Young, J. v. Lippl, J.

J-A28003-20

                                   2021 PA Super 56

    JANE YOUNG                                 :   IN THE SUPERIOR COURT OF
                                               :        PENNSYLVANIA
                       Appellant               :
                                               :
                                               :
                v.                             :
                                               :
                                               :
    JOHN E. LIPPL., P.E.                       :   No. 227 WDA 2020

               Appeal from the Judgment Entered March 10, 2020
       In the Court of Common Pleas of Allegheny County Civil Division at
                         No(s): Case no. GD-12-019194

    JANE YOUNG                                 :   IN THE SUPERIOR COURT OF
                                               :        PENNSYLVANIA
                                               :
                v.                             :
                                               :
                                               :
    JOHN E. LIPPL, P.E.                        :
                                               :
                       Appellant               :   No. 499 WDA 2020

               Appeal from the Judgment Entered March 10, 2020
       In the Court of Common Pleas of Allegheny County Civil Division at
                             No(s): GD12-019194


BEFORE: OLSON, J., MURRAY, J., and McCAFFERY, J.

OPINION BY OLSON, J.:                                FILED: March 31, 2021

        In this cross-appeal, Jane Young (“Young”) and John E. Lippl, P.E.

(“Lippl”) appeal different aspects of the March 10, 2020 judgment entered

upon a jury verdict in favor of Young in the amount of $114,947.99. 1 We
____________________________________________


1 A review of Young’s notice of appeal demonstrates that Young appealed the
January 17, 2020 order granting, in part, Lippl’s post-trial motion to correct a
mathematical error in the amount of the jury verdict. “[A]n appeal to this
Court can only lie from judgments entered subsequent to the trial court's
J-A28003-20



affirm. We remand this case, however, for the limited purpose of calculating

and awarding post-judgment interest as discussed, infra.

       The trial court summarized the factual and procedural history as follows:

       Beginning in April 2008, [Young] and her former husband, Bruce
       Goldblatt ("Goldblatt"), entered into an agreement with [a]
       builder[,] Custom Homes, Inc. ("Custom Homes")[,] for the
       construction of a [house] in Eighty-Four, Pennsylvania. Numerous
       disputes arose such that [Young] refused to allow Custom Homes
       to finish construction, resulting in [Custom Homes commencing]
       an arbitration action [against Young and Goldblatt] before the
       America Arbitration Association ("AAA").

       At the [arbitration hearing, Lippl2] argued on behalf of [Young]
       and Goldblatt that the [house] was continuing to settle and
       required stabilization due to Custom Homes' failure to dig to firm
       clay after charging for extraordinary ground preparation.

       [Lippl] consulted with John L. Suhrie, P.E. ("Suhrie") to provide
       expert analysis of and a detailed report [(“the Suhrie Report”)] on
       the claims against Custom Homes for use at [the] arbitration
       [hearing. Lippl] did not obtain [geotechnical] soil testing in
       support of [Young’s] and Goldblatt's claims.

       Arbitrator David Scotti,[Esquire (“Arbitrator”)] issued an award on
       October 14, 2010[,] in favor of Custom Homes in the amount of
       $64,032.21. The Arbitrator found that [Young] and Goldblatt []
       wrongfully terminated [their contract with] Custom Homes, [and
       denied the builder an] opportunity to correct any issues or to
____________________________________________


disposition of any post-verdict motions, not from the order denying post-trial
motions.” Johnston the Florist, Inc. v. TEDCO Constr. Corp., 657 A.2d
511, 514 (Pa. Super. 1995) (citation omitted). Here, the judgment in favor
of Young and against Lippl was entered March 10, 2020. Therefore, Young’s
notice of appeal shall be treated as filed on March 10, 2020, and as an appeal
from the entry of judgment. See McEwing v. Lititz Mut. Ins. Co., 77 A.3d
639, 645 (Pa. Super. 2013). The caption has been corrected accordingly.

2 Lippl is an attorney licensed to practice law in the Commonwealth of
Pennsylvania. Lippl is also a professional engineer licensed to practice in the
Commonwealth of Pennsylvania.


                                           -2-
J-A28003-20


     complete the [construction] project. The Arbitrator dismissed
     [Young’s] counterclaims for[,] inter alia[,] negligent construction,
     which asserted that Custom Homes' work was defective and
     incomplete. Following the award, [Lippl] was terminated as
     counsel by [Young] and Goldblatt.

     [Young] hired GeoMechanics, Inc. ("GeoMechanics"), an
     engineering company, to conduct [geotechnical] soil testing. As
     a result [of the soil testing, Young] learned that Custom Homes
     had poorly compacted the fill material under her [house].
     Moreover, GeoMechanics exposed the footers of the foundation
     and discovered that Custom Homes had not dug deep enough to
     reach firm clay.

     [Young] then filed suit on May 1, 2012[,] against Nottingham
     Township's building inspector, Code.Sys Consulting, Inc.
     ("Code.Sys"), alleging that it should have required an engineered
     caisson foundation rather than a spread footer foundation given
     the soil conditions. [Young] claimed damages for repair costs
     based on [building] code violations including[,] but not limited to,
     failure of the foundation system, permanent loss of use of the
     property, depreciation in value and marketability of the property,
     an inability to obtain refinancing[,] and escalating expert and
     engineering fees. [On September 27, 2017, a] jury ruled in favor
     of [Young and awarded her] $412,750.00 [in damages].

     In lieu of an appeal, [Young and Code.Sys] settled for
     $455,250.00 and executed a settlement and release agreement
     that specifically discharged any claims [Young] had or may have
     had against Code.Sys. The language in the agreement stated that
     [Young],

        ". . . forever discharges [Code.Sys] from any and all
        liabilities, charges, claims, causes of action or suits, of
        whatever kind or nature, absolute, contingent, unliquidated
        or otherwise, including, but not limited to, any rights,
        obligations or claims arising out of or related to the lawsuit,
        which liabilities, charges, claims, causes of action or suits
        [Young] and her affiliates, agents, representatives, heirs,
        executors, attorneys, successors and assigns can, shall or
        may have against [Code.Sys] by reason of any matter,
        cause or thing whatsoever, occurring prior to the date of this
        agreement."

     Thus, [Young] satisfied any claim she had or may have had
     against Code.Sys for the defective foundation and subsequent

                                     -3-
J-A28003-20


     repairs. The [settlement and release] agreement also discharged
     Code.Sys from any claims that [Lippl] may have had against it
     arising out of or related to [Young’s] lawsuit.

