IN THE COMMONWEALTH COURT OF PENNSYLVANIA
RMBM Corporation, Inc. :
:
v. : No. 202 C.D. 2020
: SUBMITTED: December 8, 2020
Greg Harkins, Code Enforcement :
Department Head, Debra Force, :
Berwick Borough Manager, and :
Alvin Hill, President of Borough of :
Berwick, :
Appellants :
BEFORE: HONORABLE ANNE E. COVEY, Judge
HONORABLE MICHAEL H. WOJCIK, Judge
HONORABLE ELLEN CEISLER, Judge
OPINION NOT REPORTED
MEMORANDUM OPINION
BY JUDGE CEISLER FILED: January 5, 2021
Appellants Greg Harkins, Code Enforcement Department Head, Debra Force,
Berwick Borough Manager, and Alvin Hill, President of Borough of Berwick
(collectively, Appellants) appeal from the Court of Common Pleas of the 26th
Judicial District — Columbia County Branch’s (Trial Court) January 28, 2020
interlocutory order granting in part and denying in part Appellee RMBM
Corporation, Inc.’s (Appellee) Motion for Partial Summary Judgment.1 Through this
order, the Trial Court granted peremptory mandamus relief to Appellee, as it found
that there was no genuine issue of material fact regarding whether Appellee was
1
The Trial Court’s order is dated January 24, 2020, but was not sent to the parties until
January 28, 2020. See Reproduced Record (R.R.) at 294a, 299a. Since this interlocutory order
granted peremptory mandamus relief, it was immediately appealable as of right. Pa. R.A.P.
311(a)(5).
entitled to one of two driveway construction permits Appellee had sought. See Tr.
Ct. Op., 1/28/20, at 2-13; Moskva Dep. at 51-52; R.R. at 125a. We reverse.
I. Facts and Procedural History
On May 2, 2016, Appellee filed two driveway permit applications with the
Borough of Berwick (Berwick), through which Appellee sought authorization to
connect a roughly 33-acre property it owns in Berwick (Property) to Fairview
Avenue and Spring Garden Avenue via two separate driveways. Compl., Ex. A.
These applications were reviewed on behalf of Berwick by Quad3 Architecture
Engineering Environmental Services (Quad3). Id., Ex. B. Quad 3 then issued a letter
on May 4, 2016, to Debra Force, Berwick’s then-Manager, in which Quad3 stated it
could not recommend approval of the applications unless they were substantially
revised and supplemented with additional materials. Id. Appellee subsequently
submitted a second iteration of its applications on May 12, 2016, followed by a third
on July 12, 2016, neither of which were sufficient to garner recommendations of
approval from Quad3. Id, Exs. D-E. Appellee then filed a fourth version of its
applications on September 28, 2016. Id., Ex. F. On October 14, 2016, Quad3 notified
Ms. Force that it deemed the Fairview Avenue application to be satisfactory and
recommended its approval. Id. Quad3 also recommended approval of the Spring
Garden Avenue application, albeit with a caveat. Id. Quad3 noted that the driveway
to Spring Garden Avenue would cross another piece of land and, though Appellee
had an easement agreement with that parcel’s owner, Quad3 deferred to the Berwick
Solicitor’s judgment as to whether Appellee needed the owner’s affirmative consent
to construct the driveway across his land. Id.
More than a year passed without any apparent movement by either Appellants
or Appellee, before Appellee filed the instant suit in the Trial Court on January 11,
2
2018. Therein, Appellee argued that, per Section 9-5(B) of the Berwick Code,2
Berwick’s Code Enforcement Officer was required to render a decision regarding a
permit application within 30 days of the application’s submission.3 Compl., ¶13.
Appellee claimed that it was entitled to a writ of mandamus compelling Berwick to
issue the driveway permits, as Appellee had remedied the applications’ initial
deficiencies and had secured Quad3’s imprimatur, which, according to Appellee,
therefore made approval of the applications mandatory. Id., ¶¶13-14, 22, Wherefore
Clause. In addition, Appellee requested monetary damages, in order to compensate
it for Appellants’ delays and their interference with Appellee’s use of the Property.
Id., ¶¶17-21, Wherefore Clause.4
Appellants responded by filing an Answer and New Matter, after which the
parties commenced discovery, which included deposing Roman Moskva, Appellee’s
President, on November 9, 2018. See R.R. at 76a (identifying Moskva’s
organizational role). During the course of his deposition, Moskva discussed the
Property, the driveway construction applications, Berwick’s review process, and
Appellee’s easement agreements with neighboring landowners. When asked how
2
BERWICK CODE (1977), as amended; Supplemental Reproduced Record (S.R.R.) at 309a-
19a.
