Mike M. Johnson, Inc. v. Spokane County

Chambers, J.

(dissenting) — Here the owner directed the contractor to do additional work, was fully informed of all relevant information known by the contractor, and observed the contractor perform the work. It is unjust to declare as a matter of law that the contractor is not entitled to fair compensation merely because the contractor did not also conform to additional highly technical claims procedures. It is not merely unjust, it is out of step with Washington law. The majority’s articulation of the relevant rule fails to encompass significant factors necessary for a full and fair resolution of such cases. Whether viewed as a conflict over contractual compliance or a conflict over waiver, this case requires a full hearing to determine the material facts before the law can be applied.

Under the majority’s holding today, an owner can demand additional work outside the scope of the original contract, observe the contractor perform that work, discuss the work with the contractor, and yet deny fair compensation for services rendered if, within 15 days, and before the owner’s plans are even completed, the contractor fails to submit a written request for additional time for the demanded work or fails to produce an itemized invoice in a precise technical format.

This is unreasonable and out of step with the actual practice of construction and construction law. Certainly, contracts should be enforced as written. But countervailing legal principles have compelled courts to allow recovery of fair compensation by the contractor where the owner directs the work be done and the owner is not prejudiced by the contractor’s failure to abide by the technical requirements of submitting a claim for payment.

*394The contractor, Mike M. Johnson, Inc. (MMJ), presented facts upon which a reasonable juror could find compliance with the contractual requirements regarding notice. Alternately, a reasonable juror could find facts that would establish that Spokane County waived strict compliance with the contract’s requirements for claim submission. Because I believe resolution of this case is improper on summary judgment, I respectfully dissent.

FACTS

MMJ was the low bidder for two public works projects in a competitive bidding process. The projects, Apple Valley and Wolfland, required MMJ to lay sewer lines, and then grade and pave the streets.

After the contracts were awarded but before the project began, the county learned that a road improvement district (RID) had been formed for Seventh Avenue, one of the streets in the Apple Valley project. This substantially changed the scope of the original work. The RID doubled the proposed width of Seventh Avenue and added gutters and curbs. At a preconstruction conference on April 23, 1998, the county informed MMJ of the RID and told MMJ that a change order and new design would be prepared. The proposed change order was presented to MMJ on June 4, 1998, although it was not finalized until September 1998. In the change order, the county proposed allotting an additional eight days and $69,319 for the extra work on Seventh Avenue.

The construction schedule provided that the Apple Valley and Wolfland jobs would be performed in sequence, beginning with Apple Valley. MMJ was to start on Fourth Avenue, go on to Sixth Avenue, and then to Seventh Avenue. When Seventh was complete, all three streets would be paved by MMJ’s paving subcontractor. The paving subcontractor would pave only a minimum of three streets at a time.

*395In June, MMJ installed the main sewer line on Seventh Avenue. In late June, MMJ began subgrade preparations for the roadway and encountered US West phone lines, which were not shown on the drawings furnished by the county. Mike Neville, the project superintendent for MMJ, testified that he understood that the county had already conferred with all utilities, including US West, about the location of any underground lines and equipment. His understanding was based both on the contract documents and on standard construction procedure.5 As it turned out, the county had not consulted with US West so the design changes incorporated in change order number 3 were inaccurate. When Neville discussed the problem with US West, it “[was] upset over the county releasing the drawings for construction without [US West’s] signature.” Clerk’s Papers (CP) at 723.

The county verbally instructed MMJ to stop work until the county could redesign the project. This prevented MMJ from starting work on other streets during the approximately six weeks it took to complete its redesign. When MMJ sought to do work on other streets so as to keep on schedule, the county forced MMJ to quit.

On August 7, 1998, the redesign was complete and the county told MMJ to go back to work. However, a week later, on August 14, it was discovered that the county’s design grades were erroneous. The county required MMJ to shut down again while the county corrected the problem.

On August 25, 1998, MMJ submitted a request for $98,000 and a time extension of 50 days. The claim identified each delaying event by date, line location, description of event, crew affected, time impact, hourly rate, and total cost impact. MMJ received final, corrected grades for Seventh Avenue in mid-September.

During this time, county inspectors met daily with MMJ’s superintendent, Neville. Neville met periodically, if not *396daily, with the county’s construction field engineer. Neville met weekly with the county’s construction manager/contract administrator. There were ongoing discussions regarding the time and cost associated with the change order, and MMJ sent numerous letters to the county concerning the delays and associated costs.

