This case was before this court about February 1929, and is published in 16 S.W.(2d) 901, to'Which we refer for a fuller statement of the facts in the case. In that suit the court gave a peremptory instruction. We reversed the judgment and remanded the cause, and in the case now before us the trial court submitted to the jury the facts. The suit was by Hal Hughes and against the Hoffer Oil Corporation, Hughes claiming that he had a contract with the Hoffer Oil Corporation by the terms of which the corporation was to pay him $5,000, if he drilled a well in King county to a depth of 3,500 feet, or to a less depth if oil or gas was discovered, or if the Hoffer Oil Corporation should conclude to stop the work on the well. Hughes alleged that after he had gone down to some 1,590 feet the corporation ordered him to- discontinue the drilling, and that though he waited some 4½ or 5 months and did not engage in other work in the meantime, the Hoffer Oil Corporation did not order him to continue the drilling.
The case was submitted to a jury upon special issues, and the jury found: (1) That the Hoffer Oil Corporation discharged Hughes without cause; (2) that the Hoffer Oil Corporation discharged Hal Hughes on March 24, 1920; (3) that Hal Hughes could and would have finished the well to a depth of 3,500 feet or to' a depth where oil and gas be found in paying quantities at a less depth if the Iloffer' Oil Corporation had not discharged him and had furnished what it agreed to furnish; (4) that Hal Hughes waited on orders and held himself ready to complete the well for 4½ or 5 months; (5) that it would have required Hughes some 4½ 01-5 months to finish the well if the Hoffer Oil Corporation had furnished what they agreed *427to furnish, under the contract; (6) that according to the contract said Hoffer Oil Corporation and Hal Hughes agreed as to what Hal Hughes would be entitled to receive as compensation in the event the well was completed at a depth less than 3,500 feet, and ■the said amount was $5,000; (7) that the Hoffer Oil Corporation and Hal Hughes did not agree that the Hoffer Oil Corporation could stop the drilling of the well in less than 3,500 feet unless oil or gas were found in paying quantities at a.less depth; (8) that the plaintiff and defendant, by the written contract between them, contemplated at the time it was made that plaintiff should be paid the entire sum of $5,000 only upon the completion of the well to such depth as oil or gas should be procured in paying quantities, not to exceed the depth of 3,500 feet.
Upon the verdict of the jury the court granted judgment for plaintiff for $2,550, the defendant having theretofore paid $2,450 of ■the total amount. From this judgment the' defendant has appealed.
Opinion.
The contract upon which plaintiff below sued was set out in a letter written by appellant to appellee, and signed and accepted by appellee as follows:
“Hr. Hal Hughes,
“Electra, Texas.
“Dear Sir:
“Referring to our discussion this morning concerning the drilling of a well for this company on what is known as the Patton lands in King County, Texas, I hereby wish to confirm the understanding we had this morning:
“You agree to take care of this work, furnish all of the labor necessary for the completion of this well to be the depth that we wish to go, which will not exceed 3500 feet,- and the possible depth as discussed with you this morning. We understand that you have a complete line of rotary equipment and will be able to furnish small parts of such material as might be needed in addition to that now on the ground. You agree to take care of this work and carry the same to completion, you to receive the sum of $5000.00 -for your services in connection with the well. You are to be in sole charge of the work and are to look after the entire proposition for this company, which will include the moving of the rig and all material from its present location to the new location. We are to pay all bills in connection with labor and repairs to equipment that will be needed in the drilling of this well, you agreeing to furnish freé such other necessary equipment with the exception of boilers. The drilling of the well is to be handled under our direction, and formations are to be cored and a small hole drilled ahead if we desire. You agree to immediately take over the work and get the same started to comply with our contract You are to furnish a man to look after odd jobs on the well who will forward drilling reports and information to this office every day, provided that he reaches Benjamin or can get same into the mail. In the event of formations looking favorable you will take up with Mr. Moss or myself by telephone and get our ideas with reference to same and as ■to whether or not we want further tests made. In ease of oil showings or anything favorable, the well should be shut down immediately and this office notified by wire or telephone.
. “Yours very truly,
“Hoffer Oil Corporation,
“T. B. Hoffer, President.
“Accepted: Hal Hughes.”
Appellant urges that the answer of the jury to special issue No. 8, to the effect that plaintiff and defendant by the written contract between them, contemplated at the time it was made that plaintiff should be paid the entire sum of $5,000 only upon the completion of the well to such depth as oil or gas should be procured in paying quantities, not to exceed the depth of 3,500 feet.