3
Section 9-5(B) reads as follows:
Action on application. [Berwick’s] Code Enforcement Officer shall
examine said application to determine compliance with those other
applicable codes and ordinances of Berwick and shall, within 30
days after filing, either approve or reject said application. If said
application is rejected, the Code Enforcement Officer shall inform
the applicant in writing, stating the reasons for such rejection.
Berwick Code § 9-5(B).
4
Appellee alleged that, in addition to dragging their heels regarding approving the
applications, Appellants had blocked the proposed driveway locations with unspecified types of
barricades. Compl., ¶¶17-18.
3
Appellee could potentially access the Property, other than through Fairview Avenue
and Spring Garden Avenue, Moskva responded that
[the Property is] a relatively large parcel, so there [are] a
lot of access points. There [are] access points from
different easements and Route 93. There is a Route 11
easement. There is another street in Berwick that follows
Spring Garden [Avenue], I think it’s Brittain Street, that’s
about a hundred yards away.
....
[A]nd I believe there is a Steel Street [access point in
Berwick], you know. So we have rights to both of those as
well.
Moskva Dep. Tr. at 43-44; R.R. at 123a. Appellants also showed Moskva a letter
that had been allegedly sent to him on February 20, 2018, by Curt Rider, Berwick’s
Building Code Official/Code/Zoning Official. This letter informed Moskva that
Berwick had denied the applications because approval would enable Appellee to
construct “access drives” extending both Fairview Avenue and Spring Garden
Avenue as public streets, rather than just private driveways. Appellants’ Br. in Opp’n
to Mot. for Partial Summ. J., Ex. 5; Moskva Dep. Tr. at 92-93; R.R. at 135a-36a. As
explained in Rider’s letter, Appellee’s current applications were substantively
deficient, due to the Berwick Code’s requirements covering access drives, which
differed from those governing construction of driveways, and had to be reviewed by
Berwick’s Council before they could be approved. Appellants’ Br. in Opp’n to Mot.
for Summ. J., Ex. 5. This letter also informed Moskva that, at his discretion, he could
challenge these denials before Berwick’s Code Hearing Board of Appeals. Id.; see
Berwick Code § 9-2 (establishing Code Hearing Board of Appeals and appeal
process for Code Enforcement Officer’s decisions); S.R.R. at 310a-11a. Moskva
adamantly stated that he had never seen this letter before and that his attorney would
4
certainly have responded to the denial had they been aware of it. Moskva Dep. Tr.
at 93-94; R.R. at 136a.5
Appellee thereafter filed its Motion for Partial Summary Judgment on May
13, 2019, in which it reiterated its argument that Section 9-5(B) of the Berwick Code
placed upon Berwick a mandatory, ministerial duty to rule upon Appellee’s permit
applications within 30 days of the applications’ filing. Appellee’s Br. in Support of
Mot. for Partial Summ. J. at 3-4.6 Given Berwick’s failure to comply with this
deadline, as well as Quad3’s recommendation that Appellee’s applications be
approved, Appellee claimed that it was entitled, at the summary judgment stage, to
a Writ of Mandamus directing Appellants to issue the desired permits. Id. at 4-5.
Appellants responded in opposition, after which the Trial Court held oral argument
on October 22, 2019, and eventually granted the Motion for Partial Summary
Judgment in part and denied it in part on January 28, 2020.
The Trial Court determined that there were no genuine issues of material fact
as to whether Appellee was entitled to approval of the Fairview Avenue permit, but
the same could not be said regarding the Spring Garden Avenue permit. The Trial
Court agreed with Appellee that Section 9-5(B) of the Berwick Code placed a clear
duty upon Berwick to rule upon Appellee’s permit applications within 30 days of
their submission. Tr. Ct. Op., 1/28/20, at 7. The Trial Court then examined Breinig
v. County of Allegheny, 2 A.2d 842 (Pa. 1938), which it read as holding that
5
Notably, the address to which Rider’s letter was sent, 1801 West Front Street, Berwick,
Pennsylvania 18603, is different from the address listed on both applications for Appellee and
Moskva, 1892 West Front Street, Berwick, Pennsylvania 18603. Compare Compl., Ex. A, with
Appellants’ Br. in Opp’n to Mot. for Summ. J., Ex. 5.
