployment Comp. Bd. of Rev., 991 A.2d 971, 974 (Pa. Cmwlth. 2009) (“This
Court may not consider any evidence that is not part of the certified record on appeal.”); Allen v.
Thomas, 976 A.2d 1279, 1282 (Pa. Cmwlth. 2009) (stating that “an appellate court cannot consider
anything that is not part of the record” before the trial court). Therefore, we will not consider
TOA’s extra-record evidence.
15
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
TOA Green Pond Advisors, LLC :
t/a TOA Green Pond, L.P., :
Appellant :
:
v. : No. 261 C.D. 2020
:
Bethlehem Township and The :
Pidcock Company :
ORDER
AND NOW, this 5th day of January, 2021, the Order of the Court of Common
Pleas of Northampton County, entered on February 25, 2020, is hereby AFFIRMED.
__________________________________
ELLEN CEISLER, Judge