     [Young] filed suit against [Lippl] in December 2012[,] for legal
     malpractice while the Code.Sys litigation was pending.

     [Young] claimed that [Lippl’s] failure to obtain [geotechnical] soil
     testing caused her and Goldblatt to lose at arbitration. She also
     asserted that the Suhrie [R]eport had recommended that the
     [geotechnical soil] testing be done. [Young] further argued that
     [Lippl] could have avoided the finding of improper termination had
     he shown that Custom Homes' failure to dig to a depth of firm clay
     was not only a material breach but also fraudulent.

     [Lippl] raised numerous affirmative defenses and argued that any
     reference to [geotechnical] soil testing in the Suhrie [R]eport was
     related to the risk of future settlement and that such testing would
     not have revealed that the foundation problems were incapable of
     repair.[FN1] [Lippl] also asserted that the testing would not have
     affected the arbitration award since the Arbitrator determined that
     [Young] and Goldblatt had wrongfully terminated Custom Homes.
     In fact, it was [Young’s] and Goldblatt's prior attorney[,] and not
     [Lippl,] who had recommended terminating Custom Homes.

        [FN1] In this case, [Young] alleged that she was precluded
        from seeking recovery against Custom Homes for the total
        loss of her [house] because of the doctrines of res judicata
        and collateral estoppel.   [Young] alleged that Custom
        Homes would not have been able to cure the defective
        construction because the [house] was now a total loss.
        However, this did not preclude [Young] from seeking
        damages against Code.Sys for repairs to the foundation.

     The [trial] court granted [Young’s] motion in limine to preclude
     any evidence of or reference to the Code.Sys litigation.[FN2]
     Therefore, the jury had no knowledge of [Young’s] prior recovery
     against Code.Sys. [Young] was also precluded from offering
     evidence that was not in existence or capable of being generated
     in August 2010.

        [FN2] The [trial] court also denied [Lippl’s] motion for
        judgment on the pleadings without prejudice for [Lippl] to
        argue to offset any damages awarded [in the instant case
        by the amount previously awarded] in the September 27,
        2017 jury verdict [against Code.Sys.]

                                    -4-
J-A28003-20


       A seven-day trial was held beginning September 17, 2019. The
       jury found for [Young] and awarded her $368,401.14 in damages.
       As noted on the verdict slip, the award consisted of $253,453.15
       for "work defective due to structural/foundation issues and
       repairs," $13,000.00 for the Arbitrator's fees, and $37,915.78 for
       legal fees. Also included [in the award for damages] was the
       $64,032.21 arbitration award.

       Following the dismissal of the jury, [Young] made an oral motion
       to mold the verdict. The [trial] court granted [Young’s] motion to
       mold the verdict based upon [its] assumption that the jury had
       not included the arbitration award in its calculation of the total
       judgment. Accordingly, the [trial] court entered a docketed
       verdict in the amount of $432,433.35.

Trial Court Opinion, 3/16/20, at 1-4 (extraneous capitalization and record

citations omitted).

       Lippl filed post-trial motions requesting that the trial court correct a

mathematical error in the molded verdict and grant judgment notwithstanding

the verdict, pursuant to Pa.R.Civ.P. 227.1. Young filed a post-trial motion

requesting the trial court award her pre-arbitration interest in the amount of

$127,384.20 and post-arbitration interest in the amount of $233,087.50.3 On

January 17, 2020, the trial court granted Lippl’s post-trial motion regarding

the mathematical error in the molded verdict and reduced the verdict to

$368,401.14. That same day, the trial court granted, in part, Lippl’s post-trial

motion for judgment notwithstanding the verdict and further reduced the

verdict to $114,947.99. The trial court also denied Lippl’s post-trial motion
____________________________________________


3 Young’s calculations for pre-arbitration and post-arbitration interest were
based upon the $432,433.35 molded verdict. Young requested pre-arbitration
interest at a rate of 12 per centum per annum and post-arbitration interest at
a rate of 6 per centum per annum.


                                           -5-
J-A28003-20



for judgment notwithstanding the verdict, in part, as to Lippl’s request to

overturn the verdict in its entirety.          Finally, that same day, the trial court

denied Young’s post-trial motion for pre-arbitration and post-arbitration

interest.

       On February 14, 2020, Young filed notices of appeal from the trial court’s

January 17, 2020 orders that (1) denied her post-trial motion for

pre-arbitration and post-arbitration interest, (2) granted, in part, Lippl’s

post-trial motion for judgment notwithstanding the verdict and reduced the

verdict to $114,947.99, and (3) granted Lippl’s post-trial motion request to

correct a mathematical error in the verdict. In a March 6, 2020 per curiam

order, this Court directed Young to file a praecipe to enter the judgment. The

judgment was entered on March 10, 2020. On April 14, 2020, Lippl filed a

notice of appeal from the entry of judgment against him in the amount of

$114,947.99.4       Both Young and Lippl filed concise statements of errors

complained of on appeal pursuant to Pa.R.A.P. 1925(b), and the trial court

subsequently filed separate Rule 1925(a) opinions.

       Lippl raises the following issues for our review:


____________________________________________


4 In a Second Supplemental Order entered on April 1, 2020, our Supreme
Court suspended “all time calculations for purposes of time computation
relevant to court cases or other judicial business, as well as time deadlines”
through April 30, 2020, due to the COVID-19 pandemic. See In re General
Statewide Emergency, Judicial Docket Nos. 531 and 532, Second
Supplemental Order, 4/1/20. Lippl’s appeal from the entry of judgment,
therefore, was timely filed on April 14, 2020.


                                           -6-
J-A28003-20


        1.    Whether the trial court erred in refusing to dismiss this case
              for failure to join an indispensable party, because the case
              was filed by only one of two persons having a joint interest
              in the subject matter of the case[?]

        2.    Whether the trial court erred in denying the request for
              judgment notwithstanding the verdict, because the verdict
              was not supported by sufficient evidence[?]

        3.    Whether the trial court erred in denying the request for
              judgment notwithstanding the verdict, because of an
              impermissible variance between the complaint and the
              theories at trial[?]

Lippl’s Brief at 4.

        Young raises the following issues for our review:

        1.    Did the trial court err in reducing the verdict in favor of
              [Young] by $253,453.15 based on the judgment that was
              awarded in [Young’s] lawsuit against Code.Sys?

        2.    Where the jury determined that, but for [Lippl’s] negligence,
              [Young] would have obtained an arbitration award in the
              amount of $432,433.35, did the trial court err in denying
              [Young’s] post-trial motion to mold the verdict to add
              interest on the award she should have received in the
              underlying arbitration?