6
Appellee also presented what amounts to an alternate argument, i.e., that Berwick was
required to rule upon the applications no later than 30 days after Quad3 recommended their
approval. See Appellee’s Br. in Support of Mot. for Partial Summ. J. at 4.
5
municipalities cannot unreasonably prevent landowners from securing access to
public streets from their properties. Tr. Ct. Op., 1/28/20, at 7-8. Additionally, the
Trial Court briefly discussed Verratti v. Ridley, 206 A.2d 13 (Pa. 1965), citing it for
the proposition that a municipality could be compelled via mandamus to issue a
permit, where the right to that permit was clear and, thus, its issuance was a
ministerial act, rather than one requiring discretion. Tr. Ct. Op., 1/28/20, at 11-12.
The Trial Court also criticized the fact that it took nearly two years and the filing of
a lawsuit for Berwick to take action, as well as Berwick’s failure to send the Rider
denial letter to the correct address. Id. at 9-10.
Tying these points together, the Trial Court concluded that Appellee had
established a clear right to connect the Property via a driveway to Fairview Avenue,
that Berwick had a nondiscretionary, ministerial duty to approve the Fairview
Avenue application, and that Appellee had no other viable legal avenue to obtain
approval of that application, other than via a mandamus action. Id. at 7-8, 12. By
contrast, the Trial Court determined that there was a genuine issue of material fact
as to whether mandamus relief was proper for the Spring Garden Avenue
application, as it was unclear whether Appellee needed to secure an adjacent
landowner’s approval in order to build the proposed driveway across an easement.
Id. at 12-13.
In doing so, the Trial Court minimized Moskva’s admission that there were
numerous access points to the Property, other than those implicated by Appellee’s
applications, by stating that “[Appellee] still has a right to reasonable access to [the
P]roperty from a public highway without capricious and arbitrary interference.” Id.
at 8-9. Furthermore, though the Trial Court acknowledged that Moskva had learned
at his November 2018 deposition that Berwick had denied the applications, the Trial
6
Court nonetheless stated that it would be “burdensome on the judicial system and
[Appellee]” to require Appellee to appeal that denial. Id. at 12. In essence, the Trial
Court concluded that the most efficient choice was to grant the peremptory
mandamus relief the Trial Court believed Appellee was due, rather than to delay
resolution of the underlying dispute by forcing Appellee to go through the standard
procedural channels. Id. This appeal followed.7
II. Discussion
On appeal,8 Appellants’ challenges to the Trial Court’s decision can be
distilled down to a single point: Appellants believe the Trial Court erred by granting
peremptory mandamus relief to Appellee, as, in Appellants’ view, there are genuine
issues of material fact as to whether Appellee was entitled to approval of its Fairview
Avenue application. See Appellants’ Br. at 23-47.9
“It is well settled that mandamus is an extraordinary writ which lies to compel
performance of a ministerial act or mandatory duty where there is a clear legal right
in the plaintiff, a corresponding duty in the defendant, and a want of any other
7
On March 9, 2020, the Trial Court ordered Appellants to file a Statement of Errors
Complained of on Appeal. Appellants complied with this directive on March 20, 2020. The Trial
Court then issued a short, single-page opinion on May 5, 2020, stating therein that its earlier
January 28, 2020 opinion fully and satisfactorily addressed all of the arguments Appellants sought
to raise on appeal. Tr. Ct. Op., 5/5/20, at 1.
8
When considering an appeal stemming from a lower court’s decision to grant a judgment
of peremptory mandamus, we are limited to determining whether the lower court abused its
discretion or committed an error of law. Dusman v. Bd. of Dirs. of Chambersburg Area Sch. Dist.,
113 A.3d 362, 368 n.4 (Pa. Cmwlth. 2015).
9
Appellants also argue that the Trial Court erred by declining to dismiss Ms. Force from
this action because, according to Appellants, Ms. Force is not a proper defendant to Appellee’s
action because she is no longer a Berwick employee. Appellants’ Br. at 48. We decline to address
this issue, as it appears that Appellants never formally moved to have the Trial Court dismiss Ms.
Force from this matter and, thus, there is no denial of such relief for us to review.
7
appropriate and adequate remedy.” Cooper v. City of Greensburg, 363 A.2d 813,
815 (Pa. Cmwlth. 1976). “The purpose of mandamus is not to establish legal rights
but only to enforce those legal rights that have already been established.” Orange
Stones Co. v. City of Reading, Zoning Hearing Bd., 32 A.3d 287, 290 (Pa. Cmwlth.