Despite the design delays, the county refused to extend the deadlines for completion. The county sent formal notice threatening to terminate the contract on September 10, 1998 because the project was behind schedule.

The work was completed in October. MMJ submitted another claim on December 22, 1998, which included the earlier claims as well as new ones. The county refused to consider any of the claims.

MMJ filed suit seeking compensation for the additional time and work on the projects associated with Seventh Avenue. The county filed for summary judgment, seeking dismissal of MMJ’s claims on four grounds: (1) the contract placed all risks of unknown utilities on MMJ; (2) there was no evidence that the county breached the terms of contract; (3) MMJ should be estopped from asserting its claim for unbalanced work; and (4) MMJ’s claims were barred by its failure to follow claims procedures.

In response, MMJ filed a cross motion for partial summary judgment. The trial court granted the county’s motion and denied MMJ’s motion. The trial court found that “[MMJ] did not comply with the protest and claims procedures of the contract for recovering additional compensation” and dismissed with prejudice MMJ’s claims for additional compensation. CP at 770. The trial court did not make any findings on the issues in MMJ’s cross-motion, including the issues of actual notice, prejudice, equity, substantial compliance, and reservation of rights.6

*397MMJ appealed and Division Three of the Court of Appeals reversed. Mike M. Johnson, Inc. v. Spokane County, 112 Wn. App. 462, 49 P.3d 916 (2002). The Court of Appeals found genuine issues of fact regarding whether the county had actual notice of a claim for additional compensation under a public works construction contract and whether the county waived compliance with contractual claims procedures.

The county appealed and we accepted review. Mike M. Johnson, Inc., v. Spokane County, 148 Wn.2d 1009 (2003). The county requests that we reverse the Court of Appeals and affirm the trial court’s dismissal of MMJ’s claims. MMJ requests that we affirm the Court of Appeals, or in the alternative, send the case back to the trial court for findings of fact and conclusions of law on the unaddressed issues in MMJ’s cross-motion for summary judgment.

ANALYSIS

In reviewing an order of summary judgment, the appellate court engages in the same inquiry as the trial court. Bowles v. Dep’t of Ret. Sys., 121 Wn.2d 52, 62, 847 P.2d 440 (1993). Summary judgment may be granted only if the record demonstrates that there is no genuine issue as to any material fact, and that reasonable persons could reach but one conclusion. Wilson v. Steinbach, 98 Wn.2d 434, 437, 656 P.2d 1030 (1982); CR 56(c). In reviewing the record, the court considers the facts in the light most favorable to the nonmoving party. Bowles, 121 Wn.2d at 62.

The county concedes it had actual notice of the additional time and work encountered by MMJ as a result of the county’s redesign of Seventh Avenue. However, the county argues that MMJ failed to follow the proper claims procedures and that this is fatal to MMJ’s request for compensation, because under the contract the contractor waives his right to compensation if he fails to comply with claims procedures. The county argues that the notices MMJ did submit were not sufficiently detailed or timely to comply *398with the contract, and asserts it did not waive compliance with the claims procedures. The county also argues as a matter of law that there is no actual notice exception to strict compliance with a contract’s claims provisions. There are genuine issues of fact regarding whether MMJ’s notices were sufficient to constitute compliance with the contract’s claims provisions under the circumstances.

MMJ was required under the contract to give immediate written protest if it had any objection to the proposed change order, and then to supplement the written protest within 15 days with more detailed information regarding the nature of the objection, additional costs, and additional time. First, the county argues that MMJ’s notice was not timely. Apparently the county believes the written protest was due within 15 days of June 4,1998, the date of the first change order. However, MMJ had no objection to the first change order number three. It was only when the county’s designs proved to be inaccurate that problems arose. The redesign was initially completed August 7, but additional problems were found, so it was not until August 14 that MMJ was allowed to go back to work. The county never satisfactorily explains why the August 25 claim did not suffice as written protest within 15 days. At a minimum, there is an issue of fact whether MMJ’s notice was timely and thus substantially complied with the contract’s claim requirements.