Young’s Brief at 11.5

        We begin by addressing the issues raised by Lippl. All three of Lippl’s

issues challenge the trial court’s denial of his request for judgment

notwithstanding the verdict.          Our standard of review in such cases is

well-settled. An appellate court will reverse a trial court’s denial, or grant, of

a request for judgment notwithstanding the verdict only when the trial court

____________________________________________


5   For ease of disposition, Young’s issues have been re-organized.


                                           -7-
J-A28003-20



abused its discretion or erred as a matter of law. Rost v. Ford Motor Co.,

151 A.3d 1032, 1042 (Pa. 2016).

       In his first issue, Lippl challenges the order denying his request for

judgment notwithstanding the verdict on the grounds that the trial court failed

to join Goldblatt6 as an indispensable party in Young’s legal malpractice action

against Lippl. Id. at 14-29.

       The failure to join an indispensable party implicates the trial court’s

subject matter jurisdiction and presents a question of law.             Orman v.

Mortgage I.T., 118 A.3d 403, 406 (Pa. Super. 2015). As such, our standard

of review is de novo and our scope of review plenary. Id.

       A party is indispensable when his or her rights are so connected
       with the claims of the litigants that no decree can be made without
       impairing those rights. If no redress is sought against a party,
       and its rights would not be prejudiced by any decision in the case,
       it is not indispensable with respect to the litigation. [This Court
       has] consistently held that a trial court must weigh the following
       considerations in determining if a party is indispensable to a
       particular litigation[:]

          1.     Do absent parties have a right or an interest related
                 to the claim?

          2.     If so, what is the nature of that right or interest?

          3.     Is that right or interest essential to the merits of the
                 issue?



____________________________________________


6 At the time Young filed a praecipe for writ of summons to initiate her action
against Lippl on October 11, 2012, Young and Goldblatt were engaged in a
divorce action. Goldblatt commenced a divorce action against Young on April
28, 2010, and a final divorce decree was entered on April 19, 2016.


                                           -8-
J-A28003-20


         4.    Can justice be afforded without violating the due
               process rights of absent parties?

      In determining whether a party is indispensable, the basic inquiry
      remains whether justice can be done in the absence of a third
      party.

Id. at 406-407 (quotation marks, original brackets, and citations omitted).

      Lippl contends that Young and Goldblatt were both parties to the

construction agreement with Custom Homes, that they jointly retained Lippl

to represent them in the arbitration action, and that the arbitration award was

entered jointly against both Young and Goldblatt and viewed as a joint debt

in their subsequent divorce. Lippl’s Brief at 21. Lippl argues that, “[i]t follows

as a matter of logic that, because the cause of action against Custom Homes,

and the adverse result in the litigation with Custom Homes, were shared

jointly by Young and Goldblatt, so too is the cause of action for legal

malpractice arising from the claimed loss of that joint cause of action.” Id. at

22 (emphasis omitted). Lippl asserts that Goldblatt is an indispensable party

because, inter alia, “justice cannot be afforded without violating Goldblatt’s

rights because [] his interests were not represented, protected, or accounted

for in this [legal malpractice action] and the [subsequent] judgment

entered[.]” Id. at 23.

      In determining that Goldblatt was not an indispensable party in Young’s

legal malpractice action against Lippl, the trial court stated,

      Goldblatt had no rights or interests in [Young’s] claim against
      [Lippl for legal malpractice]. Although Goldblatt was a party to
      the April 2008 contract with Custom Homes, he subsequently
      renounced his spousal interest in the property and signed a waiver

                                      -9-
J-A28003-20


      of spousal interest and spousal subordination and consent.
      Additionally, the Custom Homes[’] collection action was filed
      solely against [Young], and she further testified that she alone
      paid the $64,032.21 award.

      Notably, Goldblatt was deposed in this matter and his video
      deposition was played at trial. Goldblatt expressed no interests
      or rights in this lawsuit. Though he was aware of the pending
      litigation, he never asserted any claims against [Lippl]. Goldblatt
      also testified that he expected [Young] to pay any judgment that
      resulted from the [arbitration].

      Further, [Lippl] specifically acknowledged that his joint retention
      [by Young and Goldblatt] in no way lessoned the duties [he] owed
      individually to [Young]. Both [Young] and Goldblatt had[ the right
      to terminate [Lippl] at any time, either jointly or severally.
      Moreover, there is no Pennsylvania case law that requires
      Goldblatt to be joined as a party simply because he and [Young]
      were co-clients.

      Clearly, the basic inquiry in the joinder analysis can be answered
      in the affirmative. Justice can [be,] and has been[,] afforded
      without the joinder of [Young’s] former spouse as a party in this
      matter.

Trial Court Opinion, 6/11/20, at 7.

      A review of the record demonstrates that Young filed a cause of action

against Lippl for legal malpractice arguing that, due to Lippl’s professional

negligence, Young did not prevail in her prior claim against Custom Homes for

the defective construction of her house.       Young’s Complaint, 12/28/12, at

¶¶19-33.   Young’s prior action against Custom Homes stemmed from the

defective construction of a house that, albeit titled in both Young’s and

Goldblatt’s names, was solely Young’s property by virtue of the prenuptial

agreement between Young and Goldblatt and the waiver of spousal interest in




                                      - 10 -
J-A28003-20



the property executed by Goldblatt.7           See Goldblatt v. Young, 2017 WL

3276525, at *13 (Pa. Super. 2017) (unpublished memorandum) (stating,

“[t]he only reason [Goldblatt’s] name was on the property [deed] was so that

[Young] could obtain financing”). It is axiomatic that the legal malpractice

cause of action, which derived from Young’s loss of her defective construction

claims against Custom Homes, was Young’s sole cause of action to assert, as

well.8 We concur with the trial court that Goldblatt had no right or interest in
____________________________________________


7 Goldblatt and Young executed the agreement with Custom Homes for the
construction of Young’s house on April 12, 2008. On April 15, 2008, Goldblatt
executed the waiver of his spousal interest in the house.

