NOT FOR PUBLICATION FILED
UNITED STATES COURT OF APPEALS MAR 29 2021
MOLLY C. DWYER, CLERK
U.S. COURT OF APPEALS
FOR THE NINTH CIRCUIT
JB CARTER ENTERPRISES, LLC, DBA No. 20-15271
ATM Merchant Systems,
D.C. No.
Plaintiff-Appellant, 2:18-cv-00394-JAD-NJK
v.
MEMORANDUM*
ELAVON, INC.,
Defendant-Appellee.
Appeal from the United States District Court
for the District of Nevada
Jennifer A. Dorsey, District Judge, Presiding
Argued and Submitted March 11, 2021
Las Vegas, Nevada
Before: NGUYEN and BENNETT, Circuit Judges, and HARPOOL,** District
Judge.
In this diversity action, JB Carter Enterprises, LLC, dba ATM Merchant
Systems (“ATMMS”) appeals the district court’s order granting summary
judgment to Elavon, Inc. (“Elavon”). We have jurisdiction under 28 U.S.C.
*
This disposition is not appropriate for publication and is not precedent
except as provided by Ninth Circuit Rule 36-3.
**
The Honorable M. Douglas Harpool, United States District Judge for
the Western District of Missouri, sitting by designation.
§ 1291. We affirm on the fraud claim relating to the Equinox L5200 equipment,
reverse as to all other claims, and remand.
We review the district court’s grant of summary judgment de novo, and we
must view “the evidence in the light most favorable to the nonmoving party.”
Devereaux v. Abbey, 263 F.3d 1070, 1074 (9th Cir. 2001) (en banc). Thus, “[t]he
evidence of the non-movant is to be believed, and all justifiable inferences are to
be drawn in [its] favor.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 255
(1986).
1. The district court granted summary judgment on ATMMS’s claims
for breach of contract and breach of the implied covenant of good faith and fair
dealing because it determined that the alleged oral agreement on which those
claims were based was barred by the integration clause in the parties’ written
agreement (“Master Agreement”). Under Georgia law, contract interpretation is a
question of law.1 Hall v. Ross, 616 S.E.2d 145, 147 (Ga. Ct. App. 2005). If the
contract language is “clear and unambiguous,” “the court simply enforces the
contract according to its clear terms.” Id. (quoting Woody’s Steaks, LLC v.
Pastoria, 584 S.E.2d 41, 43 (Ga. Ct. App. 2003)).
1
Neither party challenges the district court’s holding that Georgia law governs the
Master Agreement.
2
The integration clause states that the Master Agreement represents the entire
agreement between ATMMS and Elavon “with respect to the matters contained [in
the Master Agreement],” and that the Master Agreement may be amended only in a
writing signed by the parties. Nothing in the Master Agreement covers the subject
matter of the alleged oral agreement—that Elavon would provide ATMMS with
EMV (Europay, Mastercard, Visa) technology by October 1, 2015, (“Shift Date”),
and that the Equinox L5200 device would be EMV enabled. Though the Master
Agreement defines some terms broadly, such as “payment devices” and “merchant
services,” it does not use those terms in describing Elavon’s obligations owed to
ATMMS. For example, nowhere in the Master Agreement does it state that Elavon
will provide “payment devices” or “merchant services” to ATMMS. Further,
although Schedule C was purportedly updated to include the Equinox L5200, the
updated schedule presumably, like the original, listed only the price of the device
and did not specify its functionality, including whether it would be EMV enabled,
or any delivery schedule or terms for ordered equipment. Equipment features or
functionality and equipment delivery schedules are outside the terms and scope of
the Master Agreement.2
Because the terms of the Master Agreement do not encompass the subject
2
It is also illogical that the parties would need to amend the Master Agreement to
reflect agreed-upon delivery dates or features for ordered equipment.
3
matter of the alleged oral agreement, the integration clause does not bar ATMMS’s
contract-based claims. Thus, the district court erred in granting summary judgment
on the contract-based claims.
We are unpersuaded by Elavon’s alternative argument that the contract-
based claims fail because ATMMS presents no evidence of consideration
supporting the alleged oral agreement. “Consideration is the exchange of a
promise or performance, bargained for by the parties.” Jones v. SunTrust Mortg.,
Inc., 274 P.3d 762, 764 (Nev. 2012).3 ATMMS has sufficiently identified
consideration—ATMMS bought 197 Equinox L5200s and agreed to keep Elavon
as its processor, and in exchange, Elavon promised that it would provide ATMMS
with EMV by the Shift Date and that the Equinox L5200s would be EMV enabled.
2. ATMMS alleges that Elavon provided ATMMS with various false
dates by which ATMMS could process EMV personal identification number (PIN)
debit transactions using Elavon’s processing platform (“EMV Fraud Claim”), and
that Elavon falsely represented that the Equinox L5200 device would be the EMV
PIN pad device that would work with Elavon’s processing platform (“Equipment
Fraud Claim”). The district court granted summary judgment on the EMV Fraud
Claim because ATMMS presented no evidence that Elavon knowingly
3
Elavon concedes that it is immaterial whether we apply Georgia or Nevada law in
analyzing whether ATMMS has sufficiently identified consideration.