Second, the county also points out that MMJ failed to give written notice of a request for extension of time. However, it was the county that ordered and was in control of the extension of time. Cf. Bignold v. King County, 65 Wn.2d 817, 823-24, 399 P.2d 611 (1965) (rejecting the argument that the contractor had a duty to comply with the strict terms of the contract despite effectively contrary direction from the county engineer and imposing “resolute good faith” on the county to abide by the direction of its agents). The evidence presented by MMJ was that the county told it to halt work until the county could redesign the project. It is a question of fact whether the county ordered a work *399stoppage. If the county sought the extension, then MMJ would not have had a duty to give written notice of it.

Third, the county argues that the letters and claims for additional compensation submitted by MMJ were not sufficiently detailed to comply with the claims procedures. Again, it is a factual issue whether, under the circumstances, MMJ’s notices complied. MMJ could not be expected to provide a detailed time and cost estimate when it did not even have a design to work with and did not know when one would be provided. The county forced MMJ to stop working and said, in essence, “We will tell you when we are done with the design and when you can restart. In the meantime you must forecast how long the delay will be and submit documentation upon which we will rely in determining your compensation.”

Based on the record before us, with all inferences in favor of the nonmoving party, it appears MMJ did comply with the contract. MMJ sent letters asking the county to produce the design as soon as possible and telling the county that its costs were mounting the longer it remained idle. Prior to receiving the final design, MMJ sent numerous letters to the county. For example, MMJ sent notices on June 16, 1998 (field notice from John Neville to Chad Coles); June 26, 1998 (letter to county outlining specific objections to change order number three); letters of July 7 and July 9, 1998 (concerning mounting costs due to work stoppage); letter of July 10, 1998 (requesting ability to proceed with work and avoid additional delays); and letters of July 24, July 29, August 6, August 14, and August 18, from Ben Price, MMJ’s contract administrator. The county’s response was simply to reiterate it required compliance with the claim procedures.

MMJ presented evidence that the letters and notices it provided were standard in the industry. The “contract language is interpreted in light of industry practice.” Barry B. Bramble & Michael T. Callahan, Construction Delay Claims § 2.01 (3d ed. 2000). In these circumstances, there are genuine issues of fact whether the notices provided by *400MMJ satisfied the contract requirements in light of industry practice.

1. Actual Notice Plus

I concur with the majority that “actual notice” alone is not sufficient to comply (or waive compliance with) a contract. However, the issue is more complex than that. This is largely because the “concept of construction delay is universal to the industry.” Bramble & Callahan, supra, § 1.01. The purpose of a prompt notification requirement of changed conditions involving possible delay and increased expense is to give the owner the opportunity to verify and investigate the differing site condition and to make the most cost-effective arrangements possible. James F. Nagle & Douglas S. Oles, Washington Building Contracts and Construction Law § 15.45 (1996); Sime Constr. Co. v. Wash. Pub. Power Supply Sys., 28 Wn. App. 10, 621 P.2d 1299 (1980) (owner was prejudiced by contractor’s lack of written notice because it could have made more favorable, alternate arrangements). MMJ fulfilled that purpose in notifying the county immediately of utility problems.

MMJ was required by the contract to notify the county engineer of changed conditions in writing. The engineer was required by the contract to “make an equitable adjustment in the payment or the time required for the performance of the work.” CP at 111. Now the county wants to renege on its agreement to equitably compensate MMJ for work it required merely because MMJ failed to comply with the technical requirements regarding the form of its request for additional compensation.

However, the rule in Washington has been that where the contractor notifies the owner of the changed condition, failure to precisely follow claims procedures will not defeat the contractor’s right to compensation unless that procedural error causes prejudice to the owner. Bignold, 65 Wn.2d 817. In Bignold, the county’s representative ordered the contractor to perform extra work because of an antici*401pated site condition, of which the owner had been promptly notified. The contractor sought compensation for the additional work caused by the unanticipated conditions. The county defended on the grounds that the contractor did not make a written claim according to the contract’s requirements. The court held that the county was required to make an equitable adjustment to the contract price, holding:

the [owner] became immediately aware of the changed conditions as soon as they developed and ordered the contractor to perform the changes and extra work involved .... Under such conditions, the county cannot defeat recovery by a contractor even if no written notice was given.

Bignold, 65 Wn.2d at 822.