The evidence showed that the location of the well was about 29 miles north of the town of Benjamin, Knox county, in the mountains and along the brakes. That the nearest shipping point was Benjamin. In a subsequent conversation between appellee and appellant, represented by T. B. Hoffer, 'president of the corporation, appellee told Hoffer that he thought it would be best to, find a gasoline engine because the water was bad and would have a bad effect on the boiler; that he had had experience with the same kind of water, but not so bad. The water was “gyp.” Hughes testified that “gyp” water would burn the crown sheet out of the boilers; he further testified that after he started actual drilling of the well everything looked all right, and the boiler went to .the bad; that he continued to run a little and then got the boiler maker out there, and then they would work again. Appellee further testified:
“We stopped drilling about the last of October; we had thoroughly worked the boilers over for about the second occasion, and it would do no good, and it was just up then to them to get a. new boiler, or make some different arrangements because we could not go further with the material on the ground; we had in fact from first to last worked them over a good many times and the boiler makers had done about all they could do.
“From October I waited for instructions from the Hoffer Oil Corporation until March 24th, any time they would have told me to go back'I Would have had to done it; they dismissed me about March 25th, 1926; they stayed shut down all of this time, and I wrote *428them to know what they were going to do, because I had more work coming up and if this well was going to be finished I wanted to go ahead and finish it.”
On March 24, 1926, the Hoffer Oil Corporation, by P. M. Moss, vice president, wrote ap-pellee the following letter: “With reference to the King County well, wish to advise that we have assigned our interest in the acreage and well to other parties here, and they in turn have a new contract with the land owners for the drilling of the well, I believe it is their intention to skid the rig and drill a cable tool test, using an oil engine for this purpose. I understand from Mr. Capers that you may possibly have a few small tools left at the location, and if you will be good enough to let either he or this office know when you can make a trip to the well he will go out at the same time and cheek up your material with you. What necessary adjustments, if any, with you can be made after that time.”
It is evident that the cause of stoppage of the drilling was due to “gyp” water. There is absolutely no evidence in the record as to who was required to furnish the water necessary to the drilling, although the contract provides that the driller was to furnish “all necessary equipment with the exception of the boilers.” We are inclined to think that probably under this provision of the contract it was contemplated that the driller was to furnish the proper water for such drilling operations. There is no evidence in the record that the appellee, during the 4½ or 5 months, which he stated and the jury found that he waited for orders to drill the well deeper, attempted to get any other employment.
“It is not in every case of an unwarranted discharge of an employee that such discharged employee can recover the full amount of his wages or salary for the unexpired term of his employment. Ordinarily, he can recover only the loss he has sustained by reason of such discharge, and he must show that he has used diligence to secure other employment during the unexpired term. The employee is held liable for such wages or salary as he did receive during the unexpired term, or such as he might have received by the exercise of due diligence.” Hoffer Oil Corporation v. Hughes (Tex. Civ. App.) 16 S.W.(2d) 901, 906.
In Meade v. Rutledge, 11 Tex. 44, where an overseer was employed during the fall of 1847 for a period of one year and was discharged on January 1, 1848, and sued to recover as damages for breach of contract the full contract price, alleging that he was.ready and willing at all times to perform his part of the contract, our Supreme Court said: “If the offer, by an overseer, to perform service, is equivalent, in every respect, to actual performance, he might, without doing duty for a day, recover wages for the year — although perhaps he may be engaged during the year elsewhere in some employment equally or perhaps more profitable — or might have been engaged, had he made any attempt to procure employment. This would be too monstrous to be sanctioned by any sound principles of law or rules of equal justice.”
In Porter & McMillan v. Burkett et al., 65 Tex. 383, our Supreme Court said, quoting from the headnotes:
“A person who has been stopped in the performance of a contract by the default or by the direction of his employer, is entitled to compensation for the losses he sustains; but he is entitled to compensation only, and not to the gross amount he would have received from his employer had the contract been fulfilled. * * *
“Such person may recover the natural and probable profits his contract would have yield,ed him, when they are certain, and not contingent, speculative or remote; but he should not receive, when the work is not completed, the same amount of money he would have been entitled to, had the contract been fully executed.”
In Enterprise Co. v. Neely (Tex. Civ. App.) 217 S. W. 1088, 1089, it is said:
“It is the general rule of law that a contract must be at least substantially performed according to the terms of the agreement before a party can have any ri^ht of action thereon. Linch v. Paris, 80 Tex. 23, 15 S. W. 208 ; 6 R. C. L. 951 and 966 et seq.
“A plaintiff cannot recover on an entire contract by proving part performance without allegations authorizing recovery upon a quantum meruit,” citing cases.
See Osage Oil & Ref. Co. v. Lee Farm Oil Co. (Tex. Civ. App.) 230 S. W. 518, writ of error refused.
Where a plaintiff seeks to recover the full damages he would have received had he completed the contract and acknowledges that he did not complete the contract, he must show that the failure to complete the contract was due entirely to the fault of the defendant, and that during the interim of his enforced delay he, used all reasonable effort to get other employment. There is no evidence in this case that appellee during the 4½ or 5 months of delay exercised any effort to get other employment, or that he got other employment. Hence we conclude that by reason of the affirmative answer of the jury to special issue No. 8, plaintiff did not show himself entitled to recover the full amount, or to recover at all; he having pleaded only the contract and not upon a quantum meruit.
, We conclude that the judgment below should be reversed and here rendered for appellant, and it is so ordered.