2011). “To obtain peremptory judgment, in addition to showing the elements for
mandamus relief, the moving party must show that on the facts of record, and those
facts that may be developed at trial, the right to judgment is clear. . . . Further, [the
c]ourt must examine the existing and potential record in the light most favorable to
the non-moving party.” Scarnati v. Dep’t of Env’t Prot., 220 A.3d 723, 730 (Pa.
Cmwlth. 2019), aff’d, 240 A.3d 536 (Pa. 2020) (internal citation omitted); Pa. R.C.P.
No. 1098 (“At any time after the filing of the complaint, the court may enter [a
peremptory mandamus] judgment if the right of the plaintiff thereto is clear.”).
While a decision on a motion for peremptory [mandamus]
judgment is subject to the same standards as a motion for
summary judgment, i.e., no material issue of fact and clear
legal right to relief, the court is not limited, as on summary
judgment, to consideration of pleadings, depositions,
admissions, affidavits, expert reports and answers to
interrogatories, but may enter peremptory judgment after
conducting a hearing at which the court determines that
there are no material factual disputes.
Reiver v. Kraines, 838 A.2d 814, 817 n.3 (Pa. Cmwlth. 2003).
We conclude that the Trial Court improperly granted Appellee peremptory
mandamus relief regarding the Fairview Avenue application for several reasons.
First, the Trial Court erroneously determined that Section 9-5(B) of the Berwick
Code placed a clear, mandatory duty upon Berwick to rule upon Appellee’s
applications within 30 days of their submission. To reiterate, this provision reads as
follows:
8
Action on application. [Berwick’s] Code Enforcement
Officer shall examine said application to determine
compliance with those other applicable codes and
ordinances of [Berwick] and shall, within 30 days after
filing, either approve or reject said application. If said
application is rejected, the Code Enforcement Officer shall
inform the applicant in writing, stating the reasons for such
rejection.
Berwick Code § 9-5(B); S.R.R. at 317a. The import of “shall,” as used in Section 9-
5(B), is key.10
“The word ‘shall’ . . . can be interpreted as mandatory or
merely directory.” Francis v. Corleto, . . . 211 A.2d 503,
509 ([Pa.] 1965). A court must “look to the intention and
purpose of the statute[, ordinance, or regulation] in
determining whether the word shall is to be given a
permissive or imperative meaning.” Division 85,
Amalgamated Transit Union v. Port Auth. of Allegheny
Cnty., . . . 208 A.2d 271, 272 ([Pa.] 1965) (emphasis in
original).
In re Sale of Real Estate by Lackawanna Cnty. Tax Claim Bureau, 22 A.3d 308, 314
(Pa. Cmwlth. 2011).
“When a statute[, ordinance, or regulation] directs certain
proceedings to be done in a certain way, or at a certain
time, the law will be regarded as directory and the
proceedings under it will be held valid, though the
command of the statute[, ordinance, or regulation] as to
form and time has not been strictly obeyed; the time and
manner not being the essence of the thing required to be
done.”
10
Interpretation of the language used in a local ordinance, rule, or regulation is a legal
question for which our standard of review is de novo and our scope of review is plenary. S & H
Transp., Inc. v. City of York, 210 A.3d 1028, 1038 (Pa. 2019). “Although the Statutory
Construction Act of 1972, 1 Pa. C.S. §§ 1501-1991, is not expressly applicable to the construction
of local ordinances, the rules of statutory construction are applicable to statutes and ordinances
alike.” Geerling Florist, Inc. v. Bd. of Supervisors of Warrington Twp., 226 A.3d 670, 676 (Pa.
Cmwlth. 2020).
9
Com. ex rel. Duff v. Eichmann, 45 A.2d 38, 39 (Pa. 1946) (quoting Deibert v.