The material facts in this case are substantially similar to Bignold, and the result should be the same. The majority attempts to distinguish Bignold by pointing out that it was not just the actual notice in Bignold that caused the court to grant the contractor recovery despite lack of written notice. The majority points out that “it was the owner’s knowledge of the changed conditions coupled with its subsequent direction to proceed with the extra work that evidenced its intent to waive enforcement of the written notice requirements under the contract.” Majority at 388. But that is exactly what happened here. The county knew of the changed conditions, created the plans to deal with those conditions, and subsequently directed MMJ to proceed with the extra work.

Similarly, in Lindbrook Construction, Inc. v. Mukilteo School District No. 6, 76 Wn.2d 539, 458 P.2d 1 (1969), this court required the owner to pay for additional work even though the contractor did not strictly comply with the notice and claim requirements. The contractor encountered unexpected site conditions when performing grading and drainage work at the site of a new school, requiring extra work to complete the project. The architect, who was the school district’s representative, had actual knowledge of the conditions as they surfaced. This court denied the county’s attempt to avoid payment for the contractor’s additional *402work on the basis of failure to comply with the contract’s notice provision. This court found that the owner’s actual notice was critical to the result, noting the architect was the one “who told the contractor what to do, and what not to do. It strains credulity to believe that he failed to keep the School District authorities advised of what was happening.” Lindbrook, 76 Wn.2d at 543. The court concluded that the “contractor’s right to recover under the circumstances of this case is clear.” Lindbrook, 76 Wn.2d at 544 (citing Bignold, 65 Wn.2d 817); see also Am. Sheet Metal Works, Inc. v. Haynes, 67 Wn.2d 153, 407 P.2d 429 (1965) (owner cannot deny compensation to contractor for extra work authorized and directed by owner, despite contractor’s failure to get written approval).

Accordingly, I agree that mere actual notice is not sufficient to comply with or waive the contractual notice requirements. However, an obligation to pay for work performed may be triggered by actual notice and direction by the owner or his agent to continue working.

2. Whether Absher Requires a Different Result

The county relies on Absher Construction Co. v. Kent School District No. 415, 77 Wn. App. 137, 890 P.2d 1071 (1995), for the proposition that Washington now follows a rule of strict compliance in enforcing a construction contract’s claims procedures and that unequivocal conduct is required before a contract provision will be deemed waived. This citation is not well taken. In Absher, the owner had no notice of the contractor’s additional work until it was already completed. The owner had no opportunity to investigate the differing site conditions and make a determination how to accommodate it. In Absher, the contractor went ahead and completed the work and then presented the bill. In the present case, MMJ was completing work expressly required by the county and under the county’s daily inspection. We should not extend Absher for the proposition that an owner can direct additional work be done and then avoid *403paying for it if the contractor fails to submit a claim in 15 days which includes details which could not possibly yet be known.

The county contends that under Absher, it is no longer relevant whether the owner has actual notice of the changed conditions and the additional work made necessary by those conditions. The county points out that the Court of Appeals in Absher wrote that “[e]ven if the District had known of the concerns, those concerns were not claims under the contract.” Id. at 143. Based on this language, the county contends that actual notice of changed site conditions no longer has any relevance in evaluating the contractor’s entitlement to compensation.

However, the statement in Absher regarding what the result in that case would have been if actual notice had occurred is plainly dicta. Actual notice did not occur, and therefore the parties were not meaningfully adversed on this point. The contractor did not provide any notice to the owner, and the owner did not have the opportunity to investigate alternate arrangements and was not able to direct the contractor how to proceed. The county cannot rely on dicta from a case where actual notice was not an issue. Nor can the county effectively argue that Absher changed the rules in Washington regarding actual notice. Notably, the Absher decision did not meaningfully evaluate governing Washington precedent on that issue, such as Bignold and Lindbrook.

3. Prejudice

Nor did Absher change the rule in Washington regarding the relevance of prejudice to the owner if a contractor fails to provide proper written notice. The general rule is that a contractor does not forfeit his claim to equitable adjustment merely because he has failed to technically comply with a contract’s notice provisions; the owner must also show that he has actually suffered prejudice. Kenneth M. Cushman & Joyce K. Hackenbrach, Advanced Construction Claims *404Workshop: The Law, Analysis, and Pricing of Delays and Disruptions, in Real Estate Law and Practice **44-45 (PLI Real Estate Law & Practice Course Handbook Series, Oct. 18-19, 1990), available in Westlaw 357 PLI/Real 11; Jon M. WlCKWIRE ET AL., CONSTRUCTION SCHEDULING: PREPARATION, LIABILITY, and Claims § 3.14(D) (2d ed. 2003).