8 Lippl asserts that, “[b]ecause Young and Goldblatt jointly had a cause of
action against Custom Homes, it followed that any debt or adverse judgment
associated with the pre-separation lawsuit was also one owed by them jointly.”
Lippl’s Brief at 19. This contention overlooks several important features of
the legal interests at play by the time Young commenced her legal malpractice
claim against Lippl. First, even within the context of the arbitration case,
Young’s claim for defective construction against Custom Homes was asserted
solely in her own right as the only party with an interest in the house. Second,
although Goldblatt may have been jointly liable for breach of contract at the
conclusion of the arbitration proceeding because he executed the agreement
with Custom Homes along with Young, his liability for the arbitration award
did not negate the legal effect of his waiver of his ownership interest in the
house. Third, in view of Goldblatt’s waiver of any interest in the house before
Young’s commencement of the legal malpractice action, Goldblatt lacked any
distinct, identifiable legal interest in the outcome of Young’s professional
negligence claims against Lippl. In the prior divorce litigation between Young
and Goldblatt, this Court reasoned that the mortgage secured by the property
was Young’s sole responsibility because it stayed with and attached to the
property and Goldblatt relinquished any claim or interest he had in the house.
Similarly, we said that Young solely retained any claims for defective
construction of the house because such claims stayed with and attached to
the property. Lastly, Young’s satisfaction of the arbitration award suggests
strongly that she retained an exclusive interest in any recovery stemming from
alleged legal malpractice which led to that judgment.


                                          - 11 -
J-A28003-20



Young’s legal malpractice claim because it was directly tied to the real estate,

which was solely Young’s property.             Therefore, Goldblatt was not an

indispensable party in the instance case. Consequently, Lippl’s first issue is

without merit.

      Lippl’s second issue challenges the order denying his request for

judgment notwithstanding the verdict on the grounds that the evidence was

insufficient to support a finding of causation. Lippl’s Brief at 29-36.

      The denial of a request for judgment notwithstanding the verdict based

upon insufficient evidence is appropriate if, reading the record in the light most

favorable to the verdict winner and affording that party the benefit of all

reasonable inferences, a court would conclude that there is sufficient evidence

to sustain the verdict. Rost, 151 A.3d at 1042. In reviewing a challenge to

the sufficiency of the evidence, an appellate court will reject all evidence that

does not support the verdict. Id.

      In order to establish a claim of legal malpractice, a
      plaintiff/aggrieved client must demonstrate three basic elements:

         [1.]    employment of the attorney or other basis for a duty;

         [2.]    the failure of the attorney to exercise ordinary skill
                 and knowledge; and

         [3.]    that such negligence was the proximate cause of
                 damage to the plaintiff.

      An essential element to this cause of action is proof of actual loss
      rather than a breach of a professional duty causing only nominal
      damages, speculative harm[,] or the threat of future harm.
      Damages are considered remote or speculative only if there is
      uncertainty concerning the identification of the existence of
      damages rather than the ability to precisely calculate the amount


                                      - 12 -
J-A28003-20


      or value of damages. In essence, a legal malpractice action in
      Pennsylvania requires the [aggrieved client] to prove that he[, or
      she,] had a viable cause of action against the party he[, or she,]
      wished to sue in the underlying case and that the attorney he[, or
      she,] hired was negligent in prosecuting or defending that
      underlying case (often referred to as proving a “case within a
      case”).

Kituskie v. Corbman, 714 A.2d 1027, 1029-1030 (Pa. 1998) (citations

omitted).

      Here, Lippl asserts that, “Young’s theory of liability at trial was that Lippl

should have procured geotechnical testing to convince the arbitrator that the

foundation was not built on firm clay” and that if Lippl had procured the

geotechnical testing, Young would have prevailed in her cause of action

against Custom Homes. Lippl’s Brief at 31. Lippl contends that Young “failed

to present sufficient evidence that obtaining geotechnical testing would have”

caused Young to prevail in her claim against Custom Homes. Id. Lippl asserts

that his failure to procure geotechnical testing of the foundation’s soil base

was not the reason the arbitrator found in favor of Custom Homes and against

Young in the arbitration matter. Id. at 34. Rather, Young did not prevail in

her claim against Custom Homes because Young and Goldblatt wrongfully

terminated their agreement with Custom Homes. Id. at 34.

      In finding sufficient evidence to demonstrate the element of causation,

the trial court stated,




                                      - 13 -
J-A28003-20


       Attorney Gary Hunt,[Esquire (“Attorney Hunt”),] a civil trial
       lawyer, was qualified as an expert[9] and opined as to [Lippl’s]
       representation of [Young] during the [arbitration hearing].

                                           ...

       Attorney Hunt ultimately concluded that[] had [Lippl] obtained
       geotechnical testing[,] he would have been able to show that not
       only did Custom Homes materially breach the contract, but also
       that it committed fraud in the process.[10]         Further, the []
       Arbitrator would not have found [Young’s] termination of Custom
       Homes to be improper but for [Lippl’s] failure to prove the material
       breach and subsequent fraud. Based on the testimony of Attorney
       Hunt, [Young] established her 'case within a case' by proving she
       had a viable cause of action against Custom Homes. [Young] also
       established cause[-]in[-]fact through the opinion of Attorney Hunt
       that she would have won at the [arbitration hearing] but for
       [Lippl’s] failure to obtain the geotechnical testing to prove the
       material breach.

       The Jury found Attorney Hunt to be credible and answered
       Questions #2 and #3 of the verdict slip in the affirmative, which
       read:

          [2.]   Do you find that, but for [] Lippl's negligence, [Young]
                 would have avoided the Arbitrator's Award in the sum
                 of $64,032.21?

          [3.]   Do you find that, but for [] Lippl's negligence, [Young]
                 would have prevailed in the Arbitration Action and
                 obtained a monetary award in [her] favor?[]



____________________________________________


9Attorney Hunt was qualified as an expert in litigation, construction law, AAA
arbitration, and jury trials. N.T., 9/18/19, at 10.

10 In the arbitration matter, Young’s causes of action against Custom Homes
included a breach of contract claim for failure to construct the home in
accordance with the parties’ agreement, together with a claim for fraud based
upon allegations that Custom Homes invoiced Young for work that had not
been completed, including work related to the installation of “a solid
foundation.” N.T., 9/18/19, at 29-30.


                                          - 14 -
J-A28003-20


      [Young] established, cause-in-fact by showing that her harm
      would not have come about but for [Lippl’s] negligence.

Trial Court Opinion, 6/11/20, at 9-10 (record citations omitted).

      A     review   of   the   record   demonstrates   that,   regarding   Young’s

counter-claim against Custom Homes, the Arbitrator stated,

      [Young] has made a series of claims related to work that was
      allegedly defective or not complete. The claims made do not
      consider the cost to [Custom Homes] in performing this work. The
      damages sought are based on having an outside contractor
      perform this work. However, [Young] wrongfully terminated
      [Custom Homes] and[,] therefore[, Custom Homes] was
      wrongfully denied the opportunity to correct or complete the work
      complained of by [Young]. Accordingly, [Custom Homes] is
      discharged of its obligation to perform under the [construction]
      contract and these claims are denied.