4
communicated false target dates to ATMMS. We disagree.
ATMMS’s general manager, Michael Poggi, testified that Elavon employees
told him that ATMMS “would have EMV” before the Shift Date. But Eric
Przybylek, an Elavon employee, testified that Elavon never intended to provide the
capability to process EMV PIN debit transactions using Elavon’s processing
platform by the Shift Date. Viewing this evidence in ATMMS’s favor, a factfinder
could reasonably infer that the statements made to Poggi were knowingly false. A
factfinder could also reasonably infer from other evidence that Elavon knew at
least some target dates provided to ATMMS after the Shift Date were false.
Elavon provided target dates for EMV PIN debit in 2016, yet three years later,
Elavon was still working on EMV PIN debit. A target date of months (or even a
year) versus three years is very different. The disparities between Elavon’s target
dates suggest that Elavon may have known that its target dates in 2016 were false,
or, at the very least, that Elavon had an insufficient basis for making the
representations. See Bulbman, Inc. v. Nev. Bell, 825 P.2d 588, 592 (Nev. 1992)
(per curiam) (setting forth the elements of a fraud claim, which include
“[d]efendant’s knowledge or belief that the representation is false (or insufficient
basis for making the representation)” (emphasis added)). Elavon also chose to
prioritize its Canada project over EMV PIN debit, and the Canada project took two
years to complete. Construing this evidence in ATMMS’s favor, Elavon
5
presumably knew that it would not complete EMV PIN debit so long as the Canada
project was ongoing, and thus any EMV PIN debit target dates preceding the
completion of the Canada project may have been knowingly false.
Because there is evidence supporting an inference that Elavon knowingly
communicated false target dates to ATMMS, the district court erred in granting
summary judgment on the EMV Fraud Claim.
As to the Equipment Fraud Claim, “[w]e may affirm the grant of summary
judgment on any basis supported by the record,” Newton v. Diamond, 388 F.3d
1189, 1192 (9th Cir. 2004), and the parties have fully briefed the issue. We affirm
the district court’s grant of summary judgment to Elavon on the Equipment Fraud
Claim because ATMMS presents no evidence that Elavon knowingly made false
representations about the Equinox L5200. ATMMS bought the devices based on
representations made in 2013. ATMMS points to no evidence showing that Elavon
knew that its representations about the Equinox L5200 were false when made in
2013.4
4
During oral argument, ATMMS’s counsel pointed to Lisa Carmichael’s
deposition testimony. Oral Arg. at 3:40–4:52,
https://www.ca9.uscourts.gov/media/view_video.php?pk_vid=0000019011. Her
testimony, however, does not support that Elavon knew its representations about
the Equinox L5200 were false when made in 2013. First, her testimony is
ambiguous as to whether she was referring to Elavon’s decisions about the
Equinox L5200 or providing amnesty. Second, even assuming her testimony was
about the Equinox L5200, it shows only that Elavon decided sometime in 2015 to
push back supporting the Equinox L5200 until 2016.
6
3. The district court held that the economic loss doctrine barred
ATMMS’s negligent misrepresentation claim because, although ATMMS alleged
noneconomic damages to its business reputation, it offered no evidence supporting
that allegation. The record, however, contains evidence showing that ATMMS lost
existing and new business because it did not have EMV PIN debit by the Shift
Date. Construing this evidence in ATMMS’s favor, a factfinder could reasonably
infer that ATMMS suffered some amount of reputational harm to its business.
Thus, the district court erred in granting summary judgment on the negligent
misrepresentation claim.5
4. The district court granted summary judgment on the claims for
wrongful interference with contractual and prospective business relations because
it determined that ATMMS presented no evidence that Elavon specifically
intended to disrupt or harm ATMMS’s existing or prospective business relations.
Under Nevada law, intent is a necessary element of both torts. J.J. Indus., LLC v.
Bennett, 71 P.3d 1264, 1267 (Nev. 2003) (per curiam); Las Vegas-Tonopah-Reno
Stage Line, Inc. v. Gray Line Tours of S. Nev., 792 P.2d 386, 388 (Nev. 1990) (per
curiam). The Nevada Supreme Court has adopted the definition of intent in the
Restatement (Second) of Torts: the “interference with the other’s prospective
5
We reject ATMMS’s other arguments challenging the district court’s application
of the economic loss doctrine.
7
contractual relation is intentional if the actor desires to bring it about or if he knows
that the interference is certain or substantially certain to occur as a result of his
action.” Gray Line Tours, 792 P.2d at 388 (emphasis added) (quoting Restatement
(Second) of Torts § 766B cmt. d (Am. L. Inst. 1979)).
Construing the evidence in the light most favorable to ATMMS, the
evidence shows that Elavon knew with substantial certainty that delaying EMV
PIN debit would interfere with ATMMS’s existing and prospective business
relationships. Thus, the district court erred in granting summary judgment on the
tortious interference claims.6
Each party shall bear its own costs on appeal.
AFFIRMED IN PART, REVERSED IN PART, AND REMANDED.
6
We decline to consider Elavon’s argument that ATMMS presented no evidence
that it had a prospective business relationship with any third party, so as to allow
the district court to address it in the first instance on remand.
8