Traditionally, Washington courts have followed the general rule and held that lack of written notice “can be overcome by a showing that the owner had actual or constructive knowledge or suffered no prejudice.” Nagle & Oles, supra, § 14.5. Absher did not change Washington’s adherence to the general rule. The Absher court stated that prejudice is not required to enforce contractual notice provisions. Absher, 77 Wn. App. at 145. The court then cited Sime, a case in which prejudice to the owner was an important factor of the case. Sime expressly stated that prejudice to the owner would have been avoided if notice had been given. Sime, 28 Wn. App. at 16. Thus, after Absher, the rule remains that prejudice to the owner is relevant in determining the enforceability of notice provisions.

4. Waiver

In addressing the waiver issue, the majority relies on the county’s written correspondence informing MMJ that it was not waiving the requirements of written notice and claim submission. However, the county’s actions indicated otherwise. Again, there was ample evidence presented by MMJ upon which a reasonable juror could find waiver.

The majority quotes Swenson v. Lowe, 5 Wn. App. 186, 486 P.2d 1120 (1971), stating “ ‘the requirement of a writing is for the benefit of the owner, and the owner, either expressly or by conduct, may waive such a requirement.’ ” Majority at 387 (quoting Swenson, 5 Wn. App. at 188). The majority fails to include the very next sentence in the quoted opinion, which is:

*405As stated in Annot., 2 A.L.R.3d 620, 661 (1965), “where . . . the work was orally ordered, requested, directed, authorized, or consented to by the owner. . .” the requirement is deemed waived. Morango v. Phillips, 33 Wn.2d 351, 205 P.2d 892 (1949); Eggers v. Luster, [32 Wn.2d 86, 200 P.2d 520 (1948)]; Bjerkeseth v. Lysnes, 173 Wash. 229, 22 P.2d 660 (1933); Crowley v. United States Fid. & Guar. Co., 29 Wash. 268, 69 P. 784 (1902). See 13 Am. Jur. 2d Building and Construction Contracts § 24 (1964).

Swenson, 5 Wn. App. at 188-89.

Our cases are in accord. Where the owner directs the contractor to do the work, the owner cannot then complain the contractor did not seek written authorization. The county cannot prevent waiver from occurring simply by disclaiming waiver in its letters while at the same time engaging in conduct which constitutes waiver under the law. Under our construction law, at the very least, when the county says one thing and then does another, it creates a question of fact. As in Swenson, the county may not direct that work be done and then refuse to compensate MMJ just because the original contract required that a demand for compensation be in a technical, detailed writing.

The county’s reliance on Absher regarding waiver is again misplaced. The Absher court found there was no conduct on the part of the owner that could be interpreted as a waiver of the requirement of notice or a waiver of the requirements regarding claims procedure for additional compensation. However, in the present case, there is ample evidence that the county was intending to waive the requirements of written claim procedures. The county orally ordered MMJ to halt work twice, both times without providing notice to MMJ of when it could return to work, and it orally told MMJ when to return to work. Under these facts, a reasonable juror could find that the requirement of written notice was waived.

5. Risk of Mislocated Utilities

The county argues that MMJ assumed all risk of delay and other potential problems due to utilities at the site. *406MMJ claims the county breached its implied warranty to furnish the contractor with accurate plans, and the delay was thus owner-caused.

As “[b]etween the owner and the contractor, the owner is responsible for the design and any losses due to defects in design. This responsibility is often stated in terms of the owner’s implied warranty of the adequacy of the plans and specifications.” Bramble & Callahan, supra, § 3.02(D). There is evidence submitted by MMJ that plans associated with change order number three were inaccurate. According to its standard practice, prior to soliciting bids from contractors, the county requested input from all utility companies regarding the presence of equipment within the boundaries of the Apple Valley and Wolfland projects. MMJ provided evidence through the affidavit of an expert witness in construction management that the standard in the trade is that the owner is responsible for confirming the location of utilities. However, the county failed to solicit input from utility companies after it expanded the scope of the project. The change order was presented to MMJ on June 4, 1998 and MMJ was required to start work immediately, prior to approval by the utility director. The drawings the county provided to MMJ indicating utility line placement were in error.