Trial Exhibit 12C (Award of Arbitrator), at 2 (extraneous capitalization

omitted).

      In explaining that Lippl’s failure to obtain geotechnical testing of the soil

conditions supporting the foundation was the proximate cause of Young’s

inability to obtain a judgment against Custom Homes for its defective

construction of her house, Attorney Hunt explained,

      if the geotechnical studies had been performed as [Suhrie] said
      they should have been, then we would have know[n] what they
      show[ed about the soil conditions underlying the foundation].
      That question mark would have been removed. The arbitrator
      would have heard evidence that this [house was not] built on firm
      clay. This [house] was built on loose[,] and to a great extent[,]
      unconsolidated soil[. That is] why the [rear portion of the house]
      is falling away from the rest of the house[. T]he arbitrator would
      have had more than sufficient evidence to conclude that there was
      a material breach of [the construction] contract, and if there was
      a material breach of this contract[, then] the contract could be
      terminated.     The arbitrator would have had everything the

                                         - 15 -
J-A28003-20


      arbitrator needed to reach the conclusion that there was a
      material breach, and therefore, the basis that the arbitrator used
      to essentially dismiss [] Young's claims would have been taken
      away[. Young would be entitled to a judgment in her favor against
      Custom Homes].

N.T., 9/18/19, at 66.      Attorney Hunt agreed with the Suhrie Report

recommendation that geotechnical testing was necessary to identify the cause

of continuing settlement of the house and to prove Young’s claims against

Custom Homes.      Id. at 36; see also Suhrie Report, 3/30/10, at § 4.1.7

(stating, “This type of crack indicates that settlement of the house foundation

is occurring toward the rear. This is a potentially serious problem given the

amount of fill and the slope of the embankment behind the house. Further

geotechnical investigation is required to assess this risk.”).   GeoMechanics

performed geotechnical testing of the soil base underlying the foundation and

concluded, inter alia, that the fill beneath the house had “low strength and

high compressibility” for purposes of foundational support and presented a

risk for future differential settlement of the house.        See Geotechnical

Engineering Investigation Report, 2/4/13, at 16. Attorney Hunt opined that

the geotechnical testing established that Custom Homes did not excavate to

firm clay as required by the construction contract and that the house was built,

instead, on loose, unconsolidated fill.   N.T., 9/18/19, at 38-39; see also

Construction Contract – Description of Materials, 2/21/08 (requiring, that

Custom Homes excavate “to firm clay”). Attorney Hunt explained that Custom

Homes’ failure to excavate to firm clay constituted a material breach of the

construction contract.   N.T., 9/18/19, at 58.      Moreover, Custom Homes

                                     - 16 -
J-A28003-20



invoiced Young for the additional charge of over-excavation to reach firm clay,

which amounted to fraud in Attorney Hunt’s opinion. Id. at 61-62. Attorney

Hunt opined to a reasonable degree of legal and professional certainty that

Lippl failed to identify the seriousness of the Suhrie Report recommendation

to obtain geotechnical testing of the soil base underlying the foundation to

determine the cause of continuing settlement prior to the arbitration hearing.

Id. 68-69. Explaining Custom Homes’ election to build the house on loose,

unconsolidated fill and its failure to excavate to firm clay were critical

components of the arbitration hearing, Attorney Hunt explained, and Lippl’s

failure to obtain the geotechnical testing, despite the Suhrie Report

recommendation, was the reason Young did not prevail in her counter-claims

against Custom Homes. Id.

      In considering all of the evidence in the light most favorable to Young,

as verdict winner, we find there was sufficient evidence to allow the jury, as

trier-of-fact, to find that Lippl’s legal negligence was the proximate cause of

Young’s failure to prevail in her causes of action against Custom Homes.

Consequently, Lippl’s second issue is without merit.

      Lippl’s third issue challenges the order denying his request for judgment

notwithstanding the verdict on the grounds that there was a material variance

between Young’s complaint and proof at trial. Lippl’s Brief at 36-48.

      A variance denotes difference and in reference to legal
      proceedings[,] it refers to a disagreement or difference between
      the allegations made and the proof shown, not in the sense that
      there is a failure of proof, but that, contrary to the fundamental
      principle of good pleading and practice, the proof fails to materially

                                     - 17 -
J-A28003-20


      correspond to the allegations. A material variance consists of a
      departure in the evidence from the issues on which the cause of
      action must depend.

      For purposes of determining whether a claimed or apparent
      discrepancy between pleadings and proof constitutes a variance,
      the entire pleadings and evidence should be considered.
      Generally, in order to constitute a variance, the discrepancy must
      exist between the allegations and proofs of the particular party,
      with the result that a party is not permitted to introduce evidence
      that is inconsistent with or fails to correspond to the allegations
      made by that party.

      The modern rules of pleading and practice are relatively liberal.
      Consequently, the impact of variance may be diminished by the
      preference for a liberal[,] if not informal[,] evaluation of pleadings
      emphasizing the determination of cases based upon their merits
      rather than based on mere technicalities, which policy, for
      example, may allow a party to cure a variance by offering, during
      or after trial, to amend the pleadings to conform to the proof.

      General pleading allegations which are not objected to because of
      their generality, may have the effect of extending the available
      scope of a party's proof, such that the proof would not constitute
      a variance, beyond that which the party might have been
      permitted to give under a more specific statement.

Graham v. Campo, 990 A.2d 9, 13-14 (Pa. Super. 2010) (ellipsis omitted),

appeal denied, 16 A.3d 504 (Pa. 2011). “Although the allegata and probata

may not entirely agree, if the defendant is not misled, and the variance

does not in any way affect the trial on its merits, or set up a different cause

of action, or impose any different burden on the defendant, the variance

will not be considered material.” Higgins Lumber Co. v. Marucca, 48 A.2d

48, 49-50 (Pa. Super. 1946) (emphasis in original).

      Here, Lippl contends that, “while Young [pleaded] that Lippl failed to

properly pursue negligence claims in the arbitration action, and that her



                                     - 18 -
J-A28003-20



[house] was a total loss, [Attorney] Hunt instead faulted Lippl for not

properly developing fraud and breach of contract claims and not proving

how the [house] could be repaired.”           Lippl’s Brief at 38 (emphasis in

original).   Lippl argues that Young’s complaint set forth a claim for legal

malpractice premised on the theory that because Lippl failed to obtain

geotechnical testing of the soil base supporting the foundation, Young was

unable to prevail against Custom Homes on a cause of action for negligence.

