Tibbits v. Phipps

Cullen, J.:

This action is brought to -foreclose a mechanic’s lien.

The first objection raised to. the recovery of the judgment is that 'the plaintiff’s lien was not valid, because filed for a largely excessive amount. When the plaintiff had proceeded with the building so far as to reach his third payment under the contract, a dispute arose between him and the owner as to the character and details of the work. The appellant refused to make the payment, and the plaintiff refused to proceed with the building. Thereupon the plaintiff filed his notice óf-lien, wherein he stated that the labor and services were performed and materials were furnished in the erection of- the building pursuant to a contract, and that the amount unpaid under the contract was $2,400, of which $1,300 was then due, and $1,100 would become due on its completion.

We think that the notice was in exact compliance with the statute. But, however that may be, it stated truly and accurately the facts, and, therefore, is n'ot subject to the condemnation passed in Foster v. Schneider (50 Hun, 151) and Ringle v. Wallis Iron Works (76 id. 449).

Second, under the contract the second payment became due to the contractor when the building was “ ready for- lathing, roof on, and partitions set.” When the third payment was claimed, the appellant resisted-payment on the ground that the cellar partitions had not'been erected as required by the contract, as a condition for the second payment. As the appellant made the second payment without objection, it may be-that he waived the builder’s default. But I think there was no default. The term partitions ” did not *276include the partitions in the cellars. The latter were net partitions of the building itself, but mere subdivisions of the cellar to make coal boxes for different tenants. This is conclusively shown, by reference to the specifications, which draw a distinction between partitions and cellar partitions; and the appellant’s architect testified that the specifications as to the former did not relate to the latter. We think the testimony of the builders to the effect that the cellar work is ordinarily the last ■ don'e in the course of construction, was 'competent, so as to explain the meaning of the term “ partitions ” in the contract. However, if incompetent, it worked no harm, as the evidence of the defendant’s architect settled the question.

Third, the architect condemned the plaster in the building. The referee found, and the evidence was ample to support the finding, that the plaster was good, and in substantial compliance with the specifications. The contract required the plaintiff to -obtain the' architect’s certificate as a condition'precedent to his right to demand the payment. The referee has further found that the architect’s refusal to give the certificate was unreasonable and unjustifiable. This, also, we think, was supported by the evidence. The conversations of the architect with the plaintiff and his workmen at the time he was acting on the subject-matter,, were competent as part of the res gestee. . These tended to show that he refused to give the certificate because the owner had directed him not to give it, and that, in fact, he regarded the work as good.

Foiorth, we think the appellant should have been allowed the expense of replacing the defective corner post, amounting to fifty-eight dollars and sixty cents. It is unnecessary to discuss it, as there certainly was an error in admission of the testimony as to this item, for which the judgment' must be reversed. Over the objection and exception of the -appellant, a witness was allowed to testify that he heard' the evidence of the plaintiff as to the manner in which the corner post had been spliced and set, and- that if it was so set the work was properly done. Such evidence was improper. (Reynolds v. Robinson, 64 N. Y. 589 ; Guiterman v. Liverpool, etc., Steamship Co., 83 id. 358; Link v. Sheldon, 136 id. 1.)

The judgment appealed from should be reversed and a new trial granted, costs' to abide the event-, -unless plaintiff stipulates to ireduce the recovery by the sum of fifty-eight dollars and sixty cents, *277with interest from April 15, 1895, in which case the judgment as reduced should be affirmed, without costs of this appeal to either party.

All concurred.

Judgment reversed, and new trial granted before a new referee to be appointed at.Special Term, unless within twenty days plaintiff stipulates to deduct from the recovery of damages fifty-eight dollars and sixty cents, with' interest from April 15, 1895 ; and in case such stipulation is made, then the judgment, as reduced, is affirmed, without costs of this appeal to either party.