Spokane, Portland & Seattle Railway Co. v. Ballinger

Dunbar, J.

This is an action to compel specific performance of an agreement for the sale and purchase of a railroad right of way, entered into by appellants and respondent. The agreement consists of a right of way option and letter •of acceptance. The right of way agreement was as follows:

“In consideration of the sum of one dollar to us in hand paid, the receipt of which is hereby acknowledged, and the *548further sum of eight hundred ninety-nine and no-100 dollars, to be paid on the execution of the deed hereinafter mentioned, we have agreed, and by these presents do agree, on written request, within six months from date, to sell and convey to the Portland and Seattle Railway Company, a Washington corporation, free and clear of all encumbrances, a right of way for its road over and across [here follows description], and upon payment .of said sum of nine hundred dollars ($900), we agree to make a good and sufficient deed to said company for said right of way, the company to have the right to enter and construct its road across said premises in the meantime. (Should the said company fail to exercise this option to purchase said right of way within six (6) months from the date hereof, then this agreement to be null and void.) Said company to provide one surface crossing and one 6-foot arch for the passage of stock under the track of said road, this agreement as to the arch subject to a division engineer’s approval.
“In Witness Whereof, we have hereunto subscribed our names this 26th day of December, 1906.
In the presence of I. J. Ballinger.
Geo. I. Hinckley. Elizabeth Ballinger.”

This right of way agreement was entered into on the 26th day of December, 1906. On the 4th day of January, 1907, the respondent sent to the appellants what it terms its acceptance of the option, which was as follows:

“Spokane, Washington, January 4, 1907.
“I. J. Ballinger, Esq., and Elizabeth Ballinger,
“Cheney, Washington.
“Dear Sir and Madam: Referring to right-of-way agreement made with each of you on December 28th, 1906, by which you agree to convey to Portland and Seattle Railway Company a right of way over the west half of the northwest quarter of section ten, the east half of the northeast quarter of section nine, twenty-two, forty-one.
“On behalf of the Portland and Seattle Railway Company, I beg to advise you that the same is hereby accepted and we will be prepared to make payment agreed and take title to the right of way strip. Yours truly, W. C. Sampson, Right of Way Agent.”

*549Upon failure to pay the amount of money stipulated, the appellants notified the respondent that it (the respondent) had no interest in the land, and demanded possession of the same. The respondent entered into the possession of the land and expended a large amount of money in constructing the road. After the notification to respondent by the appellants that it had no further interest in the land, the respondent tendered to the appellants the stipulated price for the land and demanded a deed, which was refused. This action was commenced in August, 1907, by the respondent, to procure a restraining order, by which appellants were restrained from interfering with respondent’s possession of said real estate and constructing a railroad thereon. The trial court found, among other things, the agreements as set forth above; that time was not of the essence of the contract for the purchase and sale of said lands; and that respondent was entitled to the exclusive possession of said right of way strip, and to a specific performance of the contract. Judgment Was entered in accordance with these findings, and appeal followed.

The trial court evidently based its judgment on the assumption that the acceptance of the option by the respondent changed the transaction between the parties from an option to an agreement to sell, binding upon both parties to the agreement and enforcible by either, and that this acceptance by the respondent destroyed and annulled the conditions of the option contract; else it could not have found that the payment of the purchase price was not a condition precedent, and that time was not of the essence of the contract. In this we think the court erred. An option is a common and familiar method of securing the right to buy land, the purchaser paying a certain amount with the privilege of forfeiting that amount if he does not see fit to pay the full purchase price agreed upon on or before a stipulated time. The conditions are plain and easily understood. If the purchase price is paid or tendered within the time specified, the obligation of the vendor is to give a deed. If it is not, no obligation whatever *550rests upon him. The limitation has been fixed by the parties and it is as binding as any statutory limitation.

It is difficult to see how the plain provisions of this option contract could be annulled by the announcement by the respondent that the agreement was accepted. Most certainly it was accepted when the one dollar consideration was paid and the agreement to sell upon certain conditions was executed by the appellants. Can it be that the mere notification of acceptance stripped away all the appellants’ rights under the contract, and left them nothing in return? The contract specially provides that, should the said company fail to exercise the option to purchase the right of way within six months, the agreement should be null and void. This certainly made time the essence of the contract, if time can be made the essence of a contract. Now, what is meant by the words “fail to exercise,” etc? This question is answered by the respondent in its note of acceptance, viz., that it would be prepared to make the payment agreed and take title. There is nothing to indicate that it would accept some of the conditions of the option contract and abrogate others; but it accepted them all. It seems to us that this letter of acceptance neither added to, nor took away, anything from the contract, and was certainly entirely useless. But if it was necessary, by its reference to the contract and its acceptance of the conditions therein expressed, it must be held to have accepted all the conditions of the contract, and that is all there is in this case. The respondent entered into an option agreement to pay a particular price at a definite time, and it allowed the time to expire. The appellants’ contention is plainly sustained by the authorities cited, viz: Neeson v. Smith, 47 Wash. 386, 92 Pac. 131; Waterman v. Banks, 144 U. S. 394, 12 Sup. Ct. 646, 36 L. Ed. 479; Lockman v. Anderson, 116 Iowa 236, 89 N. W. 1072; Pollock v. Brookover, 60 W. Va. 75, 53 S. E. 795, 6 L. R. A. (N. S.) 403; and many other cases. The respondent attempts to distinguish these cases, but in this we think it is unsuccessful; for while in some of the cases the circumstances *551were of necessity different, the principles announced sustain the appellants’ right to forfeiture.

Great stress is placed upon the fact that appellants suffered the respondent to enter into possession of the land and to expend a large amount of money thereon, and it is claimed that, for this reason, they should be estopped from demanding a sti’ict compliance with their contract. If we have placed a proper construction upon the contract, it follows that the respondent went upon this land and made expenditures at its own peril. This may be a hardship, but it is always a hardship for a person purchasing an option to lose the payment when the option expires. Sometimes the amount paid for the option is small and sometimes it is large, but this is only a matter of degree; the legal consequences are always the same. Possession can in no way change the conditions of the contract in reference to the time of payment. That was a matter which was fixed by the contract. If, as a matter of accommodation to the respondent, the appellants allowed it to take possession of the land, they should not now be deprived of any right they have under the contract. We think there is no element of estoppel shown anywhere in the record, and neither are we able to discern any special hardship in the case. The respondent need not lose its expenditures, but failing to perform the conditions of the contract it must be relegated to the exercise of the right, of eminent domain, if it desires the possession of the land.

The judgment will be reversed, and the action dismissed, with costs to the appellants.

Fullerton, Crow, Root, and Rudkin, JJ., concur.

Hadley, C. J., and Mount, J., took no part.