In the United States Court of Federal Claims
No. 20-288C
(Filed: June 21, 2021)
)
STATE OF OHIO, ) Suit for breach of contract; contract based
) on Water Supply Act of 1958, as
Plaintiff, ) amended, 43 U.S.C. § 390(b); cross-
) motions for partial summary judgment
v. )
)
UNITED STATES, )
)
Defendant. )
)
)
Ian F. Gaunt, Assistant Attorney General, Environmental Enforcement Division, State of
Ohio, Columbus, Ohio, for plaintiff. With him on the briefs were Dave Yost, Ohio Attorney
General, Daniel J. Martin, and Amber Wootton Hertlein, Assistant Attorneys General, State of
Ohio, Columbus, Ohio.
Ioana Cristei, Trial Attorney, Commercial Litigation Branch, Civil Division, United
States Department of Justice, Washington, D.C., for defendant. With her on the briefs were
Brian M. Boynton, Acting Assistant Attorney General, Robert E. Kirschman, Jr., Director, and
Deborah A. Bynum, Assistant Director, Commercial Litigation Branch, Civil Division, United
States Department of Justice, Washington, D.C., as well as Daniel Inkelas, Assistant Counsel,
Office of the Chief Counsel, and Lauren R. Horner, Assistant District Counsel, Louisville
District, United States Army Corps of Engineers.
OPINION AND ORDER
LETTOW, Senior Judge.
The State of Ohio seeks redress for the United States Army Corps of Engineers’ alleged
violation of a contract relating to flood control and water supply at the Caesar Creek Project (the
“Project”) in Southwestern Ohio. The contract, executed by Ohio and the Corps in 1970
pursuant to the Water Supply Act of 1958, Pub. L. No. 85-500, Title III, § 301 (codified at 43
U.S.C. § 390b), stipulated that the parties would share the “annual experienced joint-use
operation and maintenance costs of the Project.” First Am. Compl. Ex. A Art. 5.c.(1) (the
“Contract”), ECF No. 23-2. Ohio alleges, inter alia, that “[t]he United States has charged—and
continues to charge—the State of Ohio for costs not authorized by the . . . Contract.” First Am.
Compl. ¶ 45, ECF No. 23-1.
Pending before the court are the parties’ cross-motions for partial summary judgment.
See Pl.’s Mot. for Partial Summ. J. (“Pl.’s Mot.”), ECF No. 26; Def.’s Resp. & Cross-Mot. for
Partial Summ. J. (“Def.’s Cross-Mot.”), ECF No. 32. Following the completion of briefing, see
Pl.’s Reply & Resp. (“Pl.’s Reply”), ECF No. 33; Def.’s Reply, ECF No. 36, the court held a
hearing on May 21, 2021. The court concludes that “joint-use operation and maintenance costs
of the Project,” Contract Art. 5.c.(1), are those necessary “to maintain [the Project] as an efficient
going concern,” Nampa & Meridian Irrigation Dist. v. Bond, 268 U.S. 50, 53 (1925), i.e., “to
operate [the Project] effectively” for water storage, water availability, and flood control, id., and
“to remedy injurious effects resulting from the [P]roject’s subsequent operation,” Casitas
Municipal Water Dist. v. United States, 543 F.3d 1276, 1284 (Fed. Cir. 2008). Because
allegedly extraneous costs are at issue, plaintiff’s motion is GRANTED IN PART and the
government’s cross-motion is DENIED.
BACKGROUND 1
A. The Flood Control Act and the Water Supply Act
The Flood Control Act of 1938 “[a]uthoriz[ed] the construction of certain public works
on rivers . . . for flood control, and for other purposes.” Pub. L. No. 75-761, 52 Stat. 1215.
Congress passed the Act in response to the Ohio River flood of 1937, see Ohio v. United States,
150 Fed. Cl. 173, 176 (2020), and the Little Miami River in Ohio, of which Caesar Creek is a
tributary, was identified as an appropriate site for a future reservoir in the Ohio River Basin, see
id.; see also H.R. Rep. No. 75-2353, at 11 (1938). The Act specifically references the plan for
the Ohio River Basin as a “general comprehensive plan for flood control and other purposes.”
52 Stat. at 1217. Congress further adopted the Water Supply Act of 1958, and the Act’s 1963
amendments, for a similar purpose, see Pub. L. No. 85-500, § 301(a) (1958) (codified as
amended at 43 U.S.C. § 390b(a)); Pub. L. No. 88-140, 77 Stat. 249, and “authorized the U.S.