Id. at 42. Lippl asserts that at trial, however, Young introduced evidence

that, due to Lippl’s legal malpractice, Young was unable to prevail against

Custom Homes for claims of breach of contract and fraud. Id. Lippl contends

the resulting variance between Young’s pleadings and her proof at trial was

material and extremely prejudicial. Id. at 41-42.

      Pennsylvania courts have long-held as a general principal that “plaintiffs

should not be forced to elect a particular theory in pursuing a claim” and risk

the “possibility that meritorious claims will fail because the wrong legal theory

was chosen.”     Schreiber v. Republic Intermodal Corp, 375 A.2d 1285,

1291 (Pa. 1977) (citation omitted). “Although a plaintiff is not required to

specify the legal theory underlying the complaint, the material facts which

form the basis of a cause of action must be alleged.” Lampus v. Lampus,

660 A.2d 1308, 1312 n.2 (Pa. 1995).

      In the case sub judice, Young pleaded, in pertinent part, the following

material facts in support of her cause of action for professional negligence,




                                     - 19 -
J-A28003-20


     8. Although [Lippl] specifically raised a counter[-]claim premised
     upon negligent construction of the [house], he did not pursue this
     cause of action, instead choosing to focus on economic damages
     caused by [Custom Homes].

     9. During his representation of [Young, Lippl] retained [Suhrie] to
     provide expert analysis and opinion for [Young’s] defenses and
     affirmative claims.

                                    ...

     11. [Suhrie] specifically opined that further geotechnical
     investigation was required to assess the risk of foundation
     movement.

     12. [Lippl] did not obtain any further geotechnical investigation.

     13. [Young] requested that [Lippl] make further investigation into
     the foundation issues as recommended by [the Suhrie Report],
     but [Lippl] made no further inquiries.

                                    ...

     23. As a result of [Lippl’s] representations [as an attorney that
     specialized in construction litigation, Young] retained [Lippl’s]
     services to represent her in the underlying action.

     24. During the cour[se] of his representation, [Lippl] learned,
     through his retained expert witness, that there may be structural
     issues caused by problems with the manner in which the
     foundation was engineered and constructed.

     25. [Lippl’s] retained expert specifically recommended that further
     geotechnical evaluation be performed to determine the exact
     issues causing settlement problems on the property.

     26. [Lippl] ignored this recommendation and did not retain a
     geotechnical report.

     27. [Lippl] ignored [Young's] request to further investigate the
     recommendation that he retain a geotechnical report.

     28. [Lippl,] through his training and obligations as an attorney[,]
     knew, or should have known, that a geotechnical report was
     needed to determine the exact nature of problems with the
     foundation and uncompacted fill materials.



                                   - 20 -
J-A28003-20


      29. Had [Lippl] retained a geotechnical report, he would have
      learned that the [house] was built upon uncompacted fill materials
      and that due to this fact, the [house] would never be approved
      for occupancy.

Young’s Complaint, 12/28/12, at ¶¶8-9, 11-13, 23-29 (record citations and

extraneous capitalization omitted). Young alleged that as a result of Lippl’s

professional negligence in failing to obtain geotechnical testing of the soil base

underlying the foundation, she was precluded from bringing a cause of action

against Custom Homes, including a negligence action, for the total loss of her

house. Id. at ¶¶30(d) and 31.

      A review of Young’s complaint demonstrates that she set forth the

material facts in support of her claim against Lippl for professional negligence.

Specially, Young alleged that Lippl owed her a duty as her attorney (a fact

which is not contested by Lippl), that Lippl did not exercise ordinary skill and

knowledge in his representation of Young when he failed to obtain the

recommended geotechnical testing, and that because of Lippl’s failure to

obtain the geotechnical testing, Young was precluded from bringing a viable

cause of action against Custom Homes. We concur with the trial court that

Young was not required to set forth her legal theory as to the precise cause

of action or causes of action she was precluded from bringing against Custom




                                     - 21 -
J-A28003-20



Homes as a proximate cause of Lippl’s professional negligence.11 Therefore,

Lippl’s third issue is without merit.

       We now turn to Young’s cross-appeal and the issues raised therein. In

her first issue, Young claims the trial court erred when it granted, in part,

Lippl’s request for judgment notwithstanding the verdict and reduced the

verdict by $253,453.15 on the grounds that Young previously recovered these

damages in her suit against Code.Sys. Young’s Reply Brief at 12-31.

       This issue raises a question of law for which our standard and scope of

review are well-settled. We review a trial court’s decision to apply the one

satisfaction rule and off-set the jury verdict for an abuse of discretion or error

of law. Baker v. ACandS, 755 A.2d 664, 667 n.4 (Pa. 2000). Our scope of

review for such matters is plenary. Id. Under the long-standing Pennsylvania

precedent known as the “one satisfaction rule,” an injured party may only

recover one satisfaction for the same injury. Garman v. Angino, 230 A.3d

1246, 1256 (Pa. Super. 2020); see also Brown v. City of Pittsburgh, 186

A.2d 399, 402 (Pa. 1962) (stating, “[i]t has long been the law that for the

same injury, an injured party may have but one satisfaction, and the receipt

of such satisfaction, either as payment of a judgment recovered or

consideration for a release executed by [the injured party], from a person

____________________________________________


11 Moreover, Lippl was aware that Young was unsuccessful in her advance of
claims that Custom Homes breached its contract and committed fraud in
connection with the construction of the home because these causes of action
were set forth by Lippl as counter-claims in the arbitration matter.


                                          - 22 -
J-A28003-20



liable for such injury necessarily works a release of all others liable for the

same injury” (citation omitted)).

       Here, Young contends that, “the one-satisfaction rule only applies where

one party’s liability is ‘predicated upon the negligence of another.’” Young’s

Reply Brief at 14 (citation omitted). Young asserts that Lippl’s liability for

legal malpractice is predicated, not on Code.Sys’s negligence in failing to

properly inspect the foundation and its construction, but, rather, on Custom

Homes’ defective construction of the foundation and its failure to dig to firm

clay. Id. at 13. Young argues that Lippl is not entitled to a set-off of the jury

verdict entered against him by the amount Young received in her settlement

with Code.Sys. Instead, Young characterizes the settlement with Code.Sys as

a “fortuitous collateral remedy” and under the collateral source rule,12 Lippl is
____________________________________________


12 We find Young’s reliance on the collateral source rule to be misplaced. The
collateral source rule “prohibits a defendant in a personal injury action from
introducing evidence of the plaintiff’s receipt of benefits from a collateral
source [(for example, insurance coverage, social security benefits,
unemployment compensation, or employee benefits, such as accumulated sick
pay)] for the same injuries which are alleged to have been caused by the
defendant.’’ Simmons v. Cobb, 906 A.2d 582, 585 (Pa. Super. 2006)
(citation omitted, emphasis added) (stating, the collateral source rule is
intended to protect tort victims). “[T]he primary focus of the collateral source
rule is to avoid the preclusion or diminution of the damages otherwise
recoverable from the wrongdoer based on compensation recovered from a
collateral source [and], in some instances, the violation of the collateral source
rule can affect the jury's deliberation and decision on the issue of liability.”
Deeds v. Univ. of Pennsylvania Med. Ctr., 110 A.3d 1009, 1013
(Pa. Super. 2015). Moreover, in the instant case, which does not involve a
personal injury cause of action, preclusion of evidence of the settlement with
Code.Sys for purposes of off-setting the jury verdict in the instant case runs
afoul of the one satisfaction rule.


