In the United States Court of Federal Claims
No. 20-529C
(Filed: February 5, 2021)
)
BOSTON EDISON COMPANY, et al., ) Suit for breach of Standard Contract for
) disposal of spent nuclear fuel; standing;
Plaintiff, ) RCFC 12(b)(1); failure to state a claim;
) RCFC 12(b)(6)
v. )
)
UNITED STATES, )
)
Defendant. )
)
)
Richard J. Conway, Blank Rome LLP, Washington, D.C., for plaintiff. With him on
briefs were Frederick M. Lowther and Adam Proujansky, Blank Rome LLP, Washington, D.C.,
Nicholas W. Mattia, Jr., Tampa, Florida, and Neven Rabadjija, Deputy General Counsel,
Eversource Energy, Boston, Massachusetts.
Eric J. Singley, Trial Attorney, Commercial Litigation Branch, Civil Division, United
States Department of Justice, Washington, D.C., for the United States. With him on briefs were
Jeffrey Bossert Clark, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director,
and Lisa L. Donahue, Assistant Director, Commercial Litigation Branch, Civil Division, United
States Department of Justice, Washington, D.C., as well as Brighton Springer, Office of the
General Counsel, United States Department of Energy, Washington, D.C.
OPINION AND ORDER
LETTOW, Senior Judge.
In this latest case involving litigation spanning two decades, plaintiff, Boston Edison
Company (“Boston Edison”), seeks to remedy a breach of contract against the United States.
Boston Edison entered into a contract with the United States Department of Energy (“DOE”) in
which Boston Edison would pay DOE millions of dollars in exchange for DOE’s transport and
disposal of spent nuclear fuel (“SNF”) generated at the Pilgrim Nuclear Power Station in
Plymouth, Massachusetts. While Boston Edison performed under the contract, DOE has not
collected or disposed of the SNF. Boston Edison has since sold the power plant, and the plant
recently has ceased operation and is in decommissioning. The government moves to dismiss
Boston Edison’s claim pursuant to Rules 12(b)(1) and 12(b)(6) of the Rules of the Court of
Federal Claims (“RCFC”). The government asserts that due to the sale, Boston Edison does not
have standing to raise its claim and that Boston Edison’s theory of liability was previously
foreclosed by the United States Court of Appeals for the Federal Circuit. Because the court finds
that Boston Edison has standing and has stated a claim upon which relief can be granted,
defendant’s motion to dismiss is DENIED.
BACKGROUND 1
This case concerns a Standard Contract between Boston Edison and the DOE. Compl. ¶
2, ECF No. 1. The Standard Contract, formed in 1983 pursuant to the Nuclear Waste Policy Act
of 1982, obligated the DOE to collect, transport, and dispose of SNF from Boston Edison’s
Pilgrim Nuclear Power Station (“Pilgrim”). Compl. ¶¶ 2, 13, 16. While DOE’s contractual
obligations began on January 31, 1998, DOE has yet to collect the SNF. Compl. ¶ 2. Boston
Edison, following Massachusetts’ enactment of legislation calling for restructuring of electric
utility companies in the State, sold Pilgrim to another company, Entergy Nuclear General
Company, LLC (“Entergy”) in 1999. Compl. ¶¶ 3, 19. 2 As a part of the purchase agreement,
Boston Edison agreed to pay Entergy “tens of millions of dollars for long-term, on-site storage of
Pilgrim SNF.” Compl. ¶ 21. This payment was included in Pilgrim’s Decommissioning Trust
Fund at the time of the sale. Compl. ¶ 21. Boston Edison assigned the Standard Contract to
Entergy, stating that Boston Edison “hereby assigns, transfers and sets over unto [Entergy] . . .
all of the Assignor’s rights and interests in, and obligations under, the [Standard] Contract.”
Def.’s Mot. to Dismiss (“Def.’s Mot.”) at A2, ECF No. 14. The assignment stated that the
agreement “[e]xcept[ed] and reserve[ed] to the Assignor, however, any and all claims of the
Assignor related or pertaining to the Department of Energy’s defaults under the [Standard]
Contract” accrued as of the sale date, July 13, 1999, “whether relating to periods prior to or
1
The recitations that follow do not constitute findings of fact, but rather are recitals
attendant to the pending motions and reflect matters drawn from the complaint, the parties’
briefs, and records and documents appended to the complaint and briefs.