Army Corps of Engineers ‘to impound water for present or anticipated future demand or need for
municipal or industrial water’ in its reservoir projects.” Ohio, 150 Fed. Cl. at 176 (quoting 43
U.S.C. § 390b(b)). The Water Supply Act, as amended, briefly addresses operation and
maintenance costs, asserting that a state such as Ohio can obtain permanent rights to water
storage space so long as the state “continue[s] payment of annual operation and maintenance
costs allocated to water supply.” Pub. L. No 88-140, § 3 (codified at 43 U.S.C. § 390e).
B. The Contract
In January of 1970, the parties established a flood control contract related to the Caesar
Creek Reservoir Project in Ohio. Contract at 1. The Contract was entered pursuant to the Flood
Control Act of 1938 and the Water Supply Act of 1958 to manage water supply needs and reduce
flooding risks along various rivers, including the Little Miami River in Ohio. See id. The Corps
1
The recitations that follow are not findings of fact but rather are recitals attendant to the
pending motions and reflected matters drawn from the complaint, the parties’ briefs, and the
records and documents appended to the complaint and briefs.
2
agreed to operate and enhance the Caesar Creek Project by adding water storage capabilities and
supply. See id. Art. 1.d. Under the Contract, Ohio gained “the right . . . to utilize an undivided
48.7 percent of the storage space in the Project between elevations 800.0 and 846.0 feet above
mean sea level as deemed necessary by the State to impound water for municipal and industrial
use and to make withdrawals therefrom at any time,” a storage space “estimated to be 80,400
acre-feet.” Id. Art. 1.a.
Article 5 of the Contract provided that Ohio agreed to pay the United States a variety of
costs, including a portion of the Project’s operation and maintenance costs. Contract Art. 5.
Specifically, the Contract stated that “[t]he State shall pay 12.70 percent of the annual
experienced joint-use operation and maintenance costs of the Project” on an annual basis. Id.
Art. 5.c.(1). The Contract did not define what costs could be considered operation and
maintenance costs, but it did provide that the United States’ contracting officer possessed
discretion to determine the appropriate amount of operation and maintenance costs. Id. Art.
5.c.(3). Ohio could request additional operation and maintenance, but the State would be
responsible for “the entire cost of such additional expense.” Id.
C. Procedural History
Ohio filed suit in this court in March 2020. See Compl., ECF No. 1. Among other
claims, Ohio disputed numerous “facially improper line items” charged by the Corps as
operation and maintenance expenses. Compl. ¶ 30; see also First Am. Compl. ¶ 30. Ohio
specifically challenged charges related to “birdseed, parking lots, pedestrian bridges,
environmental management, water quality testing, travel orders, tree removal, and community
outreach.” First Am. Compl. ¶ 30. Ohio anticipated identifying additional improper charges
because “[m]any other expense items lacked sufficient detail to determine whether they relate to
operation and maintenance for the flood control and water supply [P]roject.” First Am. Compl. ¶
31.
The government subsequently moved to dismiss the complaint. Def.’s Mot. to Dismiss,
ECF No. 9. The court granted the government’s motion in part, dismissing Ohio’s takings claim,
but otherwise denied the motion. See Ohio, 150 Fed. Cl. 176. Ohio filed its first amended
complaint on February 8, 2021. See First Am. Compl.; Order of February 8, 2021, ECF No. 24.
The government filed its answer to the amended complaint on February 22, 2021. See ECF No.
25. Four days later, Ohio filed its motion for partial summary judgment, contending that it “is
entitled to partial summary judgment on the scope of the water supply contract’s definition of
‘joint-use operation and maintenance costs of the Project’ as a matter of law.” Pl.’s Mot. at 5.
The government filed a response and cross-motion for partial summary judgment, in which it
countered that “Ohio is obligated to pay 12.7 percent of the annual joint-use operation and
maintenance expenses that the contracting officer deems necessary to operate and maintain the
[P]roject for its authorized purposes.” Def.’s Cross-Mot. at 12-13. The cross-motions were fully
briefed, see Pl.’s Reply; Def.’s Reply, and the court held a hearing on May 21, 2021. 2
2
The transcript of the hearing was filed on June 1, 2021 and will be cited as “Hr’g Tr.
Page Number:Line Number,” omitting the hearing date from the citation.