                                          - 23 -
J-A28003-20



barred from “taking advantage of the fortuitous existence of a collateral

remedy.” Id. at 17-18.

      Lippl contends that in a legal malpractice case, the aggrieved client may

only recover actual losses. Lippl’s Reply Brief at 67. Lippl asserts that the

jury verdict in the instant case represents the damages Young would have

recovered from Custom Homes for, inter alia, its improper construction of the

foundation, but for Lippl’s legal malpractice. Id. at 68. Lippl contends Young

recovered damages for the improper construction of the foundation in her

settlement with Code.Sys and, therefore, is precluded from receiving more

than one recovery for the same injury. Id. at 68-69.

      In off-setting the jury verdict by $253,453.13 pursuant to the

one-satisfaction rule, the trial court explained,

      [Young] has misapplied the [one-satisfaction] rule. [Lippl’s]
      liability for "work defective due to structural/foundation issues and
      repairs" is predicated upon Code.Sys's negligence in failing to
      require a caisson foundation. It is irrelevant that [Young] won
      against Code.Sys on a breach of contract theory because the
      breach of a contractual duty may be and, in fact, was plead[ed]
      in the alternative as negligence. [Young’s] damages in both this
      case and the Code.Sys litigation included repairs to the
      foundation. In her suit against [Lippl, Young] would not have
      recovered these damages but for Code.Sys's failure to require a
      caisson foundation system.

      [T]he jury did not find liability against a party who has not been
      sued. As noted above, the jury heard no evidence related to
      Code.Sys [in the instant case]. Therefore, it could not find
      Code.Sys liable for any damages. Instead, the [trial c]ourt
      determined that [Young] had been compensated for damages
      caused by Code.Sys's failure to require the installation of [a]
      proper foundation.



                                     - 24 -
J-A28003-20


        [Young] further argues that there is no way to know which repairs
        the Code.Sys jury determined that Code.Sys was responsible for
        and that, likewise, there was no way to know which repairs this
        jury found to be caused by [Lippl]. However, [Young] cited to no
        law that required the [trial c]ourt to complete a side-by-side
        comparison of the damages that resulted from the "same injury."
        It was, therefore, proper for the [trial c]ourt to apply the
        [“one-satisfaction] rule" to reduce the verdict by the award for
        "work defective due to structural/foundation issues and repairs."
        Again, this is the same injury [Young] recovered damages for from
        Code.Sys.

Trial Court Opinion, 3/16/20, at 7-8.

        A review of the record demonstrates that in her action against Code.Sys,

Young alleged that Code.Sys failed to properly inspect and identify serious

deficiencies in the construction of the foundation, which ultimately led to

Young’s failure to obtain a certificate of occupancy and the certification of the

house as uninhabitable. A jury awarded Young $412,750.0013 for damages

sustained by Young as a result of Code.Sys’s breach of contract and

negligence.14     In the instant case, Young was awarded $253,453.15 for

Custom Homes’ defective construction work involving “structural/foundational

issues and repairs.” Lippl’s liability in the amount of $253,453.15 is predicated

upon the defective construction performed by Custom Homes that would have
____________________________________________


13   Young settled her suit against Code.Sys, post-trial, for $455,250.00.

14Young’s complaint sounded in a cause of action for negligence based upon
Code.Sys’s failure, inter alia, to properly inspect and identify the construction
deficiencies. Young also brought a cause of action for breach of the contract
Code.Sys had with the municipality in which the house was built and to which
Young was a third-party beneficiary.




                                          - 25 -
J-A28003-20



been discoverable but for Lippl’s failure to obtain geotechnical testing to

identify Custom Homes’ failure to reach firm clay prior to installing the

foundation.15 The amount awarded to Young due to Lippl’s legal malpractice

compensated       Young     for   damages      due   to   Custom   Homes’   defective

construction of the foundation. Similarly, the amount awarded to Young due

to Code.Sys’s negligence and breach of contract compensated Young for

damages due to Custom Homes’ defective construction of the foundation. The

one-satisfaction rule prevents Young from recovering more than once for

claims that centered upon Custom Homes’ defective construction of the

foundation.     We concur with the trial court that the one-satisfaction rule

requires the verdict in the case sub judice to be reduced by the amount

already recovered for the defective construction of the foundation, that is to

say $253,252.15. Therefore, Young’s first issue is without merit.

       Young’s second issue challenges the trial court’s order denying her

post-trial motion to mold the verdict to include post-arbitration interest on the

award Young would have received in the underlying arbitration action but for

Lippl’s legal malpractice.16 Young’s Brief at 51-58.
____________________________________________


15The trial court stated incorrectly that Lippl’s liability was predicated upon
Code.Sys’s failure to require a caisson foundation.

16Although Young’s Rule 1925(b) statement also challenges the trial court’s
order denying pre-arbitration interest, Young failed to set forth this issue in
her statement of questions presented or develop an argument in support
thereof in her brief. Therefore, Young waived her challenge to the trial court’s
denial of a request for pre-arbitration interest. See Harkins v. Calumet



                                          - 26 -
J-A28003-20



       Our standard of review of a trial court’s decision to deny, or grant, a

request to include post-judgment interest is “whether the trial court palpably

abused its discretion.” Zimmerman v. Harrisburg Fudd I, L.P., 984 A.2d

497, 500 (Pa. Super. 2009), appeal denied, 992 A.2d 890 (Pa. 2010).

       In a legal malpractice claim, the aggrieved client is entitled to recover

damages equal to the difference between what the aggrieved client did

recover, if any, and what the aggrieved client would have recovered but for

the attorney’s negligence. Rizzo v. Haines, 555 A.2d 58, 68-69 (Pa. 1989).