MMJ contends, and the evidence suggests, that the error was the result of the county failing to follow its standard procedures and failing to fulfill its duty to provide adequate plans. MMJ was entitled to rely on the standard practice of the county to involve utilities in the design process. This is an unresolved factual issue that is material to the outcome of the case. The county says it disclaimed the implied warranty in its contract document. Standard specification 1-07.17 allocates to the contractor all costs associated with relocation of utilities. Therefore, according to the county, MMJ’s reliance on the contract plans and specifications was unreasonable. Whether the reliance was reasonable is a question of fact, making summary judgment inappropriate in this case.

*407This is not a novel question of law. For example, in Clevco, Inc. v. Municipality of Metropolitan Seattle, 59 Wn. App. 536, 799 P.2d 1183 (1990), Clevco won a bid to install sewers in east King County. The contracts purported to allocate all risk of underground utilities to Clevco, the contractor. Like the case at bar, Metro failed to indicate utilities on its plans and Clevco submitted a bill for additional compensation. Metro moved for summary judgment, arguing the contract clearly placed the risk of utilities on the contractor. The appellate court disagreed stating the general rule is that the contractor’s recovery "is determined by the question of whether the contractor’s reliance on contractual representations was reasonable” Id. at 543 (emphasis added). Where the plans or specifications lead a public contractor reasonably to believe that conditions represented on the plans do exist and may be relied upon, he is entitled to compensation for extra expense incurred as a result of the inaccuracy of those representations. Id. at 542 (citing Dravo Corp. v. Mun. of Metro. Seattle, 79 Wn.2d 214, 484 P.2d 399 (1971)); see also Scoccolo Constr., Inc. v. City of Renton, 102 Wn. App. 611, 9 P.3d 886 (2000) (contract language stating contractor bears risk of delays due to utilities does not necessarily preclude contractor’s recovery, but what parties intended contract language to mean is a factual issue which prevents summary judgment).

CONCLUSION

I agree with the majority that actual notice is not an exception to contract compliance. But that is not the issue here. Instead, the question is whether actual notice plus direction to proceed with the work may substantially comply with a contract or waive technical portions of the claims procedure. This is a factual question ill suited for summary judgment resolution.

The county warns that if we hold there is a factual dispute regarding compliance with the contract’s notice and *408claim provisions, or a factual dispute regarding waiver, contractors will be free to run up costs and incur delays wherever they like, and then present a surprise bill to the owner at the end of the project. This is simply untrue. The general rule is, and our cases state, that when the owner directs the contractor to do work outside the contract, and then observes the work being done, the owner cannot later rely solely on technical claim provisions requiring a writing to deny equitable and reasonable compensation to the contractor, especially where the lack of a writing has not caused the owner any prejudice. The trier of fact should be the one to decide whether that is what happened here.7

We are not deciding whether there were reasonable grounds for upholding a jury’s decision. Certainly, the majority has found many potentially compelling facts from which a rational jury might find for the county. A conflict of material fact exists. I would affirm the Court of Appeals and remand the case for trial.

Johnson, Sanders, and Ireland, JJ., concur with Chambers, J.

Reconsideration denied January 28, 2004.

Also, MMJ had prior experience with Spokane County. MMJ had performed, without incident, one other contract for the county earlier in the year.

The trial court certified some issues for review and stayed others pending appellate review. The trial court stayed MMJ’s claim for unpaid contract balances on both projects, the county’s counterclaims for liquidated damages and other back charges, as well as the county’s third party claims against US West.

One of the issues raised by MMJ in its summary judgment motion, which the trial court did not address, is whether the contract’s provision regarding complete forfeiture of the contractor’s claim violates ROW 4.24.360. The statute nullified “ ‘no-damages-for-delay’ ” clauses. Scoccolo, 102 Wn. App. at 616. Under the statute, any contract language, which purports to extinguish a part/s right to an equitable adjustment for unreasonable delay, is void as against public policy. MMJ contends the county’s delays were unreasonable.

The trial court also failed to address MMJ’s claim that its reservation of rights in the executed change order effectively preserved its claims, although there is authority for that position. Thomas H. Asselin & M. Catherine Harris, How to Recognize, Preserve, Present, and Prosecute Construction Contractors’ Delay Claims, 40 S.C. L. Rev. 943, 950 (1989).