2
For a detailed description of the Massachusetts legislation, Boston Edison’s agreement
with the Massachusetts Attorney General to resolve Boston Edison’s obligations under that
legislation, and Boston Edison’s auction to sell Pilgrim and a recitation of the terms of sale, see
Boston Edison Co. v. United States, 658 F.3d 1361, 1364-65 (Fed. Cir. 2011). Among other
things,
[t]he Massachusetts Attorney General insisted that Boston Edison retain all claims
against the government arising from DOE’s expected breach of the Standard
Contract, and that any damages awarded be returned to Boston Edison’s
ratepayers as compensation for [Spent Nuclear Fuel]-related fees they had paid to
the company over a period of several years.
Id. at 1365 (footnote omitted). Further, “Massachusetts regulators approved the sale of
Pilgrim and the transfer of the decommissioning fund after concluding that Boston
Edison would ‘retain[] its claim against US-DOE’ under the reservation clause in the sale
assignment.” Id. (alteration in original).
2
following July 13, 1999.” Id. Boston Edison sent a letter to DOE apprising the agency of the
assignment on the same date. Id. at A1. 3
The Standard Contract, and DOE’s breach, has resulted in three rounds of litigation. 4
Boston Edison first filed suit in 1999. Compl. ¶ 23. This court found that DOE breached its
contractual obligations to Boston Edison and awarded Boston Edison damages exceeding $40
million for diminution of value “for SNF storage costs included in the decommissioning fund
Entergy received from Boston Edison upon the sale of Pilgrim.” Boston Edison III, 80 Fed. Cl.
at 492. On appeal, the United States Court of Appeals for the Federal Circuit reversed in part,
stating that Boston Edison could not recover “prospective damages for anticipated future
nonperformance . . . in a partial breach case.” Boston Edison VI, 658 F.3d at 136 (citing Indiana
Michigan Power Co. v. United States, 422 F.3d 1369, 1376, (2005)). On remand, this court held
that despite the Federal Circuit’s ruling, Boston Edison retained a “nascent claim for
decommissioning costs,” Boston Edison VII, 106 Fed. Cl. at 342, which would “fully mature . . .
on decommissioning,” id. at 341. The court, therefore, dismissed the case without prejudice. Id.
at 343. In November 2015, after learning that Entergy planned to cease operations at Pilgrim
beginning in June 2019, Boston Edison again filed suit in this court. Compl. ¶¶ 28-29. The
court subsequently dismissed Boston Edison’s claim without prejudice because Boston Edison’s
claim was “dependent upon decommissioning at Pilgrim” and those “damages [were] not yet
ascertainable.” Entergy Nuclear, 130 Fed. Cl. at 475. In May 2019, Pilgrim ended power
operations and began the decommissioning process. Compl. ¶ 34. Holtec Pilgrim, LLC
(“Holtec”), the successor-in-interest of Entergy, spent over $56 million in 2019 for SNF costs
associated with decommissioning. Compl. ¶¶ 40, 42. 5 According to the complaint, that money
came from the Decommissioning Trust Fund that Boston Edison funded upon the 1999 sale. See
Compl. ¶¶ 21, 42.
3
Entergy later sold Pilgrim to Holtec International and its subsidiaries, which
subsequently rebranded as Holtec Pilgrim, LLC. Def.’s Mot. at 10. That sale was completed on
August 26, 2019. Compl. ¶ 38.
4
This dispute has been the subject of litigation resulting in eight opinions from this court
and the United States Court of Appeals for the Federal Circuit. See Boston Edison Co. v. United
States, 64 Fed. Cl. 167 (2005) (“Boston Edison I” ); Boston Edison Co. v. United States, 67 Fed.
Cl. 63 (2005) (“Boston Edison II”); Boston Edison Co. v. United States, 80 Fed. Cl. 468 (2008)
(“Boston Edison III”), appeal dismissed and remanded, Boston Edison Co. v. United States, 299
Fed. Appx. 956 (Fed. Cir. 2008) (“Boston Edison IV”); Boston Edison Co. v. United States, 93
Fed. Cl. 105 (2010) (“Boston Edison V”), aff’d in part, rev’d in part, and remanded, Boston
Edison Co. v. United States, 658 F.3d 1361 (Fed. Cir. 2011) (“Boston Edison VI”); Boston
Edison Co. v. United States, 106 Fed. Cl. 330 (2012) (“Boston Edison VII”); Entergy Nuclear
Generation Co. v. United States, 130 Fed. Cl. 466 (2017).
5
Holtec additionally projected that it would spend $66 million in 2020, having already
spent one-third of that amount at the time the complaint was filed in this case in April 2020.