3
STANDARDS FOR DECISION
A. Summary Judgment
Summary judgment shall be granted “if the movant shows that there is no genuine dispute
as to any material fact and the movant is entitled to judgment as a matter of law.” Rule 56(a) of
the Rules of the Court of Federal Claims (“RCFC”). A material fact is one that “might affect the
outcome of the suit.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248 (1986) (interpreting
Fed. R. Civ. P. 56). 3 A genuine dispute exists when the finder of fact may reasonably resolve the
dispute in favor of either party. Id. at 250.
The movant bears the burden of demonstrating the absence of any genuine disputes of
material fact, see Celotex Corp. v. Catrett, 477 U.S. 317, 322 (1986), and must “cite[] to
particular parts of materials in the record, including depositions, documents, electronically stored
information, affidavits or declarations, stipulations . . . , admissions, interrogatory answers, or
other materials,” RCFC 56(c)(1)(A). The court may consider other materials in the record even
if not cited by the parties. RCFC 56(c)(3). “[T]he inferences to be drawn . . . must be viewed in
the light most favorable to the party opposing the motion.” Matsushita Elec. Indus. Co. v. Zenith
Radio Corp., 475 U.S. 574, 587 (1986) (quoting United States v. Diebold, Inc., 369 U.S. 654,
655 (1962)). If the record taken as a whole “could not lead a rational trier of fact to find for the
non-moving party, there is no ‘genuine issue for trial’” and summary judgment is appropriate.
Id. (quoting First Nat’l Bank of Ariz. v. Cities Serv. Co., 391 U.S. 253, 289 (1968)).
When both parties have moved for summary judgment, “the court must evaluate each
party’s motion on its own merits, taking care in each instance to draw all reasonable inferences
against the party whose motion is under consideration.” Mingus Constructors, Inc. v. United
States, 812 F.2d 1387, 1391 (Fed. Cir. 1987) (citation omitted). “The fact that both parties have
moved for summary judgment does not mean that the court must grant judgment as a matter of
law for one side or the other.” Id. “To the extent there is a genuine issue of material fact, both
motions must be denied.” Marriott Int’l Resorts, L.P. v. United States, 586 F.3d 962, 969 (Fed.
Cir. 2009) (citation omitted).
B. Interpretation of Contracts on Summary Judgment
The meaning of contract terms properly can be evaluated on summary judgment,
provided that the contractual language is not ambiguous. See Lucent Techs., Inc. v. Gateway,
Inc., 543 F.3d 710, 717 (Fed. Cir. 2008); Crown Laundry & Dry Cleaners v. United States, 29
Fed. Cl. 506, 515 (1993) (citation omitted) (“Pure contract interpretation is a question of law
which may be resolved on summary judgment.”). In interpreting a contract, a court begins with
the language of the agreement. Jowett, Inc. v. United States, 234 F.3d 1365, 1368 (Fed. Cir.
2000); Record Steel & Constr., Inc. v. United States, 62 Fed. Cl. 508, 513 (2004). If the terms of
3
Because RCFC 56 mirrors Fed. R. Civ. P. 56, the rules should be interpreted in pari
materia.
4
the contract are unambiguous, the court must give effect to the plain meaning and may not look
to extrinsic evidence as an interpretative guide. Barron Bancshares, Inc. v. United States, 366
F.3d 1360, 1375 (Fed. Cir. 2004). In interpreting a contract, the court is to read the contract as a
whole and endeavor to give a reasonable meaning to all its provisions. Jowett, 234 F.3d at 1368
(citations omitted).
Further, where a contract fulfills or implements a statutory requirement, the underlying
statute must guide the court’s interpretation of the contract. Dalles Irrigation Dist. v. United
States, 82 Fed. Cl. 346, 355 (2008). In these circumstances, “the express terms of the . . .
contract are illuminated by the authorizing legislation . . . and, to a lesser extent, by other
background legislation.” Id. at 355-56. As the Federal Circuit has explained: “[W]hen . . . the
contract implements a statutory enactment, it is appropriate to inquire into the governing statute
and its purpose.” Columbus Reg’l Hosp. v. United States, 990 F.3d 1330, 1345 (Fed. Cir. 2021)
(quoting Roedler v. Department of Energy, 255 F.3d 1347, 1352 (Fed. Cir. 2001)).
ANALYSIS
A. Ohio’s Motion for Summary Judgment
Ohio seeks partial summary judgment, requesting that the court adopt a definition of the
contractual term “joint-use operation and maintenance costs of the Project.” Pl.’s Mot. at 5.