Rhodes, 140 A. 515, 517 (Pa. 1928)). Though Section 9-5(B) of the Berwick Code
states that Berwick’s Code Enforcement Officer “shall” render a decision regarding
a permit application within 30 days of the application’s filing, there is nothing that
suggests that a failure to do so results in the automatic approval of the affected
application or imbues the applicant with any specific substantive rights. The essence
of Section 9-5(B) is that Berwick’s Code Enforcement Officer will review each
permit application and render a decision, not that the Officer’s failure to do so within
a specific time window deprives the Officer of their dispositional powers. As such,
we conclude that the use of the word “shall” in Section 9-5(B) is merely directory
and, thus, Berwick’s Code Enforcement Officer was not required to issue a ruling
regarding the Fairview Avenue application within 30 days of its submission. Verratti
is therefore inapposite, as in contrast to that matter, there was no ministerial
obligation to approve this application and, thus, no clear right to relief in this
situation.11
In addition, by concluding at this stage in the proceedings that Appellee had
a clear right to approval of its Fairview Avenue application, the Trial Court
disregarded the high bar for granting peremptory mandamus relief. It is true, per
Breinig, that a municipality may not deny a landowner reasonable access to their
own land, unless it adequately compensates the landowner for depriving them of this
right to access. 2 A.2d at 847. It is also true that “[r]easonable access to one’s
11
We do not dispute that “[t]he issuance of licenses and permits under conditions laid down
by the legislative authorities is a ministerial or administrative function.” Breinig, 2 A.2d at 850.
Rather, we merely decline to hold that, under the unique facts of this matter, the Code Enforcement
Officer’s failure to rule upon the Fairview Avenue application within a specific time window
created a ministerial duty to both disregard this application’s substance and grant the desired
permit.
10
property is a question of fact to be determined by the trial court.” Elser v. Dep’t of
Transp., 651 A.2d 567, 570 (Pa. Cmwlth. 1994). However, given that Moskva
himself admitted that the Property has a multitude of potential locations for ingress
and egress to nearby roads, it is not beyond dispute whether approval of the Fairview
Avenue application is necessary to enable reasonable access to the Property.
Furthermore, as shown through Rider’s letter, Berwick has concluded that Appellee
actually sought authorization to build access drives, which are subject in Berwick to
different requirements and a different review process than driveway construction
applications. Viewing these points in the light most favorable to the non-movants,
as we must, it is plainly evident that there are genuine issues of material fact which
preclude the granting of peremptory mandamus relief in Appellee’s favor, as well as
that the Trial Court erred by concluding otherwise.
Finally, the Trial Court erred by determining that Appellee had no other
appropriate and adequate legal remedy in the absence of mandamus. Like the Trial
Court, we are troubled by the fact that Berwick took almost two years to rule upon
Appellee’s applications, only acted after Appellee had commenced litigation, and
inexplicably sent the Rider letter memorializing Berwick’s decision to the wrong
address. However, it remains that Moskva was presented with this letter at his
deposition in November 2018 and was thus notified the Fairview Avenue application
had been denied, as well as that this denial could be challenged before Berwick’s
Code Hearing Board of Appeals. Simply put, Appellee cannot seek to obtain the
desired Fairview Avenue driveway permit via mandamus because it has the ability
to contest the underlying application’s denial through the administrative process set
forth in the Berwick Code. Though the Trial Court’s invocation of judicial economy
has seductive appeal, we cannot allow Appellee to skip past a viable avenue for legal
11
relief, as doing so would completely disregard the fact that mandamus may be
granted only under extraordinary circumstances.
III. Conclusion
On the basis of the foregoing analysis, we conclude that the Trial Court erred
by partially granting Appellee’s Motion for Partial Summary Judgment and
consequently reverse the Trial Court’s January 28, 2020 order, to the extent this
order granted Appellee peremptory mandamus relief against Appellants and directed
Berwick to approve Appellee’s Fairview Avenue application. We remand this matter
to the Trial Court for further proceedings consistent with this opinion.
__________________________________
ELLEN CEISLER, Judge
12
IN THE COMMONWEALTH COURT OF PENNSYLVANIA
RMBM Corporation, Inc. :
:
v. : No. 202 C.D. 2020
:
Greg Harkins, Code Enforcement :
Department Head, Debra Force, :
Berwick Borough Manager, and :
Alvin Hill, President of Borough of :
Berwick, :
Appellants :
ORDER
AND NOW, this 5th day of January, 2021, it is HEREBY ORDERED that the
Court of Common Pleas of the 26th Judicial District — Columbia County Branch’s
(Trial Court) January 28, 2020 order, which granted in part and denied in part
Appellee RMBM Corporation, Inc.’s (Appellee) Motion for Partial Summary
Judgment, is REVERSED, to the extent this order granted Appellee peremptory
mandamus relief and directed the Borough of Berwick to approve Appellee’s
Fairview Avenue driveway permit application. It is FURTHER ORDERED that this
matter is REMANDED to the Trial Court for further proceedings consistent with the
foregoing opinion.
Jurisdiction relinquished.
__________________________________
ELLEN CEISLER, Judge