Compl. ¶ 39.
3
Boston Edison filed the present suit on April 29, 2020. See Compl. 6 Boston Edison
brought two counts for breach of contract and breach of the implied covenant of good faith and
fair dealing, seeking damages in excess of $40 million, interest, and attorneys’ fees, among other
relief, stemming from decommissioning activities at Pilgrim. Compl. at 11-13. Boston Edison
states that it “was required to pay Entergy tens of millions of dollars to cover the costs of storing
SNF.” Compl. ¶ 3. Now that decommissioning has begun, “Pilgrim has spent over $56 million
for SNF costs . . . from the Decommissioning Trust Fund.” Compl. ¶ 42. Those expenses
“would not have been necessary were it not for the DOE’s prior breach,” and these “mitigation
costs . . . were directly, proximately and foreseeably” caused by the breach. Compl. ¶ 42. The
government moves to dismiss this action pursuant to RCFC 12(b)(1) and 12(b)(6), arguing that
Boston Edison lacks standing and has failed to state a claim. Def.’s Mot. at 1. Specifically, the
government argues that the United States Court of Appeals for the Federal Circuit has previously
rejected the diminution-in-value claim presented by Boston Edison in this case. Id. at 17-22. In
addition to contending that it both has standing and has properly stated a claim, Boston Edison
avers that the government’s arguments are barred by collateral estoppel. Pl.’s Resp., ECF No.
15. The motion has been fully briefed, see Def.’s Reply, ECF No. 20, and the court held a
hearing on November 24, 2020. The motion is now ready for disposition.
STANDARDS FOR DECISION
A. Rule 12(b)(1) – Lack of Subject-Matter Jurisdiction & Standing
The Tucker Act provides this court with jurisdiction over “any claim against the United
States founded either upon the Constitution, or any Act of Congress or any regulation of an
executive department, or upon any express or implied contract with the United States, or for
liquidated or unliquidated damages in cases not sounding in tort.” 28 U.S.C. § 1491(a)(1).
Boston Edison, as plaintiff, must establish a substantive right to money damages within the
court’s Tucker Act jurisdiction, see United States v. Testan, 424 U.S. 392, 398 (1976), by a
preponderance of the evidence, see Trusted Integration, Inc. v. United States, 659 F.3d 1159,
1163 (Fed. Cir. 2011) (citing Reynolds v. Army & Air Force Exch. Serv., 846 F.2d 746, 748 (Fed.
Cir. 1988)). When ruling on the government's motion to dismiss for lack of jurisdiction, the
court must “accept as true all undisputed facts asserted in the plaintiff's complaint and draw all
reasonable inferences in favor of the plaintiff.” Id. (citing Henke v. United States, 60 F.3d 795,
797 (Fed. Cir. 1995)).
To satisfy the minimum constitutional threshold for standing in a federal court, a plaintiff
must have suffered an “injury in fact” that is fairly traceable to the conduct of the defendant, and
it must be likely that the injury would be “redressed by a favorable decision.” Lujan v.
Defenders of Wildlife, 504 U.S. 555, 560-61 (1992) (quotations omitted). An injury in fact is an
invasion of a legally protected interest that is both (1) “concrete and particularized” as well as (2)
“actual or imminent, not conjectural or hypothetical.” Id. at 560 (internal quotations and
6
Separately, Entergy filed suit seeking damages for DOE’s breach of the Standard
Contract at Pilgrim. Holtec Pilgrim, LLC, Entergy’s successor-in-interest, is the present plaintiff
in the case. See Holtec Pilgrim, LLC v. United States, No. 19-1159 (Fed. Cl., filed August 9,
2019).
4
citations omitted). A particularized injury is one that affects the plaintiff in “a personal and
individual way.” Id. at 560 n.1. The plaintiff’s burden to establish each of these elements
depends upon the stage of the litigation. Id. at 561.
B. Rule 12(b)(6) – Failure to State a Claim Upon Which Relief Can Be Granted
Under RCFC 12(b)(6), a complaint will survive a motion to dismiss if it “contain[s]
sufficient factual matter, accepted as true, to ‘state a claim to relief that is plausible on its face.’”
Ashcroft v. Iqbal, 556 U.S. 662, 678 (2009) (quoting Bell Atl. Corp. v. Twombly, 550 U.S. 544,
570 (2007)). “A claim has facial plausibility when the plaintiff pleads factual content that allows
the court to draw the reasonable inference that the defendant is liable for the misconduct
alleged.” Id. (citing Twombly, 550 U.S. at 556). The factual matters alleged “must be enough to
raise a right to relief above the speculative level on the assumption that all the allegations in the
complaint are true (even if doubtful in fact).” Twombly, 550 U.S. at 555-56 (citations omitted).