Ohio argues that the Contract imposes two limitations on the operation and maintenance costs:
first, that “[t]he costs charged to the State must be for operation and maintenance,” and second,
that “the costs charged to the State for operation and maintenance must be for the shared Caesar
Creek Project.” Id. Under Ohio’s definition, operation and maintenance costs must be “related
to flood control, water storage, and water supply,” id. at 7, and be spent “to operate and keep the
[P]roject in working order or fix problems caused by the [P]roject,” id. at 5. Ohio avers that the
plain language of the Contract controls, and that the authorizing statutes and their legislative
histories inform its arguments. Id. at 5-13. The United States counters that, in support of its
proposed definition, Ohio relies on extrinsic evidence. Def.’s Cross-Mot. at 7-11. By using this
evidence, the United States asserts that Ohio implicitly concedes that the contract language is
ambiguous. Id. at 7-11.
The starting point for this analysis is the contractual language. The Contract provides
that the Project is “the Caesar Creek Reservoir on Caesar Creek, a tributary of the Little Miami
River,” construction of which “was authorized by the Flood Control Act” of 1938 and would
include “storage for municipal and industrial water supply.” Contract at 1. The Project is listed
as a “multi-purpose project” with the goals of “flood control,” “water quality control,” and
“water supply.” Id. Ex. B (emphasis omitted). Ohio agreed to pay costs in accordance with the
provisions of the Water Supply Act of 1958, as amended. Id. at 1. Among other costs, the
Contact specified that Ohio “shall pay 12.70 percent of the annual experienced joint-use
operation and maintenance costs of the Project.” Id. at Art. 5.c.(1). Further, the contracting
officer had discretion to determine “[t]he extent of operation and maintenance of the Project” and
would provide records of such costs to Ohio “for inspection and examination.” Id. at Art. 5.c.(3).
Ohio would “bear the entire cost” of operation and maintenance expenses that were above those
“deemed necessary by the Contracting Officer.” Id.
5
The parties’ arguments center around questions of the proper scope of the Project, the
definition of operation and maintenance costs, and the definition of joint use. Ohio argues that
the plain language of the Contract, binding precedent, and the associated statutes should guide
the court’s analysis. 4 The government avers, however, that the plain language of the Contract
provides substantial discretion to the contracting officer to decide what charges count as
operation and maintenance.
The court finds that the contractual language plainly places requirements on what can be
operation and maintenance costs for which Ohio is obligated to pay. Operation and maintenance
costs must be “joint-use” and they must be “of the Project.” Contract Art. 5.c.(1). While the
United States is correct that the contracting officer retains discretion as to the appropriate amount
of operation and maintenance costs to charge Ohio, see Def.’s Cross-Mot. at 12-13; Contract Art.
5.c.(3), the contracting officer does not have discretion to determine the definition of the Project
and attendant joint-use costs. Accordingly, the contracting officer cannot charge Ohio for costs
that are not joint use, not for operation and maintenance, or not related to the Caesar Creek
Project.
The parties focus on the definition of “joint use” in delineating the operating and
maintenance expenses that can be charged to Ohio under the contract. The government states
that joint use means that the costs can have “two or more purposes,” Hr’g Tr. 23:3-4, while Ohio
implies that joint-use instead should be understood in the context of the shared Project at Caesar
Creek, see Pl.’s Reply at 4; see also Hr’g Tr. 21:4-8 (United States: “[Ohio] also name[s]
something that [it] call[s] the ‘shared project,’ but that’s not actually found anywhere in the
contract, and nor does Ohio explain what this mean or if this is something that’s different from
‘joint use,’ which is, in fact, found in the [C]ontract.”).
The Contract contrasts “joint-use” with “specific-use.” See, e.g., Contract Ex. B, Sheet 5
(line item 23 “Allocated construction costs of joint-use lands & facilities” lists multiple purposes,
such as flood control, water quality and water supply, and recreation, while line item 24
“Construction costs of specific-use lands & facilities” has a single purpose, recreation). 5 In
short, joint-use costs refer to expenses which serve multiple purposes, while specific-use costs
4
The language defining the Project, including the incorporation of the authorizing
statutes, is stated in the contract’s recitals. See Contract at 1. Ohio indicated that it believes the
recitals “comport with [its] analysis of the rest of the contract.” Hr’g Tr. 9:24 to 10:1. While
courts generally “do not interpret recitals as binding contractual obligations,” Rocky Mountain
Helium, LLC v. United States, 145 Fed. Cl. 662, 666 n.6 (2019) (citation omitted), recitals “may
be read in conjunction with the operative portions of a contract in order to ascertain the intention
of the parties.” KMS Fusion, Inc. v. United States, 36 Fed. Cl. 68, 77 (1996), aff’d, 108 F.3d
1393 (Fed. Cir. 1997). Therefore, the court will read the recitals together with the contract
language to discern the meaning of the contractual terms at issue.