Section 8101 of the Pennsylvania Judicial Code provides that, “[e]xcept as

otherwise provided by another statute, a judgment for a specific sum of money

shall bear interest at the lawful rate from the date of the verdict or award, or

from the date of the judgment, if the judgment is not entered upon a verdict

or award.”     42 Pa.C.S.A. § 8101.            “Statutory post-judgment interest is a

matter of right where damages are ascertained by computation” and the

prevailing party is “entitled to interest on a judgment for a specific sum of

money from the date of the verdict.” Pittsburgh Constr. Co. v. Griffith,

834 A.2d 572, 590-591 (Pa. Super. 2003), appeal denied, 852 A.2d 313 (Pa.

2004).    ‘‘[F]or purposes of computing interest, judgment and verdict are

synonymous, and the date from which interest accrues is the date of the


____________________________________________


Realty Co, 614 A.2d 699, 703 (Pa. Super. 1992) (stating, issues not identified
in the statement of questions or issues identified but not developed in the
argument section of the brief are waived).


                                          - 27 -
J-A28003-20



verdict, not the date judgment is finally entered.’’ Hutchison v. Luddy, 946

A.2d 744, 750 (Pa. Super. 2008) (citation omitted).

      Here, Young argues that her request for post-arbitration interest on the

arbitration damages she would have been awarded but for Lippl’s legal

malpractice “is not being requested by direct operation of Section 8101” but,

rather, “is being sought as a component of damages in the context of a ‘case

within a case’ legal malpractice claim.” Young’s Brief at 53. Young contends

that the trial court’s denial of interest as a component of damages for her

“case within a case” legal malpractice claim incentivizes attorneys, such as

Lippl, “to resist settlement” and “strongly encourage[s attorneys] to engage

in extensive litigation – simply in an effort to ‘out last’ a malpractice plaintiff,

like [] Young.”    Id. at 54.    Young asserts that if she had been awarded

arbitration damages, absent Lippl’s legal negligence, she would been entitled

to interest pursuant to Section 8101. Id. at 57. Because the “interest is []

clearly a loss that [] Lippl caused, [] it is properly recoverable as an element

of damages in the ‘case with a case’” legal malpractice action. Id.

      In denying Young’s request for post-arbitration interest, the trial court

stated,

      [Young] is not entitled to pre-arbitration or post-arbitration
      interest. [Lippl] did not hold money or property which belonged
      in good conscience to [Young]. [Young] also waited more than
      two years to file suit against [Lippl] following the arbitration
      award. It would be unjust for the [trial c]ourt to require [Lippl] to
      pay interest that accrued during that time.

      Moreover, [Young] has not asserted that [Lippl] caused any undue
      delay in the proceedings that would warrant such an excessive

                                      - 28 -
J-A28003-20


      amount of interest on the judgment. The total molded award in
      this [legal malpractice] case was $114,947.99. It would be
      grossly unjust for the [trial c]ourt to award more than
      $800,000.00 in interest on the judgment.

      Last, [Young] is not entitled to post-[arbitration] interest from the
      date of the arbitration award. The date of the award or verdict
      referenced in 42 Pa.C.S.A. § 8101 means the verdict in this [legal
      malpractice] case, not the [] arbitration award. [Young] cited no
      support for such an interpretation.

      Accordingly, [Young] is entitled to post-judgment interest solely
      from the date of the jury verdict in [the legal malpractice] case.
      However, [Young] never requested that [the trial c]ourt award her
      post-judgment      interest.      Rather,    [Young]    requested
      pre-arbitration and post-arbitration interest [be awarded in her
      post-trial motion].

Trial Court Opinion, 3/16/20, at 10 (emphasis in original).

      Young’s issue presents a question of first impression as to the

application of Section 8101 as it applies within the context of a “case within a

case” legal malpractice claim. As the proper interpretation, and application of

a statute, is a pure question of law, our standard of review is de novo, and

our scope of review is plenary. Grimm v. Universal Med. Servs., Inc., 156

A.3d 1282, 1286 (Pa. Super. 2017) (citation omitted).

      A fundamental principal of a successful claim for legal malpractice is to

award the aggrieved client what they would have received if the underlying

matter had been litigated successfully but for the attorney’s negligence. See

Rizzo, 555 A.2d at 68-69. A prevailing party is entitled, as a matter of right,

to interest at the lawful rate from the date of the verdict until such time as

payment of the judgment is made to the non-prevailing party.             See 42

Pa.C.S.A. § 8101; see also Perel v. Liberty Mut. Ins. Co., 839 A.2d 426,


                                     - 29 -
J-A28003-20



430 (Pa. Super. 2003) (stating, “for purposes of calculating post[-]judgment

interest, payment necessarily occurs when the amount of the verdict (or an

otherwise agreed upon amount) - whether sent by mail, courier, electronic

funds transfer, or other mode of delivery - is received by the creditor).

Because the interest is calculated upon a “specific sum of money” awarded, it

is axiomatic that within the context of a “case within a case” legal malpractice

action, the aggrieved client is entitled to interest calculated on the specific

amount awarded in the legal malpractice case from the date of the verdict in

the legal malpractice case and not the prospective date of a verdict in the

underlying cause of action.

      In the case sub judice, we concur with the trial court that pursuant to

Section 8101, Young “is entitled to post-judgment interest solely from the

date of the jury’s verdict” in the legal malpractice case. Trial Court Opinion,

3/16/20, at 10. The trial court abused its discretion, however, in finding that

Young “never requested that [the trial c]ourt award her post-judgment

interest.” Id. A review of Young’s post-trial motion demonstrates that her

calculation of interest encompassed the period from the date of the jury

verdict in the instant case through the date her post-trial motion was filed,

October 7, 2019. Young’s Post-Trial Motion, 10/7/19, at 4. Young is entitled,

therefore, to interest calculated from the date of the jury verdict, September

26, 2019, until such date as the amount of the judgment is paid by Lippl to

Young. See 42 Pa.C.S.A. § 8101. Consequently, we remand this case for the

limited purpose that the trial court calculate and award post-judgment

                                     - 30 -
J-A28003-20



interest, pursuant to Section 8101, on the judgment totaling $114,947.99

from the date of the jury verdict in the instant case through and including the

date on which payment of the judgment is received by Young from Lippl.

      Judgment affirmed.      Case remanded for award of post-judgment

interest. Jurisdiction relinquished.



Judgment Entered.




Joseph D. Seletyn, Esq.
Prothonotary



Date: 3/31/2021




                                       - 31 -