When reviewing the complaint, “the court must accept as true the complaint’s undisputed
factual allegations and should construe them in a light most favorable to the plaintiff.”
Cambridge v. United States, 558 F.3d 1331, 1335 (Fed. Cir. 2009) (citing Papasan v. Allain, 478
U.S. 265, 283 (1986)) (additional citation omitted). Conclusory statements of law and fact,
however, “are not entitled to the assumption of truth” and “must be supported by factual
allegations.” Iqbal, 556 U.S. at 679. “‘[N]aked assertion[s]’ devoid of ‘further factual
enhancement’” are insufficient to state a claim. Id. at 678 (quoting Twombly, 550 U.S. at 557);
accord Bradley v. Chiron Corp., 136 F.3d 1317, 1322 (Fed. Cir. 1998) (“Conclusory allegations
of law and unwarranted inferences of fact do not suffice to support a claim.”).
ANALYSIS
The government contends that Boston Edison both lacks standing and fails to state a
claim upon which relief can be granted. Def.’s Mot. at 13-22. Boston Edison refutes both
arguments, contending also that the government is estopped by the court’s prior rulings from
relitigating these claims. Pl.’s Resp. at 9-19. The court agrees with Boston Edison that the
issues raised by the government in its motion have been addressed in the court’s previous
opinions. See, e.g., Boston Edison I, 64 Fed. Cl. at 185-86; Boston Edison VII, 106 Fed. Cl. at
340-41; Entergy Nuclear, 130 Fed. Cl. 466. Regardless of whether the government is barred by
collateral estoppel, the court finds that Boston Edison has standing and has properly stated a
claim. Therefore, the government’s motion to dismiss is DENIED.
A. Jurisdiction & Standing
As its basis for jurisdiction, Boston Edison cites the contractual relationship between
DOE and Boston Edison established by the Standard Contract. Compl. ¶¶ 8-9; Pl.’s Resp. at 14.
In connection with Boston Edison’s assignment of the Standard Contract to Entergy in 1999, it
reserved “any and all claims . . . related or pertaining to the Department of Energy’s defaults
under the [Standard] Contract” that accrued prior to the sale, “whether relating to periods prior to
5
or following” the sale. Def.’s Mot. at A2; see Pl.’s Resp. at 14. 7 According to plaintiff, “Boston
Edison retained its SNF claims under the plain language of the agreement.” Pl.’s Resp. at 14.
The government, contrastingly, avers that “Boston Edison . . . cannot pursue the damages that it
seeks in this litigation because it is no longer in privity of contract with the United States.”
Def.’s Mot. at 13. The government provides that “the claim Boston Edison is asserting here [is
not] something that would fit into the language of an assignment,” Hr’g Tr. 11:2-4 (Nov. 24,
2020), 8 because the claim did not accrue prior to the assignment, Def.’s Reply at 7-8. The
government’s argument rests on the idea that the Boston Edison’s assignment reservation should
be narrowly construed so not as to include decommissioning costs incurred after the assignment.
See Hr’g Tr. 14:5-13.
The court disagrees with the government’s averments. When interpreting contracts,
courts are instructed to consider the contract “as a whole” and adopt an interpretation that
“harmonize[s] and give[s] meaning to all of [the contract’s] provisions.” Julius Goldman’s Egg
City v. United States, 697 F.2d 1051, 1057-58 (Fed. Cir. 1983) (quoting State of Arizona v.
United States, 216 Ct. Cl. 221, 235 (1978)). The court agrees with Boston Edison that granting
the government’s motion on this ground would “render the phrase ‘whether relating to periods
prior to or following the Closing Date’ meaningless.” Pl.’s Resp. at 15. Boston Edison
expressly retained rights to these claims in the assignment’s reservation language. See Boston
Edison VII, 106 Fed. Cl. at 340 (“Rights flowing from [the pre-transfer breach] remain Boston
Edison’s because DOE defaulted before the transfer of the Pilgrim plant to Entergy, and Boston
Edison expressly retained rights to claims ‘related or pertaining to the D[OE]’s defaults under the
DOE Standard Contract accrued as of the Closing Date, whether relating to periods prior to or
following the Closing Date’ of the contract with Entergy.”) (alterations in original) (citation
omitted). Therefore, Boston Edison’s claim falls within the jurisdiction of this court.