5
At this juncture, the court need not resolve the question of whether the sheets appended
to Exhibit B of the Contract are actually part of the Contract itself. For purposes of the cross-
motions, the court will take them into account.
6
refer to expenses for recreational purposes only. See id. Looking at the Contract as a whole,
Jowett, 234 F.3d at 1368, the court determines that the Contract defines “joint-use” as pertaining
to more than one contractually specified use and that this definition applies throughout the
Contract.
The court next turns to the core argument—the definition of operation and maintenance.
The Contract does not provide a direct definition of operation and maintenance costs, other than
the statements included in Article 5. See Contract Art 5.c. Both parties rely on Nampa &
Meridian Irrigation District v. Bond, 268 U.S. 50 (1925), and Casitas Municipal Water District
v. United States, 543 F.3d 1276 (Fed. Cir. 2008), in support of their arguments. See, e.g., Pl.’s
Mot. at 6; Def.’s Cross-Mot. at 12. In Nampa, the Supreme Court of the United States provided
a definition for what could be considered an operation and maintenance charge. Nampa, 268
U.S. at 53. Generally, costs are considered “maintenance and operating expenses” when those
“expenditures [are] made to maintain [the system] as an efficient going concern, and to operate it
effectively to the end for which it was designed.” Id. The Federal Circuit, relying upon Nampa,
further stated that “costs . . . incurred after the project was completed to remedy injurious effects
resulting from the project’s subsequent operation” were properly characterized as operation and
maintenance costs. Casitas, 543 F.3d at 1284. Costs of the initial construction of the Project, for
example, could not be charged as operation and maintenance, but later remedial construction
could be classified as such. See id. at 1283-84. Accordingly, expenses charged to Ohio as
operation and maintenance costs must be (1) “to maintain [the Project] as an efficient going
concern,” Nampa, 268 U.S. at 53, (2) “to operate [the Project] effectively to the end[s] for which
it was designed,” id., or (3) “to remedy injurious effects resulting from the [P]roject’s subsequent
operation,” Casitas, 543 F.3d at 1284.
The purposes and goals of the Project are relevant to this analysis both as to the scope “of
the Project” as well as to whether expenses are, in fact, “operation and maintenance costs.” See
Contract Art. 5.c.(1). The Contract provides that “construction” of the Project and “storage” of
water “for municipal and industrial water supply,” id. at 1, as well as “flood control,” and “water
quality control,” id. Ex. B, are purposes of the Project. The court’s analysis is further informed by
the authorizing statutes referenced by the contract. See Dalles Irrigation, 82 Fed. Cl. at 355
(“[T]he express terms of the . . . contract are illuminated by the authorizing legislation.”). The
parties agree that the underlying legislation is relevant and important to proper resolution of this
issue. See Hr’g Tr. 25:4-6 (United States: “[T]he underlying legislation is absolutely important to
look at in making this determination.”); id. 11:2-5 (Ohio: “Our position is that [the statutes] . . .
are helpful guidance in interpreting the contract.”). The Flood Control Act of 1938 authorized
construction, such as the Caesar Creek Project, “for flood control, and for other purposes.” Pub.
L. No. 25-761, 52 Stat. 1215. The declared policy of the Water Supply Act of 1958 was to
“develop[] water supplies for domestic, municipal, industrial, and other purposes” and to facilitate
cooperation “in connection with construction, maintenance, and operation of Federal navigation,
flood control, irrigation, or multiple purpose projects.” 43 U.S.C. § 390b(a). The statutory
provisions authorizing the parties to enter into this Contract, combined with Nampa and Casitas,
indicate that “operation and maintenance costs” should be interpretated as those necessary “to
maintain [the Project] as an efficient going concern” “to operate [the Project] effectively” for the
Project’s water storage, water availability, and flood control purposes, or “to remedy injurious
effects resulting from the [P]roject’s subsequent operation.” Nampa, 268 U.S. at 53; Casitas, 543
7
F.3d at 1284. 6 Expenses that fit within the above definition can be properly charged as operation
and maintenance expenses.
The United States suggests that the definition of operation and maintenance cannot be
determined absent discovery as to the specific charges Ohio alleges it was wrongly charged as
operation and maintenance. Def.’s Cross-Mot. at 12 (“Additional discovery is needed to
determine both the costs at issue and any facts rendering those costs not properly chargeable
under the contract.”) The government argues that, as the Supreme Court stated in Nampa, “[t]he
same kind of work under one set of facts may be chargeable to construction and under a different
set of facts may be chargeable to maintenance and operation.” Nampa, 268 U.S. at 54 (citation
omitted); see also Nampa & Meridian Irrigation Dist. v. Bond, 288 F. 541, 541 (9th Cir. 1923),
(“[T]he term ‘operating expense’ is a broad and comprehensive one, and its meaning in a given
case depends on the nature and amount of the expenditure, and all the surrounding
circumstances.”), aff’d, 268 U.S. 50. Therefore, the United States avers that the court cannot
establish a definition for this contract term absent knowledge of the specific costs alleged to be
inappropriately charged. Def.’s Cross-Mot. at 12. The court finds, however, that adopting a
definition for joint-use operation and maintenance costs does not run afoul of Nampa. Contrary
to the government’s suggestion that granting summary judgment for Ohio requires this court to
decide “what costs this contract language applies to,” Def.’s Reply at 2, providing a working
definition of the contractual term at issue here does not determine whether the specific charges
Ohio challenges are properly chargeable as operation and maintenance. Those determinations
require a factual record currently being developed through discovery and, as such, would be
inappropriate for the court to evaluate on summary judgment. See Anderson, 477 U.S. at 248
(“[T]he requirement is that there be no genuine dispute of material fact.”) (emphasis omitted).
The United States further contends that by granting summary judgment, the court is
issuing an advisory opinion because it does not resolve “any claim or part of a claim.” Def.’s
Cross-Mot. at 11. The United States is correct that Rule 56 of the Rules of the Court of Federal
Claims provides that a party moving for summary judgment must “identify[] each claim or
defense—or the part of each claim or defense—on which summary judgment is sought.” RCFC
56(a); see Def.’s Cross-Mot. at 11. Nonetheless, a grant of partial summary judgment to Ohio
would not offend Rule 56. Ohio’s suit seeks to establish that the United States is incorrectly
overcharging it for joint-use operation and maintenance costs under the Contract, see First. Am.
Compl. ¶¶ 23-36, 43-45, and Ohio’s motion for summary judgment clarifies part of this claim by
establishing a definition for this contractual term, see generally Pl.’s Mot. The government’s
argument as to Rule 56, therefore, lacks merit.
6
The Contract provides that the costs must be for operation and maintenance of the
Project. Thus, operation and maintenance costs can apply to “only . . . expenses necessary to
operate and maintain the flood control, water supply, and water storage [P]roject.” Pl.’s Mot. at
7.
8
B. United States’ Motion for Summary Judgment
The government seeks partial summary judgment, requesting that the court find “that Ohio is
obligated to pay 12.7 percent of the annual joint-use operation and maintenance expenses that the
contracting officer deems necessary to operate and maintain the [P]roject for its authorized
purposes.” Def.’s Cross-Mot. at 12-13. Ohio agrees with the United States’ interpretation
insofar as it correctly quotes the contractual language. Pl.’s Reply at 2 (“To the extent that the
Government quotes the language of the [C]ontract, Ohio agrees that the [C]ontract says what the
[C]ontract says.”) Ohio suggests that the United States’ request comports with a grant of
summary judgment for Ohio because “the Government does not identify any interpretation other
than the one Ohio asks this Court to confirm.” Id. The court agrees. As the court previously
stated, see supra, the Contract does not grant the contracting officer discretion to define
operation and maintenance or joint use as contractual terms, but rather he or she can determine
the appropriate amount of expenses necessary to operate and maintain the Project and then
charge Ohio accordingly. The United States’ request, therefore, goes beyond the plain language
of the Contract.
CONCLUSION
Under the Contract, joint-use operation and maintenance costs are those necessary “to
maintain [the Project] as an efficient going concern,” Nampa, 268 U.S. at 53, “to operate [the
Project] effectively” for water storage, water availability, and flood control, id., or “to remedy
injurious effects resulting from the [P]roject’s subsequent operation,” Casitas, 543 F.3d at 1284,
that pertain to more than one purpose of the Project. Therefore, plaintiff’s motion is GRANTED
IN PART, and the government’s cross-motion is DENIED.
It is so ORDERED.
s/ Charles F. Lettow
Charles F. Lettow
Senior Judge
9