Further, the government asserts that this court previously rejected Boston Edison’s
diminution-in-value theory as too speculative to provide a concrete injury sufficient for standing,
and the court must therefore “articulate a new basis for standing that is not rooted in the
discredited ‘diminution in value’ theory.” Def.’s Mot. at 14. The court is not persuaded. In
support of its motion, the government cites previous opinions calling Boston Edison’s damages
claims too speculative or an insufficient basis for standing. Def.’s Mot. at 14. As this court has
previously stated, however, the Federal Circuit’s 2011 ruling “foreclosed further litigation on one
issue: the viability of a present claim by Boston Edison under a diminution-in-value theory” but
left outstanding Boston Edison’s other claims, including its “nascent claim for decommissioning
costs” that would ripen on Pilgrim’s commencement of decommissioning. Boston Edison VII,
106 Fed. Cl. at 342 (emphasis added). Now that decommissioning has begun, see Compl. ¶ 34,
by the court’s previous reasoning, Boston Edison’s damages claim is no longer speculative.
Boston Edison has established standing for its claim in this court.
7
Previously, the court comprehensively addressed and rejected the government’s
argument that Boston Edison lacked standing. See, e.g., Boston Edison I, 64 Fed. Cl. at 179-86
(“Boston Edison has shown that it suffered injury in fact resulting from the government’s alleged
breach of the Standard Contract, and thus that it has standing to pursue its contractual claim.”).
8
The hearing date will be omitted from additional citations to the hearing transcript.
6
B. Failure to State a Claim
The government next contends that Boston Edison has failed to state a claim and requests
dismissal pursuant to RCFC 12(b)(6). Def.’s Mot. at 17-22. Specifically, the government argues
that the Boston Edison’s diminution in value claim was “previously litigated and . . . rejected by
the Federal Circuit.” Id. at 17. Boston Edison responds that “[t]he Federal Circuit’s ruling
rejecting the diminution of value damage theory Boston Edison had advanced in a prior related
case meant that Boston Edison could not bring its SNF claim at that time, not that Boston Edison
could never bring an SNF claim.” Pl.’s Resp. at 16 (emphasis omitted). The court concurs with
Boston Edison’s reasoning. As the court previously stated, “Boston Edison’s claim for
decommissioning costs . . . will fully mature only when particular mitigating costs are expended
at and on decommissioning.” Boston Edison VII, 106 Fed. Cl. at 341. The Federal Circuit did
not foreclose Boston Edison’s claim, but rather stated that damages for “anticipated future
nonperformance” were not recoverable at the time of the prior suit. Boston Edison VI, 658 F.3d
at 1367 (citing Indiana Michigan, 422 F.3d at 1376).
To the extent that the government challenges the factual basis for Boston Edison’s
damages as warranting dismissal, Def.’s Mot. at 19-20, the court finds that Boston Edison has
pled facts sufficient to state a claim. To survive a motion to dismiss, a complaint must “contain
sufficient factual matter” to “state a claim to relief that is plausible on its face.” Iqbal, 556 U.S.
at 678 (citation omitted). The Federal Circuit has repeatedly noted that plaintiffs are not required
to “allege details of the damages calculation in the complaint” provided that they assert facts
sufficient to support “at least some economic injury.” Oliva v. United States, 961 F.3d 1359,
1364 (Fed. Cir. 2020) (quoting Crow Creek Sioux Tribe v. United States, 900 F.3d 1350, 1354
(Fed. Cir. 2018), and In re Johnson & Johnson Talcum Power Prods. Mktg., Sales Pracs. &
Liab. Litig., 903 F.3d 278, 287 (3d Cir. 2018)) (emphasis removed). Boston Edison, in its
complaint, alleges that it paid over $40 million at the time of the sale into the Decommissioning
Trust Fund, and that Holtec, as a part of Pilgrim’s decommissioning, has already spent over $56
million from the fund. See, e.g., Compl. ¶ 42. These facts are sufficient to state a claim that
Boston Edison is entitled to damages and survive the government’s motion to dismiss.
CONCLUSION
For the foregoing reasons, defendant’s motion to dismiss under Rules 12(b)(1) and
12(b)(6) of the Rules of the Court of Federal Claims is DENIED. The government shall file its
answer by March 3, 2021.
It is so ORDERED.
s/ Charles F. Lettow
Charles F. Lettow
Senior Judge
7